Purpose of the studyPurpose of the study
• Consider all practical routes for the extension of Route 710
• Gather information on soil and sub-surface conditions
• Provide for public input and involvement
33
Why Tunnels?Why Tunnels?
• Reduce impacts to communities and sensitive areas
44
Objective of the Objective of the Exploration ProgramExploration Program• A total of 5 potential zones will be
investigated
• Collect geotechnical, geological, and hydro-geological information for each zone
• Information to be used for screening purposes
55
Exploration Plan ZonesExploration Plan Zones
66
Key Factors Influencing Key Factors Influencing TunnelingTunneling• Faulting
• Fault displacement • Rupture zone length
• Uniformity of geologic material• Potential for adverse tunneling conditions
• Flowing/squeezing soils, boulders
• Properties of geologic materials• Groundwater conditions • Hazardous materials
77
Geotechnical Exploration Geotechnical Exploration ProgramProgram
• Data collection and review
• Geologic mapping• Geophysical surveys• Drilling, sampling, and
logging• Laboratory testing
88
Boring ActivitiesBoring Activities
• 33 small diameter borings; six locations in Pasadena
• Vertical and Inclined drilling
• Each boring will take 7 to 10 days to complete
• Work area is about 12 feet by 60 feet
• Drilling performed daytime hours
99
Seismic Reflection Seismic Reflection TestingTesting
• 20 seismic reflection surveys; two locations in Pasadena
• Non-destructive• Most Geophysical testing
will be performed at night• One location per night
1010
SummarySummaryZones # of
BoringsTotal Lineal
feet (ft)# of Geophysical
LinesLength of Tunnel
(mi)
1 8 2,800 5 5.2 – 5.7
2 5 1,600 3 4.9 – 5.6
3 12 3,700 7 4.4 – 5.4
4 4 1,100 2 6.2 – 7.4
5 4 1,100 3 9.6 – 11.5
1111
Exploration Program Exploration Program ScheduleSchedule
6/09 20103/09 9/099/08 2009
Encroachment Permit
Site Reconnaissance
Geologic Mapping
Summary Report
NTP
Drilling by Caltrans
Drilling by CH2M HILL
Lab Testing
Data Evaluation
1212
Recent FindingsRecent Findings
• Two superfund sites were identified• The sites are located within Zones 4 and 5• Groundwater in this area is known to be
contaminated with Volatile Organic Compounds
• Depth of groundwater ranges from 50 feet to 150 feet below ground surface
• Tunnel is expected to be at about 200 feet below ground surface
1313
Superfund Site Superfund Site Locations within Zones Locations within Zones 4 and 54 and 5
1414
Planned ActivitiesPlanned Activities
• Proceed with the borings in Zones 1, 2 and 3.• Postpone borings in Zones 4 and 5, pending
additional information related to the Superfund Sites.
• Borings to be done by both Caltrans and CH2M HILL
• Borings to begin in early January 2009• Each boring is expected to take about 7 to 10
days to complete
City Exploration Activity # of Visits# of Stakeholders
added to Database
Alhambra Borings: 3 Geophysical Line: 2 294 34
Los Angeles Borings: 6 184 5
Pasadena Z3-B2 (Caltrans 710 ROW north of Del Mar
Blvd)Boring: 1
12 3
Total visits to Homes/Businesses: 490 # of Stakeholders added to database: 42Total visits to Homes/Businesses: 490 # of Stakeholders added to database: 42
Summary of Public Outreach Summary of Public Outreach ActivitiesActivities
1616
Public Outreach and Public Outreach and Notification ProgramNotification Program• Field Surveys of Boring Sites• Federal, State and Local Elected Officials
Briefings• Public Notices and Fact Sheet• Posting and Distribution of Notices
• Public Facilities• Websites• Canvassing
• Field Outreach to affected/sensitive users• Information Line
1717
SR-710 Community SR-710 Community Facilitation Scope of WorkFacilitation Scope of Work • Coordinate Study Meetings• Conduct Community Awareness Campaign & Report
Public Input• Study Information Office and Website• Events & Presentations• Community Workshops• Focus Groups
1818
For more information:For more information:
SR-710 Technical Tunnel Study Information Office
3412 N. Eastern Ave.Los Angeles, CA 90032
Toll Free: (877) 710-INFOTel. (323) 222-1710Fax: (323) 222-9710
http://www.710tunnelstudy.info
1919
Question and Answer
Top Related