Post on 01-Jan-2017
Method Statement Esprit Control Equipment Rail 350 Installation
Document revision history for Esprit Installation Method Statement
Version Date Comments/Amendments Main author
1.0 26/01/2015 Initial document release Andrew Moon
1. Background This method statement has been prepared by EA Technology Limited, to provide the
instructions that should be followed in order to connect the Rail 350 Power Quality Monitor to
the Esprit control and monitoring equipment within a low voltage substation.
2. Introduction This method statement defines the principles that should be followed in order to connect the
Rail 350 equipment1.
All equipment should be installed DEAD when possible and LIVE only when it is safe to do
so and if justified by a written risk assessment.
Where appropriate, instruction for the installation of equipment will be specific to the chosen
location. The following generic instructions regarding installation will generally apply.
3. Management of Safety The following requirements will be complied with at all times throughout the installation
process.
1. Safety rules and other procedures must be followed whilst undertaking work in
accordance with this work instruction. The following documents are particularly relevant
and must be adhered to at all times:
Safety precautions and procedures applicable to low voltage systems as detailed in
the relevant DNO operational safety rules.
When work is to be undertaken in proximity to live LV conductors it is necessary to
justify this decision. A risk assessment complying with the relevant DNO policy is
therefore required.
2. Prior to commencing work a full assessment of risk will be undertaken in accordance
with DNO Injury Prevention Process. This will include a stage one assessment in
advance of work commencing and a stage two on site assessment which shall be
undertaken prior to work commencing. This assessment must be agreed by all members
of the working party and signed off accordingly.
3. The working party will consist of at least two persons who will be appropriately
authorised to undertake the proposed installation work in accordance with DNO
Operational Safety Rules.
4. System control will be advised prior to work starting and upon completion of the work.
5. Personal Protective Equipment will be worn in accordance with the relevant DNO Health
and Safety policy.
4. General Requirements for Installation This method statement provides details regarding how to install Rail 350 equipment safely in
ground mounted distribution sub stations. It focuses on the methods to be followed in order
to make the necessary current connections via current transformers into the rail 350 unit and
1 For the purposes of this document, relating to the installation of the equipment on the trial networks of the My Electric Avenue project, the Rail 350 equipment comprises the IP65 rated cabinet containing the Rail 350 Power Quality Monitor along with the external connections for load monitoring and power supply.
Monitor Controller. This method statement provides guidance regarding the positioning of
Rail 350 equipment within distribution substation.
The below installation instructions shall be followed. Some site specific modifications may be
required.
1.1. Rail 350 equipment, specifically the Rail 350 enclosure, will always be installed as
close to the Esprit Monitor Controller as possible.
1.2. Current References – All 3 phase2 (no neutral) current values will be obtained by
using fully insulated sensing transducers (Current Transformers). The sensors will
be installed around the cable connections at suitable locations as close as
practically possible to the Rail 350 enclosure.
1.3. Where a generic installation instruction is to be followed, a full assessment of
options for the connection of current sensors will be made prior to any work
commencing.
1.4. Prior to work commencing, a visual inspection of the connection points will be
carried out with particular attention being made to positions where current sensors
are to be installed. If there is any doubt regarding the condition of the connection
point, work shall not commence and the issue shall be referred to the person
responsible for instructing the installation.
5. Order of Installation The order of installation and connections will be the same in each case:
1. Detailed visual Inspection 2. Cable routes and ducting prepared and installed or existing routes identified. 3. Power off Esprit enclosure by disconnecting commando socket 4. Additional cable entry holes to be drilled and prepared with glands in MC enclosure
bottom plate 5. Power supply connections to be made through the Esprit Monitor Controller power
supply terminals 6. Connection of CTs to cables and Rail 350 Unit 7. Esprit unit commando plug connected to Power supply socket (of 3)
The work required for each of the steps and the options available are described in the next sections. The order that the cables should be connected can be summarised as follows.
1. Connect the Rail 350 5 core flex earth to the topside terminal block within the MC enclosure
2. Connect the Rail 350 5 core flex N, L1, L2 and L3 cables to the topside terminal block within the MC enclosure. Connect the neutral first, then the three phases. Do not connect the commando socket at this stage
3. CTs are to be installed 4. CTs are to be made off to the Rail 350 enclosure 5. Connect the supply commando plug and socket after all works have been completed
2 Where CTs cannot be placed around all 3 phase connections then they shall be connected in order of priority to be confirmed on a site-by-site basis by the EA Technology on-site representative.
6. Detailed Visual Inspection In addition to the requirements detailed in sections 3 and 0 a visual inspection shall be
carried out:
1. A detailed visual inspection shall include:
Cables and connection methods; this shall include the inspection of all cable
cores to identify any damage/ breakdown of insulation and overheating issues.
Inspection of abnormal connections.
2. Where an unsafe situation is identified all work on site will cease and appropriate
repairs will be instigated. No monitoring equipment will be installed until repairs have
been completed and any unsafe situation has been rectified.
3. Wherever possible the enclosure for the Rail 350 unit will be fixed in its permanent
position before installation of the associated connections commences.
Care should be taken to ensure that any equipment installed will not interfere with or prevent the safe operation of any equipment related to the distribution board.
7. On-site Civil Installation Works 1. The Rail 350 enclosure shall be positioned such that the distance between the MC
and the Rail 350 enclosure is minimized.
2. Position of Rail 350 – To ensure that no trip hazard is introduced, the Rail 350
enclosure should be placed at a suitable location within the building and securely
fixed to a wall.
3. All cables (power supply, current measuring etc.) exiting the equipment will be
protected using suitable flexible ducting or conduits or other similar materials.
It is important that the cable access route shall be installed at a practical position,
where it must not obstruct or affect the operation of doors.
8. Rail 350 Power Supply Installation
Reminder - This is a Live Network, appropriate PPE must be worn at all times and only
approved insulated tools shall be used!
8.1. Rail 350 Power Supply (general).
Wherever possible existing MC enclosure terminal blocks will be used as power supply
points. The Rail 350 equipment requires power supply points one per phase and neutral
(3P+N) connection. All connection points should be connected before the commando socket
is connected to the Esprit equipment.
Figure 1 Power Supply Terminal block within MC enclosure.
8.2. Installation of Rail 350 Power Supply at the Monitor Controller Enclosure
A 5 core flex cable will be provided, which will be connected to the Rail 350 enclosure. It
should be connected to the MC enclosure terminal block in Figure 1.This should be carried
out in the sequenced outlined in Section 5. Cable entry should be through the bottom plate
on the MC enclosure pictured in Figure 2. To allow this, a new entry point should be drilled
and a gland added. Tools and glands are to be supplied by the installer. The new 5 core flex
cable within the MC should be cable tied and made secure.
Figure 2. MC Enclosure bottom plate with Rail 350 MODBUS and power supply cable. Note, gland not shown.
9. Installation of Current Transformers
A 5 core flex cable will be provided, which will be connected to the Rail 350 enclosure.
There is no set arrangement for connection of the CTs and therefore great caution should be
taken when installing these cables.
Install and secure the coil (1 per phase) in position making sure that the arrows on the coil
are pointing in the direction that the load is flowing away from the LV busbars for outgoing
cables as per the manufacturer’s instructions.
Once installed, position all coil / transducer cables in their final location – in line with
manufacturer’s instructions.
Run all cables through the pre- prepared cable access route / duct from the original Esprit
installation.
Coils are to be positioned so as not to block the removal or replacement of cable fuse-links,
minimise strain on connections, and to avoid locations where cables could be abraded or
otherwise damaged.
If installed around cable crutches etc., the cable must first be inspected to confirm its
integrity and stability.
Cable cores may only be flexed or moved using very gentle force, and connections at the
points where the cable cores are made off should be inspected afterwards to ensure that
cable remains intact and correctly fixed.
10. Installation of MODBUS Cable
Figure 3. Nortech EV10 with MODUS RS485 port (green).
A 3 core MODBUS cable will be provided, which will come connected to the Rail 350
enclosure. It should be connected to Envoy EV10 MODBUS input block in Figure 3. MODUS
terminal numbers are prewired, but may need to be rewired following gland installation. An
EA representative will provide instruction. Cable entry should be through the bottom plate on
the MC enclosure pictured in Figure 2. To allow this, a new entry point of appropriate size
should be drilled and a gland added. The new 3 core MODBUS cable, within the MC, should
be cable tied and made secure.
11. Supply of Equipment
All specialised equipment will be supplied by the MEA team. All signage and risk assessments when under operation is the responsibility of responsible person onsite. All other ancillary equipment is to be supplied by IDEC or SSEC in NPG and SSEPD area respectively.
Appendix I
Esprit Monitor Controller
The Monitor Controller is connected to the LV mains electricity network, close to the
distribution board. The unit monitors the current on each of the three phases & can make
intelligent decisions about the distribution network – issuing commands, via PLC, to
connected Intelligent Control boxes.
The external enclosure dimensions of the Monitor Controller are: (WxDxH) 320x230x85mm.
Figure 4 Esprit Monitor Controller (v1.2) mounting points (marked by arrows)
Top
Bottom
p
Figure 5. Rail 350 enclosure.
Figure 6. Esprit Enclosure with Rail 350 equipment installed.