1 BROOKHAVEN SCIENCE ASSOCIATES
Accelerator Systems Installation
F. Willeke, ASD Director6th ASAC
October 22-23, 2009
2 BROOKHAVEN SCIENCE ASSOCIATES
Outline
• Magnet Girder Integration• Installation Preparation• Installation Schedule• Installation Resource Planning• Installation Overview• Availability of Buildings• Girder Installation Details• Storage Ring Installation Logistics
3 BROOKHAVEN SCIENCE ASSOCIATES
Magnet Girder Integration
4 BROOKHAVEN SCIENCE ASSOCIATES
Girder Integration Workflow
2 Girders /months 2 girders / week
@ 18 months (incl. learning curve effect)
Starting 04-Aug-1 Finish 13-Jan-12
High precision Alignment
Preassembly
2 days
90 MP Girders, 60 Dipole Girders
5 BROOKHAVEN SCIENCE ASSOCIATES
Database Entries in Support of Installation
Quadrupole magnet
Configuration type “D”
Specification (9809)
Girder 2, Cell 1
30.25 meters from ID center
De-focussing Quad
Magnet A terminal to supply Negative terminal
Magnet B terminal to supply Positive terminal
Power supply spec type “B”, 175 Amp
252 kcmil wire required
Located in mezzanine Cell 1 rack A1
19 RU from bottom of rack
Powers magnet QL1 in cell 1
Comprehensive Information on all subsystems and their relations including connecting cables will support installation
6 BROOKHAVEN SCIENCE ASSOCIATES
Storage Ring Magnet Conventions
Example: Wiring details for Quad QL1G2C01A
• Wire type : 252 kcmil, 175 amps max 138 amps nominal• Wire starts in tunnel : 30.25 meters from Long ID center Cell 1• Wire ends in mezzanine : Cell 01 Rack A1 Height from bottom 19 RU• Connected as a de-focus quad:
• A terminal to supply negative terminal• B terminal to supply positive terminal
• Wire marking: load / source• QL1G2C01A-A / SR-PS-QBL1-C01-A1 NEG for negative voltage conductor• QL1G2C01A-B / SR-PS-QBL1-C01-A1 POS for positive voltage conductor
• Testing of wiring via traveller (QA documentation requirements)• Hipot to 2Kv prior to connection to magnet• Continuity check for wire polarity• Electrical check for magnet polarity
7 BROOKHAVEN SCIENCE ASSOCIATES
Storage Ring Electrical Utilities: Detailed Planning
Racks will be equipped on the Mezzanine
8 BROOKHAVEN SCIENCE ASSOCIATES
Civil Construction Sequence
9 BROOKHAVEN SCIENCE ASSOCIATES
Installation Overview
Building BOD Installation Activity Start DatePentant 1*) 1-Feb-11 SR Components 20-Jun-11
Pentant 1 1-Feb-11 SC RF Cavities 21-Sep-12
RF Bld 23-May-11 RF Power Systems & Cryog’s 29-Mar-12
Inj. Bld 18-May-11 Booster RF Cavity 21-Jun-11
Inj. Bld 18-May-11 LINAC 18-Oct-11
Inj. Bld 18-May-11 Booster 08-Jun-12
Pentant 2 02-May-Jun SR Components 20-Oct-11
Pentant 3 27-Sep-11 SR Components 14-Feb-12
Pentant4 28-Nov-11 SR Components 16-Apr-12
Pentant 5 09-Feb-12 SR Components 28-Jun-12
*) includes central cooling tower building and access tunnels
10 BROOKHAVEN SCIENCE ASSOCIATES
Installation Overall Plan
• LINAC Installation: responsibility and work by vendor
• Booster Installation: responsibility of the vendor, but BNL will provide experienced and trained installation and rigging staff under a BNL installation supervisor
• Storage Ring Installation: Carried out by AS staff and
BNL rigging crews, 50% will be temporary labor
11 BROOKHAVEN SCIENCE ASSOCIATES
12 BROOKHAVEN SCIENCE ASSOCIATES
Planned Resources
50 FTE planned this needs reassessment
13 BROOKHAVEN SCIENCE ASSOCIATES
Even Cell Girders
G3 G5 G6G2 G4
G1
Black border indicates an even cell
ID Section
14 BROOKHAVEN SCIENCE ASSOCIATES
Odd Cell Girders
G1
G3 G5 G6G2 G4
ID Section
Water manifolds are shown schematically as
a double red line (Aluminum)
a double green line (Copper)
Red border indicates an odd cell
15 BROOKHAVEN SCIENCE ASSOCIATES
Typical cell rack groups
BlueBlue border indicates a rack group 22, 33, or 44 racks wide
Cable tray is shown schematically as a double dashed line
G3 G5 G6G2 G4
16 BROOKHAVEN SCIENCE ASSOCIATES
The first slice; Pentant 1 plus…
17 BROOKHAVEN SCIENCE ASSOCIATES
Dolly assembly is removed from girder with air casters inflated
Blocks are positioned at sides of floor mounting plates
Note: Threaded support shafts and hardware will not be installed at this stage
Installation of Magnet Girders
18 BROOKHAVEN SCIENCE ASSOCIATES
Girder Transport in the Tunnel
Used for RHIC
New models
19 BROOKHAVEN SCIENCE ASSOCIATES
“Stearman” Type Dolly system components
The dolly system includes “Stearman” Dolly components rated at 9000# and 13,500#
Expected girder weight is 17,000#
MODEL ST-8MAXIMUM LOAD CAPACITY: 13,500 LBS. (SAFETY FACTOR = 1.5)
Number of Wheels Weight Height Width Depth
Swivel Pad Diameter
Distance from center of swivel pad to handle
Handle Length
Roller Dimensions
8 91 lbs. 4.25" 23.5" 19.5" 6.625" 12" 45" 3.25" x 3.25"
MODEL RT-3MAXIMUM LOAD CAPACITY: 4,500 LBS. (SAFETY FACTOR = 1.5)
Number of Wheels Total Weight Height Width Pad Diameter Roller Dimensions
3 73 lbs. 4.25" 18" 6.625" 3.25" x 3.25"
20 BROOKHAVEN SCIENCE ASSOCIATES
Pentant 1 installation Zones
24 25 27 2823
Experimental floor
Tunnel
24 25 26 2722
Mezzanine
23
26
Service Building
21 BROOKHAVEN SCIENCE ASSOCIATES
Storage ring Pentant 1 installation: Week
24 25 27 2823
Exp’l floor
Tunnel
Service Building
24 25 26 2722
Mezzanine
23
Status:
~ 1/3 of material in building
Installation starting
26
2
Activities:
•Prepare tunnel
•Stage components on floor
•Start cable tray on mezzanine
22 BROOKHAVEN SCIENCE ASSOCIATES
Storage ring Pentant 1 installation: Week
24 25 27 2823
Exp’l floor
Tunnel
Service Building
24 25 26 2722
Mezzanine
23
Status:
Most material in building
Installation on mezzanine
Begin in tunnel
26
4
Activities:
•Stage components on floor
•Start racks on mezzanine
23 BROOKHAVEN SCIENCE ASSOCIATES
Storage ring Pentant 1 installation: Week
24 25 27 2823
Exp’l floor
Tunnel
Service Building
24 25 26 2722
Mezzanine
23
Status:
Most material in building
Installation on mezzanine
Installation in tunnel
26
6
Activities:
•Tray and manifolds in place in tunnel
•Racks well underway
•Stage cable and start pulling
24 BROOKHAVEN SCIENCE ASSOCIATES
Storage ring Pentant 1 installation: Week
24 25 27 2823
Exp’l floor
Tunnel
Service Building
24 25 26 2722
Mezzanine
23
Status:
Multipole girder installation
26
8
Activities:
•Begin Girder installation
•Start populating racks
•Begin Utility installation in SB
25 BROOKHAVEN SCIENCE ASSOCIATES
Storage ring Pentant 1 installation: Week
24 25 27 2823
Exp’l floor
Tunnel
Service Building
24 25 26 2722
Mezzanine
23
Status:
Half way in schedule
26
10
Activities:
•Girder installation
•Populating racks
•Utility installation in SB
26 BROOKHAVEN SCIENCE ASSOCIATES
Storage ring Pentant 1 installation: Week
24 25 27 2823
Exp’l floor
Tunnel
Service Building
24 25 26 2722
Mezzanine
23
Status:
Most wiring pulled
Process utilities connected
26
12
Activities:
•Girder installation
•Populating racks
•Terminating cables
27 BROOKHAVEN SCIENCE ASSOCIATES
Storage ring Pentant 1 installation: Week
24 25 27 2823
Exp’l floor
Tunnel
Service Building
24 25 26 2722
Mezzanine
23
Status:
About ¾ through schedule
26
14
Activities:
•Girder installation
•Racks populated
•Terminating cables
28 BROOKHAVEN SCIENCE ASSOCIATES
Storage ring Pentant 1 installation: Week
24 25 27 2823
Exp’l floor
Tunnel
Service Building
24 25 26 2722
Mezzanine
23
Status:
About ½ vacuum complete
26
16
Activities:
•Girder installation
•Cable pulls all done
•Testing underway
29 BROOKHAVEN SCIENCE ASSOCIATES
Storage ring Pentant 1 installation: Week
24 25 27 2823
Exp’l floor
Tunnel
Service Building
24 25 26 2722
Mezzanine
23
Status:
About 2/3 vacuum complete
26
18
Activities:
•Girder installation
•Cable pulls all done
•Testing underway
30 BROOKHAVEN SCIENCE ASSOCIATES
Storage ring Pentant 1 installation: Week
24 25 27 2823
Exp’l floor
Tunnel
Service Building
24 25 26 2722
Mezzanine
23
Status:
All equipment in place
System testing underway
26
20
Activities:
•final utility connections
•equipment shakeout
31 BROOKHAVEN SCIENCE ASSOCIATES
32 BROOKHAVEN SCIENCE ASSOCIATES
Conclusion
• Magnet Girder Integration re-planned: is the backbone for the installation activity
• Installation of utilities on the mezzanine and cabling well planned making use of the equipment relational data base
• Installation schedule has recently been re-optimized and aligned with building schedule
• Resource for installation still need to be revised and optimized, concern is large number of temporary staff (~30)
• Installation logistics, intermediate storage and space management well advanced
• Conclusion: Installation Planning is very advanced