ENVIRONMENTAL IMPACT ASSESSEMENT /
ENVIRONMENTAL MANAGEMENT PLAN REPORT
ALONG WITH FORM- I, FORM- IA, CONCEPTUAL PLAN
AND ANNEXURE
(FOR ENVIRONMENTAL CLEARANCE)
RESIDENTIAL PLOTTED COLONY
(102.70 Acres)
at
VILLAGE NAURANGPUR, SECTOR- 78 & 79, DISTRICT -
GURGAON, HARYANA
APPLICANT ENVIRONMENTAL CONSULTANT
M/S REVITAL REALITY PVT LTD
1114, 11th floor, Hemkunth Chambers, 89, Nehru Place, New Delhi
Email: ashokvardhan@supertechlimited.com
VARDAN ENVIRONET QCI/NABET ACCREDITED
S. No. 158 D-142, Sushant Lok- III, Sec- 57,
Gurgaon- 122001 E-Mail: vardanenviro165@gmail.com Phone No.: 9971684812; 9899651342
mailto:vardanenviro165@gmail.com
INDEX
S. No. Particulars Page No.
1 Form I 1-16 2 Form I A 17-39 3 Conceptual Plan 40-82 4 Terms of Reference issued by MoEF & CC 83-87 5 Compliance of Terms of Reference 88-91
EIA Report
6 Chapter- 1 (Introduction) 1-7 7 Chapter-2 (Project Description) 8-36 8 Chapter-3 (Description of Environment) 37-97 9 Chapter-4(Anticipated Environmental Impacts & Mitigation Measures) 98-112
10 Chapter- 5 (Specific Studies) 113-122 11 Chapter- 6 (Environmental Monitoring Program) 123-126 12 Chapter- 7 (Additional Studies) 127-140 13 Chapter- 8 (Project Benefits) 141-142 14 Chapter- 9 (Environmental Management Plan) 143-149 15 Chapter- 10 (Summary and Conclusion) 150-155 16 Chapter- 11 (Disclosure of Consultant) 156-157 17 Chapter- 12 (Corporate Environmental Responsibility) 158-159
Annexures 1. License from DTCP 160 2. Board of Resolution 187 3. Perspective View of the project 189 4. Accreditation certificate of consultant from QCI/NABET 191 5. Affidavit from Project Proponent 193 6. NOC from forest Divisional Forest Officer, Gurgaon 203 7. Assurance for power supply DHBVN 205 8. Assurance for water supply 207 9. Receipt of External Development Charges paid to HUDA 209 10. Baseline Data (Lab Analysis Reports) 212 11. NOC from Administrator HUDA for supply of treated water for construction
purpose 222
12. Site Photographs 224 13. Electrical Standards and Codes 226 14. Health, Safety and Occupational Measures 231 15. Mitigation measures to control green house effect. 233 16. Codes of Earthquake 235 17. Risk Assessment Plan 237 18. Codes of Fire Fighting 240 19. Geo-Technical Investigation Report 244 20. Buffer Map of 2 km 282 21. Landscape Plan 284 22. Layout Plan 286 23. Service Layout Plan 288 24. Parking cum Traffic Circulation Plan 290 25. Undertaking regarding additional ToR Points 292
RESIDENTIAL PLOTTED COLONY M/S REVITAL REALITY PVT. LTD. VILLAGE- NAURANGPUR, SECTOR-
DISTRICT- GURGAON, HARYANA
Prepared by: Vardan EnviroNet, Gurgaon
(I) BASIC INFORMATION
S.No. Items
1 Name of the Project
2 Serial No. in schedule
3 Proposed capacity/area/length/tonnage to be
handled/command area/lease area/number of
wells to be drilled
4 New/Expansion/Modernization
5 Existing capacity/Area etc.
6 Category of project
7 Does it attract the general
please specify
8 Does it attract the specific
please specify
9 i) Location of unit
ii) Plot, Survey No, Khasra No.
- 78 & 79,
Prepared by: Vardan EnviroNet, Gurgaon
Details
Residential plotted colony
M/s Revital Reality Pvt. Ltd.
8(b) Township & Area Developement P
Notification 14/9/2006
Proposed capacity/area/length/tonnage to be
handled/command area/lease area/number of
Total Plot Area [415612.154 m2 (102.70 Acres)
Net Plot Area [3, 77, 805.80 m2 (93.3583 Acres)
Total Built Up Area = 443997.81 m
Total Ground Coverage : 107292.3405 m
Total FAR : 2, 99, 157.422 m2
New/Expansion/Modernization New
Not Applicable
B
Does it attract the general condition? If Yes, No
Does it attract the specific condition? If Yes, No
Khasra No.
Village- Naurangpur, District
18/1, 14, 15, 16, 23/2, 24, 25, 21/1, 4/2, 27, 17, 21/2, 21/2,
21/1, 21/3, 21/4, 21/5, 24/1, 1, 2, 24, 3, 8, 13/1, 14, 17, 7, 5/2,
6/1, 114, 113, 19, 21/2, 22, 23, 1, 10/1, 3, 18, 2/1 , 1,
15/1, 11/1, 6, 15/2, 10, 11/3, 10/2, 6/1, 11
25/1, 4, 5/1, 7/3, 27, 2/1/1, 2/2/1, 2/3/1, 9/2, 12/1,
18/2/1, 4/3/1, 4/2, 14/2, 15/1, 6/3, 25/2, 5/2, 6/2, 21,
12, 19, 20/1, 2/1, 9/1, 10/1, 1/3, 1/2, 9/2, 1/1, 18/1,
22, 23/1, 4, 6, 7/1, 15, 10, 11/
17/2, 1/2, 2, 10/1, 4/1, 3, 8/2, 9, 12/1, 13, 19/1,
10/3/2, 11/1/1, 6/2, 7/1, 11, 13/1, 9/2, 8, 9/1,
13/2, 15/2, 17, 18, 19/1, 22/2, 4, 14, 15/1,
10/2, 19/2, 22/1, 21, 11/1, 20/1, 20/2, 15,
FORM-1
Page 1
Township & Area Developement Projects as per MoEF
415612.154 m2 (102.70 Acres)]
3, 77, 805.80 m2 (93.3583 Acres)]
443997.81 m2
107292.3405 m2
2
, District- Gurgaon
18/1, 14, 15, 16, 23/2, 24, 25, 21/1, 4/2, 27, 17, 21/2, 21/2, 20,
21/1, 21/3, 21/4, 21/5, 24/1, 1, 2, 24, 3, 8, 13/1, 14, 17, 7, 5/2,
6/1, 114, 113, 19, 21/2, 22, 23, 1, 10/1, 3, 18, 2/1 , 1, 7/1, 11/2,
15/1, 11/1, 6, 15/2, 10, 11/3, 10/2, 6/1, 11/2, 15/3, 16, 24/2,
25/1, 4, 5/1, 7/3, 27, 2/1/1, 2/2/1, 2/3/1, 9/2, 12/1, 18/1/1,
18/2/1, 4/3/1, 4/2, 14/2, 15/1, 6/3, 25/2, 5/2, 6/2, 21, 25, 5, 11/3,
12, 19, 20/1, 2/1, 9/1, 10/1, 1/3, 1/2, 9/2, 1/1, 18/1, 7/2, 14, 18/2,
22, 23/1, 4, 6, 7/1, 15, 10, 11/1, 22, 19, 20/1, 20/2, 16, 17/1,
4/1, 3, 8/2, 9, 12/1, 13, 19/1, 11/2/1, 6/2, 15/4,
10/3/2, 11/1/1, 6/2, 7/1, 11, 13/1, 9/2, 8, 9/1, 12/1, 6/2, 7, 12/2,
13/2, 15/2, 17, 18, 19/1, 22/2, 4, 14, 15/1, 16/2, 23, 24, 11/1,
21, 11/1, 20/1, 20/2, 15, 16, 25, 6/2, 4/2, 5, 6/2,
RESIDENTIAL PLOTTED COLONY M/S REVITAL REALITY PVT. LTD. VILLAGE- NAURANGPUR, SECTOR-
DISTRICT- GURGAON, HARYANA
Prepared by: Vardan EnviroNet, Gurgaon
iii) Village
iv) Tehsil
v) District
vi) State
10 Nearest Railway station/Air
distance in kms.
11 Nearest town, City, Distt. Head Quarter
with distance in kms.
12 Village Panchayat, Zila P
Corporation, Local body(Complete postal
addresses with telephone nos. to be given)
13 Name of Applicant
14 Regd. Address
15 Address for correspondence(1):
Name
Designation
Address
Pin Code
E mail
Telephone
Mobile
Fax No.
Address of correspondence(2):
- 78 & 79,
Prepared by: Vardan EnviroNet, Gurgaon
7/1, 14/1/2, 15/1, 16/2, 2/2, 9/1, 12/2,
11/2/2, 20/2/1
Village- Naurangpur, District
-----
Gurgaon
Haryana
Airport along with Garhi Harsaru Jundction Railway Station
North -West
Distt. Head Quarter along Manesar Approx. 3.2 Km, Sou
Parishad, Municipal
Local body(Complete postal
addresses with telephone nos. to be given)
Municipal Corporation
Opposite General Civil Hospital
Gurgaon- 122001, Haryana
Phone: 18001801817
Email: contact@mcg.gov.in
M/s Revital Reality Pvt. Ltd.
1114, 11th Floor, Hemkunth Chambers, 89, Nehru Place, New
Delhi-19
Address for correspondence(1): M/s Revital Reality Pvt. Ltd.
1114, 11th Floor, Hemkunth Chambers,
89, Nehru Place, New Delhi-
Mr. A.shok Vardhan Singh
Authorized Signatory
Supertech House, B 28-29, Sector
201307
as.khurana@supertechlimited.com
record@supertechlimited.com
0120-4572600
+91 - 8588837646
0120-466991
Address of correspondence(2): Environment Consultant
M/s Vardan EnviroNet
(Accredited from QCI/NABET)
D-142,SushantLok-III, Golf Course Extension Road,
Gurgaon, Haryana
FORM-1
Page 2
7/1, 14/1/2, 15/1, 16/2, 2/2, 9/1, 12/2, 3/1, 4/1/1, 10/2/1, 11/1/2,
Naurangpur, District- Gurgaon
Garhi Harsaru Jundction Railway Station Approx. 10 km in
South-Wast
Opposite General Civil Hospital
, Haryana
Floor, Hemkunth Chambers, 89, Nehru Place, New
Floor, Hemkunth Chambers,
-110019
29, Sector-58, Noida
as.khurana@supertechlimited.com
record@supertechlimited.com
(Accredited from QCI/NABET)
Golf Course Extension Road,
RESIDENTIAL PLOTTED COLONY M/S REVITAL REALITY PVT. LTD. VILLAGE- NAURANGPUR, SECTOR-
DISTRICT- GURGAON, HARYANA
Prepared by: Vardan EnviroNet, Gurgaon
16 Detail of alternative site, if any
these sites should be shown on a topo
17 Interlinked Project
18 Whether separate application for
project has been submitted
19 If, Yes Date of Submission
20 If no , reason
21 Whether proposal involves
under: if yes, details of same and status to given
a) Forest (conservation) Act 1980?
b) Wild life protection Act 1972
c) CRZ notification 1991?
22 Whether there is any Govt. order/policy
relevant/relating site?
23 Forest land involved(hectares)
24 Whether there is any litigation pending against
the project and / or land in which is project is
proposed to be setup:
a) Name of court
b) Case No.
c) Orders/directions of Court,
its relevance with the proposed project.
(II) ACTIVITY:
1. Construction, operation or decommissioning of the Project involving actions, which will cause physical
changes in the locality (topography, land use, changes in water bodies, etc.)
- 78 & 79,
Prepared by: Vardan EnviroNet, Gurgaon
Tel No. 0124-4291036
Email: vardanenviro165@gmail.com
Detail of alternative site, if any. Location of
these sites should be shown on a topo-sheet.
This is a residential plotted colony
already been awarded by Director Town and Country Planning.
Hence, Not applicable in this case
There is not any interlinked project
Whether separate application for interlinked
Not Applicable. In view of item No. 17 above
Not Applicable. In view of item No. 17 above
Not Applicable. In view of item No. 17 above
Whether proposal involves approval/clearance
under: if yes, details of same and status to given
Forest (conservation) Act 1980?
Wild life protection Act 1972?
?
No. The unit does not fall in any notified reserved forest area
No. The proposed project
protected area.
No. The unit does not fall in any Notified coastal
zone.
Whether there is any Govt. order/policy 1. Town and Country Planning Department
2. Assurance of water supply
(hectares) No Forest land is involved in
Whether there is any litigation pending against
the project and / or land in which is project is
Orders/directions of Court, if any and
its relevance with the proposed project.
There is no litigation pending against the project and
Therefore, Information required against
applicable.
Construction, operation or decommissioning of the Project involving actions, which will cause physical
(topography, land use, changes in water bodies, etc.)
FORM-1
Page 3
vardanenviro165@gmail.com
residential plotted colony project for which license has
by Director Town and Country Planning.
this case.
There is not any interlinked project.
In view of item No. 17 above
. In view of item No. 17 above
In view of item No. 17 above
No. The unit does not fall in any notified reserved forest area.
proposed project site does not fall in any wildlife
No. The unit does not fall in any Notified coastal regulation
1. Town and Country Planning Department
Assurance of water supply from HUDA
involved in the proposed project.
There is no litigation pending against the project and land.
Information required against point a, b & c is not
Construction, operation or decommissioning of the Project involving actions, which will cause physical
RESIDENTIAL PLOTTED COLONY M/S REVITAL REALITY PVT. LTD. VILLAGE- NAURANGPUR, SECTOR-
DISTRICT- GURGAON, HARYANA
Prepared by: Vardan EnviroNet, Gurgaon
S.No. Information/Checklist
Confirmation
1.1 Permanent or temporary change in land use,
land cover or topography including increase in
intensity of land use(with respect to local land
use plan)
1.2 Clearance of existing land, vegetation and
building?
1.3 Creation of new land uses?
1.4 Pre-construction investigations e.g. bore house, soil
testing?
1.5 Construction works?
1.6 Demolition works?
1.7 Temporary sites used for construction works or
Housing of construction workers?
1.8 Above ground building, structures or
Earthworks including linear structures, cut and
fill or excavations
1.9 Underground work including mining or
tunneling?
1.10 Reclamation works?
1.11 Dredging?
1.12 Offshore structures?
- 78 & 79,
Prepared by: Vardan EnviroNet, Gurgaon
Yes/ No Details thereof (with approximate quantities/ rates,
wherever possible) with source of information data
Permanent or temporary change in land use,
land cover or topography including increase in
intensity of land use(with respect to local land Yes
Land has been allotted for
Gurgaon-Manesar Master Plan
residential plotted colony will be constructed on the
barren land of the proposed project site.
Clearance of existing land, vegetation and
Yes
There is no structure present on the
fully vacant. The existing vegetation at site
wild grasses and weeds which shall be cleared at the
time of construction. The proposed project has green
area development plan;
species shall be planted within the project area.
Yes
The proposed site is vacant
weeds. The land shall be used for the construction of
residential plotted colony
investigations e.g. bore house, soil Yes
Soil investigation was carried out and the results
were found satisfactory.
Yes
The Construction activities
the project premises; there will be no physical
outside the project boundary.
No Project site is vacant land.
required.
Temporary sites used for construction works or
No
All the construction activity including stocking of
raw materials will be confined within the project site
only. No temporary shelters for labour
Local labors from nearby area will be hired.
Sanitation facilities will be developed at site.
Above ground building, structures or
Earthworks including linear structures, cut and Yes
Excavation will be carried out for foundation of
buildings only. The excavated soil will be used in
backfilling and other area development
Underground work including mining or No
No underground work
required except excavation of earth.
No No reclamation work is
No No dredging is required.
No No offshore structure is
FORM-1
Page 4
approximate quantities/ rates,
wherever possible) with source of information data
Land has been allotted for residential purpose under
Manesar Master Plan-2031. Hence, a
colony will be constructed on the
barren land of the proposed project site.
re is no structure present on the site. The site is
The existing vegetation at site consists of
wild grasses and weeds which shall be cleared at the
time of construction. The proposed project has green
area development plan; the local and indigenous
species shall be planted within the project area.
The proposed site is vacant consisting wild grass and
weeds. The land shall be used for the construction of
olony.
investigation was carried out and the results
were found satisfactory.
onstruction activities will be confined within
the project premises; there will be no physical change
outside the project boundary.
Project site is vacant land. Hence, demolition is not
All the construction activity including stocking of
raw materials will be confined within the project site
shelters for labour are proposed.
from nearby area will be hired.
Sanitation facilities will be developed at site.
Excavation will be carried out for foundation of
The excavated soil will be used in
backfilling and other area development activities.
No underground work including mining/ tunneling is
required except excavation of earth.
is required.
required.
is required.
RESIDENTIAL PLOTTED COLONY M/S REVITAL REALITY PVT. LTD. VILLAGE- NAURANGPUR, SECTOR-
DISTRICT- GURGAON, HARYANA
Prepared by: Vardan EnviroNet, Gurgaon
1.13 Production and manufacturing processes?
1.14 Facilities for storage of goods or materials?
1.15 Facilities for treatment or disposal of solid
waste or liquid effluents?
- 78 & 79,
Prepared by: Vardan EnviroNet, Gurgaon
Production and manufacturing processes? No
No production/ manufacturing process
the proposed project is a
storage of goods or materials?
Yes
Raw material will be stored at site in a covered area.
Cement will be separately stored under cover in
bales. Sand will be stacked neatly under tarpaulin
cover. Bricks and steel will be laid in open.
treatment or disposal of solid
Yes
Solid Waste:
The solid waste generated from the project will be in
the form of:
Domestic Waste:
Approximately 9520 kg/day
estimated to be generated from the project
this will be collected from designated locations and
segregated into inorganic and organic wastes.
inorganic non-biodegradable wastes will be sold to
authorize vendors for recycling and the
biodegradable wastes will be disposed according to
MSW (Management& H
Hazardous Waste
No hazardous waste will be produced from project
activities.
Liquid effluents
During construction phase, sewage will be treated
through septic tank. The waste
phase will be treated up to tertiary level in a STP
having the capacity of
sewage will be reused for flushing
development. The rest of the treated water will be
given to the nearby construction
purpose only. Dewatered/
from the STP plant will be used as manure for
landscape development & tree plantation
FORM-1
Page 5
manufacturing process is involved as
the proposed project is a residential plotted colony.
Raw material will be stored at site in a covered area.
Cement will be separately stored under cover in
bales. Sand will be stacked neatly under tarpaulin
cover. Bricks and steel will be laid in open.
The solid waste generated from the project will be in
kg/day domestic solid waste is
estimated to be generated from the project activity;
this will be collected from designated locations and
gregated into inorganic and organic wastes. The
biodegradable wastes will be sold to
vendors for recycling and the
astes will be disposed according to
& Handling) Rules, 2000.
No hazardous waste will be produced from project
During construction phase, sewage will be treated
. The wastewater in operation
phase will be treated up to tertiary level in a STP
having the capacity of 1926 KLD and the treated
age will be reused for flushing and landscape
. The rest of the treated water will be
onstruction site for construction
Dewatered/ dried sludge generated
from the STP plant will be used as manure for
scape development & tree plantation.
RESIDENTIAL PLOTTED COLONY M/S REVITAL REALITY PVT. LTD. VILLAGE- NAURANGPUR, SECTOR-
DISTRICT- GURGAON, HARYANA
Prepared by: Vardan EnviroNet, Gurgaon
1.16 Facilities for long term housing of operational
workers?
1.17 New road, rail or sea traffic during
construction of operation?
1.18 New road, rail, air waterborne or other
transport infrastructure including new or
altered routes and stations, ports, airport etc?
1.19 Closure or diversion of existing transport
routes or infrastructure leading to changes in
traffic movements?
1.20 New or diverted transmission lines or
pipelines?
1.21 Impoundment, damming, culverting,
realignment or other changes to the hydrology
of watercourses or aquifers?
1.22 Stream crossings?
1.23 Abstraction or transfers of water from ground
or surface waters?
1.24 Changes in water bodies or the land surface
affecting drainage or run-off?
- 78 & 79,
Prepared by: Vardan EnviroNet, Gurgaon
Facilities for long term housing of operational
No
Local labour will be hired from nearby areas during
construction phase. So, t
permanent facilities for long
operational workers.
New road, rail or sea traffic during
No
The site has good connectivity to
roads, paths will be developed for vehicular
movements of construction material during
construction phase whereas internal tracks and paths
will be developed for traffic circulation (to avoid any
congestion) during operational phase.
New road, rail, air waterborne or other
transport infrastructure including new or
altered routes and stations, ports, airport etc?
No
The site is well connected through the road network.
The nearest highway is
approximately 2.7 km towards
Closure or diversion of existing transport
routes or infrastructure leading to changes in No
Since the site is well connected to NH
high traffic density; not required the
closure of existing traffic routes.
New or diverted transmission lines or No
There will not be any new/
or pipeline around the proposed project
Impoundment, damming, culverting,
other changes to the hydrology No
No impoundment, damming,
or other changes to the hydrology of surface
watercourses is proposed.
No There is no stream running across the site.
Abstraction or transfers of water from ground No
Total water requirement
include 1066 KLD for fresh water requirement &
KLD for recycled water requirement
752 KLD will be used for flushing an
be used for landscape development.
construction phase, wa
STP treated water. During operation
will be supplied through
Changes in water bodies or the land surface No
Runoff will increase due to increased paved surface.
However, increased runoff will be managed by well
designed rainwater harvesting system and storm
water management plan.
FORM-1
Page 6
will be hired from nearby areas during
construction phase. So, there will be no need to create
permanent facilities for long-term housing of
connectivity to NH-8. Only internal
paths will be developed for vehicular
movements of construction material during
construction phase whereas internal tracks and paths
will be developed for traffic circulation (to avoid any
operational phase.
The site is well connected through the road network.
The nearest highway is NH-8 at a distance of
km towards North-West.
well connected to NH-8 which has
; not required the diversion or
closure of existing traffic routes.
There will not be any new/ diverted transmission line
ne around the proposed project.
No impoundment, damming, culverting, realignment
or other changes to the hydrology of surface
watercourses is proposed.
no stream running across the site.
Total water requirement will be 1920 KLD, which
KLD for fresh water requirement & 854
KLD for recycled water requirement out of which
752 KLD will be used for flushing and 102 KLD will
be used for landscape development. During
construction phase, water demand will be fulfilled by
During operational phase, water
will be supplied through HUDA.
Runoff will increase due to increased paved surface.
However, increased runoff will be managed by well-
designed rainwater harvesting system and storm
water management plan.
RESIDENTIAL PLOTTED COLONY M/S REVITAL REALITY PVT. LTD. VILLAGE- NAURANGPUR, SECTOR-
DISTRICT- GURGAON, HARYANA
Prepared by: Vardan EnviroNet, Gurgaon
1.25 Transport of personnel or materials for
construction, operation or decommissioning?
1.26 Long-term dismantling or decommissioning
or restoration works?
1.27 Ongoing activity during decommissioning
which could have an impact on the
environment?
1.28 Influx of people to an area in either temporarily
or permanently?
1.29 Introduction of alien species?
1.30 Loss of native species or genetic diversity?
2. Use of Natural resources for construction or operation of the Project (such as land, water,
especially any resources which are non
S.No. Information/Checklist confirmation
2.1 Land especially undeveloped or agricultural
land (ha)
- 78 & 79,
Prepared by: Vardan EnviroNet, Gurgaon
Transport of personnel or materials for
operation or decommissioning? Yes
Transport of personne
and operation phase are envisaged.
space within the project site for loading and
unloading of materials will be provided.
Adequate parking space will be provided during
operational phase of the project
the premises.
term dismantling or decommissioning No
No Long term dismantling or decommissioning or
restoration work will be involved.
Ongoing activity during decommissioning
which could have an impact on the No
No decommissioning activity is
impact on the environment by the proposed project
supposed.
in either temporarily
No
Local laborers from nearby area will be employed
during the construction phase. In the operation phase,
most of the expected occupants will be from the
surrounding areas. Hence, the project will lead to a
redistribution of occupants within the city. Thus, no
significant influx of people is envisaged.
No
The landscaping will be carried out with mainly local
species with a few ornamental varieties of flora that
are well suited to the local conditions
Loss of native species or genetic diversity? No There will be no significant impact on the native
species or genetic diversity.
Use of Natural resources for construction or operation of the Project (such as land, water,
especially any resources which are non-renewable or in short supply):
Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/ rates,
wherever possible) with source of information data
especially undeveloped or agricultural No
Proposed site is having wild grasses which shall be
cleared and residential plotted
constructed on vacant land
plant species shall also
project site.
FORM-1
Page 7
el/ material during construction
are envisaged. Adequate parking
space within the project site for loading and
unloading of materials will be provided.
Adequate parking space will be provided during
operational phase of the project for the residents of
No Long term dismantling or decommissioning or
be involved.
decommissioning activity is involved, Hence, No
impact on the environment by the proposed project is
Local laborers from nearby area will be employed
during the construction phase. In the operation phase,
most of the expected occupants will be from the
surrounding areas. Hence, the project will lead to a
ution of occupants within the city. Thus, no
significant influx of people is envisaged.
The landscaping will be carried out with mainly local
species with a few ornamental varieties of flora that
the local conditions.
There will be no significant impact on the native
species or genetic diversity.
Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy,
Details thereof (with approximate quantities/ rates,
wherever possible) with source of information data
Proposed site is having wild grasses which shall be
residential plotted colony shall be
vacant land. Local and indigenous
also be planted at proposed
RESIDENTIAL PLOTTED COLONY M/S REVITAL REALITY PVT. LTD. VILLAGE- NAURANGPUR, SECTOR-
DISTRICT- GURGAON, HARYANA
Prepared by: Vardan EnviroNet, Gurgaon
2.2 Water (expected source & competing users)
unit: KLD
2.3 Minerals (MT)
2.4 Construction material stone, aggregates,
and/soil (expected source MT)
2.5 Forests and timber (source MT)
2.6
Energy including electricity and fuels (source,
competing users) Unit: fuel (MT), energy
(MW)
2.7 Any other natural resources (use appropriate
standard units)
3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human
health or the environment or raise concerns about actual or perceived risks to human health.
S.No.
Information/Checklist confirmation
3.1 Use of substance or materials, which are
hazardous (as per MSIHC rules) to human
health or the environment (flora, fauna
and water supplies)
3.2 Changes in occurrence of disease or affect
disease vectors (e.g. insect or water borne
diseases)
- 78 & 79,
Prepared by: Vardan EnviroNet, Gurgaon
Water (expected source & competing users) Yes
Total water requirement for the proposed will be
1920 KLD which include
requirement and 854
water requirement.
Yes Minerals such as sand and aggregates will be
required during the construction phase.
stone, aggregates,
Yes
All materials for construction will be arranged
through selected suppliers.
Yes
All material forests and timber will be provided by
selected suppliers. However
used to minimize the use of timber.
Energy including electricity and fuels (source,
fuel (MT), energy Yes The total demand load is estimated
Power will be supplied by
Any other natural resources (use appropriate No
No other natural resource wil
project except the mentioned
Use, storage, transport, handling or production of substances or materials, which could be harmful to human
health or the environment or raise concerns about actual or perceived risks to human health.
Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/ rates,
wherever possible) with source of information data
Use of substance or materials, which are
rules) to human
health or the environment (flora, fauna
Yes The proposed project is a
plotted colony project. H
chemicals (as per MSIHC
occurrence of disease or affect
disease vectors (e.g. insect or water borne
No Suitable drainage and waste management measures
(with frequent spray of insecticides etc.) will be
adopted in both the construction and operational
phase such that there will be no stagnation of water
or accumulation of waste. This will effectively
restrict the reproduction and growth of disease
vectors.
FORM-1
Page 8
Total water requirement for the proposed will be
KLD which include 1066 KLD for Fresh water
854 KLD for recycled/treated
Minerals such as sand and aggregates will be
required during the construction phase.
All materials for construction will be arranged
suppliers.
All material forests and timber will be provided by
selected suppliers. However, steel frames etc shall be
used to minimize the use of timber.
total demand load is estimated 11500 KVA.
Power will be supplied by DHBVN.
No other natural resource will be involved in the
t the mentioned above.
Use, storage, transport, handling or production of substances or materials, which could be harmful to human
health or the environment or raise concerns about actual or perceived risks to human health.
Details thereof (with approximate quantities/ rates,
wherever possible) with source of information data
The proposed project is a development of residential
project. Hence, storage of hazardous
s per MSIHC Rules) is not expected.
Suitable drainage and waste management measures
(with frequent spray of insecticides etc.) will be
adopted in both the construction and operational
phase such that there will be no stagnation of water
or accumulation of waste. This will effectively
t the reproduction and growth of disease
RESIDENTIAL PLOTTED COLONY M/S REVITAL REALITY PVT. LTD. VILLAGE- NAURANGPUR, SECTOR-
DISTRICT- GURGAON, HARYANA
Prepared by: Vardan EnviroNet, Gurgaon
3.3 Affect the welfare of people e.g. by
changing living conditions?
3.4 Vulnerable groups of people who could be
affected by the project e.g. hospital
patients, children, the elderly etc
3.5 Any other causes
4. Production of solid wastes during construction or operatio
S.No. Information/Checklist confirmation
4.1 Spoil, overburden or mine wastes
4.2 Municipal waste (domestic and or
commercial wastes)
4.3 Hazardous wastes (as per Hazardous
Waste Management Rules)
4.4 Other industrial process wastes
4.5 Surplus product
4.6 Sewage sludge or other sludge from
effluent treatment
4.7 Construction or demolition wastes
- 78 & 79,
Prepared by: Vardan EnviroNet, Gurgaon
Affect the welfare of people e.g. by Yes Socio-economic standard of people will improve due
to increased employment opportunities provided by
this project. This will lead
will also set a standard for future developments in
the area.
Vulnerable groups of people who could be
affected by the project e.g. hospital
ents, children, the elderly etc
No Impacts of this type are not expected.
No No other causes are involved except the mentioned
above.
Production of solid wastes during construction or operation or decommissioning (MT/month)
confirmation Yes/No Details thereof (with approximate
rates, wherever possible) with source of
information data
Spoil, overburden or mine wastes No No such spoil, overburden or mine wastes will be
generated.
estic and or Yes The total municipal solid waste to be generated is
approximately 9520 kg/day
biodegradable wastes will be sold to
vendors for recycling and the biodegradable
will be disposed according to
Handling) Rules, 2000.
Hazardous wastes (as per Hazardous NO No Hazardous Waste is been expected from the
proposed project.
No Not applicable as this is a
No Not applicable as this is a
Sewage sludge or other sludge from Yes Sludge generated from the STP plant will be dried and
later will be used as manure for
development.
demolition wastes Yes The construction waste will consist of excess earth
and construction debris along with cement bags, steel
in bits and pieces, insulating and packaging materials
etc.
FORM-1
Page 9
economic standard of people will improve due
to increased employment opportunities provided by
this project. This will lead to better quality of life and
will also set a standard for future developments in
Impacts of this type are not expected.
No other causes are involved except the mentioned
n or decommissioning (MT/month)
Details thereof (with approximate quantities/
rates, wherever possible) with source of
No such spoil, overburden or mine wastes will be
solid waste to be generated is
kg/day. The inorganic non-
biodegradable wastes will be sold to authorized
vendors for recycling and the biodegradable wastes
will be disposed according to MSW (Management &
No Hazardous Waste is been expected from the
as this is a residential plotted colony.
Not applicable as this is a residential plotted colony.
Sludge generated from the STP plant will be dried and
later will be used as manure for landscape
The construction waste will consist of excess earth
and construction debris along with cement bags, steel
in bits and pieces, insulating and packaging materials
RESIDENTIAL PLOTTED COLONY M/S REVITAL REALITY PVT. LTD. VILLAGE- NAURANGPUR, SECTOR-
DISTRICT- GURGAON, HARYANA
Prepared by: Vardan EnviroNet, Gurgaon
4.8 Redundant machinery or equipment
4.9 Contaminated soils or other materials
4.10 Agricultural wastes
4.11 Other solid wastes
5. Release for pollutants or any hazardous, toxic or
S.No. Information/Checklist confirmation
5.1 Emissions from combustion of fossil fuels
from stationary or mobile sources
5.2 Emissions from production processes
5.3 Emissions from materials
including storage or transport
5.4 Emissions from construction activities
including plant and equipment
5.5 Dust or odors from handling of materials
including construction materials,
and waste
- 78 & 79,
Prepared by: Vardan EnviroNet, Gurgaon
Recyclable waste construction materials will be sold
to authorized recyclers. Unusable and excess
construction debris will be disposed at designated
places in tune with the local norms.
Redundant machinery or equipment No Redundant machinery will not be generated.
Contaminated soils or other materials No Contaminated soils or other materials will not be
generated.
No No agricultural wastes will be generated.
No No other solid waste would be generated.
Release for pollutants or any hazardous, toxic or noxious substances to air (Kg/hr).
Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/ rates,
wherever possible) with source of information data
Emissions from combustion of fossil fuels
mobile sources
Yes The project does not envisage any major air
pollution sources except
generated from the vehicular
check by regular check up of vehicles
plants will be used in tree plantation to reduce the
impact of pollution.
Emissions from production processes No No production processes
residential plotted colony project.
be no such emissions.
Emissions from materials handling Yes Small quantities of fugitive emissions are envisaged
during transport and handling of construction
materials. Such emissions will be temporary and
controlled by the use of sprinkling and other viable
techniques like covering of loose material.
Emissions from construction activities
Yes This will be restricted to the construction phase and
the construction site only.
Dust or odors from handling of materials
construction materials, sewage
Yes Dust is anticipated during loading and unloading of
construction material and excavation of upper earth
surface. These will however be temporary in nature,
which will be controlled by providing water
FORM-1
Page 10
Recyclable waste construction materials will be sold
recyclers. Unusable and excess
construction debris will be disposed at designated
places in tune with the local norms.
Redundant machinery will not be generated.
Contaminated soils or other materials will not be
wastes will be generated.
No other solid waste would be generated.
Details thereof (with approximate quantities/ rates,
wherever possible) with source of information data
The project does not envisage any major air
pollution sources except vehicles. The pollution
generated from the vehicular movement will be
check by regular check up of vehicles. Local native
in tree plantation to reduce the
No production processes is involved as it is a
colony project. Hence, there will
Small quantities of fugitive emissions are envisaged
during transport and handling of construction
materials. Such emissions will be temporary and
controlled by the use of sprinkling and other viable
ike covering of loose material.
This will be restricted to the construction phase and
the construction site only.
Dust is anticipated during loading and unloading of
construction material and excavation of upper earth
surface. These will however be temporary in nature,
which will be controlled by providing water
RESIDENTIAL PLOTTED COLONY M/S REVITAL REALITY PVT. LTD. VILLAGE- NAURANGPUR, SECTOR-
DISTRICT- GURGAON, HARYANA
Prepared by: Vardan EnviroNet, Gurgaon
5.6 Emissions from incineration of waste
5.7 Emissions from burning of waste
(e.g. slash materials, construction debris)
5.8 Emissions from any other sources
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No. Information/Checklist confirmation
6.1
From operation of equipment e.g. engines,
ventilation plant, crushers
6.2
From industrial or similar processes
- 78 & 79,
Prepared by: Vardan EnviroNet, Gurgaon
sprinklers. Tarpaulin cover will be provided on
stored loose materials to reduce the dust emission.
Emissions from incineration of wastes No Not applicable. There will not be any incineration of
waste is proposed.
Emissions from burning of waste in open air
(e.g. slash materials, construction debris)
No Open burning of biomass/
prohibited on site as this is a construction of
residential project.
Emissions from any other sources No Not Applicable
and Vibration, and Emissions of Light and Heat:
Information/Checklist confirmation Yes/No
Details thereof (with approximate quantities/
rates, wherever possible) with source of
information data
From operation of equipment e.g. engines,
Yes
The machinery to be used for construction will be
of high standard and will adhere to international
standard. These standards itself take care of noise
control/vibration control and air emission
Hence, insignificant impacts due to construction
machinery are envisaged. Apart from this, the
construction activities will be restricted to day time
only. All the machinery will be of highest standard
of reputed make and will comply with standard
From industrial or similar processes No
No industrial processes will be carried
proposed project ex
construction equipments/
maintenance of machineries will reduce the
generation of noise and vibration. All the workers
will be equipped with
phase.
FORM-1
Page 11
Tarpaulin cover will be provided on
stored loose materials to reduce the dust emission.
t applicable. There will not be any incineration of
pen burning of biomass/ other material will be
as this is a construction of
Details thereof (with approximate quantities/
rates, wherever possible) with source of
The machinery to be used for construction will be
of high standard and will adhere to international
standard. These standards itself take care of noise
control/vibration control and air emission control.
Hence, insignificant impacts due to construction
machinery are envisaged. Apart from this, the
construction activities will be restricted to day time
All the machinery will be of highest standard
of reputed make and will comply with standard.
No industrial processes will be carried out in the
proposed project except running of various
nstruction equipments/ machinery. Proper
maintenance of machineries will reduce the
generation of noise and vibration. All the workers
will be equipped with PPEs during construction
RESIDENTIAL PLOTTED COLONY M/S REVITAL REALITY PVT. LTD. VILLAGE- NAURANGPUR, SECTOR-
DISTRICT- GURGAON, HARYANA
Prepared by: Vardan EnviroNet, Gurgaon
6.3
From construction or demolition
6.4 From blasting or piling
6.5
From construction or operational traffic
6.6
From lighting or cooling systems
6.7
From any other sources
7. Risks of contamination of land or water from releases of pollutants into the ground of into sewers, surface waters,
groundwater, coastal waters or the sea:
S.No. Information/Checklist confirmation
7.1 From handling, storage, use or spillage of
hazardous materials
7.2 From discharge of sewage or other effluents
to water or the land (expected mode and
place of discharge)
7.3 By deposition of pollutants emitted to air
- 78 & 79,
Prepared by: Vardan EnviroNet, Gurgaon
From construction or demolition Yes
Due to various construction activities, there
short-term noise impacts in the immediate vicinity
of the project site. The construction activities will
include the following noise generating activities:
Concreting, mixing & operation of DG sets.
Construction plant and heavy vehicle
movement.
No No blasting or mechanized piling will be done.
From construction or operational traffic Yes
Some noise will be generated from vehicular
movement in the construction and operational
phase but that will be mitigated with
development.
From lighting or cooling systems No
No significant noise impact will result from
lighting or cooling systems.
No There will be no other sources for noise &
vibration generation except the mentioned above.
Risks of contamination of land or water from releases of pollutants into the ground of into sewers, surface waters,
groundwater, coastal waters or the sea:
Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/
rates, wherever possible) with source of
information data
From handling, storage, use or spillage of No There will be no handling, storage, use or spillage
of any type of hazardous material.
From discharge of sewage or other effluents
to water or the land (expected mode and
No There will be no discharge of untreated sewage on
land or into water bodies. Adequate treatment of
sewage will be carried out
capacity of 1926 KLD
Recycled water will be re
landscaping and rest of the recycled water
given to nearby construction sites
purpose only.
By deposition of pollutants emitted to air No There will be no deposition of pollutants emitted
FORM-1
Page 12
Due to various construction activities, there will be
term noise impacts in the immediate vicinity
of the project site. The construction activities will
include the following noise generating activities:
Concreting, mixing & operation of DG sets.
Construction plant and heavy vehicle
No blasting or mechanized piling will be done.
Some noise will be generated from vehicular
movement in the construction and operational
phase but that will be mitigated with landscape
No significant noise impact will result from
systems.
There will be no other sources for noise &
vibration generation except the mentioned above.
Risks of contamination of land or water from releases of pollutants into the ground of into sewers, surface waters,
Details thereof (with approximate quantities/
rates, wherever possible) with source of
There will be no handling, storage, use or spillage
of any type of hazardous material.
There will be no discharge of untreated sewage on
land or into water bodies. Adequate treatment of
sewage will be carried out in STP having the
1926 KLD within the project premises.
will be re-used for flushing and
of the recycled water will be
nearby construction sites for construction
There will be no deposition of pollutants emitted
RESIDENTIAL PLOTTED COLONY M/S REVITAL REALITY PVT. LTD. VILLAGE- NAURANGPUR, SECTOR-
DISTRICT- GURGAON, HARYANA
Prepared by: Vardan EnviroNet, Gurgaon
into the land or into water
7.4 From any other sources
7.5 Is there a risk of long term build up of
pollutants in the environment from these
sources?
8. Risk of accidents during construction or operation of the Project, which could affect human health or the
environment
S.No. Information/Checklist confirmation
8.1 From explosions, spillages, fires etc from
storage, handling, use or production of
hazardous substances
8.2 From any other causes
8.3 Could the project be affected by natural
disasters causing environmental damage
(e.g. floods, earthquakes, landslides,
- 78 & 79,
Prepared by: Vardan EnviroNet, Gurgaon
to air into the land or into water by any source.
No No other sources are involved except the
mentioned above.
Is there a risk of long term build up of
pollutants in the environment from these No
There will be no such
Risk of accidents during construction or operation of the Project, which could affect human health or the
Information/Checklist confirmation Yes/No Details thereof (with approximate
quantities/ rates, wherever possible) with
source of information data
From explosions, spillages, fires etc from
storage, handling, use or production of
Yes This is a residential project and does not involve
major hazardous construction activity. Hence
chances of explosions, spillages, fires etc. are
minimal.
During construction, suitable personal protective
equipment will be provided to all construction
workers as required under
norms. Awareness & Training about safety norms
will be provided to all the supervisor and
construction workers involved in construction
activities.
To deal with any fire related accident, fire fighting
facility of single handed hydrant
reel, and portable fire extinguisher shall be
provided.
No No other causes are involved except the mentioned
above.
Could the project be affected by natural
disasters causing environmental damage
(e.g. floods, earthquakes, landslides,
No The project falls under seismic active Zone IV
according to the Indian Standard Seismic Zoning
Map.
FORM-1
Page 13
into the land or into water by any source.
No other sources are involved except the
There will be no such risk in the coming future.
Risk of accidents during construction or operation of the Project, which could affect human health or the
Details thereof (with approximate
wherever possible) with
source of information data
project and does not involve
major hazardous construction activity. Hence
chances of explosions, spillages, fires etc. are
During construction, suitable personal protective
equipment will be provided to all construction
workers as required under the health & safety
norms. Awareness & Training about safety norms
will be provided to all the supervisor and
construction workers involved in construction
To deal with any fire related accident, fire fighting
facility of single handed hydrant valve, long hose
reel, and portable fire extinguisher shall be
No other causes are involved except the mentioned
The project falls under seismic active Zone IV
according to the Indian Standard Seismic Zoning
RESIDENTIAL PLOTTED COLONY M/S REVITAL REALITY PVT. LTD. VILLAGE- NAURANGPUR, SECTOR-
DISTRICT- GURGAON, HARYANA
Prepared by: Vardan EnviroNet, Gurgaon
cloudburst etc)?
9. Factors which should be considered (such as
effects or the potential for cumulative impacts with other existing or planned activities in the locality.
S.No. Information/Checklist confirmation
9.1 Lead to development of supporting
facilities, ancillary development or
development stimulated by the project
which could have impact on the
environment e.g.
Supporting infrastructure
(roads, power supply, waster
or wastewater treatment, etc.)
housing development
extractive industries
supply industries
other
9.2 Lead to after-use of the site, which could
have an impact on the environment
9.3 Set a precedent for later developments
9.4 Have cumulative effects due to proximity
to other existing or planned projects with
similar effects
- 78 & 79,
Prepared by: Vardan EnviroNet, Gurgaon
Suitable seismic coefficient will be adopted in
horizontal and vertical direction respectively,
while designing the structure.
There is no possibility of flood as per records
available on the proposed project site.
Factors which should be considered (such as consequential development) which could lead to environmental
effects or the potential for cumulative impacts with other existing or planned activities in the locality.
Information/Checklist confirmation Yes/No Details thereof (with approximate qua
rates, wherever possible) with source of
information data
Lead to development of supporting
facilities, ancillary development or
stimulated by the project
which could have impact on the
Supporting infrastructure
(roads, power supply, waster
or wastewater treatment, etc.)
housing development
Yes
Yes
Yes
No
No
No
The proposed project is for
lead to development of supporting services and
infrastructure in and around the area.
The project will have positive impact on the
ancillary infrastructure like road, markets, public
health, amenities, conveyance facilities etc.
The project is proposed
residential plotted colony
Not Applicable
Not Applicable
Not Applicable
use of the site, which could
have an impact on the environment No Not Anticipated
developments No Not Applicable
Have cumulative effects due to proximity
to other existing or planned projects with No Not Applicable
FORM-1
Page 14
coefficient will be adopted in
horizontal and vertical direction respectively,
while designing the structure.
There is no possibility of flood as per records
available on the proposed project site.
consequential development) which could lead to environmental
effects or the potential for cumulative impacts with other existing or planned activities in the locality.
Details thereof (with approximate quantities/
rates, wherever possible) with source of
The proposed project is for residential use; it may
lead to development of supporting services and
infrastructure in and around the area.
The project will have positive impact on the
ancillary infrastructure like road, markets, public
health, amenities, conveyance facilities etc.
The project is proposed for the development of
olony only.
RESIDENTIAL PLOTTED COLONY M/S REVITAL REALITY PVT. LTD. VILLAGE- NAURANGPUR, SECTOR-
DISTRICT- GURGAON, HARYANA
Prepared by: Vardan EnviroNet, Gurgaon
(III) ENVIRONMENTAL SENSITIVITY
S.No. Information/Checklist confirmation
1. Areas protected under international
conventions, national or local legislation
for their ecological, landscape, cultural or
other related value.
2. Areas which are important or sensitive for
ecological reasons
watercourses or other water bodies, coastal
zone, biospheres, mountains & forests
3. Areas used by protected, important or
sensitive species of flora or fauna for
breeding, nesting, foraging, resting, over
wintering, migration
4. Inland, coastal, marine or underground
waters.
5. State, National boundaries
6. Routes or facilities used by the public for
access to recreation or other tourist,
pilgrim areas.
7. Defense installations
8. Densely populated or built-up area
9. Areas occupied by sensitive manmade land
uses (hospitals, schools, places of worship,
community facilities)
- 78 & 79,
Prepared by: Vardan EnviroNet, Gurgaon
ENVIRONMENTAL SENSITIVITY
Information/Checklist confirmation Name/Identity
Aerial distance
Proposed project location
Areas protected under international
conventions, national or local legislation
for their ecological, landscape, cultural or Not Applicable
There is no area under
international
or local legislation for their
ecological, landscape, cultural or
other related value.
Areas which are important or sensitive for
Wetlands,
watercourses or other water bodies, coastal
mountains & forests
Not Applicable
There is no area
important or sensitive for
ecological reasons.
Areas used by protected, important or
sensitive species of flora or fauna for
breeding, nesting, foraging, resting, over
Not Applicable
There is
species of flo
the study area.
Inland, coastal, marine or underground Not Applicable Not Applicable
Not Applicable
No State or International
falls within the 15 km radius of the
project site.
Routes or facilities used by the public for
access to recreation or other tourist,
NH-8
Approx
Not Applicable Not Applicable
up area Manesar Village
Approximately
project site in
Areas occupied by sensitive manmade land
uses (hospitals, schools, places of worship,
S.
No. Particulars Distance
Hospitals
1. Yashlok Medical
Center 2.5 km
FORM-1
Page 15
Aerial distance (within 15km.)
Proposed project location
boundary
There is no area under
international conventions, national
or local legislation for their
ecological, landscape, cultural or
other related value.
There is no area which is
important or sensitive for
ecological reasons.
is no ecologically sensitive
species of flora or fauna found in
the study area.
Not Applicable
No State or International Boundary
falls within the 15 km radius of the
project site.
Approx. 2.7 km in NW direction
Applicable
Approximately 3.6 km from
project site in SE direction
Distance Direction
km NW
RESIDENTIAL PLOTTED COLONY M/S REVITAL REALITY PVT. LTD. VILLAGE- NAURANGPUR, SECTOR-
DISTRICT- GURGAON, HARYANA
Prepared by: Vardan EnviroNet, Gurgaon
10. Areas containing important, high quality or
scarce resources (ground water resources,
surface resources, forestry, agriculture,
fisheries, tourism, minerals)
11. Areas already subjected to pollution or
environmental damage. (Those where
existing legal environmental standards are
exceeded)
12. Areas susceptible to natural hazard which
could cause the project to present
environmental problems (earthquakes,
subsidence, landslides, erosion, flooding or
extreme or adverse climatic conditions)
- 78 & 79,
Prepared by: Vardan EnviroNet, Gurgaon
2. Life Care Hospital 3.6 km
Temples
1. Prachin Temple 2.2 km
2. Siddhartha Teerth
Jain Temple 2.4 km
Banks
1. Bank of Baroda 1.5 km
2. ICICI Bank limited 3.0 km
Areas containing important, high quality or
scarce resources (ground water resources,
surface resources, forestry, agriculture, Not Applicable
Ground
study area are depleting at very
fast rate and
resources.
Areas already subjected to pollution or
environmental damage. (Those where
existing legal environmental standards are
Not Applicable
There is
to pollution or environmental
damage. All parameters of Air,
Water and Noise etc. will be
maintained within permissible
limit specified by SPCB/
proper mitigation measures.
hazard which
could cause the project to present
environmental problems (earthquakes,
subsidence, landslides, erosion, flooding or
extreme or adverse climatic conditions)
Not Applicable
The site falls under the zone IV as
per the Seismic Zone Map of India.
There is no possibility of flood as
per records available on the
proposed project site
FORM-1
Page 16
km SW
km NE
km NW
km SW
km SW
Ground-water resources in the
study area are depleting at very
fast rate and declared as scarce
resources.
There is no area which is subjected
to pollution or environmental
damage. All parameters of Air,
Water and Noise etc. will be
maintained within permissible
limit specified by SPCB/ CPCB with
proper mitigation measures.
The site falls under the zone IV as
per the Seismic Zone Map of India.
There is no possibility of flood as
per records available on the
proposed project site.
RESIDENTIAL PLOTTED COLONY M/S PARSVNATH DEVELOPERS LIMITED VILLAGE- SOHNA, SECTOR- 2,
DISTRICT- GURGAON, HARYANA FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 17
CHECK LIST OF ENVIRONMENTAL IMPACTS
(Project proponents are required to provide full information and wherever necessary attach
explanatory notes with the Form and submit along with proposed Environmental Management
Plan & Monitoring Programmed).
SECTION 1- LAND ENVIRONMENT:
(Attach panoramic view of the project site and the vicinity)
1.1 Will the existing land use get significantly altered from the project that is consistent with
the surroundings? (Land use must conform to the approved Master Plan/Development Plan of
the area. Change of land use, if any and the statutory approval from the competent authority
are submitted). Attach Maps of (i) site location, (ii) surrounding features of the site (within 500
meters) and (iii) the site (indicating levels & contours) to appropriate scales. If not available
attach only conceptual plans.
No
The project site is barren land. It is anticipated that the construction activities of the project will not
have an adverse effect on the land use activities in the project area. The site is earmarked for
residential development as per the Gurgaon-Manesar Master Plan - 2031. The tree plantation and
landscape development will enhance the visual aesthetics of the area.
Location Map, Map showing surrounding features of the site within 500 m and Contour Map
indicating levels and contours are enclosed in the report.
CONNECTIVITY
S. No. Detail Distance Direction 1. Nearest Highway (NH-8) 2.7 Km North-West 2. Garhi Harsaru Jundction Railway Station 10 Km North-West 3. Indira Gandhi National Airport (IGI) 25 Km North-East
1.2 List out all the major project requirements in terms of the land area, built up area,
water consumption, power requirement, connectivity, community facilities, parking needs etc.
RESIDENTIAL PLOTTED COLONY M/S PARSVNATH DEVELOPERS LIMITED VILLAGE- SOHNA, SECTOR- 2,
DISTRICT- GURGAON, HARYANA FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 18
LAND REQUIREMENT Table 1: Area Statement
S. No. Particulars Area ( m2)
1 Project Name Residential plotted colony M/s Revital Reality Pvt. Ltd.
2 Activity in the complex
Residential Apartments, EWS Apartments, Commercial Area, Nursing Homes, Nursery School, Primary School, Clinic and Beauty Parlour
3 Total Plot Area 415612.154 m2 (102.70 Acres)
4 Net Plot Area 3, 77, 805.80 m2 (93.3583 Acres)
5 Ground Coverage Detail 107292.3405 m2
6 FAR Detail 2, 99, 157.422 m2
7 Built-up Area Detail 443997.81 m2
8 No. of Units 793 plots a Residential Units 435 b NPNL Units 199
c EWS Units 159
9 Surface Parking 324 ECS Basement Parking 420 ECS (Basement-1, Basement-2)
10 Power Requirement & Sources 11500 KVA Source: Dakshin Haryana Bijli Vitran Nigam (DHBVN)
11 No. of DG Sets 2 Nos. of DG Sets having Total Capacity of 630 KVA (1 x 250 KVA + 1 x 380 KVA)
12 Water requirement & Sources
Total Water Requirement:1920 KLD Fresh Water Requirement: 1066 KLD Treated/ Recycled Water Requirement: 854 KLD Source: HUDA
RESIDENTIAL PLOTTED COLONY M/S PARSVNATH DEVELOPERS LIMITED VILLAGE- SOHNA, SECTOR- 2,
DISTRICT- GURGAON, HARYANA FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 19
13 Sewage Treatment & Disposal
STP capacity :1926 KLD Sewage discharge: Total 854 KLD of water will be obtained after the recycling of wastewater out of which 752 KLD shall be utilized for the purpose of flushing, 102 KLD for landscape development and 591 KLD shall be supply to nearby construction sites for construction purpose only.
14 Estimated Population Total: 25633 Persons
15 Proposed Green Area @ 24.33 % 101247.36 m2
16 Cost of the project Rs. 1134 Crores (Approx.) *FAR = Floor Area Ratio
1.3 What are the likely impacts of the activity on the existing facilities adjacent to the site?
(Such as open spaces, community facilities, details of the existing land use and disturbance to
the local ecology).
The project being a well planned activity will result in organized open spaces and green areas. About
101247.36 m2 of the area is earmarked for landscaping. The project will have an overall positive
impact on the existing land use and will not cause any disturbance to the local ecology. Hence,
proposed activity shall have no impact on surroundings.
1.4 Will there be any significant land disturbance resulting in erosion, subsidence &
instability? (Detail of soil type slope analysis, vulnerability to subsidence, seismicity etc may be
given).
There shall be no land disturbance resulting in erosion, subsidence and instability as it is a flat land.
The project site falls under the zone IV i.e., High Damage Risk Zone (MSK-VIII) as per Earthquake
Hazard Map of Haryana. The project will be earthquake resistant taking into account the latest
provisions of Indian Standards Codes.
RESIDENTIAL PLOTTED COLONY M/S PARSVNATH DEVELOPERS LIMITED VILLAGE- SOHNA, SECTOR- 2,
DISTRICT- GURGAON, HARYANA FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 20
Source: Maps of India
Figure-2: Earthquake Hazard Map of Haryana showing Project Site
1.5 Will the proposal involve alteration of natural drainage system? (Give details on a
contour map showing the natural drainage near the project site).
The project does not intersect any natural drainage route. No perennial or non-perennial drainage
system is found to exist in the project area or being obstructed by the project. The surroundings
comprise an urbanized stretch. Well planned storm water drainage has been designed to take care of
internal storm water drainage. Thus, no impact on the natural drainage system is anticipated.
1.6 What are the quantities of earthwork involved in the construction activity-cutting,
filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of fill
materials from outside the site etc?)
The only excavation work is involved in the proposed project for establishing the pillar of Residential
Plotted Colony. The filling works will be done by the excavated material and no extra material will be
used. All the topsoil excavated from construction activities shall be stored separately and used in
PROJECT SITE
RESIDENTIAL PLOTTED COLONY M/S PARSVNATH DEVELOPERS LIMITED VILLAGE- SOHNA, SECTOR- 2,
DISTRICT- GURGAON, HARYANA FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 21
landscape development within the project site. Hence, the need for movement of soil to and from the
site is not anticipated.
1.7 Give details regarding water supply, waste handling etc. during the construction period.
Water requirement during construction phase will be met from STP treated water.
Waste handling during the construction phase shall be done by the site contractor whose
responsibility lies with collection and storage of construction and demolition waste generated
on the site. All construction wastes generated during construction will be used within the site
itself for filling the floors, roads, aggregate for mortar etc. to the extent feasible. Remaining
will be sent to the agency for proper disposal.
1.8 Will the low lying areas & wetlands get altered? (Provide details of how low lying and
wetlands are getting modified from the activity).
No. The site area is a flat land and the surroundings are characterized by an urbanized stretch. No low
lying areas or wetlands are found in the vicinity of the project site.
1.9 Whether construction debris & waste during construction cause health hazard? (Give
quantities of various types of wastes generated during construction including the construction
labor and the means of disposal).
No significant health hazard is associated with the proposed construction.
During construction period, source of fugitive dust generation will be material handling and
vehicular movement. Impact due to fugitive dust emission is negligible as water sprinklers will be
used to suppress fugitive dust emission as and when generate. However, the impacts will be
confined to laborers/workers particularly with regard to occupational exposure. Proper Personal
Protective Equipments will be provided to the workers working in the potential areas (e.g. masks,
ear plugs etc.).
Careful design, planning and good site management would minimize waste of materials such as
concrete, mortars and cement grouts. Construction wastes will be segregated as much as possible at
site itself to increase the feasibility of recycling concrete and masonry as filling material and steel
pieces as saleable scrap. Litter disposal and collection points will be established around the work
sites. Empty packaging materials, drums, glass, tin, paper, plastic, pet bottles, wood, thermocol and
other packaging materials, etc will be disposed through recyclers. The construction spoils will be
temporarily stored at designated dumpsite located inside the site premises. Later on these wastes
RESIDENTIAL PLOTTED COLONY M/S PARSVNATH DEVELOPERS LIMITED VILLAGE- SOHNA, SECTOR- 2,
DISTRICT- GURGAON, HARYANA FORM 1A
Prepared by: Vardan EnviroNet, Gurgaon Page 22
will be used for land filling / leveling work within the site premises. An estimate of the average
composition of waste generated from the onsite construction activities given in Table-2.
Table-2: Waste Composition - During Construction Phase
S. No. Constituents Percentage Composition (%) 1 Soil, Sand and Gravel 35.80 2 Brick and Masonry 30.66 3 Concrete 23.24 4 Metal 5.10 5 Bitumen 2.10 6 Wood 2.10 7 Other 1.00 Total 100.00
Source: TIFAC Report Utilization of Waste from Construction Industry, 2001
SECTION-2 WATER REQUIREMENT
2.1 Give the total quantity of water requirement for the proposed project with the breakup of
requirement for various uses, how will the water requirement met? State the sources &
quantities and furnish a water balance statement.