Monthly ReportSeptember 2020By H.G. Reynolds Company
Center for Knowledge NorthBlythewood, South Carolina
Center for Knowledge NorthBlythewood, South Carolina
SEPTEMBER 2020/PAGE 1
Center for Knowledge North - September 2020 Progress Summary
Executive SummaryWork continues to focus on the interior of the building since reaching the building dry-in milestone. Systems rough-ins, installation of metal studs, and drywall are progessing. Painting has begun.
FinancialOriginal Contract Amount........................................................................$8,592,267.00Approved Allowance Proposals..................................................................$209,941.10Pending Allowance Proposals.......................................................................$9,293.00 ScheduleContract Date....................................................................................................1.6.2020Contract Substantial Completion Date..............................................................1.6.2021Current Substantial Completion Date.............................................................1.22.2021Pending Weather/Delay Days.......................................................................................0Payment StatusWork completed as of 9.30.2020............................................................$5,432,371.00Retainage as of 9.30.2020...........................................................................$190,133.00 Percent Complete as of 9.30.2020........................................................................63.2%
Work in Progress/PlannedHVAC Pipe hangers.HVAC ductwork being insulatedElectrical Rough inSprinkler work continuesContinue metal studs and drywallStorefront continuesPainting continuesMetal Roofing and wall panels continue
Center for Knowledge NorthBlythewood, South Carolina
SEPTEMBER 2020/PAGE 2
Site Work Activity
Fine grading is ongoing.
Building Activity
Plumbing, Mechanical, and Electrical overhead rough-in continues, as well as fire sprinkler work. Drywall installation, storefront glass, and painting are ongoing. Ac-cess control, intrusion detection, and cameras have begun. Metal roof and wall panels have started. Canopies over windows are complete.
Schedule Update - September 2020
See attached.
H.G. REYNOLDS COMPANY, INC.SEPTEMBER 2020/PAGE 3
Activity Name OriginalDuration
Start Finish
GENERALGENERALGENERALGENERAL
BID DATE 0 05-Dec-19 08:00 AM A
NOTICE TO PROCEED 0 06-Jan-20 08:00 AM A
SUBSTANTIAL COMPLETION 0 22-Jan-21 05:00 PM
SITEWORKSITEWORKSITEWORKSITEWORK
MOBILIZATION 5 06-Jan-20 08:00 AM A10-Jan-20 05:00 PM A
GRADE PREP BUILDING PAD 20 13-Jan-20 08:00 AM A24-Feb-20 05:00 PM A
STORM DRAINAGE 30 10-Feb-20 08:00 AM A20-Mar-20 05:00 PM A
WATER & SEWER 20 23-Mar-20 08:00 AM A17-Apr-20 05:00 PM A
CONCRETE CURB & GUTTER 20 15-Jun-20 08:00 AM A10-Jul-20 05:00 PM A
PAVING 20 13-Jul-20 08:00 AM A07-Aug-20 05:00 PM A
BUILDING & FINISHESBUILDING & FINISHESBUILDING & FINISHESBUILDING & FINISHES
FOUNDATIONS 20 18-Feb-20 08:00 AM A16-Mar-20 05:00 PM A
UNDERGROUND PLUMBING 20 24-Feb-20 08:00 AM A20-Mar-20 05:00 PM A
UNDERGROUND ELECTRICAL 20 24-Feb-20 08:00 AM A20-Mar-20 05:00 PM A
PREP/POUR SLABS 20 10-Mar-20 08:00 AM A06-Apr-20 05:00 PM A
HM FRAMES 5 31-Mar-20 08:00 AM A06-Apr-20 05:00 PM A
MASONRY WALLS 50 08-Apr-20 08:00 AM A16-Jun-20 05:00 PM A
BRICK 73 29-Apr-20 08:00 AM A07-Aug-20 05:00 PM A
STRUCTURAL STEEL 58 20-May-20 08:00 AM A07-Aug-20 05:00 PM A
HVAC ROUGH-IN 63 17-Jun-20 08:00 AM A11-Sep-20 05:00 PM A
PLUMBING ROUGH-IN 63 17-Jun-20 08:00 AM A11-Sep-20 05:00 PM A
ELECTRICAL ROUGH-IN 63 17-Jun-20 08:00 AM A11-Sep-20 05:00 PM A
FIRE PROTECTION 63 17-Jun-20 08:00 AM A11-Sep-20 05:00 PM A
ROOFING 65 24-Jun-20 08:00 AM A22-Sep-20 05:00 PM A
METAL STUD ROUGH-IN 33 01-Jul-20 08:00 AM A14-Aug-20 05:00 PM A
WINDOWS 20 05-Aug-20 08:00 AM A01-Sep-20 05:00 PM A
EXTERIOR DOORS 15 05-Aug-20 08:00 AM A25-Aug-20 05:00 PM A
DRYWALL INSTALLATION 30 05-Aug-20 08:00 AM A15-Sep-20 05:00 PM A
PRIME PAINT 20 19-Aug-20 08:00 AM A15-Sep-20 05:00 PM A
BUILDING DRY-IN 0 21-Aug-20 08:00 AM A
CEILING GRID 20 02-Sep-20 08:00 AM A29-Sep-20 05:00 PM A
HVAC DIFFUSERS 20 16-Sep-20 08:00 AM A13-Oct-20 05:00 PM
LIGHT FIXTURES/TRIM OUT 20 16-Sep-20 08:00 AM A13-Oct-20 05:00 PM
PERMANENT POWER 0 22-Sep-20 08:00 AM A
HVAC START UP 10 23-Sep-20 08:00 AM A06-Oct-20 05:00 PM
MILLWORK 30 23-Sep-20 08:00 AM A03-Nov-20 05:00 PM
CEILING TILE 20 23-Sep-20 08:00 AM A20-Oct-20 05:00 PM
PLUMBING TRIM OUT 20 30-Sep-20 08:00 AM A27-Oct-20 05:00 PM
DOORS & HARDWARE 20 30-Sep-20 08:00 AM A27-Oct-20 05:00 PM
FLOOR FINISHES 30 30-Sep-20 08:00 AM A10-Nov-20 05:00 PM
FINAL PAINT 20 07-Oct-20 08:00 AM03-Nov-20 05:00 PM
TOILET PARTITIONS/ACCESSORIES 10 11-Nov-20 08:00 AM24-Nov-20 05:00 PM
FINAL CLEAN UP 15 25-Nov-20 08:00 AM15-Dec-20 05:00 PM
OSF FINAL INSPECTION 0 01-Dec-20 05:00 PM
MOVE IN CLASSROOMS 10 17-Dec-20 08:00 AM30-Dec-20 05:00 PM
DEMO PORTABLES 10 31-Dec-20 08:00 AM13-Jan-21 05:00 PM
EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM
20 27 04 11 18 25 01 08
September 2020 October 2020 November 2020
HVAC ROUGH-IN
PLUMBING ROUGH-IN
ELECTRICAL ROUGH-IN
FIRE PROTECTION
ROOFING
DRYWALL INSTALLATION
PRIME PAINT
CEILING GRID
HVAC DIFFUSERS
LIGHT FIXTURES/TRIM OUT
PERMANENT POWER
HVAC START UP
MILLWORK
CEILING TILE
PLUMBING TRIM OUT
DOORS & HARDWARE
FLOOR FINISHES
FINAL PAINT
CENTER FOR KNOWLEDGE - NORTH
Actual Work
Remaining Work
Critical Remaining Work
Milestone
H.G. Reynolds Company, Inc.
H.G. REYNOLDS COMPANY, INC.SEPTEMBER 2020/PAGE 4
Date Rainfall Amount Jobsite Rain Guage Job ConditionSEPTEMBER
123456789
1011 0.50121314151617 2.5018192021222324 0.2525 1.0026272829 0.7530
Number of days missing work due to Bad Weather 0
We therefore request a 0 day time extension for weather in SeptemberTOTAL RAINFALL FOR THE MONTH = 5" // PROJECT = 41.85"
H.G. REYNOLDS COMPANY, INC.SEPTEMBER 2020/PAGE 5
MONTHLY PROGRESS PHOTOS
H.G. REYNOLDS COMPANY, INC.SEPTEMBER 2020/PAGE 6
MONTHLY PROGRESS PHOTOS
H.G. REYNOLDS COMPANY, INC.SEPTEMBER 2020/PAGE 7
MONTHLY PROGRESS PHOTOS