Presentation of Project’s Timetable Presentation of Project’s Timetable and Partners’ Responsibilities and Partners’ Responsibilities
National Technical University of Athens National Technical University of Athens Unit of Environmental Science and Technology Unit of Environmental Science and Technology
By: Simos MalamisBy: Simos Malamis
Athens, 25 October 2005Athens, 25 October 2005
Kick-off MeetingKick-off Meeting
Life-Environment Project Life-Environment Project Sustainable Construction in Public and Private Sustainable Construction in Public and Private
Works through IPP Approach (SUSCON)Works through IPP Approach (SUSCON)
General Remarks General Remarks
Project duration = 36 months Project duration = 36 months
Start date: 01/10/2005Start date: 01/10/2005
End-date: 30/09/2008End-date: 30/09/2008
7 Tasks in Total implemented by 6 7 Tasks in Total implemented by 6 partnerspartners
TaskTask TitleTitle StartStart End End DurationDuration
(months)(months)
11 Task Management & Task Management & Reporting to the EC Reporting to the EC
01/10/0501/10/05 30/09/0830/09/08 3636
22 Analysis and Analysis and Documentation of the Documentation of the Construction Sector Construction Sector
01/11/0501/11/05 31/03/0631/03/06 55
33 LCA in 2 construction LCA in 2 construction sitessites
01/01/0601/01/06 30/06/0630/06/06 66
44 Development of eco-Development of eco-design criteria design criteria
01/07/0601/07/06 28/02/0728/02/07 88
55 Application of eco-design Application of eco-design criteria in construction criteria in construction
01/03/0701/03/07 30/09/0830/09/08 1919
66 Online database for the Online database for the construction industry construction industry
01/01/0601/01/06 30/09/0830/09/08 3333
77 Dissemination Dissemination 01/01/0601/01/06 30/09/0830/09/08 3333
TaskTask TitleTitle Task leaderTask leader Involved Involved partnerspartners
11 Task Management & Task Management & Reporting to the EC Reporting to the EC
NTUANTUA AllAll
22 Analysis and Analysis and Documentation of the Documentation of the Construction Sector in Construction Sector in
Greece , Cyprus and EU Greece , Cyprus and EU level level
EPTAEPTA EDRASISEDRASIS
CYBARCO CYBARCO ETEKETEK
33 LCA in 2 construction sitesLCA in 2 construction sites NTUANTUA EDRASISEDRASIS
CYBARCOCYBARCO
44 Development of eco-design Development of eco-design criteria criteria
EPTAEPTA NTUA NTUA
UCYUCY
Task NoTask No TitleTitle Task LeaderTask Leader Involved Involved Partners Partners
55 Application of eco-design Application of eco-design criteria in construction criteria in construction
EPTAEPTA EDRASIS EDRASIS
CYBARCOCYBARCO
NTUANTUA
66 Online database for the Online database for the construction industry construction industry
UCYUCY AllAll
77 Dissemination Dissemination NTUANTUA AllAll
Task 1: Task 1: Task management & reporting to the ECTask management & reporting to the EC Action 1:Action 1:Task Management Task Management
• NTUA is legally & financially responsible for the project NTUA is legally & financially responsible for the project implementation & the management of the tasksimplementation & the management of the tasks
• All partners shall participate in the coordination groupAll partners shall participate in the coordination group
Action 2: Reporting to the EC Action 2: Reporting to the EC • NTUA is responsible for submitting reports to the ECNTUA is responsible for submitting reports to the EC
Action 3: Project Meetings Action 3: Project Meetings • 3 in Greece & 3 in Cyprus + kick-off (NTUA) 3 in Greece & 3 in Cyprus + kick-off (NTUA)
Action 4: Monitoring & Evaluation Action 4: Monitoring & Evaluation • All partners through the co-ordination groupAll partners through the co-ordination group• NTUA & EPTA shall develop the performance indicatorsNTUA & EPTA shall develop the performance indicators
Action 5:Advisory BoardAction 5:Advisory Board• EPTA and UCY are responsible for the organisation and EPTA and UCY are responsible for the organisation and
the co-ordination of the Advisory Board in each country. the co-ordination of the Advisory Board in each country.
Task 2: Analysis and Documentation of the Task 2: Analysis and Documentation of the
Construction Sector in Greece, Cyprus & EU levelConstruction Sector in Greece, Cyprus & EU level Action 1:Action 1:Analysis of the construction Analysis of the construction
sector in Greece & Cyprussector in Greece & Cyprus• Co-ordinated & implemented by EPTA and Co-ordinated & implemented by EPTA and
EDRASIS (Greece) and by CYBARCO and ETEK EDRASIS (Greece) and by CYBARCO and ETEK (Cyprus) (Cyprus)
Action 2:Action 2:Environmental Impact Environmental Impact
Assessment from the construction Assessment from the construction activitiesactivities• Implemented by EPTA Implemented by EPTA
Task 3: Task 3: LCA in two construction activitiesLCA in two construction activities
Action 1: Action 1: Data collection for the two Data collection for the two construction categoriesconstruction categories• EDRASIS & CYBARCO shall provide data EDRASIS & CYBARCO shall provide data • NTUA responsible for the co-ordination NTUA responsible for the co-ordination
Action 2:Action 2:Conduction of a LCA studyConduction of a LCA study
• NTUA is responsible NTUA is responsible
Task 4: Task 4: Development of eco-design criteriaDevelopment of eco-design criteria
Action 1: Action 1: General assessment of eco-General assessment of eco-design strategiesdesign strategies• EPTA is responsibleEPTA is responsible
Action 2: Action 2: • Creation of an eco-design matrix and an eco-Creation of an eco-design matrix and an eco-
design checklistdesign checklist NTUA is responsibleNTUA is responsible
Action 3:Action 3:Development of eco-design Development of eco-design criteria criteria • UCY responsible UCY responsible
Task 5: Application of eco-designTask 5: Application of eco-design
criteria in construction criteria in construction Action 1: Action 1: Software production for the evaluation Software production for the evaluation
of the environmental performance of construction of the environmental performance of construction works works • NTUA is responsible for subcontracting the software NTUA is responsible for subcontracting the software
design design
Action 2:Action 2:Application of the software to the Application of the software to the construction projects in the companiesconstruction projects in the companies• EDRASIS & CYBARCO shall apply the software tool to EDRASIS & CYBARCO shall apply the software tool to
their construction projects their construction projects • Comparison of their environmental performance Comparison of their environmental performance
Action 3:Action 3:Drafting National Institutional Drafting National Institutional ArrangementsArrangements• Participation of all partners Participation of all partners
Task 6: Online Database for the Task 6: Online Database for the
Construction IndustryConstruction Industry Action 1:Action 1:General Specifications and functional General Specifications and functional
requirementsrequirements• UCY is responsibleUCY is responsible
Action 2:Action 2:Web-site structure design and Web-site structure design and implementation implementation • NTUA & UCYNTUA & UCY
Action 3:Action 3:Creation and Operation of the databaseCreation and Operation of the database• NTUA shall sub-contract the data-base developmentNTUA shall sub-contract the data-base development• UCY responsible for the continuous up-grading of the UCY responsible for the continuous up-grading of the
data-base data-base
Task 7:Dissemination ActivitiesTask 7:Dissemination Activities Action 1:Web-site design & developmentAction 1:Web-site design & development
• NTUA is responsible; all partners shall provide input for updating NTUA is responsible; all partners shall provide input for updating the web-page the web-page
Action 2:Action 2:Organization of a national annual competition for ‘sustainable Organization of a national annual competition for ‘sustainable construction project’construction project’• EPTA & UCYEPTA & UCY
Action 3a:Action 3a:Organization of one-day informational events Organization of one-day informational events • EDRASIS and CYBARCOEDRASIS and CYBARCO
Action 3b: Final Conference Organization Action 3b: Final Conference Organization • Co-ordination by NTUA & EDRASIS with all partners involvedCo-ordination by NTUA & EDRASIS with all partners involved
Action 4:Newsletters Action 4:Newsletters • Template development by EPTATemplate development by EPTA• NTUA responsible for their productionNTUA responsible for their production• All partners involved in their distribution All partners involved in their distribution
Action 5:Advertisement Campaign Action 5:Advertisement Campaign • All partners involvedAll partners involved
One task manager shall be assigned One task manager shall be assigned for each Task for each Task
Each task manager shall be Each task manager shall be responsible for the successful and responsible for the successful and on-time submission of the Taskon-time submission of the Task