Program and Project Management
Policy Development
Overview and Rationale
Sandra Smalley
Office of the Chief Engineer
Used with permission
Page 2
Objectives of Session
Provide: • A high-level overview of recent policy
developments• An understanding of the purpose of
the selected developments• A preview of some upcoming policy
developments
Page 3
Recent Policy Developments
Overview
Pre-
Page 4
Policy Developments2007
• NPR 7120.5 D - NASA Space Flight Program and Project Management Requirements
“This revision of NPR 7120.5 is part of a realignment of governing documents within NASA designed to increase accountability and general clarity in the flow-down of management process requirements.”
• NPR 7123.1A - NASA Systems Engineering Processes and Requirements
Page 5
Policy Developments2008
• NPD 1000.0A - Governance and Strategic Management
• NPR 7120.7 - NASA Information Technology and Institutional Infrastructure Program and Project Management Requirements
• NPR 7120.8 - NASA Research and Technology Program and Project Management Requirements
• NPR 8000.4 - Agency Risk Management Procedural Requirements
Page 6
Policy Developments2009
• NPD 1000.5 - Policy for NASA Acquisition
• NPR 7120.5D - NID
• NPD 7120.4 - Program/Project Management
Page 7
Policy DevelopmentOther Supporting Work
Handbook development • The SRB Handbook • The Risk Management Handbook • NPR 7120.5 Handbook • WBS Handbook • Cost Estimating Handbook • Schedule Management Handbook
Page 8
Policy Development Why all the activity?
• Improve program/project performance against external commitments (real and perceived)
• More effectively support programs and projects by improving and tailoring policy, processes, and requirements– Recognize the multi-center environment in many
programs and projects. This includes giving more attention to common principles, terminology, and practices while recognizing the differences that exist in Center processes and historic practices.
Page 9
Improving Agency PerformanceApproach
• Employ a sound approach to Acquisition – NPD 1000.5
• Ensure early and continuing alignment of program project planning and budget process– Strategic planning meetings – NPR 7120.5D NID
– PPBE process with annual portfolio review
• Establish the proper set of requirements
• Establish a life cycle process that keeps the program/project on track
Page 10
Selected Policy Developments
• Acquisition• Establishing the proper set of requirements• Space Flight and IT
Baseline PolicyJoint Confidence Level (JCL) Policy
• Preview of NPR 7120.5 Rev E
Page 11
Selected Policy DevelopmentsAcquisition – Definition (NPD 1000.5)
Acquisition is the process for obtaining the systems, service, construction, and supplies the Agency needs to fulfill its mission.
Acquisition, which may include procurement (contracting for products and services), beginswith an idea or proposal that aligns with the NASA Strategic Plan and fulfills an identified need and ends with the completion of the program or project or the final disposition of the product or service.
Page 12
Selected Acquisition Policy (NPD 1000.5)
• Meet programmatic, institutional, technical, cost, and schedule commitments
• Base acquisition on realistic cost estimates and achievable schedules
• For space flight and IT, Agency commitments are to be based on the budgeted cost and schedule associated with the confidence level approved by the decision authority.
• Programs and projects are to be annually reviewed by the responsible Mission Directorate or Mission Support Office to confirm to the decision authority that their current baseline life cycle cost estimates, funding strategy, and the annual NASA budget submissions are consistent.
Page 13
Selected Policy Developments
• Acquisition• Establishing the proper set of requirements• Space Flight and IT
Baseline PolicyJoint Confidence Level (JCL) Policy
• Preview of NPR 7120.5 Rev E
Page 14
Establishing the proper set of requirements
• Good requirements that are properly managed are essential to any successful undertaking.
• 7120 Series NPRs focus programmanagement requirements on specific product lines.
• Tailoring Principles provide a means to adjust prescribed requirements to a specific task (e.g., a program/project).
Page 15
Tailoring - Definition
Tailoring - the process used to adjust or seek relief from a prescribed requirement to accommodate the needs of a specific task or activity (e.g., program/project)
The Tailoring process results in the generation of Deviations and Waivers depending on the timing of the request.
Page 16
Tailoring Principles
• The organization at the level that established the requirement approves the request for tailoring of that requirement unless this authority has been formally delegated elsewhere.
• The involved management at the next higher level is informed in a timely manner of the request for tailoring of a prescribed requirement.
Page 17
Policy Selected Developments
• Acquisition• Establishing the proper set of requirements• Space Flight and IT
Baseline PolicyJoint Confidence Level (JCL) Policy
• Preview of NPR 7120.5 Rev E
Page 18
Space Flight and IT – Baseline and JCL
• SMC baseline and JCL policy discussions date back several years.
• The concept and details continue to evolve.
• A number of changes and implementation details are being considered for NPR 7120.5 Rev. E.
Perspective
Page 19
Baseline PolicyGoal
Improve the cost and schedule performance of programs and projects by improved planning based on the integration of cost, schedule, and risk
Page 20
Joint Cost and Schedule Confidence LevelDefinition (Simplified)
The probability that cost will be equal to or less than the targeted cost and theschedule will be equal to or less than the targeted schedule date.
Page 21
Joint Bivariate Cumulative Probability Distribution of Cost and
Schedule
21Cost (x) ($M)
Schedule (y) (Months)
Probability
Page 22
Current Policy
• Policy applies to Space Flight and IT programs and projects in implementation.
• Programs/projects are to be baselined or rebaselined based on a joint cost and schedule probabilistic analysis.
• Programs - Baselined or rebaselined at a confidence level of 70 percent or the level approved by the decision authority
• Projects are to be baselined or rebaselined at a confidence level consistent with the program's JCL.
• Projects - As a minimum, funded at a level that is equivalent to a confidence level of 50 percent or as approved by the decision authority
Page 23
Current Policy (Cont.)
• Programs in extended operations generally are not required to develop a JCL, but new or upgraded capabilities while in ops will require a JCL.
• Program and project proposed cost and schedule baselines will be assessed by an independent review team.
• External commitments will be based on the JCL approved by the decision authority.
Page 24
Baseline Policy
• Commitment Baseline – Basis for commitments to OMB and Congress
• Management Baseline – Basis for program/project execution and strategic management process reporting
Page 25
Commitment BaselineKey Attributes
• It is an integrated set of project requirements, cost, schedule, technical content, and agreed to JCL that forms the basis for NASA’s commitment to OMB and Congress.
• It is established at the Key Decision Point (KDP) that initiates the Implementation Phase.
• The Commitment Baseline is the only officialNASA baseline for a project.
Page 26
Unallocated Future Expenses (UFEs)Needed to understand Management Baseline
Unallocated Future Expenses -The portion of estimated cost required to meet specified JCL that cannot yet be allocated to the specific project WBS sub-elements because the estimate includes probabilistic risks and specific needs that are not known until these risks are realized.
Page 27
Unallocated Future Expenses (UFEs) (Cont.)
• The term ‘UFE’ was established to make it clear that (based on experience) these funds are expected to be required to complete the projectbut cannot yet be allocated to a specific WBS activity.
(The UFE concept is consistent with the non-deterministic nature of joint cost and schedule estimates based on probabilistic analysis.)
• All UFE are included in the commitment baseline and the project’s budget.NOTE – The relationship of UFE to Commitment and Management Baselines is illustrated in an upcoming slide.
Page 28
Management Baseline - Key Attributes
• An integrated baseline (set of requirements, cost, schedule, technical content, and associated JCL) that forms the foundation for program/project execution
• The Management Baseline is established at the Key Decision Point (KDP) that initiates the Implementation Phase as approved by the decision authority.
Page 29
Management Baseline Key Attributes (cont.)
• The program Management Baseline is the aggregate of the project Commitment Baselines plus program operating expenses.
Similarly, the project Management Baselineequals the Commitment Baseline less any portion of UFE not released to the project for project execution.
Page 30
Project Management Baseline(Project Execution)
Project Commitment Baseline(External commitments)
This UFE is controlled by the Program/MD
ProjectManager Control
UFE
Not to scale.
Relationship of UFE to ProjectCommitment and Management Baselines
Page 31
Project -1 Project -2 Program
ProgramOperatingExpense
Project Management Baseline
UFE Held by Program
Program Management Baseline
Program and Project BaselinesTotal Baseline Cost
Project -2
UFE Held by Project 1
UFE Held by Project 2
UFE Held by Project 1
UFE Held by Project 2
Project -1
Project Commitment Baseline
Page 32
Selected Policy Developments
• Acquisition• Establishing the proper set of requirements• Space Flight and IT
Baseline PolicyJoint Confidence Level (JCL) Policy
• Preview of NPR 7120.5 Rev E
The Rev E development is in its early stages.This preview should be viewed as both notional and pre-decisional.
Page 33
Rev. E Development Charter
• Build on the NID• Issue Rev. E before the expiration of the NID• Fully vet and resolve policy issues raised but not
resolved during the NID development• Incorporate:
– Any additional changes in NASA policy and practice,
– Findings from OCE survey process and other audits
– Lessons learned
Page 34
Rev. E Development Charter (Cont.)
• Ensure proper flow down from NPD1000.0A, and NPD 1000.5
• Address inconsistencies among fundamental OCE documents. The primary focus will be on NPR 7120.5, NPD 7120.4, NPD 1000.5, and NPR 7123.1A.
Page 35
Rev. E Development Working Groups
• Life Cycle Review• Baseline Policy• JCL Clarify • Highly Specialized IT - Cover from PM’s perspective• NPR 7123 – NPR 7120.5 – Inconsistencies and review
criteria• Requirements Relief – e.g., Batch processing• Ops and Program and Project Reviews – Streamline
reviews• OSMA Issues – Misc.
Page 36
Rev. E Development Life Cycle Review
KDP B to KDP CPhase B
(Preliminary Design and Technology Completion)
Page 37
Current Project Life CycleArea of Focus - KDP B to KDP C
Page 38
KDP B to KDP COverview
Conduct IBRsand update JCL
ILCR
KDP C
PDR Readiness Assessment
PDR
Phase A Phase B
Checkpoint to DA(If a significant
change occurs or the interval from the ILCR
exceeds 6 months )
Prerequisite for locking down the date of the PDR
and ILCR
Technical baseline with
cost, schedule, and risk
information
Integrated review of programmatic
baselines integrated with technical
baseline updates
Implementation
KDP B
Formulation
Periodic SRB Involvement as Appropriate
P/pBrief
CenterBrief
MDBrief
Not To Scale
Phase C
This preview should be viewed as both notional and pre-decisional.
Post Review Reporting to DA
PDR-Based
Page 39
Single Project and Tightly Coupled Programs
ILCR
KDP IIAssessment of
plan to take projects to KDP C
PDR
Program
Implementation
KDP 1
Post Review Reporting to DA
Not To Scale
Start of projects
Projects
PDR ILCR
ILCRPDR
ILCRPDR
Readiness assessment
Readiness assessment
Readiness assessment
Post Review Reporting to DA
Checkpoint if significant changeor 6 months
KDP C
Assessments and Checkpoints
This preview should be viewed as both notional and pre-decisional.
Page 40
Rev. E DevelopmentSchedule
First Rev E development meeting – 10/09
NID Expiration – 9/10
Page 41
Concluding Remarks
• The intent of policy developments is to improveAgency performance.
• If you view that the resulting processes do not add value … don’t just tolerate it… or worse yet ignore it…provide feedback to the office responsible. They want your feedback.
• Get involved in your office/Center’s process for providing input during the policy development process. This input is highly valued.