MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Status of MICE and Spectrometer Solenoids Spectrometer Solenoids

description

Status of MICE and Spectrometer Solenoids. MICE Oversight Committee Meeting RAL, 24 April 2014. Paul Soler on behalf of the MICE Collaboration. Contents. Agenda of Meeting Organisation MICE general status by MICE-UK Work Package Spectrometer solenoid status Conclusion. - PowerPoint PPT Presentation

Transcript of Status of MICE and Spectrometer Solenoids

Page 1: Status of MICE and  Spectrometer Solenoids

MICE Oversight Committee MeetingRAL, 24 April 2014

Paul Soler on behalf of the MICE Collaboration

Status of MICE and Status of MICE and Spectrometer Solenoids Spectrometer Solenoids

Status of MICE and Status of MICE and Spectrometer Solenoids Spectrometer Solenoids

Page 2: Status of MICE and  Spectrometer Solenoids

2

ContentsContents

1. Agenda of Meeting

2. Organisation

3. MICE general status by MICE-UK Work Package

4. Spectrometer solenoid status

5. Conclusion

MICE OsC Meeting, RAL, 24 April 2014

Page 3: Status of MICE and  Spectrometer Solenoids

3

Agenda of meetingAgenda of meeting MICE Oversight Committee meeting agenda

−11:45: MICE Status and Spectrometer Solenoids (P. Soler)

−12:10: Status of Focus Coils (R. Preece)−12:30: Lunch−13:00: Tour of R9 (Focus Coil and Spectrometer

Solenoid)−13:30: Spend in FY13/14 and Project Risks

(R. Preece)−14:10: Schedule and financial forecast for future

years (A. Grant)

MICE OsC Meeting, RAL, 24 April 2014

Page 4: Status of MICE and  Spectrometer Solenoids

4

New MICE OrganisationNew MICE Organisation Personnel:

− Spokesperson: Prof Ken Long (Imperial College)− Collaboration Board Chair: Prof Alain Blondel (U. Geneva)− MICE Project Manager: Mr. Roy Preece (STFC)− MICE Project Engineer: Mr Andy Nichols (STFC)− MICE UK Capital Project Associate: Mr Alan Grant (STFC)− Accelerator Integration Scientist: Dr J. Pasternak (Imperial)− Experimental Integration Scientist: Dr P. Hanlet (IIT)− US MAP Director: Dr M. Palmer (FNAL)− MICE US Construction Project Manager: Dr A. Bross (FNAL)− MICE UK Principal Investigator: Dr Paul Soler (U. Glasgow)

MICE OsC Meeting, RAL, 24 April 2014

Page 5: Status of MICE and  Spectrometer Solenoids

5

General StatusGeneral Status Work Package 1: Project Management

−MICE International Project Office (MIPO): construction of project

Page 6: Status of MICE and  Spectrometer Solenoids

6

General StatusGeneral Status

MICE OsC Meeting, RAL, 24 April 2014

West Wall Mezzanine (for Step IV)Rack room 2

Work Package 2: Mechanical Integration− MICE Hall Manager: John Govans

Page 7: Status of MICE and  Spectrometer Solenoids

7

General StatusGeneral Status

MICE OsC Meeting, RAL, 24 April 2014

Decay Solenoid power supply

Step IV control racks

Work Package 3: Electrical Integration −Focus coil quench detection system and control−Rack room 2: control racks, 30 kVA UPS−Decay solenoid power supply and quench detection

Page 8: Status of MICE and  Spectrometer Solenoids

8

General StatusGeneral Status

MICE OsC Meeting, RAL, 24 April 2014

Insertion hydrogen turret and absorber into FC 1

Work Package 4: Absorber-Focus Coil Module−AFC integration: hydrogen turret + absorber in FC 1−Focus Coil status: see Roy Preece’s talk

Page 9: Status of MICE and  Spectrometer Solenoids

9

General StatusGeneral Status

MICE OsC Meeting, RAL, 24 April 2014

Insertion hydrogen turrent and absorber into FC 1

Work Package 5: Hydrogen delivery system− Most activity on integration of AFC− LH2 delivery system simplified due to PRY solution− HAZOP review: diagnostic system, expansion tank, vacuum

relief valve, control system, nitrogen purge gas− Second LH2 absorber: ready to ship (KEK/Osaka)

Page 10: Status of MICE and  Spectrometer Solenoids

10

General StatusGeneral Status

MICE OsC Meeting, RAL, 24 April 2014

Work Package 6: RF Power− Delivery 2 MW power at 201 MHz at Daresbury (last OsC)− TIARA milestone met: installation RF amplifiers at MICE

RF loads installed under mezzanine

Page 11: Status of MICE and  Spectrometer Solenoids

11

General StatusGeneral Status

MICE OsC Meeting, RAL, 24 April 2014

Final stage amplifier with triode valve

Work Package 6: RF Power− Delivery 2 MW power at 201 MHz at Daresbury (last OsC)− TIARA milestone met: delivery of >500 kW power from

TH116 amplifier at MICE

Page 12: Status of MICE and  Spectrometer Solenoids

12

General StatusGeneral Status

MICE OsC Meeting, RAL, 24 April 2014

Work Package 6: RF Power− Cavity tests at the MTA stand at Fermilab− RF workshop at Fermilab on 2 June 2014 with UK team

(K. Ronald, T. Stanley) Tuner arms

Page 13: Status of MICE and  Spectrometer Solenoids

13

General StatusGeneral Status

MICE OsC Meeting, RAL, 24 April 2014

Work Package 7: Vacuum−The design of the vacuum system for Step IV is

complete and has been mocked up in the MICE Hall.

−A complete services inventory for the vacuum system has been compiled and is being used by the services design engineer to make the overall layout.

Page 14: Status of MICE and  Spectrometer Solenoids

14

General StatusGeneral Status Work Package 8: Magnetic Field Mitigation

−Partial Return Yoke and floor fixing designs completed and sent out tender

MICE OsC Meeting, RAL, 24 April 2014

Partial Return Yoke (PRY)

Page 15: Status of MICE and  Spectrometer Solenoids

15

General StatusGeneral Status

MICE OsC Meeting, RAL, 24 April 2014

Work Package 9: Software and Computing− Computing and controls

Work Breakdown Structure− Finite-state-machine

implemented in EPICS

Spectrometer solenoid control panel

Computing WBS

Page 16: Status of MICE and  Spectrometer Solenoids

16

General StatusGeneral Status

MICE OsC Meeting, RAL, 24 April 2014

Work Package 10: Operations and analysis−MICE Experiment Management Office (MEMO):

operations, maintenance and analysis

Page 17: Status of MICE and  Spectrometer Solenoids

17

General StatusGeneral Status

MICE OsC Meeting, RAL, 24 April 2014

Work Package 10: Operations and analysis− MICE Analysis Structure− Combination of simulation and analysis tools and physics

activities

Page 18: Status of MICE and  Spectrometer Solenoids

18

Target trajectory

S7 beam loss

ISIS beam loss

Magnet ramps

General StatusGeneral Status Work Package 10: Operations and analysis

− Target: operated at 0.8 Hz (April 2014) with little beam loss− Pneumatically activated proton absorber

MICE OsC Meeting, RAL, 24 April 2014

Proton absorber

Page 19: Status of MICE and  Spectrometer Solenoids

19

General StatusGeneral Status

MICE OsC Meeting, RAL, 24 April 2014

Muon decays in EMR

Work Package 10: Operations and analysis− First MICE physics paper published: D. Adams et al.,

“Characterisation of muon beams for the Muon Ionization Cooling experiment”, E. Phys.J. C73 (2013) 2582.

− EMR delivered by U. Geneva – EMR run Oct. 2013

Page 20: Status of MICE and  Spectrometer Solenoids

20

General StatusGeneral Status

MICE OsC Meeting, RAL, 24 April 2014

Criteria for success

Work Package 10: Operations and analysis− Step V vs VI running decision will be motivated by physics

criteria and schedule, financial constraints− Expect collaboration decision before end of 2014 after

careful evaluation

Page 21: Status of MICE and  Spectrometer Solenoids

21

Spectrometer SolenoidSpectrometer Solenoid

SS2 ready for shipping at Wang NMR

Spectrometer solenoid status:− Completion of the assembly, training, 3D magnetic mapping

and shipping to RAL of SS2 (October 2013)

MICE OsC Meeting, RAL, 24 April 2014

Magnetic field mapping SS2 at Wang NMR

Page 22: Status of MICE and  Spectrometer Solenoids

22

Spectrometer SolenoidSpectrometer Solenoid

Training sequence SS1 and SS2

Spectrometer solenoid status:− SS1 also assembled, trained and mapped at Wang NMR− SS1 is ready to be shipped to RAL (27 April 2014)

MICE OsC Meeting, RAL, 24 April 2014

SS1 at Wang NMR during final vacuum vessel assembly

Page 23: Status of MICE and  Spectrometer Solenoids

23

Spectrometer-Tracker Spectrometer-Tracker integrationintegration

MICE Tracker

Integration of the spectrometer solenoid and scintillating fibre tracker− Trackers have been available for a number of years and

commissioned with cosmic rays

Individual tracker stationMICE OsC Meeting, RAL, 24 April 2014

Page 24: Status of MICE and  Spectrometer Solenoids

24

Spectrometer-Tracker Spectrometer-Tracker integrationintegration

Tracker 2 just before inserting into bore SS2 Tracker 2 in bore SS2

MICE OsC Meeting, RAL, 24 April 2014

Integration of the spectrometer solenoid and scintillating fibre tracker− Installation tracker 2 in upstream SS2 completed 31 March

2014 and will be moved to MICE Hall 29 April 2014

Page 25: Status of MICE and  Spectrometer Solenoids

25

Spectrometer-Tracker Spectrometer-Tracker integrationintegration

Tracker 2 installed and light-guides in place

Integration of the spectrometer solenoid and scintillating fibre tracker− Installation tracker 2 in upstream SS2 completed 31 March

2014 and will be moved to MICE Hall 29 April 2014

Closed SS2 with tracker inserted

MICE OsC Meeting, RAL, 24 April 2014

Page 26: Status of MICE and  Spectrometer Solenoids

26

ConclusionsConclusions MICE is proceeding towards Step IV Many achievements in last six months:

– New organisation with change of spokesperson– Mechanical and electrical integration being achieved– Hydrogen absorber inserted into FC– RF power in MICE Hall milestone achieved– Partial Return Yoke design achieved: out to tender– Target doubled rate and proton absorber completed– EMR delivered and running well– Spectrometer solenoid SS2 integrated with tracker 2

and SS1 completed at Wang NMR, ready for shipping Focus coil status, schedules and resources to be

shown by Roy Preece and Alan Grant in next talksMICE OsC Meeting, RAL, 24 April 2014