MICE PM Report
•Completion of Infrastructure•Target, solenoids•Phase Two planning & schedule•Non-MICE costs•Staffing & visitors
•Don’t have time for a detailed status report, have a look at: http://mice.iit.edu/mico/
MICE CMPB, 24th October, 2008
![Page 2: 1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.](https://reader035.fdocuments.us/reader035/viewer/2022072014/56649e7c5503460f94b7eb1a/html5/thumbnails/2.jpg)
Completion of Infrastructure
Very good progress last few weeks:– South wall complete– North Wall, 75% plates fitted– Quench reaction block being cast today– False floor in progress off-site– Believable completion date of 12th December– Negotiated our way out of fireproof painting - good
2
![Page 3: 1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.](https://reader035.fdocuments.us/reader035/viewer/2022072014/56649e7c5503460f94b7eb1a/html5/thumbnails/3.jpg)
Target & solenoidsTarget:
– Decided we can re-design shafts and bearings– Get to a new starting point with ISIS– Be ready Easter time next year– Engineering help (Jason Tarrant) for Sheffield
Decay solenoid:– No changes from last meeting– But worst case might be to remove complete solenoid
• Remove North wall• Build shield on inside of synchrotron so work in Hall unaffected• Do at Christmas• Likely cost £25-30K
Spectrometer solenoid:– Priority shifted to magnet#2– Field map as originally planned– We get it late Jan ‘09
3
![Page 4: 1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.](https://reader035.fdocuments.us/reader035/viewer/2022072014/56649e7c5503460f94b7eb1a/html5/thumbnails/4.jpg)
Phase Two planning
We just had the Collaboration Meeting– Reviews of major Phase two subsystems included– Much useful information and milestones emerged– But a lot still to do– No excuses now not to make the project plan!– LH2 project is struggling badly though
• It’s still competing for effort with Decay solenoid and focus coils – engineering effort MUST be reinforced quickly
– Focus coil final design review at Oxford 3rd November– RFCC modules in good shape – cavities ready for
manufacture– Coupling coil review early December
4
![Page 5: 1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.](https://reader035.fdocuments.us/reader035/viewer/2022072014/56649e7c5503460f94b7eb1a/html5/thumbnails/5.jpg)
Non-MICE costs
2 MVA electrical upgrade will be required by Step Five– Various ways to do it, have budget prices between
£200 & £600K– Two year lead time, which I can well believe– Need to worry about it now– RAL’s line on the WFL:
• ‘it was a CCLRC-specific fund and there’s no STFC equivalent.’
• Discussed with Sean Stewart and Paul Hartley – predictable outcome!
• Requested to put it on the Capital Investment plan• Watch this space…..
Tony has provided cost centre for railings and door stuff– Does that mean I can use it?
5
![Page 6: 1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.](https://reader035.fdocuments.us/reader035/viewer/2022072014/56649e7c5503460f94b7eb1a/html5/thumbnails/6.jpg)
Staffing, visitors & admin
Transition to Phase Two has been a bit of a shambles– My fault for not being clear about cost centres– Have agreement with Finance that I will adjust staff
bookings at end of each month myself– All UK project members being circulated with correct
Phase two cost code for capital items
•Need some clarification of visa & work permits for US types
•Admin Officer, Rose Hayes starts 29th October• We need to agree her terms of reference/job
description, does Susan do this?
•MICE has had its first lost-time accident – we’re now on the HSE’s radar