01 Overview of demolition works
Transcript of 01 Overview of demolition works
01 Overview of demolition works
The Our Hospital Project is a once-in-a-generation project that will deliver a fully integrated, 21st century health care facility. The project will be an integral part of the local community and will give patients greater choice and access to, and provision of, quality and efficient services that will enhance the overall health and well-being of Islanders.
This exhibition provides an overview of the information related to the demolition works as part of the Our Hospital Project, including the phasing and timeline, buildings to be demolished, site access and traffic management, environmental management, and ways in which neighbours and the Our Hospital Project team will continue to communicate and engage.
We are sharing this information in advance of our Planning Application submission, which is anticipated to be submitted at the end of July 2021, to demolish those buildings on the existing Overdale Hospital site which are already in Government of Jersey (GOJ) ownership. For the full Planning Application Overview, visit: ourhospital.je/timeline
Design and Delivery Partner
Town Planning Public Consultation
Overdale Hospital
Lead Architects Landscape Architects
Consultant Engineers
Project background
Project team
02 Phasing and timeline
Phase 2
Phase 1
Phase 3
2021 MID 2021
We are here
EIA screening
Overdale demolition
extent confirmed
Planning application submitted
Planning approval
Key project milestone
Community consultation
Proposed demolition milestones
Transport and Asbestos Refurbishment & Demolition
(R&D) surveys
Initial site
set-up
2022
Asbestos removal
First phase demolition
commences
Clinical services begin
migration to the former Les
Quennevais School
MID 2022
Demolition of remaining
buildings
Demolition works indicative timeline
ourhospital.je/community
The demolition work on the existing Overdale Hospital site is planned to start in the first quarter of 2022. We will first safely remove any asbestos from site, and then follow through with the phased demolition. A total of 20 buildings within the Overdale Hospital site are due to be demolished. The demolition phases are defined based on the current usage of the building and how readily the services being provided within them can be relocated to the former Les Quennevais School building in St Brelade.
03 Buildings to be demolished
Temporary perimeter fencingSolid perimeter fencing (approximately 2.5 metres high) around the entire site boundary (the thin purple in the above diagram) will be progressively installed, to replace the temporary site set-up perimeter fence, which is currently in situ.Due to the nature of the site, it is proposed to erect higher perimeter fencing closer to the Crematorium as shown by the thick purple line in the above diagram. This fence will be approximately 4 metres in height (see indicative image to the right).
Not included in this planning application
Perimeter fencing example for Crematorium interface
Westmount Centre (16)
Kitchens (4) OT Store (5)
Substation (20)
Secker House (2)
Porters’ Lodge (15)Laundry and Boiler House (12)
Admin 1 Building (8)
Existing condition photos
ourhospital.je/community
1
2
3
47
8
6
5 17
18
16
20
1915
14
1311
12
109
Phase 11. McKinstry2. Secker House3. Jessie Scott4. Kitchens5. OT Store6. Poly-tunnels/Greenhouse7. Carpenters’ workshop8. Admin 1 Building
Phase 29. Eva Wilson & Diabetic Centre10. Child Development Centre11. Hearing Resource Centre12. Laundry & Boiler House13. Admin 3 – Psychology14. Old Chapel15. Porters’ Lodge
Phase 316. Westmount Centre17. William Knot18. Poplars Day Centre19. The Lodge20. Sub station
04 Site access and traffic management
Traffic managementDue care shall be taken to ensure that the public highway is kept clean of site waste materials. Waste materials shall be stored securely and subsequently loaded for removal within the defined demolition phase boundary.
During demolition Phases 1-2, contractors will adhere to strict site rules to ensure that hospital traffic remains free-flowing and functional – allowing staff and patients
to continue to utilise Overdale Hospital services with minimal impact.
Qualified Banksman will marshal all vehicles on site. All vehicles leaving the site will be required to wash their wheels prior to exiting. For the safety of all on-site, vehicular and pedestrian segregation will be strictly enforced.
Access and egress routesThroughout the three phases of demolition, we do not anticipate any disruption in traffic flow for surrounding residents. The traffic management plan will be displayed on a notice board, on site, and will be kept up to date to reflect any changes required as a result of other activities and conditions in the vicinity (e.g. other roads works).
Construction traffic will access the site through the existing entry and egress through the existing exit points at the Overdale site (shown with the blue dotted line in the diagram below).
Movement of traffic, including deliveries and waste removal, will be carefully managed to avoid peak periods. Covered lorries will transport materials away from site, to the waste recycling centre at La Collette, via the route, shown on the map opposite.
ourhospital.je/community
Site Entrance
Site Exit
Area 1 Exit
Area 2 Exit Area 2 Entrance
Phase 2
Phase 1
Phase 3 OUT
IN(site entrance)
(site exit)
Area 1 Entrance
Transport route from Overdale to La Collete
Transport route from La Collette to Overdale
05 Environmental management
ourhospital.je/community
Minimising construction impactsRoK FCC JV are committed to being good neighbours and will carefully manage the environment in and around the site, during the demolition with care.
All works will be contained and carried out behind solid fencing, and we will employ the most suitable techniques, equipment and processes to minimise impact and disruption:
• Dust will be minimised using water spray, as and when required. All reasonable measures will be taken during construction works to contain demolition materials within the site, e.g. regular road-sweeping on-site and of surrounding roads, effective traffic management, covered-lorries removing demolition materials away from site and vehicle wheel-washing before exiting the site. Should any odours arise from the demolition, they will be suppressed by a misting system.
• Noise will be minimised by using modern, silenced and muffled equipment, which will be located and oriented away from sensitive areas. Noise monitoring equipment will be utilised in sensitive areas as required. Operatives, contractors and visitors are to wear suitable protective equipment in the established, hearing protection zones – which will be clearly signposted.
• Vibration control will be achieved by using modern, low-vibration plant available for the task.
Any noise-generating works will be contained during 08:00 - 18:00 Monday to Friday and 08:00 - 13:00 Saturday, with regular breaks and intervals in between.
Further details will be included in the planning application submission.
View of Val AndreView of existing Oak Tree on site
Ecological considerationsThe team are also taking a range of ecological considerations into account to ensure that any impacts from the proposed demolition works are mitigated.
All works will be sensitively timed to minimise the impact to surrounding flora and fauna, for example the presence of roosting bats in any of the proposed buildings or any possibility of nesting birds on site.
Inspections will be carried out to confirm the presence of roosting bats and nesting birds in any of the proposed buildings or in close proximity, and appropriate mitigation and compensation measures implemented in advance of any works.
Tree protectionA tree survey was conducted to identify, label and categorise all the trees across the existing Overdale site according to its life expectancy and quality.
The survey data informs which trees need protection throughout the entire construction project and helps formulate a Root Protection Plan.
In the demolition plan, all the trees and shrubs in the demolition zone will be retained.
06 Ongoing engagement and next steps
ourhospital.je/community
Your Feedback
Please provide feedback for the Demolition Works exhibition. There is an online feedback form at:ourhospital.je/community
To ensure that your formal feedback is given due consideration prior to the planning application submission, you will need to submit it no later than Friday 9 July 2021, 17:00.
Next Steps
Following the submission for the demolition planning application, you can comment on the application by sending your thoughts to the planning authority within 21 days of the application first being publicised.
If you have any further questions on this process, please email the team at:[email protected]
Feedback and next stepss
Communicating with our neighbours
In addition to the ongoing community consultation programme, RoK FCC JV are keeping Islanders informed of planned works, via the Our Hospital Project website, social media channels and email communications. If you are a direct neighbour we will also provide letter drop communications on any planned works to ensure you are informed and kept up-to-date.During the demolition works the contractors will be required to monitor a telephone line, in and outside of working hours, so that any unwelcome or unexpected occurrence can be reported and dealt with.If you have any questions or concerns, please call the Our Hospital Project Office on 01534 481297, Monday to Friday 09:00 - 17:00, or email: [email protected]
Sign up for project updates
We welcome your ideas, thoughts or comments on Our Hospital Project.
As well as our project email and website, you can also call us during office hours on:
01534 481297
Share your ideas
For further information please visit:
ourhospital.je/ community
You can also follow us on:@OurHospitalJSY@OurHospitalJSYOur Hospital Jersey
Get in touch
If you would like to join our e-distribution list or are interested in attending future meetings, please contact us at [email protected]
If you know of groups who would like to access this information in another language, please share their details so we can get in touch.