1 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Lessons Learned Michael P. Bromfield, Construction...
-
Upload
esther-gilmore -
Category
Documents
-
view
216 -
download
0
Transcript of 1 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Lessons Learned Michael P. Bromfield, Construction...
1 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
Michael P. Bromfield, Construction EngineerConvention Facilities Advisory Committee Review
March 10 –11, 2009
2 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
• Outline• Site Preparation Purpose• Existing Site• Prior BNL Work• Site Preparation Scope• Lessons Learned• Path Forward
3 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Purpose
• Site Preparation was included as an early procurement (authorized pre-CD-3) to:• Provide an activity that reduced schedule risk to the
Ring Building by:– Reducing potential for unknown utilities or site conditions
delaying construction start– Reduce GC schedule risk during early construction– Be mobilized to correct any deficiencies left over from
previous activity at the site (leftover facilities or environmental liabilities)
• It provided a number of other benefits as well
4 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation - Existing Site
Bldg 100 Demolished
Bldg 87 Demolished
Bldg 210 Demolished
Bldg 481 Demolished
Bldg 211 Demolished
Ring Bldg Footprint
Construction Area Perimeter
Existing Buildings to be removed prior to construction
Bldg 209 Demolished
5 BROOKHAVEN SCIENCE ASSOCIATES
Prior Work by BNL
• On-going BNL program removed excess facilities/structures• Relocated Warehouse Facilities• Demolished Existing Facilities and Slabs/Foundations• Prepared Recycling Area and recycled concrete foundations• Remove Rail Road tracks and ties• Performed clean up and removal of oil-water separators and
related sanitary piping
6 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Scope
• Site Preparation Scope/Construction Packages• Clear and Grub Trees• Abandon Existing Site Utilities/Relocate Utilities• Abandon Monitoring Wells/Relocate Wells• Verify no environmental liabilities• Provide Utilities for Construction (power and communication)
7 BROOKHAVEN SCIENCE ASSOCIATES
Site Prep Status
• All base scope work completed -2/17/09 running under budget
• Some minor punchlist / closeout items remain• Added some items to scope
• Enlarged recharge basin & stockpiled structural fill due to seasonal environmental permit constraint
• Added maintenance of erosion control until Ring Bldg Contractor mobilizes
• Added clean-up of miscellaneous debris• No evidence of environmental liabilities • Ready for Ring building GC
11 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
• Summary– Site access control requirements– NSLS-II CM Staff increased knowledge of BNL
systems, procedures, personnel and points of contact – Understanding of requirements for shutdowns,
notifications, permits and utility tie-ins– Utility mark-outs and surveys will assist Ring Building
utility installation– Improved coordination of field inspectors and safety
engineers in oversight of contractor performance
12 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
• Better understanding of site access control requirements
– Repeated unauthorized incursions of area by Lab personnel- Despite Signs, Roadblocks and Web & Email Postings
– Additional time & effort spent:- Chasing Unauthorized Personnel from Area, - Maintaining Signs & Barricades
– On-site fauna destroyed construction fencing in path to food, habitats
– Need for well managed “permanent fence” instead of temporary construction fence
13 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
• NSLS-II CM Team new to BNL– Different Culture– “Outside world” experience
• Site Preparation work facilitated:– Knowledge / Understanding of BNL/DOE expectations and
requirements– Enhanced familiarity with BNL systems, procedures, personnel
and points of contact
14 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
• Lessons Learned–Understanding of requirements for shutdowns,
notifications, permits and utility tie-ins
• Determine Timeframe required for coordination with BNL Depts.
• Requirements for off-hour work due to maintenance of operations, personnel availability.
15 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
• Lessons Learned– Utility mark-outs and surveys will assist Ring Building Utility
installation:
• Facilitated planning for temporary utilities, as well as familiarity with existing and surrounding site utilities, infrastructure;
• Exposed unmarked structures, utilities, and identified “known-unknown utilities”.
16 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
• Lessons Learned– Improved coordination of field inspectors and safety engineers in
oversight of contractor performance:
• Good Planning & Project Oversight by CF & ESH Teams,• Collaborative Approach With Contractors Mitigated Weather
Impacts & Potential Impacts due to Scope Changes,• No Impact to Vehicular & Pedestrian Traffic.
17 BROOKHAVEN SCIENCE ASSOCIATES
Site Preparation Lessons Learned
• Lessons Learned and experience brought– From “Outside Staff”:
• New Technologies, Systems for Administering, managing projects;• Implementation of Primavera Contract Manager,• “Slight” Modification of BNL Procedures to incorporate
experiences• Experience with CM scheduling and estimating methods• Experience with claims prevention and mitigation
18 BROOKHAVEN SCIENCE ASSOCIATES
Path Forward
• Employ Lessons Learned on Site Preparation
• Start Permitting Process Early,• Recommend Site Access Control Measures to Ring Building
Contractor• Continue to Coordinate with BNL Site Operations to preclude
delays,• Keep current with BNL Procedures / Systems
• Partner with Ring Building GC to expedite mobilization and communication, to facilitate efficient resolution of issues as they will inevitably arise.