MEP Works Overview

14
MEP WORKS OVERVIEW

description

MEP Overview

Transcript of MEP Works Overview

Page 1: MEP Works Overview

MEP WORKS

OVERVIEW

Page 2: MEP Works Overview

MEP MECHANICAL ELECTRICAL PLUMBING

Page 3: MEP Works Overview

Projects

Needs tender drawings to be submitted to authority having jurisdiction for reviewing and approving so the owner can start his project.

MEP PREPARING AND DESIGNING STAGE

Page 4: MEP Works Overview

Consultants

Prepares tender package for the owner of the project.

Tender package Contains:

design drawings

Bill of quantity (BOQ)

Vendor list

Method of measurements

specification

MEP PREPARING AND DESIGNING STAGE

Page 5: MEP Works Overview

MEP TENDERS

Tender work

The owner searching for a contractor with the lowest cost and best technicalities.

So all possible contractors submits there offers with two component:

Financial offer

Technical offer

And this is up to the contractor

Page 6: MEP Works Overview

MEP APPROVALS

Page 7: MEP Works Overview

MEP APPROVALS

Page 8: MEP Works Overview

MEP APPROVALS

• Material approval

All suppliers and manufacturers of any thing (technical offer).

• Shop drawing approval

Submitted from the contractor to the consultant for reviewing and approving

Page 9: MEP Works Overview

MEP APPROVALS

Page 10: MEP Works Overview

By the contractor

1.Supplying

2.Material inspection request MIR

3.Storing

4.Installation

5.Inspection requests IR

MEP SITE WORKS

Page 11: MEP Works Overview

By the contractor

1.Supplying

MEP SITE WORKS

Page 12: MEP Works Overview

MIR

Submitted by the contractor to the consultant for being sure that each peace is just like the approved materials in the technical offers.

IR

By the contractor to the consultant after installation to review and be sure that the installations are just like approved shop drawings.

Consultant work in site is called supervision.

MEP SITE WORKS

Page 13: MEP Works Overview

After finishing all the systems in the project the contractor hands it over to the owner with the approval from the super visor.

And from this a guarantee and maintenance year starts.

MEP HAND OVER

Page 14: MEP Works Overview