Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
1.0 PROJECT OVERVIEW
1.1 PROJECT BACKGROUND
The Government of India under the nodal Ministry of Shipping, Road Transport and Highways (MOSRT&H) has taken up the development of the National Highways in the country to enhance the traffic capacity and safety for efficient transportation of goods as well as passenger traffic. The National Highways Authority of India (NHAI) has been entrusted with implementation of this development project. NHAI under NHDP Phase II programme aims at developing section of NH-47, by widening the existing two lane road to four lane dual carriageway including strengthening of existing 2 lanes on Design, Built, Finance, Operation & Transfer (DBFOT) basis.
NHAI appointed the Artefact Projects Limited India, as Independent Engineer for Walayar – Vadakkancherry Section of NH-47 from Km. 182+250 to Km. 240+000 (Design Chainage 236+135) in the state of Kerala to carry out the review of Designs, Drawings, Construction, Progress Monitoring, affirmation of all certifications done by the Concessionaire, etc. The Independent Engineer shall be involved in day-to-day implementation of the Project.
1.2 THE SITE
The Project Highway starting point is near Walayar (Km.182+250) and the termination point is near Vadakkancherry (Km. 240+000). The Project Highway covers Palakkad District in State of Kerala.
1.3 THE CONCESSION AGREEMENT
The Concession Agreement for Design, Built, Finance, Operation & Transfer (DBFOT) basis of NH-47 under NHDP phase II was signed on 17 th September, 2012 between National Highways Authority of India having principal office at G-5 & 6, Sector-10, Dwarka, New Delhi-110075 and KNR WALAYAR TOLLWAYS PRIVATE LIMITED (KWTPL) having registered office at Plot no. 114, Phase 1, Kavuri Hills, Jubilee Hills, Hyderabad – 500033, Andhra Pradesh.
1.4 INDEPENDENT ENGINEERING SERVICES
Independent Engineering Services for four laning of Walayar – Vadakkancherry from existing Km.182.250 to Km.240.000 in the state of Kerala under NHDP Phase-II to be executed on BOT (Toll) on DBFOT Basis (Package No.NS-2/BOT-KL-2/Phase-II) was signed on 15th April 2013 between National Highways Authority of India and Artefact Projects Limited (India), Nagpur.
The Independent Engineering Services commenced on the 15 thJune 2013. An office has been established at Palakkad. The Team Leader has been mobilized in the month of September 2013, Resident cum Highway Engineer and other key and Sub professionals have been mobilized in June -July 2013.
1.5 THE SCOPE OF PROJECT
The scope of the Project shall include the followings during the Concession Period:Construction of the Project Highway on the Site set forth in Schedule-A and as specified in Schedule-B together with provision of Project Facilities as specified in Schedule-C, and in conformity with the Specifications and Standards set forth in Schedule-D;Operation and Maintenance of the Project Highway in accordance with the provisions of the Concession Agreement and Performance and fulfillment of all other obligations of the Concessionaire in accordance with the provisions of the Concession Agreement and matters
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 1
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
incidental thereto or necessary for the performance of any or all of the obligations of the Concessionaire under the Concession Agreement.
Construction of Project Highway 53.885 Kms Construction of Service Roads . 47.230 Kms
Construction of Grade Separated/ Intersections 1 Nos. (1 No deleted – ve COS) Construction of Major Junctions 7 Nos.(2 No new VUP;s proposed
COS) Construction of Minor Intersections 36 Nos. Construction of Major Bridges 2 Nos. Construction of Rail Over Briges 1 Nos. Construction of Vehicular Under Passes 7 Nos(3 Nos proposed under COS) Construction of Cattle Under Passes 4 Nos. Construction of Minor Bridges 12 Nos. Construction of Culverts 165 Nos(28 Nos Additional
proposed Under COS).
Construction of toll Plaza at Km 189+438 1 Nos. Construction of Bus bays 49 Nos.
1.6 SALIENT FEATURES OF THE PROJECT
PROJECT DETAILS
i. Name of Project : Four Laning of Walayar – Vadakkancherry Section in Kerala from Km. 182.250 (Design Chainage Km. 182.250) to Km. 240.000 (Design Chainage Km. 236.135) of NH-47 – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II. (Total Length 53.885 Kms)
ii. Construction Package No. : NS-2/BOT/KL-2.
iii. Performance Security : Rs. 34.10 Crores, (To be Refunded after 1 year or earlier upon expending 20% of the Total Project Cost i.e. 136.40 Crores)
AGENCIES INVOLVED
iv. Client : General Manager (Kerala)National Highways Authority of IndiaG5 & 6, Sector – 10, Dwaraka, New Delhi – 110 075
v. PIU : Project Director,National Highways Authority of India,Project Implementation Unit (PIU), No. 8/1187, Arumughan Colony,Chandranagar, Palakkad, Kerala – 678 007
vi. Independent Engineer : Artefact Projects Limited“SRIVATSAN”Chandranagar Extension,
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 2
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
Pirivusala, Palakkad,Kerala – 678 007
vii. Concessionaire : KNR Walayar Tollways Pvt. Ltd, (KWTPL)KNR House, 3rd& 4th Floor,Plot No. 114, Phase-I, Kavuri Hills,Jubilee Hills, Hyderabad – 500 033, Andhra Pradesh.
viii. EPC Contractor : KNR Constructions Limited, (KNRCL)KNR House, 3rd& 4th Floor,Plot No. 114, Phase-I, Kavuri Hills,Jubilee Hills, Hyderabad – 500 033, Andhra Pradesh.
ix. Lenders Independent Engineer (LIE) : M/s Feedback Infra Limited, BengaluruNo. 9, K.H. Road, opp KSRTC Central OfficeBangalore – 560027
x. Lenders Legal Council (LLC) : M/s India Law Services, New DelhiThapar House, Central Wing, 1st Floor,124 JANAPAT, New Delhi – 110001
xi. Lenders Insurance Advisor (LIA) : M/s India Insurance Risk Management&Insurance Broking Pvt. Ltd., 405,ArchanaArcade, St. Johns Road, Secunderabad – 500025, AP.
PROJECT TIMELINES Date of agreement : 17-09-2012 NHAI TPC : Rs. 682 crores Concession Period : 20 years including construction period. Appointed Date : 18-05-2013 Scheduled date of completion : 13-11-2015 Construction period : 910 days Project Length : 54 Kms (from Km 182.250 to Km 240.00 ,Design
Chainage 236+135) Client : National Highways Authority of India Consultant (IE) : Artefact Projects Limited Concessionaire : KNR WalayarTollways Private Limited EPC : KNR Constructions Limited Date of EPC agreement : 28-11-2012 Date of financial closure : 16-03-2013 (Scheduled) Date of financial closure : 13-05-2013 (Actual) EPC cost : Rs. 790.50 Crores Loan amount : 500 Crores Grant : 264.60 Crores Project Equity Capital : 135.91 Crores Concessionaire’s TPC : Rs. 900.51 crores Lead Banker : Central Bank of India
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 3
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
PROJECT FINANCIALSProject Cost Amt. in Rs. Cr.EPC CostsCivil Construction Costs 775.00Contingency (as % of Civil Construction Costs 15.50Total EPC Cost 790.50Non – EPC CostInsurance during Construction 2.37Preliminary Exp. 7.75Other SPC Overheads 17.44Total Non-EPC Cost 27.56Premium to be paid on COD 0.00Total Capital Cost (excluding IDC) 818.06IDC 82.46Total Project Cost (including IDC) 900.51
Sl. No. Particulars Amount
(Rs. Crores) %
1 KNR Constructions Limited 135.91 100 % of equity
2 Others 0.00 0 % of equity
3 Promoters’ Equity 135.91 15.09% of TPC
4 Grant 264.60 29.38% of TPC
5 Senior Debt 500.00 55.52% of TPC
Total Project Cost 900.51 100.0
LENDERS DETAILS AND CONTRIBUTION:
Sl No. Bank Name
Amount of Contribution(Rs. Crores)
Remarks
1. Central Bank of India 175 Lead Bank
2. Bank of India 100 Consortium Bank
3. Corporation Bank 90 Consortium Bank
4. Canara Bank 85 Consortium Bank
5. Vijaya Bank 50 Consortium Bank
Total Loan Amount 500
PROJECT MILESTONES AS PER SCHEDULE - G OF CA
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 4
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
Sl No. Mile stone Target Date Target Percentage
1. I 180 Days from the Appointed date (November 13, 2013)
10%
2. II 400 Days from the Appointed Date (June 21, 2014)
35%
3. III 650 Days from the appointed date(February 26, 2015)
70%
4. IV 910 Days from the Appointed date(November 13, 2015)
100%
SCOPE OF THE PROJECT CONSTRUCTION SCHEDULES B, C & D xii. Project Length : 53.885 Kms
xiii. Service Roads : 47.230 Kms xiv. Major Intersections : 7 No’s (2 Nos VUP;s proposed)
xv. Minor Junctions : 36 No’s
xvi. Grade Separated Intersections : 1 No’s (1 No deleted –ve COS and VUP proposed)
xvii. Underpasses : VUP’s : 7 No’s CUP’s : 4 No’s Total : 11Nos
xviii. Major Bridges : 2 No’s
xix. ROB : 1 No.
xx. Minor Bridges : 12 No’s
xxi. Culverts : Pipe Culverts : 51 Nos
Box Culverts - Widening : 122 Box Culverts - Reconstructions : 20 (All including COS)
xxii. Toll Plaza : 1 No. (Km. 189+400)
xxiii. Bus Bays : LHS : 26 No’s RHS : 23 No’s
Total : 49 No’s
xxiv. Truck Lay bays : Nil
xxv. Rest Areas : Nil
xxvi. HTMS : Not Required till Traffic reaches 40,000 PCU
xxvii. Physical Progress Up to 30th June 2014 : 58.20 %
xxviii. Financial Progress Up to 30th June 2014 : 58.66 %
1.7 GENERAL FEATURES OF THE PROJECT
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 5
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
i. Width of Paved Carriagewaya) Main Carriageway (4 Lanes) : 17.5mb) Service Road : 7.0m
ii. Carriageway Width : 8.75m (including 1.5m Hard Shoulder)
iii. Unpaved Shoulder : 1.5m (on Both Sides)
iv. Bridge width : 12m (end to end)
v. Median Width : 2.0mtrs to 4.5 mtrs: 1.0m (at Median openings)
vi. Cross slope : 2.5% (on carriage way): 3% (on shoulder)
vii. Embankment Side Slop : 1 in 1 to 1 in 2
viii. Super Elevation : 7% (Maximum)
ix. Gradient (maximum) : ……..% Maximum (at Km ____ to _____)
x. Radius (minimum) : ……..m (at Km _______ & at Km. _______)
xi. Pattern of widening as per Existing Chainage (Given in CA)a) Concentric : 28.857Kms.b) Eccentric
LHS : 13.678 Kms. RHS : 11.450Kms.
Total : 53.885Kms.
xii. Design speed : 100 KMPH (except few locations)xiii. Pavement Design for Rigid Pavement for Toll Plazas.Sl No. Layer Thickness (Tentative)
1 PQC 300 mm2 DLC 150 mm3 GSB 200 mm4 Sub Grade 500mm
xiv. Pavement Design for New Construction / Reconstruction and Widening
Homogeneous Section HS-01 HS-02Design Chainage (From -To) 182.250 - 204.000 204.000 -236.140Design CBR in % 10 10
Design Traffic in MSA 73 76(15 yrs) (15 yrs)
BC in mm 50 50DBM in mm 120 120WMM in mm 250 250GSB in mm 200 200Subgrade in mm 500 500
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 6
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
xv. Pavement Design for Service Roads / Slip Roads
Design CBR Value in % 10
Design Traffic in MSA 5
Wearing Course (SDBC), mm 25
Binder Course (DBM), mm 50
Base Course (WMM), mm 250
Granular Sub-base Course (GSB), mm 150
Sub-grade layers, mm 500
2.0 EXECUTIVE SUMMARY
2.1 COMMENTS ON CONCESSIONAIRE MPR
The MPR was submitted on 16th July 2014.But it is to be submitted on or before 7 days after the close of each month as seen in article 13.1 of concession agreement .Financial progress achieved up to date is said to be 58.66% as planned 43.05%.
This achieved progress is said to be the payment made by the Concessionaire for which no records can be reviewed.
The Physical progress is said to be 58.20% and this figure is arrived at is not detailed. The reason for changes in the FRL is not yet properly documented.
2.2 PHYSICAL & FINANCIAL PROGRESS:
Cost of the Project: 900.51 CroresConstruction Period: 910 days Construction Time Lapse at the end of June 2014 : 409 days – 44.95%Construction Time Remaining at the end June 2014 : 501 days – 55.05%
Physical ProgressTill Last Month
(Up to May 2014) %
This Month(June 2014) %
To Date(End of June 2014) %
Scheduled (%) 38.17 3.01 41.18
Actual (%) 54.05 4.15 58.20
Financial Progress Till Last Month This Month To Date
Scheduled (%) 40.06 2.99 43.05
Actual (%) 54.57 4.09 58.66
Note: The S – Curve of the Financial Progress is shown in Annexure – 14.
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 7
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
2.3 WORKING METHODOLOGY : REVIEW OF DESIGNS & DRAWINGS
STATUS OF DRAWING APPROVALS (Highways)
S. No Details of drawings
Submitted by Concession-
aire
Comments/ Conditional
Approval given by IC/
NHAI.
Resubmitted by Concessionaire
after incorporating all
comments
GFC drawings
issuedRemarks
ROAD
1
Plan & Profile182+250 to 205+570 (23.32Kms)
23.32 km No Resubmitted YesGFC Drawings are issued
206+000 to 236+135 (30.18Kms) 30.18 km No Resubmitted Yes
GFC Drawings are issued
2 Typical Cross-section (Total 17Nos) 17 Reviewed and
Commented Resubmitted Yes GFC Drawings Issued
3 Miscellaneous Drawings
Junction Drawings submitted
Review and commented Resubmitted No
Under Review by IE
Median Openings and
Bus Bay
Reviewed and Commented Yes Yes
GFC Drawings Issued
STATUS OF DRAWING APPROVALS (STRUCTURES)
MAJOR BRIDGES
SUB STRUCTURE SUPER STRUCTURESUBMITTED APPROVED GFC
ISSUED SUBMITTED APPROVED GFC ISSUED
1.198+870 YES YES YES YES YES YES2.207+900 YES YES YES YES YES YES
MINOR BRIDGES
SUB STRUCTURE SUPER STRUCTURESUBMITTED APPROVED GFC
ISSUED SUBMITTED APPROVED GFC ISSUED
1.182+237 YES YES YES YES YES YES2.190+970 YES YES YES YES YES YES3.194+470 YES YES YES YES YES YES4.201+295 YES YES YES YES YES YES5.204+680 YES YES YES YES YES YES6.209+950 YES YES YES YES YES YES7.213+160 YES YES YES YES YES YES8.214+272 YES YES YES YES YES YES9.219+570 YES YES YES YES YES YES10.222+165 YES YES YES YES YES YES11.224+902 YES YES YES YES YES YES12.235+180 YES YES YES YES YES YES
GRADE SEPARATOR SUB STRUCTURE SUPER STRUCTURE
SUBMITTED APPROVED GFC ISSUED SUBMITTED APPROVED GFC
ISSUED1.203+900 YES YES YES YES YES YES
VEHICULAR UNDERPASS SUBMITTED APPROVED GFC ISSUED
1. 197+730 YES YES YES2. 202+750 YES YES YES3. 205+850 YES YES YES
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 8
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
4. 209+076 YES YES YES5. 217+310 YES YES YES6. 225+507 YES YES YES7.235+400 YES YES YESPEDESTRIAN UNDERPASS SUBMITTED APPROVED GFC ISSUED1. 187+350 YES YES YES2. 216+400 YES YES YES3. 222+680 YES YES YES4. 223+530 YES YES YES CULVERTS TOTAL SUMITTED APPROVED1.PIPE CULVERTS 51 30 19 Nos commented2.BOX CULVERTS 142 107 75 Nos commentedRE WALL SUBMITTED APPROVED GFC ISSUED1. 187+350(PUP approach) YES YES YES2. 197+730(VUP approach) YES YES YES3. 202+750(VUP approach) YES YES YES4. 206+310(VUP approach) NO NO NO5. 209+076(VUP approach) YES NO NO6. 216+337(PUP approach) YES YES YES7. 217+310(VUP approach) YES YES YES8. 222+622(PUP approach) YES YES YES9. 223+530(PUP approach) YES YES YES10. 225+500(VUP approach) YES NO NO11. 235+400(VUP approach) YES NO NO12.203+900(Grade Separator approach) YES NO NO
13.198+875(Major Bridge Approach RHS Vadakenchery side) YES YES YES
14.209+000(ROB) YES NO NO
2.4 STATUS OF MOBILISATIONa) Independent Engineer has mobilized their project team with effect from 15 thJune 2013
with their key personnel; Team Leader has been mobilized in the month of September 2013,Resident cum Highway Engineer, Sr. Quality Material Expert, Highway Design Engineer, Structural cum Bridge Engineer, Sr. Bridge Design Engineer, Assistant Highway Engineers, Assistant Bridge Engineers, Assistant Material Engineers, Survey Engineer and Administrative staff are mobilized in the month of June, July and August 2013. The project office was set up in Palakkad Town.
Sl. No Name Designation Date
Key Personnel (Professionals Staff)1 Mr. Mohammed Musthafa Basha TL cum Sr. HE2 Mr. Ashok Gupta Sr. Bridge Design Engineer3 Mr. K. Chandrasekhar Reddy Resident cum HE
4 Mr. Mohan Raj.S Highway Design EngineerRelieved
on 13.05.2014
5 Mr. Shaik Khasim Peera Bridge/Structural Engineer
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 9
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
6 Mr. Mohan Chawla Sr. Pavement Specialist7 Mr. J.K. Joshi Sr. Quality cum Material Expert8 Mr. Murali Krishna Traffic and Transportation Expert 9 Mr. Arif Zafar Road Safety Expert
10 Mr. Sandeep M Batta. Financial Expert 11 Mr. Raju Chhabra Legal Expert
Sub Professionals Staff1 Mr.M.S.Midhun/Mr. Ankaiah.M Survey Engineer(1)2 Mr.C.Siva Kumar/Mr.D.Udaya Bhaskar Survey Engineer(2)
3 Mr.Packiaraj.C AHE (1)Resigned
0n10.05.2014
4 Mr.P.Maruthy/Mr. Elango C AHE (2)Resigned
On08.05.2014
5 Mr. Ketan Jibhenkar CAD Expert6 Mr. Prateek Thakkar Environmental Engineer7 Mr. Jaganathan ABE (1)8 Mr.Dhakshinamurthy .R ABE (2)9 Mr. RejithBalakrishnan AME (1)
10 Mr. Mohammed Rafi AME (2)11 Mr. Subash Kholekar Electrical Engineer12 TBN HTMS/Toll Expert13 Mr.Santosh Akotkar Quantity Surveyor14 Mr. Gunwant Deotale Horticulture Cum Landscaping Expert
Administration Staff 1 Mr. V.P. Radhakrishnan Office Manager2 Mr.M.Sankar/Mr.Biju Accountant3 Mr. Prasadan C Cashier4 Mr.K.Vijayan/Mr.V.Sivadasan Photo Copy Machine Operator5 Mr. Mohammed Rafi Steno 6 Mr.Vaishak /Mr.K.Anu Kumar Computer Operator7 Mr.G.Manikandan/Mr.V.Janardhanan/Mr.Kumaran Day Guard8 Mr.Gopi/Mr.Velayudan/Mr.Unnikrishnan Night Guard9 Mr.V.Sivadasan/Mrs.A.Kamalam Photocopy Machine Operator
10 Mr.M.Manoj/Mr.V.Ramadas/Mrs. Ranjini Office Boy/Girl
Note: Details are shown in Independent Engineer Organization Chart – Annexure 1.
b) The Concessionaire has mobilized their key personnel and technical personnel for the project. The project office was set up near Walayar. They have constructed project office at Km. 187+420.
Project Monitoring & Control Team
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 10
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
Sl No. Name Designation1. E. SreenivasaRao Team Leader Cum Sr. Highway Engineer2. K.D.P. Rao Sr. Material Engineer3. Ajo Abraham Safety In- charge4. T. Gopal Krishna Land Acquisition In-charge5. Sudhakar Bridge Engineer6. Surendra Highway Engineer7. Sekhar Q.C. Engineer8. Ravi Survey Engineer9. Prasanth Reddy Lab Technician
Status of EPC Contractor Man Power mobilized at Site
Sl. No.
Name Designation Nos. Remarks
1. V.Venugopal Reddy Project Co-ordinator 1
2. M. Ramakrishna Reddy Project Manager 1
3. Ch. Yakambaram Construction Manager 1
4. C.Rajender Reddy Asst. General Manager (Mech.) 1
5. Vijay Kumar Pandey Chief Surveyor 1
6. Ritesh N Sr. Mechanical Engineer 1
7. P. Surender Reddy Manager Q & C 1
8. Tirupathi Reddy A In-charge Crusher / Plant 1
9. Panicker R S Admin. Manager 1
10. Purshottam Dash Accounts Manager 1
11. Accounts Team 3
12. Administration Team 17
13. Civil-Highway 17
14. Civil-Structure 38
15. Civil-Survey 8
16. Lab. Team 26
17. Earth Moving Equipment Operators 71
18. Workshop / Garage Team 42
19. All Plants Team 53
20. Drivers 89
21. Helpers 39
22. Store Team 24
23. Supervisor's Mechanical 16
Total 458
Note: Organization charts of SPV, EPC Contractor enclosed in Annexure – 2 & 3.
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 11
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
LIST OF PLANTS, MACHINERIES & EQUIPMENT
a) Plants
Sl.No
Name of the Equipment Make /Model Qty
Mobilized
Location (Road Side,
Quarry, Plant)
Date of Mobilizat
ionRemarks
1
Crusher
Puzzalona 150 TPH 1 No. Palathurai 05-01-2013
2 Nawa 250 TPH 1 No. Mangalamdam
18-01-2013
3 Puzzalona 250TPH 1 No. Pudussery East Village
24-04-2013
Total 3 No's
4
Batching Plant
Penta 60 Cum/Hr 1 No. PLANT @ Km. 187.000
10-10-2012
5 Miller 30 Cum/Hr 1 No. PLANT @ Km. 231.735
08-02-2013
6 SchwingStetter 30 Cum/Hr 1 No. PLANT @
Km. 207.00030-03-2013
Total 3 No's
7 HOT MIXING PLANT D&G 240 TPH 1 No. PLANT @
Km. 231.73531-03-2013
Total 1 No.
b) Machineries & Vehicles
Sl No. Name of the Equipment Make /Model Qty Mobilized1
Generators
Crompton Greaves 7.5 KVA 1 No.
2 Kirloskar 15 KVA 2 No.
3 Cummins 40 KVA 1 No.
4 Greaves 40 KVA 2 No.
5 Kirloskar 40 KVA 3 No’s6 Kirloskar 50 KVA 2 No’s7 Kirloskar 62.5 KVA 1 No.
8 Kirloskar 75 KVA 1 No.9 Kirloskar 100 KVA 1 No.
10 Cummins 125 KVA 2 No.
11 Catterpiller 200 KVA 2 No.
12 Catterpiller 365 KVA 1 No.
13 Catterpiller 500 KVA 2 No’s
14 Catterpiller 600 KVA 3 No’s
Total 24 No's15 Excavators KOBELCO SK 140 LC 8 3 No's
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 12
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
16 KOBELCO SK 210 12 No’s
17 Kobleco SK-350 LC 8 9 No's
18 Kobleco SK-480 LC 8 2 No’s.
Total 27 No's19
Soil Compactor
IR SD 110 6 No’s
20 CAT - 533E 3 No’s
21 CAT - CS533E 2 No.
22 IR ISD 100 5 No’s
23 IR SD Roller 2 No’s
24 PTR – 220 1 No.
Total 19 No's
25 Asphalt Compactor/Tandom Roller
Greaves 1 No.
26 Baby HD-12W 1 No.
Total 2 No's
27
Motor Grader
CAT-120 H 2 No’s
28 CAT-140 K 2 No’s
29 CAT-140 H 5 No’s
Total 9 No's
30
Dozers
CAT D5G 1 No.
31 CAT D5G XL 1 No.
32 CAT D6G XL 1 No.
Total 3 No's
33 Weigh Bridge Essae 3 No’s
34 Tyre Mounted Crane KATO 3 No.
35Hydra Crane
Escorts TRX 2319 1 No.
36 Escort F15 1 No.37 TIL 1 No.38 Tadano 2 No’s
39 Hydraulic crawler 100 Ton 2 No’s
Total 8 No’s
40 Boom Placer Putzmeister 2 No.
41
Loader
HM 2021 3 No’s
42 Liugon – CLG856 2 No’s
43 CAT 950H 2 No’s
Total 7 No’s
44 Lighting Source IR 4 No’s
45 Kerb Machines Appolo KP 40 1 No.
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 13
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
46Paver
Vogele 1 No.
47 CAT 1 No.
Total 2 No’s
48 Containers 12 No’s
49 Cement Silo 2 No’s
50 Riggers SANDVIK DX-700 1 No.
51 Breakers Doosan XL1700 4 No’s
52 Piling Machine MAIT 180 1 No.
53 Hydraulic Breaker Doosan 4 No’s
54
Tippers
Volvo 36 No’s
55 Bharat Benz 10 No’s
56 Bharat Benz (Rock Body) 4 No’s
57 AMW 18 No’s
58 Hino 10 No’s
59 Man 3 No’s
60 Ashok Leyland 9 No’s
Total: 88 No’s
61
Transit Mixers
Ashok Leyland 2 No.
62 TATA 2 No.
63 AMW 4 No.
64 Taurus 6 No’s
Total: 14 No’s
65 Eichers 6 No’s
66 Trailors 4 No’s
67 Water Tankers Ashok Leyland 6 No’s68 Tata 2 No’s
Total: 8 No’s69 Diesel Tankers TATA 2 No’s
70 Ashok Leyland 1 No.
Total: 3 No’s
71 Tractor with Compressors 9 No’s
72 LMV’s 24 No’s
73 Two Wheelers 16 No’s
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 14
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
c) List of Lab Equipments Mobilized at Site
Sl. No Description UnitEquipment Available
at LabRemarks
1 Hot air Oven (size 900mm X 600mm) No 1
2 Hot air Oven size 600mm X600mm No 1
3 Electronic Weighing Balance 20Kg capacity No’s 1
4 Electronic Weighing Balance 10Kg capacity No’s 5
5 Electronic Weighing Balance 50 kg capacity No’s 3
6 Electronic Weighing Balance 200 gm capacity No’s 1
7 Electronic Weighing Balance 60 Kg capacity No’s 2
8 Weighing Balance 30kg capacity with weights, manual operating No’s 3
9 Digital Thermometer range up to 0 deg C to 300 deg C No’s 10
10 Mercury in Glass Thermometer 0 deg C to 360 deg C No’s 10
SOIL TESTING EQUIPMENTS
11 Plastic Limit Set Set 2
12 Cone Penetrometer Set 2
13Atterberg Liquid Limit Device with casa Grande tools Hand operated with Counter as per IS: 2720(part - V)
No’s 2
14 Sand Pouring Cylinder (Sand Replacement Method) 100mm dia No’s 3
15 Sand Pouring Cylinder (Sand Replacement Method) 150mm dia No’s 6
16 Sand Pouring Cylinder (Sand Replacement Method) 200mm dia No’s 5
17 Trays with centre hole 100mm dia No’s 3
18 Trays with centre hole 150mm dia No’s 6
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 15
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
19 Trays with centre hole 200mm dia No’s 6
20 Sample Container 50mm No’s 6
21 Sample Container 75mm No’s 60
22 Sample Container 100mm No’s 40
23 Spatula No’s 4
24 Standard Compaction Test (Proctor Compaction Mould) 100mm internal dia No. 1
25 Standard Compaction Test (Proctor Compaction Mould) 150mm internal dia No’s 10
26 Speedy Moisture Meter 0% to 50% complete with chemicals No’s 4
27 Pycnometer (1 Ltr glass jar with brass cone locking ring and rubber seal) No’s 3
28 California Bearing Ratio Apparatus Electrically operated. No. 2
29 CBR Mould 150mm dia No’s 50
30 Displacer Block 148mm dia& 47.7mm long No’s 10
31 Surcharge Weight 2.5kgs No’s 100
32 Perforated Brass Plate with locking nut & stem No’s 80
33 Tripod Stand No’s 6
34 Cutting Collar No’s 7
35 Dial Gauge 0.01 mm X 25 BAKER make No’s 10
36
Test sieves for Coarse Aggregate made of GI Sheet 450mm dia as per IS-460(Part - I) sizes 125mm, 106, 100, 90, 16, 13, 2, 12.5, 11.2, 10, 9.5, 6.7, 6.3, 5.6, 4.75,2.36, 1.18mm
Set 2
37
Test sieves for Coarse Aggregate made of GI Sheet 300mm dia as per IS-460(Part - I) sizes 125mm, 106, 100, 90, 80, 75, 63, 60, 53, 50, 45, 40, 37.5, 31.5, 26.5, 25.22, 4, 20, 19, 16, 13.2, 12.5, 11.2, 10, 9.5, 6.7, 6.3, 5.6, 4.75, 2.36, 1.18mm
Set 2
38Test sieves for Fine Aggregate made of Brass frame and Stainless Steel Mesh as per IS: 460(Part-I) sizes 1.00mm
Set 4
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 16
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
1.18, 1.40, 1.70, 2.00, 2.8, 2.36, 3.35, 4.75mm and 850microns, 710, 600, 500, 425, 355, 250, 212, 180, 150, 100
39 -do- 75microns and 90 microns Set 14
40 Standard Sand each bag of 25kgs (Grade I,II,III Set 2
AGGREGATE & CEMENT TESTING EQUIPMENTS
41 Flakiness index (Thickness gauge) No’s 5
42 Elongation index (Length gauge) No’s 7
43 Cylindrical Measures (Metal Measures) 3 Lit, 15 Lit, 30 Lit capacity No’s 1
44 Density Basket No’s 4
45 Riffle Box No’s 1
46 Aggregate Impact Tester. No’s 2
47 Slump Test Apparatus No’s 10
48 Tamping Rod No’s 9
49 Flow Table motorized as IS:5512 No. 1
50 Laboratory Concrete Mixer Motorized capacity 1 cuft No. 1
51 Standard Spatula as per IS: 4031 No’s 2
52 Gauging Trowel as per IS: 4031 No. 1
53 Flexure Testing Machine motorized 100 KN capacity as IS: 516 No. 1
54Cube Moulds made of Cast Iron size 150mm X 150mm (8.25Kgs) as per IS: 4031, 516
No’s 200
55Cube Moulds made of Stainless steel 7.06cm X 7.06cm X 7.06cm as per IS: 4031,516
No’s 18
56 Vibrating Table size 1 mtr X 1 mtr No’s 1
57 Motor Cube Vibrator or Vibrating Machine No’s 1
58 Le- chrtlier Apparatus Set 10
59 Core Drilling Machine No’s 1
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 17
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
60 Flexure Beams as IS: 516 No’s 9
BITUMEN & BITUMENIOUS TESTING EQUIPMENT
60 Water bath capacity of 10 Ltrs. No’s 2
61 Ring and Ball Apparatus as per IS: 1205 - 1958 No’s 1
62 Flash & Fire Apparatus No’s 1
63 Specific Gravity Bottle 50ml BOROSIL make No’s 5
64 Dial Thermometer No’s 10
65 Depth Gauge - 12" No’s 10
66 Standard Penetro meter with needles electrically operated No’s 1
67 Ductility Testing Apparatus as per IS: 1208, 1958, ASTMD:D113 No’s 1
68 Centrifuge Bitumen Extractor (Motorized) No’s 2
69Marshall Stability Test apparatus Electrically operated load frame capacity 50KN
No’s 1
70 Marshall Moulds with base plate 100mm dia No’s 24
71 Marshall Rammer for 100mm mould No’s 8
72 Commercial Benzene Ltr 200
73 Say bolt Viscometer No. 1
74 Straight Edge with Steel Wedge Size 3 mtrs No’s 2
75 Camber Board No. 1
76 Trays 45cm X 45cm Set 43
77 Rain Gauge No’s 3
78 Compressive Testing Machine motorized 2000 KN capacity as IS: 516 No’s 1
79 Ten% fines value Apparatus No’s 1
80 Max - Minimum Thermometers No’s 5
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 18
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
81 Le- chatlier Flask No’s 4
82 Borosil jars 100ml No’s 8
83 Sand equivalent Apparatus No’s 1
84 Rubber Hammers No’s 4
85 Cube Moulds made 10cm X 10cm X 10cm as per IS: 4031,516 No’s 37
86 Cube Moulds made 5 cm X 5 cm X 5 cm as per IS: 4031,517 No’s 17
87 Electronic Weighing Balance 40 kg capacity No’s 2
88 Diamond Core Bits 100mm Dia No’s 4
89 Gmm Jars with vacuum pump No’s 2
90 Marshall Pedestal No’s 1
2.4. a SUMMARY OF ROAD PROGRESS-FOUR LANE COMPLETED
Sl. No Item Total
(Kms)Completed
(Kms)Balance(Kms)
1 Embankment 53.885 50.267 3.618
2 Subgrade 53.885 43.750 10.135
3 Granular Sub Base 53.885 29.250 24.365
4 Wet Mix Macadam 53.885 26.025 27.860
5 Dense Bituminous Macadam 53.885 25.785 28.100
6 Bituminous concrete 53.885 0.000 53.885
2.4. b. HIGHWAY PROGRESS LEANIER (MCW) as on 30-06-2014
Sl No.
Item
Left Side Right Side
Length
(Kms)
Comp.
(Kms)
Bal.(Kms
)
Length
(Kms)
Comp.
(Kms)
Bal.(Kms
)
1 Embankment 53.885
51.050 2.835 53.88
549.48
5 4.400
2 Subgrade 53.885
43.750
10.135
53.885
43.750
10.135
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 19
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
3 Granular Sub Base 53.885
29.750
24.135
53.885
28.750
25.135
4 Wet Mix Macadam 53.885
25.700
28.235
53.885
26.385
27.500
5 Dense Bituminous Macadam
53.885
25.185
28.700
53.885
26.385
27.500
6 Bituminous concrete 53.885 0.000 53.88
553.88
5 0.000 53.885
2.4. c. HIGHWAY PROGRESS LEANIER (Service Road) as on 30-06-2014
Sl No.
Item
Left Side Right Side
Length
(Kms)
Comp.
(Kms)
Bal.(Kms)
Length
(Kms)
Comp.
(Kms)
Bal.(Kms
)
1 Embankment 25.800
15.700
10.100
23.900 8.900 15.00
02 Subgrade 25.80
0 8.400 17.400
23.900 5.400 18.50
03 Granular Sub Base 25.80
0 7.900 17.900
23.900 5.300 18.60
04 Wet Mix Macadam 25.80
0 7.000 18.800
23.900 5.300 18.60
05 Dense Bituminous
Macadam25.80
0 4.500 21.300
23.900 5.300 18.60
06 Semi Dense Bituminous
Concrete25.80
0 0.000 25.300
23.900 0.000 23.90
0
2.5 STATUS OF STRUCTURES PROGRESS UPTO 30st JUN 2014
SL. No. Description Total No. Completed In
ProgressBalance to be
Taken up Remarks
1 Pipe Culverts 51 45 2 042 Box Culverts 142 124 6 12
3 Minor Bridges 12 9 3 - Approach slab in progress
4 CUP / PUP 4 4 0 - Approach slab in progress
5 VUP 7 3 4 -
Approach slab in progress
(3Nos of VUP in COS)
6 Major Bridges 2 2 0 -
Approach slab & expansion
joint in progress
7 R.O.B 1 - 1 08 Grade Separators 1+1(deleted
)- 1 0 Grade
separator at Km225+500
deleted and at Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 20
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
Km203+900 is in progress
9 Toll Plaza 1 - 1 -
Note: Details are given in Annexure – 11.
2.6 MATERIAL ,SOURCES & CONFIRMITY OF SPECIFICATIONS
1. TESTING All basic and routine tests for earth work, granular materials, bitumen materials and concrete
works are carried out at project laboratory. Test for cement, water, aggregate, admixture, reinforcement steel, low relaxation steel,
bitumen emulsions are being done at approved Independent Laboratory. Tests Like bearings, sheathing duct, NP4 Pipe etc are also done. Calibration for testing apparatus, Laboratory equipments and plants has been carried out. Concessionaire has established site Laboratory at the following Location:
Location Test CoverageKM 187 + 400 LHS 1. Earthworks
2. GSB3. Wet Mix Macadam4. Mineral Aggregates5. Concrete6. Bitumen and Bituminous mixes7. Cement
2. SOURCES OF AGGREGATE AND SAND
Fine and coarse aggregate for WMM,DBM,DC,BM,SDBC and Concrete etc are made available from a quarry located at off 5 Km 166+000 LHS about 20 Km from project starting point. Concessionaire already set up the quarry and crusher at 187+400 and 8Km off 232+000 LHS (near Mangalam dam location).
3. CONCRETE MIX DESIGN
The Concrete mix design carried out by the concessionaire have been verified and approved for permanent works using Chettinad,penna,Bharathi and dalmia Cement OPC 43 Grade.
SL.NO GRADE OF CONCRETE USED FOR
1 M15 PCC in Structures
2 M20 PCC in Structures3 M25 RCC in Structures
4 M30 RCC in Structures/ RE Wall Blocks
5 M35 Pile, Under Pass Slab
6 M40 RCC for Crash BarrierPQC for rigid pavement
7 M45 PSC Girder
8 M50 PSC Box Girder
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 21
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
QUALITY CONTROL TEST
Material testing has been done as per requirement of the contract and MORTH specification.
Quality Control Report From IE For the Month of June 2014
SOIL TESTING (Cut Soil & B A)
Sl.No Name of testTotal no of test done
Total no of test passed
Total no of test failed Remarks
1 Proctor Test 03 03 -2 Atterberg limits 03 03 -3 Free swell index 03 03 -4 Gradation 03 03 -5 CBR 00 00 -
WMM1 Gradation 05 052 Atterberg limits 05 053 AIV 03 034 FI & EI 03 03
CEMENT TESTING
Sl.No Name of testTotal no of test done
Total no of test passed
Total no of test failed Remarks
1 Consistency 04 04 -2 Initial setting time 04 04 -3 Final setting time 04 04 -4 Fineness - - -5 Soundness - - -6 Cement mortar cubes(3days) 01 01 -7 Cement mortar cubes(7days) 03 03 -8 Cement mortar cubes(28days) 03 03 -
GSB TESTING Gradation 02 02 Atterbergs Limits 02 02
AGGREGATE TESTING1 Gradation of 20mm 06 06 -2 Gradation of 12.5mm 06 06 -34
Gradation of Sand Combined Gradation
0606
0606 -
5 AIV 06 06 -6 Flakiness Index 06 06 -
BITUMEN TESTING
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 22
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
1 Penetration 01 01
2 Softening Point 01 01
DBM
1 Individual Gradation (28-18,18-12,12-5,5-0 & Filler) 00 00
2 Combined Gradation 00 003 Dry Mix Gradation 00 004 Extraction and Gradation 06 065 Stability & Flow 06 066 AIV 04 047 FI+EI 04 048 Core Density 20 209 Gmm 02 02
COMPRESSIVE STRENGTH OF CONCRETE OF CUBES1 M-10 DLC (7 days) 00 00 - -2 M-15 PCC (7 days) 00 00 - -3 M-15 PCC (28 days) 02 02 - -4 M-20 (7 days) 15 15 _ 5 M-20 (28 days) 27 27 _ 6 M-25 (7 days) 21 21 _ 7 M-25 (28 days) 18 18 _8 M-30 (7 days) 38 38 _
9 M-30 (28 days) 129 129__
10 M-35 (7 days) 13 13 _11 M-35 (14 days) 00 00 -
12 M-35 (28 days) 30 30 -13 M-40 (7 days) 35 35 -14 M-40 (14 days) 00 00 -15 M-40 (28 days) 40 40 -16 M-45 (7 days) 10 10 -17 M-45 (14 days) 00 0018 M-45 (21 days) 00 00 -19 M-45 (28 days) 12 1220 M-50 (7 DAYS) 01 0121 M-50 (7 DAYS) 15 1522 Grouting(7 days) 06 0620 Masonry cubes 14 14
Total Tests
Cumulative total by concessionaire up to 30th June 2014 34348
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 23
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
Total test done by Concessionaire in the month of 30th June 2014 2562 Test witnessed by IE 557(21.74 %)
MATERIALS SOURCESSL.NO PARTICULAR SUPPLIER
1 Cement, Grade OPC 43
1.Chettinad Cement2.Penna Cement3.Bharathi4.Dalmia
2 Reinforcing Steel bar (TMT) 1.RINL Vizag Plant2.JSW Steel Ltd, Salem
3 Admixture for Concrete 1.Fair mate Chemicals2.BASF
4 Low Relaxation,PC Stranded Wires 1.Tata Steel Wire Division5 Sheathing pipes 2.Rex Poly Extrusion Ltd.
6 NP4 pipes 1.Chennai Span Pipes Industries, Pollachi
7 Strip seal 1.Z-Tech (Industries) Ltd, New Delhi
8 Bitumen 1.MRPL Ltd, Mangalore
9 Emulsion 1.Hincol, Chennai 2.IWL Ltd Chennai
10 Bearing (POT-PTEE Megaba Bridge Products Pvt Ltd, Kolkata 11 Pre-stressing System BBR India Pvt Ltd, Banglore12 RE Wall System STRATA GEO SYSTEM (I) PVT LTD13 Strip Seal Expansion Joints SANFIELD BHOPAL
2.7. PRE CONSTRUCTION ACTIVITIES
2.7 a Land acquisition
As per clause 10.3.2 under Article 10 of the Concession agreement, the authority has to handover 80% or more of land required for four laning of the project highway before or on appointed date. Clause 10.3.1 requires Authority and Concessionaire to jointly inspect the site and prepare a memorandum which includes an inventory of vacant and unencumbered land, buildings, structures, road works, trees etc. It must also have an Annexure showing parts of site where vacant access and right of way have not been handed over to the client.
A memorandum of inventory was signed on the 14 th March 2013 by the Authority, Concessionaire and the EPC Representative mentioning that 92% of land is available and only 8% is to be handed over. As per Clause 10.3.2 of CA, at least 80% of the land shall be handed over on or prior appointed date.The details of land handed over till is as given under in Table 4.1:
Table 4.1 Details of land handed over to Concessionaire as of 30th June, 2014
S. No Description
SideTotalLHS
(Sqm)RHS
(Sqm)
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 24
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
1 Total Land to be Made available 1124015 1484524 26085392 Area Handed over up to May'
2014 1121318 1484152 2605470
3 Area made available in June' 2014 750 0 750
4 Balance land yet to be made available 1947.5 372.00 2319.5
% of Land to be made Available 0.09%
2.7 b Shifting of Utilities
As per the provisions of CA, 80% of Hindrance free land shall be handed over to the concessionaire on appointed date
2.7 c Tree Cutting
The tree cutting has been already awarded by NHAI directly to third party agency, and tree cutting is in progress. There are approximately 4365 trees to be cut in the project highway as on date 4173 Nos were cut and there is a balance about 192 Nos to be cut and removed from site, as confirmed after Joint Site Visit by IE & Concessionaire.
Details of Tree Cutting
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 25
From To From To1 182.250 183.000 0.750 0 0 0 28 209.000 210.000 1.000 0 0 02 183.000 184.000 1.000 0 5 5 29 210.000 211.000 1.000 3 0 33 184.000 185.000 1.000 0 9 9 30 211.000 212.000 1.000 0 0 04 185.000 186.000 1.000 0 10 10 31 212.000 213.000 1.000 0 0 05 186.000 187.000 1.000 0 40 40 32 213.000 214.000 1.000 0 0 06 187.000 188.000 1.000 0 0 0 33 214.000 215.000 1.000 0 0 07 188.000 189.000 1.000 4 0 4 34 215.000 216.000 1.000 0 0 08 189.000 190.000 1.000 0 0 0 35 216.000 217.000 1.000 2 10 129 190.000 191.000 1.000 0 0 0 36 217.000 218.000 1.000 0 0 010 191.000 192.000 1.000 0 0 0 37 218.000 219.000 1.000 0 0 011 192.000 193.000 1.000 0 0 0 38 219.000 220.000 1.000 0 4 412 193.000 194.000 1.000 0 0 0 39 220.000 221.000 1.000 0 7 713 194.000 195.000 1.000 0 0 0 40 221.000 222.000 1.000 0 0 014 195.000 196.000 1.000 0 0 0 41 222.000 223.000 1.000 0 0 015 196.000 197.000 1.000 0 5 5 42 223.000 224.000 1.000 1 0 116 197.000 198.000 1.000 0 1 1 43 224.000 225.000 1.000 1 0 117 198.000 199.000 1.000 0 0 0 44 225.000 226.000 1.000 1 4 518 199.000 200.000 1.000 0 0 0 45 226.000 227.000 1.000 0 0 019 200.000 201.000 1.000 9 0 9 46 227.000 228.000 1.000 0 0 020 201.000 202.000 1.000 0 8 8 47 228.000 229.000 1.000 0 0 021 202.000 203.000 1.000 0 0 0 48 229.000 230.000 1.000 0 0 022 203.000 204.000 1.000 0 0 0 49 230.000 231.000 1.000 0 0 023 204.000 205.000 1.000 4 0 4 50 231.000 232.000 1.000 3 6 924 205.000 206.000 1.000 0 0 0 51 232.000 233.000 1.000 5 10 1525 206.000 207.000 1.000 0 0 0 52 233.000 234.000 1.000 2 10 1226 207.000 208.000 1.000 0 0 0 53 234.000 235.000 1.000 2 5 727 208.000 209.000 1.000 0 0 0 54 235.000 236.135 1.135 6 15 21
S. No
Chainage LengthS. No
Chainage Length LHS RHS Total Remarks RemarksLHS RHS Total
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
Total Length 53.885 Balance Trees 192
2.7 d. Utility Shifting- ElectricalRegarding electrical lines, Kerala State Electricity Board (KSEB) has furnished 9 Nos of estimates for shifting electrical utilities in the divisions of Palakkad, Chitur and Alathur for an amount of Rs. 4.156 Cr. Further PIU, NHAI vide their letter no NHAI/PD/Palakad/KL-2/352 Dt 4th March 2013 entrusted the work of shifting of electrical lines is given to the concessionaire at KSEB approved rates. Concessionaire entrusted the shifting of Electrical to EPC Contractor under variation item. As per approved estimate NHAI paid Supervision charges to KSEB. The shifting of electrical utilities is in progress by the EPC contractor.As on date 36.950 Kms (i.e. 68.57 %) have been shifted out of 53.885 Kms,.
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 26
53.885 313Total Length Balance Trees
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
Details of Electrical – Utility Shifting
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 27
From To1 182.250 183.000 0.750 Completed -2 183.000 184.000 1.000 Completed -3 184.000 184.300 0.300 Completed -4 184.300 185.000 0.700 Completed -5 185.000 186.000 1.000 Completed -6 186.000 187.000 1.000 Completed -7 187.000 188.000 1.000 Completed -8 188.000 189.000 1.000 Completed -9 189.000 190.000 1.000 Completed 1 NO TRANSFORMER SHIFTING PENDING10 190.000 191.000 1.000 Completed -11 191.000 192.000 1.000 Completed -12 192.000 193.000 1.000 Completed -13 193.000 194.000 1.000 Completed -14 194.000 195.000 1.000 Completed LTline shifting- 9 spans15 195.000 196.000 1.000 In progres HT Crossing,HT & LT LINE In Progress16 196.000 197.000 1.000 In progres work in progress (1no’s road crossing and 2 no’s LT line)17 197.000 198.000 1.000 Completed -18 198.000 199.000 1.000 Completed HT Crossing,Trasformer shifting inprogres19 199.000 200.000 1.000 Completed -20 200.000 200.800 0.800 In progres -21 200.800 201.000 0.200 Completed -22 201.000 202.000 1.000 Completed Trasformer Shifting in progress23 202.000 203.000 1.000 In progres 2no Crossings removed line under progress 24 203.000 204.000 1.000 Completed -25 204.000 205.000 1.000 In progres 1 DP shifting completed & Tree cutting in progress26 205.000 206.000 1.000 In progres Tree Cutting & Buidling Dismantling in progress27 206.000 207.000 1.000 In progres Trasformer Shifting in progress28 207.000 208.000 1.000 In progres 1 NO LT CROSSING,3- SPAN LT LINE pending29 208.000 209.000 1.000 Completed Poles lifting & Conductor laying work completed30 209.000 210.000 1.000 Completed -31 210.000 211.000 1.000 Completed -32 211.000 212.000 1.000 Completed -33 212.000 213.000 1.000 Completed -34 213.000 214.000 1.000 Completed 1 no LT Crossing35 214.000 215.000 1.000 Completed -36 215.000 216.000 1.000 In progres 1 no LT Crossing completed 37 216.000 217.000 1.000 Completed -38 217.000 218.000 1.000 Completed -39 218.000 219.000 1.000 In progres 1 no LT Crossing completed 40 219.000 220.000 1.000 Completed 1 no LT Crossing completed 41 220.000 221.000 1.000 Completed -42 221.000 222.000 1.000 In progres HT and LTcrossing-1no,LTline shifting-4no underprogress43 222.000 223.000 1.000 In progres HT line progress at underpass44 223.000 224.000 1.000 Completed -45 224.000 225.000 1.000 Completed -46 225.000 226.000 1.000 In progres HT Cros,Htline shifting-5 spans, 47 226.000 227.000 1.000 Completed -48 227.000 228.000 1.000 Completed -49 228.000 229.000 1.000 Completed LT 5-span Pending50 229.000 230.000 1.000 Completed51 230.000 231.000 1.000 Completed -52 231.000 232.000 1.000 Completed -53 232.000 233.000 1.000 In progres -54 233.000 234.000 1.000 In progres -55 234.000 235.000 1.000 In progres -56 235.000 236.000 1.000 In progres -57 236.000 236.135 0.135 In progres -
53.885
S.No Chainage Length Status of Work Remarks
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
Total Electrical lines shifting length completed - 36.950 Kms.2.7 e. Utility Shifting- Water supply lines
Similarly, towards shifting water supply utility lines 7 Nos estimates amounting Rs. 4.09 Cr. have been furnished by Kerala Water Authority (KWA) covering Rural Water Supply schemes (RWSS) in seven towns and 5 estimates belonging to 5 local Panchayat. The shifting of water supply utility lines has been begun by the EPC Contractor. PD, PIU, NHAI entrusted the work of shifting of water supply lines is given to the concessionaire at KWA approved rates. Concessionaire entrusted the shifting of Electrical to EPC Contractor under variation item.The shifting of Water Supply lines has been started by the EPC contractor. As on date 23.450 Kms (i.e 73.05%) have been shifted out of 32.650 Kms.
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 28
From To1 182.250 183.000 0.750 Completed -2 183.000 184.000 1.000 Completed -3 184.000 184.300 0.300 Completed -4 184.300 185.000 0.700 Completed -5 185.000 186.000 1.000 Completed -6 186.000 187.000 1.000 Completed -7 187.000 188.000 1.000 Completed -8 188.000 189.000 1.000 Completed -9 189.000 190.000 1.000 Completed 1 NO TRANSFORMER SHIFTING PENDING10 190.000 191.000 1.000 Completed -11 191.000 192.000 1.000 Completed -12 192.000 193.000 1.000 Completed -13 193.000 194.000 1.000 Completed -14 194.000 195.000 1.000 Completed LTline shifting- 9 spans15 195.000 196.000 1.000 In progres HT Crossing,HT & LT LINE In Progress16 196.000 197.000 1.000 In progres work in progress (1no’s road crossing and 2 no’s LT line)17 197.000 198.000 1.000 Completed -18 198.000 199.000 1.000 Completed HT Crossing,Trasformer shifting inprogres19 199.000 200.000 1.000 Completed -20 200.000 200.800 0.800 In progres -21 200.800 201.000 0.200 Completed -22 201.000 202.000 1.000 Completed Trasformer Shifting in progress23 202.000 203.000 1.000 In progres 2no Crossings removed line under progress 24 203.000 204.000 1.000 Completed -25 204.000 205.000 1.000 In progres 1 DP shifting completed & Tree cutting in progress26 205.000 206.000 1.000 In progres Tree Cutting & Buidling Dismantling in progress27 206.000 207.000 1.000 In progres Trasformer Shifting in progress28 207.000 208.000 1.000 In progres 1 NO LT CROSSING,3- SPAN LT LINE pending29 208.000 209.000 1.000 Completed Poles lifting & Conductor laying work completed30 209.000 210.000 1.000 Completed -31 210.000 211.000 1.000 Completed -32 211.000 212.000 1.000 Completed -33 212.000 213.000 1.000 Completed -34 213.000 214.000 1.000 Completed 1 no LT Crossing35 214.000 215.000 1.000 Completed -36 215.000 216.000 1.000 In progres 1 no LT Crossing completed 37 216.000 217.000 1.000 Completed -38 217.000 218.000 1.000 Completed -39 218.000 219.000 1.000 In progres 1 no LT Crossing completed 40 219.000 220.000 1.000 Completed 1 no LT Crossing completed 41 220.000 221.000 1.000 Completed -42 221.000 222.000 1.000 In progres HT and LTcrossing-1no,LTline shifting-4no underprogress43 222.000 223.000 1.000 In progres HT line progress at underpass44 223.000 224.000 1.000 Completed -45 224.000 225.000 1.000 Completed -46 225.000 226.000 1.000 In progres HT Cros,Htline shifting-5 spans, 47 226.000 227.000 1.000 Completed -48 227.000 228.000 1.000 Completed -49 228.000 229.000 1.000 Completed LT 5-span Pending50 229.000 230.000 1.000 Completed51 230.000 231.000 1.000 Completed -52 231.000 232.000 1.000 Completed -53 232.000 233.000 1.000 In progres -54 233.000 234.000 1.000 In progres -55 234.000 235.000 1.000 In progres -56 235.000 236.000 1.000 In progres -57 236.000 236.135 0.135 In progres -
53.885
S.No Chainage Length Status of Work Remarks
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
Details of Water Supply Lines - Utility Shifting
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II Page | 29
From To183.200 183.800 0.600 160 mm PVC RHS 0.500 0.100 183.200-183.700=0.500183.900 184.400 0.500 140 mm PVC LHS 0.400 0.100 183.900-184.300=0.400185.400 186.600 1.200 90 mm PVC LHS 1.200 0.000 185.400-186.600=1.200185.400 186.600 1.200 80 mm GI LHS 0.600 0.600 186.000-186.600=0.600
3 RWS to Canal Piruvu 187.900 188.200 0.300 75 mm PVC LHS 0.000 0.300 -194.900 197.800 5.800 110 mm PVC RHS 5.200 0.600 195.000-197.800=2.600*2194.900 197.800 2.900 250 mm PVC LHS 2.700 0.200 195.100-197.800=2.700199.400 201.000 3.200 160 mm PVC RHS 3.200 0.000 199-400-201.000=3.200200.500 200.700 0.200 160 mm PVC LHS 0.000 0.200 -200.700 201.000 0.600 90 mm PVC BHS 0.600 0.000 201.400-201.700=0.600201.350 201.500 0.150 63 mm PVC LHS 0.150 0.000 201.350-201+500=0.150202.100 202.450 0.350 110 mm PVC LHS 0.150 0.200 202.100-202.250=0.150202.100 202.450 0.350 90 mm PVC RHS 0.200 0.150 202.100-202.300=0.200202.450 203.100 0.650 90 mm PVC LHS 0.400 0.250 202.600-203.000=0.400202.500 203.100 0.600 110 mm PVC RHS 0.500 0.100 202.500-203.000=0.500202.500 203.100 0.600 160 mm PVC LHS 0.450 0.150 202.500-202.950=0.450203.100 203.700 0.600 90 mm PVC LHS 0.000 0.600 -203.100 204.200 1.100 110 mm PVC RHS 0.400 0.700 203.450-203.850=0.400203.100 204.200 1.100 160 mm PVC LHS 0.400 0.700 203.450-203.850=0.400204.000 204.600 0.600 90 mm PVC LHS 0.400 0.200 204.000-204.400=0.400206.900 207.700 0.800 90 mm PVC RHS 0.000 0.800 -206.800 207.700 0.900 110 mm PVC RHS 0.000 0.900 -206.400 207.700 1.300 140 mm PVC LHS 0.700 0.600 206.600-207.300=0.700213.100 214.400 1.300 160 mm PVC RHS 1.300 0.000 213.100-214.440=1.300213.100 214.400 1.300 90 mm PVC RHS 1.300 0.000 213.100-214.440=1.300213.300 213.800 0.500 75 mm PVC LHS 0.500 0.000 213.300-213.800=0.500214.600 215.600 1.000 250 mm PVC RHS 1.000 0.000 214.600-215.500=1.000215.300 215.500 0.200 250 mm PVC LHS 0.200 0.000 215.300-215.500=200215.750 216.300 0.550 200 mm PVC RHS 0.000 0.550217.700 219.400 1.700 140 mm PVC RHS 1.400 0.300 217.700-219.100=1.400217.900 218.400 0.500 90 mm PVC LHS 0.000 0.500
32.650 23.850 8.800Total length
4 RWS to Pudussery
5 RWS to Marutha Road
6 Palakkad
1 RWS to Walayara
2 RWS to Vattappara
7 RWS to Kuzhalmannam
S.No Location Chainage Estimated Length in KM
Pipe Dia Side Completed Length in KM
Balance in KM Status of Work
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
2.8 ENVIRONMENTAL PROTECTIONIndependent Engineer staff carries out regular site visits and observe the construction areas and check the following areas:
Stone quarries and borrow areas;
Crusher plants;
Storage area of Oil and Lubricants yard;
Roadways and Campsite;
Disposal of debris and unsuitable materials.
Keeping in view to the environment compliances, the Concessionaire has been instructed to avoid damage or nuisance to persons or to property of the public or other resulting from pollution, noise or other causes arising as a consequence of their method of operation.
There were certain issues to be complied by the Concessionaire as mentioned below: - Improper debris disposal and management. Improper waste management. Inadequate drainage/waste water disposal facility. Improper Borrow area operation and management.
2.9 ROAD SAFETY
The existing two lanes though in good shape and in service the riding quality were constantly
checked. Some Potholes had been filled up. where construction is in progress, the following
action has to be implemented by Concessionaire to increase the safety to road users;
a)Warning and information signs in line with IRC/MORT&H standards and specification;
b)Signage boards at junction/urban areas to control the speed;
c)Barricades and reflector tapes to areas where ongoing excavation are carried out;
Concessionaire was regularly reminded to keep acceptable safety arrangements at construction zones as per IRC-SP-55 for smooth flow of traffic. Independent Engineer instructed to Concessionaire to improve the road safety vide our letter no. IE/APL/KL-2/2013/002 and letter no IE/APL/Kl-2/2013/005 safety measures during four lane construction.
2.10 ROAD ACCIDENT REPORT
Independent Engineer is given instructions to Concessionaire to collect and submit the accidental data for every month, identify accidental prone zones to made adequate safety arrangements, signboards etc. to avoid accidents. Advised to carryout safety audit along with Independent Engineer Representative.
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II Page | 30
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II Page | 31
Client : National Highways Authority of IndiaIndependent Engineer : Artefact Projects LimitedConcessionaire : KNR Walyar Tollways Private LimitedEPC Contractor : KNR Constructions LimitedName of PIU's / CMU's : Palakkad1) Stretch : Walayar - Vadakkancherry2) Stretch Chainage : Km. 182.250 to Km. 240.0003) State : Kerala4) District : Palakkad5) Police Station :
A B C D E F G H
Accident Location
Nature of Accident
Classification of Accident Causes Road
featureRoad
Condition
Intersection Type and Control
Weather Conditoin Fatal Grevious Minor Non-
injured
1 05-06-2014 07:30:00:PM 235+300 2 2 2 2 1 2 3 Motor CycleKL49D 9893- Cycle KL0 92016 - 1 - - - -
2 07-06-2014 06:45:00:PM 192+000 8 3 2 2 2 1 3 Lorry HR55K 4652 - Pedestrain - - 1 - - -
3 08-06-2014 11:30:00:AM 226+050 8 2 2 2 1 - 3 Auto KL49 A 1977 - Pedestrain - 1 - - - -
4 12-06-2014 02:15:00:PM 194+500 3 3 2 2 1 - 3 Lorry TN34 P 547 - Motor Cycle - - 1 - - -
5 13-06-2014 06:00:00:PM 200+700 8 1 2 2 2 - 3 Bus KL09 AG 3518 - Pedestrain 1 - - - - -
6 19-06-2014 01:30:00:PM 228+100 2 3 2 4 2 2 3 Car KLP7126 - Truck TN42Y 5199 - - 1 - - -
7 24-06-2014 05:45:00:PM 209+950 3 3 2 2 1 3 1 Truck KL19C 7477 - Motor Cycle KL9W 6603 - - 1 - - -
8 25-06-2014 08:00:00:PM 205+500 2 2 2 2 1 - 1 Car KL42 D 1322 - J eep - 1 - - - -
9 25-06-2014 10:00:00:PM 200+000 2 2 2 2 2 - 1 Motor Cycle TN37CD8659-Truck - 1 - - - -
10 26-614 11:00:00:AM 227+100 3 3 2 4 1 - 1 Car KA04MM8411 - Auto KL51 8165 - - 1 - - -
ACCIDENT DATA
Sl No. DateTime of
Acc. (am/pm)
Vehicle Responsible
No. of affected Persons No. of Animals killed if
any
Help Provided by Ambulance /
patrolling Vehicle
Remarks
Walayar, Kasaba, Palakkad Rural Circle, Kozhalmannam, Alathur, Vadakkencherry
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
2.11 MAINTENANCE OF EXISTING TWO LANE HIGHWAY
Independent Engineer given instructions to concessionaire to carry out the routine maintenance of existing carriage way i.e., filling of pot holes, patches and removal of water in water logged areas on the existing carriage way.
The Concessionaire is taking regular actions in the maintenance of the existing carriage way in the month of June 2014.It was made aware to the Concessionaire road maintenance shall be a continuous process until the Schedule Date of Completion and until the O& M team to takes over the Highway.
2.12 WORKING METHODOLOGY
The method of construction is submitted by the concessionaire and reviewed by the Independent Engineer. Field works are monitored by conducting field and laboratory tests, Materials used are in compliance with Specification and Standards.
2.13 CONFIRMITY OF SPECIFICATION OF STANDARD OF WORKS
The source of materials used for the construction works are regularly checked by Independent Engineer for conformity with the Specifications and Standards. Routine checks were regularly conducted by the Independent Engineer field team. The Team Leader also attended to some tests like cube crushing etc. during his site inspection with the Concessionaire. It was found that the materials used were within limits of Specifications and Standards were being maintained by the Concessionaire in the month of June 2014. The quality of materials used for execution and other tests were all within the specified limits.
The structural works that is major bridges, minor bridges, VUP and Box Culverts are in progress; Independent Engineer representatives are regularly attending and checking the activities.
2.14 NON COMPLIANCE REPORT (N C R) FOR RECTIFICATIONS DEFAULTS
So far 7 Nos NCR was issued to the Concessionaire.So far 6 Nos of NCR was closed.
2.15 REQUEST FOR INSPECTION (R F I)
2.16 TEAM LEADER’S COMMENTS, LAPS, DEFECTS & DEFIENCES
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II Page | 32
Number of RFI’s submitted by Concessionaire and attended/checked and closed by IE:
From 01-06-2014 to 30-06-2014
Sl. No. DescriptionTotal No. of RFIs
submitted by Concessionaire
Attended/ Checked
by IE% age
attendedNo. of RFIs
approvedRemarks
1 For Materials 2 2 100 2
2 For Highway 1062 114 10.73% 114 3 For Structures 742 87 11.7% 87
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
The programmed monthly financial progress on 01-06-2014 to 30-06-2014 is 43.06 % and achieved is58.66 % . Physical progress programmed is 41.18 and achieved is 58.20%
The first mile stone is surpassed. The ensuing month progress also shall be overcome.The second milestone also achieved by 31st March 2014 i.e 35 % i.e 400 days from the appointed date (June 21st 2014)The Cumulative planned progress up to 30th June is 43.05% achieved 58.66 %.
1. There are total 221 no cross structures. The progress of structures 2 nos Pipe culverts, 3 nos. minor bridges, 4 nos. VUP, 6nos Box culverts, 1 No grade separator, 1 No ROB, are in progress. 4 nos pipe culverts and 12 nos box culverts to be taken up. Major Bridge 2no(approach slab & expansion joint not done) ,Minor Bridges 9Nos (approach slab & expansion joint in progress),VUP 3nos,PUP 4nos (approach slab & expansion joint not done),Box culverts 124nos,Pipe culverts 45nos,. Completed..
2. Highway progress, Embankment Top 51.050 (LHS) ,49.485 (RHS) Kms. Sub Grade Top 43.750 (LHS), 43.750 (RHS) Kms. Completed, GSB 29.750 (LHS),28.750 (RHS) Completed.WMM 25.700 Kms (LHS) 26.385 Kms (RHS), Completed.DBM 25.185 (LHS), 26.385 (RHS)., BC not yet started.
3. Traffic was diverted at 206+200 LHS for Construction of under pass and 234+240 RHS and LHS for Construction of VUP. Concessionaire was instructed to provide adequate Safety arrangement as per IRC SP 55 at Traffic Diversion Locations.
4. Concessionaire was instructed to improve Road Safety at Construction Zones as per IRC -SP 55.
5. Cleaning the encumbrances, tree cutting, shifting of electrical poles and water supply lines are in progress which is to be completed early.
6. RFI are to be submitted to Independent Engineer in advance so that arrangements can be made for inspection.
7. Environmental returns submitted for one half year. To submit periodically.8. Safety arrangements are to be increased at the bye pass locations of structures.9. Highway maintenance during construction period is to be continued. Pre Rainfall works to
complete.10. Casting of RE Blocks is in progress at 3 locations. So far casted is less than 50% . Balancing
to increase daily out turn. 11. Toll plaza building works at Km 189+438 LHS in progress, PQC laying in progress.12. R.E Wall erecting is in progress at.197+730,217+520,203+900,220+620 and 223+520 Geogrid
laying is in order. Placing filter media is to be required width. Wherever there is culverts below the RE wall, proper encasing is required .Required special type of soil to form in between the RE walls is to be borrowed .This may delay Highway works. During rainy season Borrowing is not passable, Advance action is necessary.
13. At.197+730 Blocks are cracking. Under investigation. 14. Back filling of Structures with filter media not up to the standard, it should be improved15. Curing of structures to improve. A set of cubes casted is to be cured at site condition and
tested.16. Adjacent to the structures and culverts walls on embankment side to be filled with Filter media
and rolled with Baby rollers.17. Electrical design and drawings for street lighting, near toll plaza, for HTMS are to be decided
prior to doing any B.T. works.18. The surface drainage system is decided laying 600 dia pipes done in few locations before
DBM.19. Utility crossings in the entire length of the project is to be provided so that any public Utilities
shall pass through it without cutting the highway. 20. The exposed concrete faces like head wall etc shall be neatly finished.
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 33
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
21. Fixing of strip seal joints to be done after lying BC on structures. 22. Crushing of aggregates seems to be slowed. This is to be watched. 23. Balance design and drawings need approval should be submitted early. a. Working cross section for every 50 meters intervals is to be submitted.
b. Electrical street lighting to submit. c. Trees plantations in median and in ROW., resubmit attending remarks.
2.17 WEATHER CONDITIONS & REPORTIndependent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 34
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
S. No Date
TEMPARATURE 0C RAIN FALL (mm)
Camp : at Km. 187+500 (RHS)
Camp : at Km. 232+180 (LHS)
Camp : at Km.
187+500 (RHS)
Camp : at Km.
232+180 (LHS)Max 0C Min0C Max 0C Min0C
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 35
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
1 01.06.2014 36.5 25.4 37.2 25.6 0.0 0.02 02.06.2014 35.4 25.0 36.3 24.9 0.0 0.03 03.06.2014 34.0 25.2 35.2 25.3 0.0 0.04 04.06.2014 35.2 24.5 34.4 25.5 0.0 0.05 05.06.2014 36.0 25.0 36.2 25.8 0.0 0.06 06.06.2014 35.2 24.5 35.3 24.6 0.0 0.07 07.06.2014 36.4 25.0 37.0 25.9 0.0 0.08 08.06.2014 35.7 24.5 36.2 25.2 0.0 4.09 09.06.2014 36.4 25.5 34.2 25.8 0.0 0.010 10.06.2014 34.5 25.0 35.1 25.9 0.0 0.011 11.06.2014 35.6 24.5 35.2 24.3 2.0 2.012 12.06.2014 33.1 25.4 33.8 25.2 0.0 2.013 13.06.2014 32.0 24.4 32.6 24.8 0.0 3.014 14.06.2014 31.5 23.5 31.3 24.5 0.0 2.015 15.06.2014 30.6 24.0 31.1 24.6 0.0 0.016 16.06.2014 31.7 23.5 32.1 24.3 0.0 0.017 17.06.2014 30.4 24.0 30.9 25.4 2.0 14.018 18.06.2014 31.7 23.5 31.3 25.2 41.0 0.019 19.06.2014 28.4 24.2 29.2 24.8 20.0 11.020 20.06.2014 27.3 24.7 28.6 25.1 16.0 14.021 21.06.2014 27.0 23.5 29.2 25.9 5.0 58.022 22.06.2014 26.5 24.0 28.9 25.6 3.0 35.023 23.06.2014 25.7 23.0 29.2 24.9 0.0 2.024 24.06.2014 27.0 23.5 26.6 25.6 0.0 0.025 25.06.2014 28.5 24.5 29.3 25.2 0.0 0.026 26.06.2014 27.0 23.5 27.8 25.9 0.0 0.027 27.06.2014 26.5 24.0 29.2 26.2 0.0 0.028 28.06.2014 31.5 23.0 31.2 25.9 0.0 0.029 29.06.2014 30.4 23.5 30.9 26.2 0.0 0.030 30.06.2014 31.5 24.0 31.2 25.8 0.0 0.0
This Month Total Rainfall: mm 89.000 147.000
upto previous Month Rainfall: mm 2186.700
Total Rainfall: mm 2422.700Print separate
1. (ORG CHART of IE IN FOLDER)
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 36
BOARD OF DIRECTORS
VICE PRESIDENT/PROJECT HEAD
GENERAL MANAGER IN HOUSE DESIGN &FINANCE (HO) MONITORING TEAM
SITE OPERATIONS PROJECTMANAGEMENT & CONTROL TEAM
CHEIF PROJECT MANAGERHIGHWAY BRIDGES
SAFETY TEAM O & M TEAM QUALITY LAOFFICERCONTROL
EPC CONTRACTOR(M/s KNR Constructions Limited)
Four Laning of Walayar - Vadakancherry Section in Kerala (Km. 182.250 to Km. 240.000 of NH-47) - Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
ORGANIZATION CHART OF SPV
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
2. Organization Chart of SPV
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II Page | 37
BOARD OF DIRECTORS
VICE PRESIDENT/PROJECT HEAD
GENERAL MANAGER IN HOUSE DESIGN &FINANCE (HO) MONITORING TEAM
SITE OPERATIONS PROJECTMANAGEMENT & CONTROL TEAM
CHEIF PROJECT MANAGERHIGHWAY BRIDGES
SAFETY TEAM O & M TEAM QUALITY LAOFFICERCONTROL
EPC CONTRACTOR(M/s KNR Constructions Limited)
Four Laning of Walayar - Vadakancherry Section in Kerala (Km. 182.250 to Km. 240.000 of NH-47) - Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
ORGANIZATION CHART OF SPV
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
3. Organization Chart of EPC Contractor
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 38
Jr. ENGINEERs – 10
CIVIL MATEs – 10
SUPERVISORs – 10
SR. ENGINEERs– 2(to be named)
STORES MANAGERMr. Ravinder Reddy
STORE ASST.s– 4
STORE CLERKs -10
AGM (MECHANICAL)
Mr. C. Rajender Reddy
PRO
ASST. LIAISONING OFFICERs -2
Sr. MECHANICAL ENGINEER(Mr. Ritesh)
Jr.MECHANICAL ENGINEERs -5
MECHANICs -20
PLANTS INCHARGEA. Tirupathi Reddy
CRUSHER INCHARGE -3
H M PLANT INCHARGE -2
BATCHING PLANT
INCHARGE -3
ACCOUNTS MANAGER
ACCOUNTANTS -3
ADMIN. & HR MANAGER
ASST. MANAGERADMIN.
WORKS CO-ORDINATOR
CAMP INCHARGE
ASST. CAMP INCHARGEs-2
SITEINCHARGEs-3
Dy. PROJECT MANAGER Mr. G. Bamhananda Reddy
CONSTRUCTION MANAGER
CONSTRUCTION MANAGER
PROJECT MANAGER -HIGHWAYSMr. M. Ramakrishna Reddy
Jr. ENGINEERs – 8
CIVIL MATEs – 8
SUPERVISORs – 10
Jr. ENGINEERs – 8
CIVIL MATEs – 8
SUPERVISORs – 10
CONSTRUCTION MANAGER -
Mr. Vinod Saga
Material Engineer1. Mr. P. Surender Reddy2. Mr. Gopinath Pathudu
QCE -3
LAB TECHNICIANs-6
LAB HELPERs -10Jr. ENGINEERs – 2
SUPERVISORs – 2
CONSTRUCTION MANAGER(to be named)
PROJECT MANAGER -STRUCTURESMr. C. H. Yakambaram
CHIEF SURVEYORMr. Vijay Kunar Pandey
ASST. SURVEYORs -2
SURVEY HELPERs -6
PROJECT HEADMr. Venugopal Reddy
EXECUTIVE DIRECTOR/PROJECT EXECUTIVE, HO (VP)
PLANNING ENGINEER
QUANTITY SURVEYOR
J. Surender Reddy
CAD ENGINEERJ. Dinesh Kumar
DATA ENTRY OPERATORs -3
SAFETY ENGINEER
SUPERVISORs – 2
SAFETY HELPERs– 6
CASTING YARD INCHARGE
Four Laning of Walayar - Vadakancherry Section in Kerala (Km. 182.250 to Km. 240.000 of NH-47) - Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
ORGANIZATION CHART OF EPC CONTRACTOR
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
4 LINE DIAGRAM OF EPC CONTRACTOR CAMP SETUP
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 39
KNR WALAYAR TOLLWAYS PRIVATE LIMITED
COIMBATORE THRISSUR
Km. 1
82+2
50
(Sta
rt Po
int o
f th
e Pro
ject)
Walayar Km
. 187
+500
Four laning of Walayar – Vadakkancherry Section in Kerala (Km 182/250 to Km 240/000 of NH – 47) – Package NS-2/BOT/KL-2 – on DBFOT (Toll) basis under NHDP Phase-IILINE DIAGRAM OF THE EPC CONTRACTOR CAMP SET UP
BP - I
Km. 2
07+0
00Police Station
Km. 2
36+1
35Va
dakk
anch
eery
(End
Poi
nt o
f th
e Pro
ject)
BC - I
Palathurai
Q & C - I
Q & C - III
BC - II
Mangalamdam
NOTE:BC : BASE CAMPQ & C : QUARRY & CRUSHER PLANTBP : BATCHING PLANTHMP : HOT MIX PLANT
Km. 2
31+7
35
8.00 Kms
WWMP : WET MIX PLANT
5.25 Kms
13.5
Kms
WMMP - II,BP - II
WAL
AYAR
10.5
Kms
Offset 1.5 Kms
Offset 0.100 Kms
4.4 Kms
53.885 Kms
Q & C - II
0.500
Km
s
HMP - I
0.100
Km
s
BP - IIIHMP - II,
WMMP - I&
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
5.BAR CHART SHOWING THE DETAILS OF HIGHWAY PROGRESS
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II Page | 40
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 41
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
6.LINEAR WISE LHS MAIN CARRIAGEWAY STATUS
LHS – MCW
Sl No.
ChainageLength
Progress Status
From To C & G EMB Top SG TOP GSB Top WMM Top
Prime/TackCoat DBM BC
1 182.250 184.000 1.750 1.750 1.750 1.750 1.750 1.750 1.750 1.750 2 184.000 184.700 0.700 0.700 0.700 0.700 0.700 0.700 3 184.700 189.100 4.400 4.400 4.400 4.400 4.400 4.400 4.400 4.400 4 189.100 189.700 0.600 0.600 0.600 0.600 0.600 0.600 5 189.700 195.200 5.500 5.500 5.500 5.500 5.500 5.500 5.500 5.500 6 195.200 195.400 0.200 0.200 0.200 0.200 0.200 0.200 7 195.400 196.000 0.600 0.600 0.600 0.600 8 196.000 196.200 0.200 0.200 0.200 9 196.200 197.000 0.800 0.800 0.800 0.800 0.800 0.800 0.800 0.800
10 197.000 197.300 0.300 0.300 0.300 11 197.300 198.200 0.900 0.900 0.900 0.900 12 198.200 198.700 0.500 0.500 0.500 0.500 0.500 0.500 0.500 0.500 13 198.700 198.900 0.200 0.200 0.200 0.200 0.200 14 198.900 199.200 0.300 0.300 0.300 0.300 15 199.200 199.400 0.200 0.200 0.200 0.200 0.200 16 199.400 201.800 2.400 2.400 2.400 2.400 2.400 2.400 2.400 2.400 17 201.800 201.900 0.100 0.100 0.100 0.100 0.100 0.100 18 201.900 202.400 0.500 0.500 0.500 19 202.400 203.000 0.600 0.600 20 203.000 203.800 0.800 0.800 0.800 0.800 21 203.800 204.000 0.200 0.200 0.200 0.200 0.200 22 204.000 205.500 1.500 1.500 1.500 1.500 23 205.500 206.800 1.300 1.300 1.300
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 42
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
24 206.800 209.300 2.500 2.500 2.500 2.500 25 209.300 212.700 3.400 3.400 3.400 3.400 3.400 26 212.700 213.400 0.700 0.700 0.700 0.700 27 213.400 215.500 2.100 2.100 2.100 2.100 2.100 2.100 2.100 2.100 28 215.500 215.600 0.100 0.100 0.100 0.100 0.100 29 215.600 216.500 0.900 0.900 30 216.500 217.000 0.500 0.500 0.500 31 217.000 217.500 0.500 0.500 0.500 0.500 32 217.500 218.000 0.500 0.500 0.500 33 218.000 218.500 0.500 0.500 0.500 0.500 0.500 0.500 0.500 0.500 34 218.500 218.700 0.200 0.200 0.200 0.200 0.200 0.200 35 218.700 219.100 0.400 0.400 0.400 36 219.100 219.500 0.400 0.400 0.400 0.400 37 219.500 219.700 0.200 0.200 0.200 38 219.700 219.900 0.200 0.200 39 219.900 220.500 0.600 0.600 0.600 0.600 40 220.500 221.600 1.100 1.100 1.100 1.100 1.100 1.100 1.100 1.100 41 221.600 222.900 1.300 1.300 1.300 1.300 42 222.900 223.200 0.300 0.300 0.300 43 223.200 223.400 0.200 0.200 44 223.400 223.500 0.100 0.100 0.100 0.100 45 223.500 225.000 1.500 1.500 1.500 1.500 46 225.000 226.000 1.000 1.000 1.000 47 226.000 226.100 0.100 0.100 0.100 0.100 0.100 0.100 48 226.100 230.100 4.000 4.000 4.000 4.000 4.000 4.000 4.000 4.000 49 230.100 230.300 0.200 0.200 50 230.300 230.400 0.100 0.100 0.100 0.100 51 230.400 231.100 0.700 0.700 0.700 0.700 0.700 0.700 0.700 0.700 52 231.100 231.900 0.800 0.800 0.800 0.800
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 43
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
53 231.900 232.100 0.200 0.200 0.200 54 232.100 232.400 0.300 0.300 0.300 0.300 55 232.400 233.000 0.600 0.600 0.600 56 233.000 233.700 0.700 0.700 0.700 0.700 57 233.700 234.200 0.500 0.500 0.500 58 234.200 234.800 0.600 0.600 59 234.800 235.000 0.200 0.200 0.200 60 235.000 235.400 0.400 0.400 0.400 0.400 61 235.400 236.000 0.600 0.600 0.600 62 236.000 236.135 0.135 0.135
Total: 53.885 51.050 43.750 29.750 25.700 25.185 25.185
7.STATUS OF RHS MAIN CARRIAGEWAY. RHS – MCW
Sl No.
ChainageLength
Progress Status
From To C & G EMB Top SG TOP GSB Top WMM Top
Prime/TackCoat DBM BC
1 182.250 184.400 2.150 2.150 2.150 2.150 2.150 2.150 2.150 2.150 2 184.400 184.600 0.200 0.200 0.200 0.200 0.200 0.200 3 184.600 186.700 2.100 2.100 2.100 2.100 2.100 2.100 2.100 2.100 4 186.700 187.100 0.400 0.400 0.400 0.400 0.400 5 187.100 195.000 7.900 7.900 7.900 7.900 7.900 7.900 7.900 7.900 6 195.000 195.200 0.200 0.200 0.200 0.200 0.200 0.200 7 195.200 195.800 0.600 0.600 0.600 0.600 8 195.800 196.200 0.400 0.400 0.400 9 196.200 197.100 0.900 0.900 0.900 0.900 0.900 0.900 0.900 0.900
10 197.100 199.300 2.200 2.200 2.200 2.200 11 199.300 199.400 0.100 0.100 0.100 0.100 0.100
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 44
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
12 199.400 201.800 2.400 2.400 2.400 2.400 2.400 2.400 2.400 2.400 13 201.800 202.000 0.200 0.200 0.200 0.200 14 202.000 203.000 1.000 1.000 15 203.000 203.300 0.300 0.300 0.300 16 203.300 203.700 0.400 0.400 0.400 0.400 17 203.700 204.200 0.500 0.500 0.500 0.500 0.500 0.500 0.500 0.500 18 204.200 204.300 0.100 0.100 0.100 0.100 19 204.300 205.000 0.700 0.700 0.700 20 205.000 205.200 0.200 0.200 0.200 0.200 21 205.200 205.600 0.400 0.400 0.400 22 205.600 206.400 0.800 0.800 23 206.400 206.900 0.500 0.500 0.500 24 206.900 207.600 0.700 0.700 0.700 0.700 25 207.600 208.000 0.400 0.400 0.400 26 208.000 208.600 0.600 0.600 0.600 0.600 27 208.600 209.300 0.700 0.700 28 209.300 210.500 1.200 1.200 1.200 1.200 29 210.500 210.600 0.100 0.100 0.100 0.100 0.100 0.100 30 210.600 212.000 1.400 1.400 1.400 1.400 1.400 1.400 1.400 1.400 31 212.000 212.700 0.700 0.700 0.700 0.700 0.700 0.700 32 212.700 212.800 0.100 0.100 0.100 0.100 33 212.800 213.400 0.600 0.600 0.600 34 213.400 213.500 0.100 0.100 0.100 0.100 35 213.500 215.500 2.000 2.000 2.000 2.000 2.000 2.000 2.000 2.000 36 215.500 216.000 0.500 0.500 0.500 0.500 37 216.000 216.600 0.600 0.600 38 216.600 217.000 0.400 0.400 0.400 39 217.000 217.500 0.500 0.500 0.500 0.500 40 217.500 218.000 0.500 0.500 0.500
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 45
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
41 218.000 218.500 0.500 0.500 0.500 0.500 0.500 0.500 0.500 0.500 42 218.500 220.000 1.500 1.500 1.500 1.500 43 220.000 220.300 0.300 0.300 0.300 44 220.300 220.500 0.200 0.200 0.200 0.200 0.200 45 220.500 222.000 1.500 1.500 1.500 1.500 1.500 1.500 1.500 1.500 46 222.000 222.900 0.900 0.900 0.900 0.900 47 222.900 223.500 0.600 0.600 0.600 48 223.500 224.100 0.600 0.600 0.600 0.600 49 224.100 224.500 0.400 0.400 0.400 0.400 0.400 50 224.500 225.000 0.500 0.500 0.500 0.500 51 225.000 225.900 0.900 0.900 52 225.900 226.000 0.100 0.100 0.100 53 226.000 229.600 3.600 3.600 3.600 3.600 3.600 3.600 3.600 3.600 54 229.600 229.800 0.200 0.200 0.200 0.200 0.200 0.200 55 229.800 231.100 1.300 1.300 1.300 1.300 1.300 56 231.100 233.800 2.700 2.700 2.700 2.700 57 233.800 234.200 0.400 0.400 0.400 58 234.200 234.600 0.400 0.400 59 234.600 236.000 1.400 1.400 1.400 1.400 60 236.000 236.135 0.135 0.135 0.135
Total: 53.885 49.485 43.750 28.750 26.385 26.385 26.385
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 46
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
8. LINEAR WISE LHS SERVICE ROAD STATUSLHS (S.R.)
Sl No.
ChainageLength
Progress Status
From To C & G EMB Top SG TOP GSB Top WMM Top
Prime/TackCoat DBM SDBC
1 183.200 183.500 0.300 0.300 0.300 2 183.500 184.100 0.600 0.600 0.600 0.600 0.600 0.600 0.600 0.600 3 184.100 184.400 0.300 0.300 0.300 4 184.400 184.600 0.200 0.200 0.200 0.200 5 184.600 184.800 0.200 0.200 0.200 0.200 0.200 6 184.800 185.200 0.400 0.400 0.400 7 186.300 187.300 1.000 1.000 1.000 8 187.300 187.900 0.600 0.600 0.600 0.600 0.600 9 191.200 191.600 0.400 0.400
10 191.600 192.000 0.400 0.400 0.400 11 192.000 192.100 0.100 0.100 12 192.100 192.500 0.400 0.400 0.400 13 192.500 193.500 1.000 1.000 14 193.500 193.800 0.300 0.300 0.300 15 193.800 193.900 0.100 0.100 0.100 0.100 0.100 16 193.900 194.100 0.200 0.200 0.200 0.200 17 194.100 195.800 1.700 1.700 1.700 1.700 1.700 1.700 18 195.800 196.200 0.400 0.400 19 196.200 197.000 0.800 0.800 0.800 0.800 0.800 0.800 20 197.000 198.400 1.400 1.400 1.400 1.400 1.400 1.400 1.400 1.400
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 47
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
21 198.400 198.600 0.200 0.200 22 202.600 203.000 0.400 0.400 0.400 0.400 0.400 0.400 0.400 0.400 23 203.000 203.100 0.100 0.100 0.100 0.100 24 205.000 207.200 2.200 2.200 25 209.100 209.900 0.800 0.800 26 212.400 213.700 1.300 1.300 27 213.700 214.200 0.500 0.500 0.500 28 215.100 215.200 0.100 0.100 29 215.200 215.700 0.500 0.500 0.500 30 215.700 217.000 1.300 1.300 31 217.000 218.000 1.000 1.000 1.000 32 222.200 222.300 0.100 0.100 33 222.300 224.100 1.800 1.800 1.800 1.800 1.800 1.800 1.800 1.800 34 224.100 224.600 0.500 0.500 0.500 35 224.600 225.100 0.500 0.500 36 225.100 225.400 0.300 0.300 0.300 37 225.400 226.000 0.600 0.600 38 226.000 226.800 0.800 0.800 0.800 39 229.200 229.800 0.600 0.600 0.600 40 233.600 234.200 0.600 0.600 41 234.200 234.500 0.300 0.300 0.300 0.300 0.300 0.300 0.300 0.300 42 234.500 235.000 0.500 0.500
Total: 25.800 15.700 8.400 7.900 7.000 4.500 4.500
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 48
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
9. LINEAR WISE RHS SERVICE ROAD STATUSRHS (S.R)
Sl No.
ChainageLength
Progress Status
From To C & G EMB Top SG TOP GSB Top WMM Top
Prime/TackCoat DBM SDBC
1 187.000 187.900 0.900 0.900 0.900 0.900 0.900 0.900 0.900 0.900 2 191.200 197.700 6.500 6.500 3 197.700 197.800 0.100 0.100 0.100 4 197.800 198.300 0.500 0.500 0.500 0.500 0.500 0.500 0.500 0.500 5 198.300 198.600 0.300 0.300 6 202.200 203.200 1.000 1.000 7 203.500 203.900 0.400 0.400 0.400 0.400 0.400 0.400 0.400 0.400 8 205.000 206.000 1.000 1.000 1.000 9 206.000 207.100 1.100 1.100
10 209.100 209.900 0.800 0.800 0.800 0.800 0.800 0.800 0.800 0.800 11 212.400 214.200 1.800 1.800 12 215.100 217.200 2.100 2.100 13 217.200 217.900 0.700 0.700 0.700 0.700 0.700 0.700 0.700 0.700 14 217.900 218.000 0.100 0.100 0.100 15 222.200 222.400 0.200 0.200 16 222.400 223.300 0.900 0.900 0.900 17 223.300 223.400 0.100 0.100 18 223.400 224.200 0.800 0.800 0.800 0.800 0.800 0.800 0.800 0.800 19 224.200 225.000 0.800 0.800 20 225.000 225.900 0.900 0.900 0.900 0.900 0.900 0.900 0.900 0.900 21 225.900 226.000 0.100 0.100 0.100 0.100
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II Page | 49
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
22 226.000 226.800 0.800 0.800 0.800 23 229.200 229.800 0.600 0.600 0.600 24 233.600 234.200 0.600 0.600 25 234.200 234.500 0.300 0.300 0.300 0.300 0.300 0.300 0.300 0.300 26 234.500 235.000 0.500 0.500
Total: 23.900 8.900 5.400 5.300 5.300 5.300 5.300
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 50
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
10. PROGRESS VS ACHIEVEMENT AGAINST SCOPE OF WORK
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 51
C&G in Km
EMB TOP in Km SG in Km GSB in
KmWMM In
Km
DBM 1st Layer in
Km
DBM 2nd Layer in
KmBC Pipe
CulvertsBox
Culverts PUP VUP Minor Bridges
Major Bridges Piles Girders Planks
RE Wall BlocksCasting
RE Wall Blocks
Erection
107.77 107.77 107.77 107.77 107.77 107.77 107.77 107.77 51 142 4 7 12 2 40 227 200 1064867 98782
107.77 100.535 87.500 58.500 52.085 51.570 51.570 0.000 47 128 4 4 11 2 40 227 200 562802 34892
0.000 0.885 3.150 6.800 5.185 8.770 8.770 0.000 1 1 0 1 0 0 0 0 0 58285 3784
100% 93% 81% 54% 48% 48% 48% 0% 92% 90% 100% 57% 92% 100% 100% 100% 100% 53% 35%
SUMMARY
During the Month
% of Work done
Scope
Achievement
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
11. PROGRESS VS ACHIEVEMENT AGAINST SCOPE OF WORK (SERVICE ROAD)
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 52
C&G in Km
EMB TOP in Km SG in Km GSB in
KmWMM In
KmDBM in
Km SDBC C&G in Km
EMB TOP in Km SG in Km GSB in
KmWMM In
KmDBM in
Km SDBC
LHS RHS
25.800 25.800 25.800 25.800 25.800 25.800 25.800 23.900 23.900 23.900 23.900 23.900 23.900 23.900
25.800 15.700 8.400 7.900 7.000 4.500 0.000 23.900 8.900 5.400 5.300 5.300 5.300 0.000
0.500 0.500 0.800 0.700 0.400 0.400 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
1.00 0.609 0.33 0.306 0.271 0.174 0.000 1.00 0.372 0.23 0.222 0.222 0.222 0.000% of Work done
Side
SUMMARY
Scope
Achievement
During the Month
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
12.“S” CURVE
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 53
650
78.00 79.00 80.00 81.00 82.00 83.00 84.00 85.00 86.00 87.00 88.00 89.00 90.00 91.00 92.00 93.00 94.00 95.00 96.00 97.00 98.00 99.00 100.00 101.00 102.00 103.00 104.00 105.00 106.00 107.00 108.00
Month
May-1
3
Jun-
13
Jul-1
3
Aug-
13
Sep-
13
Oct-1
3
Nov-
13
Dec-
13
Jan-
14
Feb-
14
Mar-1
4
Apr-1
4
May-1
4
Jun-
14
Jul-1
4
Aug-
14
Sep-
14
Oct-1
4
Nov-
14
Dec-
14
Jan-
15
Feb-
15
Mar-1
5
Apr-1
5
May-1
5
Jun-
15
Jul-1
5
Aug-
15
Sep-
15
Oct-1
5
Nov-
15
Planned Amount in lac 822
985
1025
1091
1177
1759
2630
2473
2625
3349
3827
4615
5290
2361
2539
2390
4773
3655
2717
3182
3432
3744
4082
3521
2751
1160
1261
1240
2196
1672
705
Achived Amount in lac 2616
2212
4159
1447
1109
1959
2814
3248
4405
5015
6059
4269
3827
3235
Cumulative Amount in lac (Planned) 82
2
1807
2832
3923
5101
6859
9489
1196
2
1458
7
1793
6
2176
4
2637
9
3166
9
3402
9
3656
9
3895
9
4373
2
4738
7
5010
4
5328
6
5671
8
6046
2
6454
4
6806
5
7081
6
7197
7
7323
8
7447
8
7667
4
7834
5
7905
0
Cum Amount in lac (Achived) 26
16
4827
8986
1043
3
1154
2
1350
1
1631
5
1956
2
2396
7
2898
2
3504
1
3931
0
4313
7
4637
2
% of progress (Planned) 1.04
1.25
1.30
1.38
1.49
2.22
3.33
3.13
3.32
4.24
4.84
5.84
6.69
2.99
3.21
3.02
6.04
4.62
3.44
4.03
4.34
4.74
5.16
4.45
3.48
1.47
1.60
1.57
2.78
2.11
0.89
% of progress (Achved)
3.
31
2.
80
5.
26
1.
83
1.
40
2.
48
3.
56
4.
11
5.
57
6.
34
7.
66
5.
40
4.
84
4.
09
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Cumulative at the end of the month %
(Planned) 1.04
2.29
3.58
4.96
6.45
8.68
12.0
0
15.1
3
18.4
5
22.6
9
27.5
3
33.3
7
40.0
6
43.0
5
46.2
6
49.2
8
55.3
2
59.9
5
63.3
8
67.4
1
71.7
5
76.4
9
81.6
5
86.1
0
89.5
8
91.0
5
92.6
5
94.2
2
96.9
9
99.1
1
100.
00
Cumulative at the end of the month %
(Achived) 3.31
6.11
11.3
7
13.2
0
14.6
0
17.0
8
20.6
4
24.7
5
30.3
2
36.6
6
44.3
3
49.7
3
54.5
7
58.6
6
COMMENCEMENT DATE 18-May-2013 Concessionare : KNR Walayar Tollways Private Limited. CONSTRUCTION PERIOD 910 Days
AGREEMENT DATE 17-Sep-2013 Four Laning of Walayar - Vadakancherry Section in Kerala Km. 182.250 (Design Chainage Km. 182.250) to Km. 240.000 (Design Chainage Km. 236.135) of NH-47 –Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II CONCESSION PERIOD 20 Yrs
EPC : K N R Constructions Ltd. CONTRACT AMOUNT IN Lac Rs: 79050.00
Mile Stone -1 ( 180 Days) 10% (Fn) : 13/Nov/2013 Mile Stone-2 (400 Days) 35%(Fn) : 21/Jun/2014 Mile Stone-3 (650 Days) 70% (Fn) : 26/Feb/2015 Mile Stone-4 (910 Days) 100% Length : 14/Nov/2015
TARGET / COMPLETION DATE 13-Nov-20153.
31 6.11 11
.37
13.2
0
14.6
0
17.0
8
20.6
4
24.7
5
30.3
2 36.6
6
44.3
3 49.7
3
54.5
7
58.6
6
1.04 2.29 3.58 4.96 6.45 8.68 12
.00
15.1
3
18.4
5
22.6
9
27.5
3 33.3
7 40.0
6
43.0
5
46.2
6
49.2
8 55.3
2
59.9
5
63.3
8
67.4
1
71.7
5
76.4
9 81.6
5
86.1
0
89.5
8
91.0
5
92.6
5
94.2
2
96.9
9
99.1
1
100.
00
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
110.00
May-
13
Jun-
13
Jul-1
3
Aug-1
3
Sep-
13
Oct-1
3
Nov-
13
Dec-
13
Jan-
14
Feb-
14
Mar-1
4
Apr-1
4
May-
14
Jun-
14
Jul-1
4
Aug-1
4
Sep-
14
Oct-1
4
Nov-
14
Dec-
14
Jan-
15
Feb-
15
Mar-1
5
Apr-1
5
May-
15
Jun-
15
Jul-1
5
Aug-1
5
Sep-
15
Oct-1
5
Nov-
15
Cumu
lative
wor
k %
Month Achived Planned
MS-2 (35%) 21/Jun/2014
MS-3 (70%) 26/Feb/15
MS-1 (10%) 13/Nov/13
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II
Page | 54
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
13.PHOTOGRAPHS ON SITE ACTIVITIES
Casting of Crash Barrier
At KM 217 + 500 VUP Service Road ROW concrete Drain in progress
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II Page | 55
Artefact Projects LtdIndependent Engineer
M O N T H L Y P R O G R E S S R E P O R T J U N E 2 0 1 4
Slope protection work. Revetment on progress. Testing Field density at KM 203 + 120 LHS
Independent Engineering Services for Four Laning of Walayar - Vadakkancherry Section in Kerala (Km. 182+250 to Km. 240+000 of NH-47) – Package NS-2/BOT/KL-2 on DBFOT (Toll) Basis under NHDP Phase II