MICE Oversight Committee MeetingRAL, 24 April 2014
Paul Soler on behalf of the MICE Collaboration
Status of MICE and Status of MICE and Spectrometer Solenoids Spectrometer Solenoids
Status of MICE and Status of MICE and Spectrometer Solenoids Spectrometer Solenoids
2
ContentsContents
1. Agenda of Meeting
2. Organisation
3. MICE general status by MICE-UK Work Package
4. Spectrometer solenoid status
5. Conclusion
MICE OsC Meeting, RAL, 24 April 2014
3
Agenda of meetingAgenda of meeting MICE Oversight Committee meeting agenda
−11:45: MICE Status and Spectrometer Solenoids (P. Soler)
−12:10: Status of Focus Coils (R. Preece)−12:30: Lunch−13:00: Tour of R9 (Focus Coil and Spectrometer
Solenoid)−13:30: Spend in FY13/14 and Project Risks
(R. Preece)−14:10: Schedule and financial forecast for future
years (A. Grant)
MICE OsC Meeting, RAL, 24 April 2014
4
New MICE OrganisationNew MICE Organisation Personnel:
− Spokesperson: Prof Ken Long (Imperial College)− Collaboration Board Chair: Prof Alain Blondel (U. Geneva)− MICE Project Manager: Mr. Roy Preece (STFC)− MICE Project Engineer: Mr Andy Nichols (STFC)− MICE UK Capital Project Associate: Mr Alan Grant (STFC)− Accelerator Integration Scientist: Dr J. Pasternak (Imperial)− Experimental Integration Scientist: Dr P. Hanlet (IIT)− US MAP Director: Dr M. Palmer (FNAL)− MICE US Construction Project Manager: Dr A. Bross (FNAL)− MICE UK Principal Investigator: Dr Paul Soler (U. Glasgow)
MICE OsC Meeting, RAL, 24 April 2014
5
General StatusGeneral Status Work Package 1: Project Management
−MICE International Project Office (MIPO): construction of project
6
General StatusGeneral Status
MICE OsC Meeting, RAL, 24 April 2014
West Wall Mezzanine (for Step IV)Rack room 2
Work Package 2: Mechanical Integration− MICE Hall Manager: John Govans
7
General StatusGeneral Status
MICE OsC Meeting, RAL, 24 April 2014
Decay Solenoid power supply
Step IV control racks
Work Package 3: Electrical Integration −Focus coil quench detection system and control−Rack room 2: control racks, 30 kVA UPS−Decay solenoid power supply and quench detection
8
General StatusGeneral Status
MICE OsC Meeting, RAL, 24 April 2014
Insertion hydrogen turret and absorber into FC 1
Work Package 4: Absorber-Focus Coil Module−AFC integration: hydrogen turret + absorber in FC 1−Focus Coil status: see Roy Preece’s talk
9
General StatusGeneral Status
MICE OsC Meeting, RAL, 24 April 2014
Insertion hydrogen turrent and absorber into FC 1
Work Package 5: Hydrogen delivery system− Most activity on integration of AFC− LH2 delivery system simplified due to PRY solution− HAZOP review: diagnostic system, expansion tank, vacuum
relief valve, control system, nitrogen purge gas− Second LH2 absorber: ready to ship (KEK/Osaka)
10
General StatusGeneral Status
MICE OsC Meeting, RAL, 24 April 2014
Work Package 6: RF Power− Delivery 2 MW power at 201 MHz at Daresbury (last OsC)− TIARA milestone met: installation RF amplifiers at MICE
RF loads installed under mezzanine
11
General StatusGeneral Status
MICE OsC Meeting, RAL, 24 April 2014
Final stage amplifier with triode valve
Work Package 6: RF Power− Delivery 2 MW power at 201 MHz at Daresbury (last OsC)− TIARA milestone met: delivery of >500 kW power from
TH116 amplifier at MICE
12
General StatusGeneral Status
MICE OsC Meeting, RAL, 24 April 2014
Work Package 6: RF Power− Cavity tests at the MTA stand at Fermilab− RF workshop at Fermilab on 2 June 2014 with UK team
(K. Ronald, T. Stanley) Tuner arms
13
General StatusGeneral Status
MICE OsC Meeting, RAL, 24 April 2014
Work Package 7: Vacuum−The design of the vacuum system for Step IV is
complete and has been mocked up in the MICE Hall.
−A complete services inventory for the vacuum system has been compiled and is being used by the services design engineer to make the overall layout.
14
General StatusGeneral Status Work Package 8: Magnetic Field Mitigation
−Partial Return Yoke and floor fixing designs completed and sent out tender
MICE OsC Meeting, RAL, 24 April 2014
Partial Return Yoke (PRY)
15
General StatusGeneral Status
MICE OsC Meeting, RAL, 24 April 2014
Work Package 9: Software and Computing− Computing and controls
Work Breakdown Structure− Finite-state-machine
implemented in EPICS
Spectrometer solenoid control panel
Computing WBS
16
General StatusGeneral Status
MICE OsC Meeting, RAL, 24 April 2014
Work Package 10: Operations and analysis−MICE Experiment Management Office (MEMO):
operations, maintenance and analysis
17
General StatusGeneral Status
MICE OsC Meeting, RAL, 24 April 2014
Work Package 10: Operations and analysis− MICE Analysis Structure− Combination of simulation and analysis tools and physics
activities
18
Target trajectory
S7 beam loss
ISIS beam loss
Magnet ramps
General StatusGeneral Status Work Package 10: Operations and analysis
− Target: operated at 0.8 Hz (April 2014) with little beam loss− Pneumatically activated proton absorber
MICE OsC Meeting, RAL, 24 April 2014
Proton absorber
19
General StatusGeneral Status
MICE OsC Meeting, RAL, 24 April 2014
Muon decays in EMR
Work Package 10: Operations and analysis− First MICE physics paper published: D. Adams et al.,
“Characterisation of muon beams for the Muon Ionization Cooling experiment”, E. Phys.J. C73 (2013) 2582.
− EMR delivered by U. Geneva – EMR run Oct. 2013
20
General StatusGeneral Status
MICE OsC Meeting, RAL, 24 April 2014
Criteria for success
Work Package 10: Operations and analysis− Step V vs VI running decision will be motivated by physics
criteria and schedule, financial constraints− Expect collaboration decision before end of 2014 after
careful evaluation
21
Spectrometer SolenoidSpectrometer Solenoid
SS2 ready for shipping at Wang NMR
Spectrometer solenoid status:− Completion of the assembly, training, 3D magnetic mapping
and shipping to RAL of SS2 (October 2013)
MICE OsC Meeting, RAL, 24 April 2014
Magnetic field mapping SS2 at Wang NMR
22
Spectrometer SolenoidSpectrometer Solenoid
Training sequence SS1 and SS2
Spectrometer solenoid status:− SS1 also assembled, trained and mapped at Wang NMR− SS1 is ready to be shipped to RAL (27 April 2014)
MICE OsC Meeting, RAL, 24 April 2014
SS1 at Wang NMR during final vacuum vessel assembly
23
Spectrometer-Tracker Spectrometer-Tracker integrationintegration
MICE Tracker
Integration of the spectrometer solenoid and scintillating fibre tracker− Trackers have been available for a number of years and
commissioned with cosmic rays
Individual tracker stationMICE OsC Meeting, RAL, 24 April 2014
24
Spectrometer-Tracker Spectrometer-Tracker integrationintegration
Tracker 2 just before inserting into bore SS2 Tracker 2 in bore SS2
MICE OsC Meeting, RAL, 24 April 2014
Integration of the spectrometer solenoid and scintillating fibre tracker− Installation tracker 2 in upstream SS2 completed 31 March
2014 and will be moved to MICE Hall 29 April 2014
25
Spectrometer-Tracker Spectrometer-Tracker integrationintegration
Tracker 2 installed and light-guides in place
Integration of the spectrometer solenoid and scintillating fibre tracker− Installation tracker 2 in upstream SS2 completed 31 March
2014 and will be moved to MICE Hall 29 April 2014
Closed SS2 with tracker inserted
MICE OsC Meeting, RAL, 24 April 2014
26
ConclusionsConclusions MICE is proceeding towards Step IV Many achievements in last six months:
– New organisation with change of spokesperson– Mechanical and electrical integration being achieved– Hydrogen absorber inserted into FC– RF power in MICE Hall milestone achieved– Partial Return Yoke design achieved: out to tender– Target doubled rate and proton absorber completed– EMR delivered and running well– Spectrometer solenoid SS2 integrated with tracker 2
and SS1 completed at Wang NMR, ready for shipping Focus coil status, schedules and resources to be
shown by Roy Preece and Alan Grant in next talksMICE OsC Meeting, RAL, 24 April 2014