Monthly ReportSeptember 2020By H.G. Reynolds Company

Center for Knowledge NorthBlythewood, South Carolina

Page 2: Monthly Report September 2020...Monthly Report September 2020 By H.G. Reynolds Company Center for Knowledge North ... EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM 20 27

Center for Knowledge NorthBlythewood, South Carolina

SEPTEMBER 2020/PAGE 1

Center for Knowledge North - September 2020 Progress Summary

Executive SummaryWork continues to focus on the interior of the building since reaching the building dry-in milestone. Systems rough-ins, installation of metal studs, and drywall are progessing. Painting has begun.

FinancialOriginal Contract Amount........................................................................$8,592,267.00Approved Allowance Proposals..................................................................$209,941.10Pending Allowance Proposals.......................................................................$9,293.00 ScheduleContract Date....................................................................................................1.6.2020Contract Substantial Completion Date..............................................................1.6.2021Current Substantial Completion Date.............................................................1.22.2021Pending Weather/Delay Days.......................................................................................0Payment StatusWork completed as of 9.30.2020............................................................$5,432,371.00Retainage as of 9.30.2020...........................................................................$190,133.00 Percent Complete as of 9.30.2020........................................................................63.2%

Work in Progress/PlannedHVAC Pipe hangers.HVAC ductwork being insulatedElectrical Rough inSprinkler work continuesContinue metal studs and drywallStorefront continuesPainting continuesMetal Roofing and wall panels continue

Page 3: Monthly Report September 2020...Monthly Report September 2020 By H.G. Reynolds Company Center for Knowledge North ... EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM 20 27

Center for Knowledge NorthBlythewood, South Carolina

SEPTEMBER 2020/PAGE 2

Site Work Activity

Fine grading is ongoing.

Building Activity

Plumbing, Mechanical, and Electrical overhead rough-in continues, as well as fire sprinkler work. Drywall installation, storefront glass, and painting are ongoing. Ac-cess control, intrusion detection, and cameras have begun. Metal roof and wall panels have started. Canopies over windows are complete.

Schedule Update - September 2020

See attached.

Page 4: Monthly Report September 2020...Monthly Report September 2020 By H.G. Reynolds Company Center for Knowledge North ... EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM 20 27

H.G. REYNOLDS COMPANY, INC.SEPTEMBER 2020/PAGE 3

Activity Name OriginalDuration

Start Finish

GENERALGENERALGENERALGENERAL

BID DATE 0 05-Dec-19 08:00 AM A

NOTICE TO PROCEED 0 06-Jan-20 08:00 AM A

SUBSTANTIAL COMPLETION 0 22-Jan-21 05:00 PM

SITEWORKSITEWORKSITEWORKSITEWORK

MOBILIZATION 5 06-Jan-20 08:00 AM A10-Jan-20 05:00 PM A

GRADE PREP BUILDING PAD 20 13-Jan-20 08:00 AM A24-Feb-20 05:00 PM A

STORM DRAINAGE 30 10-Feb-20 08:00 AM A20-Mar-20 05:00 PM A

WATER & SEWER 20 23-Mar-20 08:00 AM A17-Apr-20 05:00 PM A

CONCRETE CURB & GUTTER 20 15-Jun-20 08:00 AM A10-Jul-20 05:00 PM A

PAVING 20 13-Jul-20 08:00 AM A07-Aug-20 05:00 PM A

BUILDING & FINISHESBUILDING & FINISHESBUILDING & FINISHESBUILDING & FINISHES

FOUNDATIONS 20 18-Feb-20 08:00 AM A16-Mar-20 05:00 PM A

UNDERGROUND PLUMBING 20 24-Feb-20 08:00 AM A20-Mar-20 05:00 PM A

UNDERGROUND ELECTRICAL 20 24-Feb-20 08:00 AM A20-Mar-20 05:00 PM A

PREP/POUR SLABS 20 10-Mar-20 08:00 AM A06-Apr-20 05:00 PM A

HM FRAMES 5 31-Mar-20 08:00 AM A06-Apr-20 05:00 PM A

MASONRY WALLS 50 08-Apr-20 08:00 AM A16-Jun-20 05:00 PM A

BRICK 73 29-Apr-20 08:00 AM A07-Aug-20 05:00 PM A

STRUCTURAL STEEL 58 20-May-20 08:00 AM A07-Aug-20 05:00 PM A

HVAC ROUGH-IN 63 17-Jun-20 08:00 AM A11-Sep-20 05:00 PM A

PLUMBING ROUGH-IN 63 17-Jun-20 08:00 AM A11-Sep-20 05:00 PM A

ELECTRICAL ROUGH-IN 63 17-Jun-20 08:00 AM A11-Sep-20 05:00 PM A

FIRE PROTECTION 63 17-Jun-20 08:00 AM A11-Sep-20 05:00 PM A

ROOFING 65 24-Jun-20 08:00 AM A22-Sep-20 05:00 PM A

METAL STUD ROUGH-IN 33 01-Jul-20 08:00 AM A14-Aug-20 05:00 PM A

WINDOWS 20 05-Aug-20 08:00 AM A01-Sep-20 05:00 PM A

EXTERIOR DOORS 15 05-Aug-20 08:00 AM A25-Aug-20 05:00 PM A

DRYWALL INSTALLATION 30 05-Aug-20 08:00 AM A15-Sep-20 05:00 PM A

PRIME PAINT 20 19-Aug-20 08:00 AM A15-Sep-20 05:00 PM A

BUILDING DRY-IN 0 21-Aug-20 08:00 AM A

CEILING GRID 20 02-Sep-20 08:00 AM A29-Sep-20 05:00 PM A

HVAC DIFFUSERS 20 16-Sep-20 08:00 AM A13-Oct-20 05:00 PM

LIGHT FIXTURES/TRIM OUT 20 16-Sep-20 08:00 AM A13-Oct-20 05:00 PM

PERMANENT POWER 0 22-Sep-20 08:00 AM A

HVAC START UP 10 23-Sep-20 08:00 AM A06-Oct-20 05:00 PM

MILLWORK 30 23-Sep-20 08:00 AM A03-Nov-20 05:00 PM

CEILING TILE 20 23-Sep-20 08:00 AM A20-Oct-20 05:00 PM

PLUMBING TRIM OUT 20 30-Sep-20 08:00 AM A27-Oct-20 05:00 PM

DOORS & HARDWARE 20 30-Sep-20 08:00 AM A27-Oct-20 05:00 PM

FLOOR FINISHES 30 30-Sep-20 08:00 AM A10-Nov-20 05:00 PM

FINAL PAINT 20 07-Oct-20 08:00 AM03-Nov-20 05:00 PM

TOILET PARTITIONS/ACCESSORIES 10 11-Nov-20 08:00 AM24-Nov-20 05:00 PM

FINAL CLEAN UP 15 25-Nov-20 08:00 AM15-Dec-20 05:00 PM

OSF FINAL INSPECTION 0 01-Dec-20 05:00 PM

MOVE IN CLASSROOMS 10 17-Dec-20 08:00 AM30-Dec-20 05:00 PM

DEMO PORTABLES 10 31-Dec-20 08:00 AM13-Jan-21 05:00 PM

EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM

20 27 04 11 18 25 01 08

September 2020 October 2020 November 2020

HVAC ROUGH-IN

PLUMBING ROUGH-IN

ELECTRICAL ROUGH-IN

FIRE PROTECTION

ROOFING

DRYWALL INSTALLATION

PRIME PAINT

CEILING GRID

HVAC DIFFUSERS

LIGHT FIXTURES/TRIM OUT

PERMANENT POWER

HVAC START UP

MILLWORK

CEILING TILE

PLUMBING TRIM OUT

DOORS & HARDWARE

FLOOR FINISHES

FINAL PAINT

CENTER FOR KNOWLEDGE - NORTH

Actual Work

Remaining Work

Critical Remaining Work

Milestone

H.G. Reynolds Company, Inc.

Page 5: Monthly Report September 2020...Monthly Report September 2020 By H.G. Reynolds Company Center for Knowledge North ... EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM 20 27

H.G. REYNOLDS COMPANY, INC.SEPTEMBER 2020/PAGE 4

Date Rainfall Amount Jobsite Rain Guage Job ConditionSEPTEMBER

123456789

1011 0.50121314151617 2.5018192021222324 0.2525 1.0026272829 0.7530

Number of days missing work due to Bad Weather 0

We therefore request a 0 day time extension for weather in SeptemberTOTAL RAINFALL FOR THE MONTH = 5" // PROJECT = 41.85"

Page 6: Monthly Report September 2020...Monthly Report September 2020 By H.G. Reynolds Company Center for Knowledge North ... EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM 20 27

H.G. REYNOLDS COMPANY, INC.SEPTEMBER 2020/PAGE 5

MONTHLY PROGRESS PHOTOS

Page 7: Monthly Report September 2020...Monthly Report September 2020 By H.G. Reynolds Company Center for Knowledge North ... EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM 20 27

H.G. REYNOLDS COMPANY, INC.SEPTEMBER 2020/PAGE 6

MONTHLY PROGRESS PHOTOS

Page 8: Monthly Report September 2020...Monthly Report September 2020 By H.G. Reynolds Company Center for Knowledge North ... EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM 20 27

H.G. REYNOLDS COMPANY, INC.SEPTEMBER 2020/PAGE 7

MONTHLY PROGRESS PHOTOS