BROOKHAVEN SCIENCE ASSOCIATES
1
2014 SC PM WorkshopJuly 15-17, 2014
Brookhaven National Laboratory
Cathleen Lavelle
Diane Hatton, Joe Eng
BROOKHAVEN SCIENCE ASSOCIATES
2
One of five multi-program science labs managed by DOE-SC
Established in 1947; operated by BSA since 1998
Approximately 3,000 scientists, engineers, and support staff; 4200 facility users; 1,000 scientists visit each year
BNL operates world-class user facilities for research
Key missions in: Basic Energy Sciences Nuclear Physics Bio-medical Sciences High Energy Physics Energy Supply / Climate Change
Seven Nobel Prizes
BNL Overview
BNL at a Glance: FY 2013DOE SC - Physical Assets
• 5322 acres• 310 buildings
Human Capital• 2882 FTEs (3012 heads)• Direct/indirect: 0.59/0.41• 480 undergrad/grad students • 4134 facility users• 1377 visiting scientists
3
FY 2013 Total Lab Operating Costs: $629.9 million ($652.8)*FY 2013 Total DOE/NNSA Costs: $22.6 millionFY 2013 WFO (Non-DOE/Non-DHS) Costs: $52.5 millionFY 2013 WFO as % Total Lab Operating Costs: 8.3%FY 2013 DHS Costs: $0.8 million *including OLABS ($8.5M) and A/R Other ($14.4M)
FY 2013 Funding by Source ($M)
4
Historical Project Budget and 5 Year Project Outlook
Historical Annual Construction Budget (10 year average not including GPP/IGPP)•Line Item—$109M•MIE—$21M•Operating Expense*—$467M
Projected Annual Construction Budget (not including GPP/IGPP)•Line Item—$12M•MIE—$46M•Operating Expense*—$561M
*Operating includes all operating. Historically, operating funds associated with construction projects are not reported separately.
BROOKHAVEN SCIENCE ASSOCIATES
5
BNL Organization
BROOKHAVEN SCIENCE ASSOCIATES
6
Project Management Center Organization
Recent Change at BNL:
Provide centralized tools and standards to BNL project managers:Large Capital Asset Projects andSmall projects (tailored approach)
•Keep core staff small•Centralized Resource Pool•Process Improvement•Transfer knowledge•Support/Train Dept. resources
BROOKHAVEN SCIENCE ASSOCIATES
7
BNL’s Major Projects
Completed Projects CFN, ISB, RSLII
Ongoing Projects NSLS-II NEXT (NSLS-II Experimental Beamlines) ABBIX (Advanced Biological Beamlines)
US Atlas Upgrade Partner/Other Beamlines
Future Projects sPHENIX Electron Ion Collider
TPC greater than $20M
BROOKHAVEN SCIENCE ASSOCIATES
8
• Large Projects managed within Directorate
• Central Project Management Center (PMC) provides support, tools , systems, process, training, resources
• Institutional Risk Management Committee (IRMC)
– Comprised of Lab Director and senior management
– conducts periodic project reviews status/issues (quarterly)
– Scope, schedule, cost, ESH, procurement, staffing, risks, PM concerns
• Institutional Key Performance Parameters (IKPIs) – monitored quarterly reporting of major project performance
• Director’s Reviews in advance of DOE reviews (Internal/External) and EVMS Annual Laboratory Self Assessment
• Standardization of PM Systems and Reporting
Managing Major/MIE ProjectsLab Oversight
BROOKHAVEN SCIENCE ASSOCIATES
9
BNL Project ProjectionProjects Program Sponsor TPC ($M) &
BNL's WBS FY Start FY Finish CD-Status
NSLS-II BES $912 2007 2015 CD-3NEXT BES $90 2013 2017 CD-3ABBIX BES $45 2013 2016 CD-3 EquivOperations (NxtGen) & Partner Beamlines BES $43 2014 2017 TBDNSLS Hazadous Removal BES $5-10 2015 2016 TBD APUL HEP $12 2011 2014 CD-4ATLAS PH-I HEP ($33) $12 2014 2018 CD-1ATLAS PH-II HEP ($200) $35-45 2016 2022 TBDLARP-LHC Accelerator Luminosity Upgrade HEP ($200) $35-45 2015 2024 TBDLSST HEP ($150) $40 2013 2019 CD-3LAR1-ND (Short Base Line Exp) HEP ($13) $3 2014 2018 TBDDark Side Dark Matter HEP ($10) $2 2014 2018 TBDAccelerator Test Facility (ATF) Relocation HEP $5 2014 2017 CD-2 EquivLBNE HEP ($1,500) $50 2013 2028 CD-1 HFT NP $16 2011 2015 CD-3sPHENIX NP $50 2015 2020 TBDBLIP Raster NP $5 2014 2016 CD-3 EquivLEReC NP $10 2014 2018 CD-2 EquivElectron Ion Collider (EIC) NP TBD 2018 2026 TBDEIC Detector NP TBD 2018 2026 TBD RSL II SLI $51 2010 2014 CD-4CFR-I SLI $25-31 2016 2018 TBDCFR-II SLI $30-36 2018 2020 TBDCFR-III SLI $40-45 2020 2022 TBDCentral Computer Bldg SLI $27-33 2022 2024 TBD UESC 3rd Party $15 2014 2017 CD-3 EquivAlternative Finance Office Bldg 3rd Party $38 2017 2021 TBDPortal to Discovery 3rd Party $50 2017 2021 TBDAEGIS 3rd Party $70 2016 2019 TBD
BROOKHAVEN SCIENCE ASSOCIATES
10
• Internal/External Director’s Reviews• Advisory Committees for Project guidance• IRMC –Institutional Risk Management Committee
(Project Management Reviews)• Home grown systems that provide tools/data for
PM/CAMs ( cost estimating, Risk ID, configuration management and cost/schedule reporting).
• Central Project Management support provides tools, templates, systems, process, training, resources
What works well at BNL
BROOKHAVEN SCIENCE ASSOCIATES
11
• Applying tailored Project Management for small R&D projects – Risk based graded approach
• Communicate Lessons Learned across projects – Directorates/projects act in isolation
• Develop Project Management “track” and formal training for Project Managers
• Streamline systems – Peoplesoft/Project SW tools interfaces need to be established. IT support required.
Improvements BNL is working on
BROOKHAVEN SCIENCE ASSOCIATES
12
Backup Slides
13 BROOKHAVEN SCIENCE ASSOCIATES
BNL Manages Projects with Proven Systems and Software
Deltek Cobra™
Cost and Earned Value Management Solution
Deltek Cobra™
Cost and Earned Value Management Solution
SchedulingSoftware Financial
Management System
StandardRates & Burdens
• Burdens• Rates• Escalation
• Milestones• Critical Path• Deliverables• Resource Loading
• Authorized Funding• Commitments• Actual Costs
• Performance Baseline• Analysis• Reporting
• Fiscal Year Budgets
14 BROOKHAVEN SCIENCE ASSOCIATES
Web basedCost Estimating
(CED)
IntegratedProject Database
(IPD/IPDv2)
Web basedCost Estimating
(CED)
IntegratedProject Database
(IPD/IPDv2)
Primavera 6.2Schedule
Primavera 6.2Schedule
Cost/Schedule Baseline Development/Measurement
WBS &WBS DictionaryResources:-Labor hours-M&S $-Travel $Schedule:-Activities-Durations Risk ID & AssessmentBOE
Resources•Develop Logic/dates•Timephase resources•Milestones
ResourcesSchedule
•EV assessment•Rate Tables•Burdened Esc $
CobraCost Baseline
Reporting
Activities, Durations
Iterative Process to develop Proposed Baseline