Monthly Report September 2020 By H.G. Reynolds Company Center for Knowledge North Blythewood, South Carolina

Transcript of Monthly Report September 2020...Monthly Report September 2020 By H.G. Reynolds Company Center for...

Page 1: Monthly Report September 2020...Monthly Report September 2020 By H.G. Reynolds Company Center for Knowledge North ... EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM 20 27

Monthly ReportSeptember 2020By H.G. Reynolds Company

Center for Knowledge NorthBlythewood, South Carolina

Page 2: Monthly Report September 2020...Monthly Report September 2020 By H.G. Reynolds Company Center for Knowledge North ... EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM 20 27

Center for Knowledge NorthBlythewood, South Carolina

SEPTEMBER 2020/PAGE 1

Center for Knowledge North - September 2020 Progress Summary

Executive SummaryWork continues to focus on the interior of the building since reaching the building dry-in milestone. Systems rough-ins, installation of metal studs, and drywall are progessing. Painting has begun.

FinancialOriginal Contract Amount........................................................................$8,592,267.00Approved Allowance Proposals..................................................................$209,941.10Pending Allowance Proposals.......................................................................$9,293.00 ScheduleContract Date....................................................................................................1.6.2020Contract Substantial Completion Date..............................................................1.6.2021Current Substantial Completion Date.............................................................1.22.2021Pending Weather/Delay Days.......................................................................................0Payment StatusWork completed as of 9.30.2020............................................................$5,432,371.00Retainage as of 9.30.2020...........................................................................$190,133.00 Percent Complete as of 9.30.2020........................................................................63.2%

Work in Progress/PlannedHVAC Pipe hangers.HVAC ductwork being insulatedElectrical Rough inSprinkler work continuesContinue metal studs and drywallStorefront continuesPainting continuesMetal Roofing and wall panels continue

Page 3: Monthly Report September 2020...Monthly Report September 2020 By H.G. Reynolds Company Center for Knowledge North ... EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM 20 27

Center for Knowledge NorthBlythewood, South Carolina

SEPTEMBER 2020/PAGE 2

Site Work Activity

Fine grading is ongoing.

Building Activity

Plumbing, Mechanical, and Electrical overhead rough-in continues, as well as fire sprinkler work. Drywall installation, storefront glass, and painting are ongoing. Ac-cess control, intrusion detection, and cameras have begun. Metal roof and wall panels have started. Canopies over windows are complete.

Schedule Update - September 2020

See attached.

Page 4: Monthly Report September 2020...Monthly Report September 2020 By H.G. Reynolds Company Center for Knowledge North ... EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM 20 27

H.G. REYNOLDS COMPANY, INC.SEPTEMBER 2020/PAGE 3

Activity Name OriginalDuration

Start Finish

GENERALGENERALGENERALGENERAL

BID DATE 0 05-Dec-19 08:00 AM A

NOTICE TO PROCEED 0 06-Jan-20 08:00 AM A

SUBSTANTIAL COMPLETION 0 22-Jan-21 05:00 PM

SITEWORKSITEWORKSITEWORKSITEWORK

MOBILIZATION 5 06-Jan-20 08:00 AM A10-Jan-20 05:00 PM A

GRADE PREP BUILDING PAD 20 13-Jan-20 08:00 AM A24-Feb-20 05:00 PM A

STORM DRAINAGE 30 10-Feb-20 08:00 AM A20-Mar-20 05:00 PM A

WATER & SEWER 20 23-Mar-20 08:00 AM A17-Apr-20 05:00 PM A

CONCRETE CURB & GUTTER 20 15-Jun-20 08:00 AM A10-Jul-20 05:00 PM A

PAVING 20 13-Jul-20 08:00 AM A07-Aug-20 05:00 PM A

BUILDING & FINISHESBUILDING & FINISHESBUILDING & FINISHESBUILDING & FINISHES

FOUNDATIONS 20 18-Feb-20 08:00 AM A16-Mar-20 05:00 PM A

UNDERGROUND PLUMBING 20 24-Feb-20 08:00 AM A20-Mar-20 05:00 PM A

UNDERGROUND ELECTRICAL 20 24-Feb-20 08:00 AM A20-Mar-20 05:00 PM A

PREP/POUR SLABS 20 10-Mar-20 08:00 AM A06-Apr-20 05:00 PM A

HM FRAMES 5 31-Mar-20 08:00 AM A06-Apr-20 05:00 PM A

MASONRY WALLS 50 08-Apr-20 08:00 AM A16-Jun-20 05:00 PM A

BRICK 73 29-Apr-20 08:00 AM A07-Aug-20 05:00 PM A

STRUCTURAL STEEL 58 20-May-20 08:00 AM A07-Aug-20 05:00 PM A

HVAC ROUGH-IN 63 17-Jun-20 08:00 AM A11-Sep-20 05:00 PM A

PLUMBING ROUGH-IN 63 17-Jun-20 08:00 AM A11-Sep-20 05:00 PM A

ELECTRICAL ROUGH-IN 63 17-Jun-20 08:00 AM A11-Sep-20 05:00 PM A

FIRE PROTECTION 63 17-Jun-20 08:00 AM A11-Sep-20 05:00 PM A

ROOFING 65 24-Jun-20 08:00 AM A22-Sep-20 05:00 PM A

METAL STUD ROUGH-IN 33 01-Jul-20 08:00 AM A14-Aug-20 05:00 PM A

WINDOWS 20 05-Aug-20 08:00 AM A01-Sep-20 05:00 PM A

EXTERIOR DOORS 15 05-Aug-20 08:00 AM A25-Aug-20 05:00 PM A

DRYWALL INSTALLATION 30 05-Aug-20 08:00 AM A15-Sep-20 05:00 PM A

PRIME PAINT 20 19-Aug-20 08:00 AM A15-Sep-20 05:00 PM A

BUILDING DRY-IN 0 21-Aug-20 08:00 AM A

CEILING GRID 20 02-Sep-20 08:00 AM A29-Sep-20 05:00 PM A

HVAC DIFFUSERS 20 16-Sep-20 08:00 AM A13-Oct-20 05:00 PM

LIGHT FIXTURES/TRIM OUT 20 16-Sep-20 08:00 AM A13-Oct-20 05:00 PM

PERMANENT POWER 0 22-Sep-20 08:00 AM A

HVAC START UP 10 23-Sep-20 08:00 AM A06-Oct-20 05:00 PM

MILLWORK 30 23-Sep-20 08:00 AM A03-Nov-20 05:00 PM

CEILING TILE 20 23-Sep-20 08:00 AM A20-Oct-20 05:00 PM

PLUMBING TRIM OUT 20 30-Sep-20 08:00 AM A27-Oct-20 05:00 PM

DOORS & HARDWARE 20 30-Sep-20 08:00 AM A27-Oct-20 05:00 PM

FLOOR FINISHES 30 30-Sep-20 08:00 AM A10-Nov-20 05:00 PM

FINAL PAINT 20 07-Oct-20 08:00 AM03-Nov-20 05:00 PM

TOILET PARTITIONS/ACCESSORIES 10 11-Nov-20 08:00 AM24-Nov-20 05:00 PM

FINAL CLEAN UP 15 25-Nov-20 08:00 AM15-Dec-20 05:00 PM

OSF FINAL INSPECTION 0 01-Dec-20 05:00 PM

MOVE IN CLASSROOMS 10 17-Dec-20 08:00 AM30-Dec-20 05:00 PM

DEMO PORTABLES 10 31-Dec-20 08:00 AM13-Jan-21 05:00 PM

EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM

20 27 04 11 18 25 01 08

September 2020 October 2020 November 2020

HVAC ROUGH-IN

PLUMBING ROUGH-IN

ELECTRICAL ROUGH-IN

FIRE PROTECTION

ROOFING

DRYWALL INSTALLATION

PRIME PAINT

CEILING GRID

HVAC DIFFUSERS

LIGHT FIXTURES/TRIM OUT

PERMANENT POWER

HVAC START UP

MILLWORK

CEILING TILE

PLUMBING TRIM OUT

DOORS & HARDWARE

FLOOR FINISHES

FINAL PAINT

CENTER FOR KNOWLEDGE - NORTH

Actual Work

Remaining Work

Critical Remaining Work

Milestone

H.G. Reynolds Company, Inc.

Page 5: Monthly Report September 2020...Monthly Report September 2020 By H.G. Reynolds Company Center for Knowledge North ... EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM 20 27

H.G. REYNOLDS COMPANY, INC.SEPTEMBER 2020/PAGE 4

Date Rainfall Amount Jobsite Rain Guage Job ConditionSEPTEMBER

123456789

1011 0.50121314151617 2.5018192021222324 0.2525 1.0026272829 0.7530

Number of days missing work due to Bad Weather 0

We therefore request a 0 day time extension for weather in SeptemberTOTAL RAINFALL FOR THE MONTH = 5" // PROJECT = 41.85"

Page 6: Monthly Report September 2020...Monthly Report September 2020 By H.G. Reynolds Company Center for Knowledge North ... EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM 20 27

H.G. REYNOLDS COMPANY, INC.SEPTEMBER 2020/PAGE 5

MONTHLY PROGRESS PHOTOS

Page 7: Monthly Report September 2020...Monthly Report September 2020 By H.G. Reynolds Company Center for Knowledge North ... EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM 20 27

H.G. REYNOLDS COMPANY, INC.SEPTEMBER 2020/PAGE 6

MONTHLY PROGRESS PHOTOS

Page 8: Monthly Report September 2020...Monthly Report September 2020 By H.G. Reynolds Company Center for Knowledge North ... EXTERIOR CLASSROOM 7 14-Jan-21 08:00 AM22-Jan-21 05:00 PM 20 27

H.G. REYNOLDS COMPANY, INC.SEPTEMBER 2020/PAGE 7

MONTHLY PROGRESS PHOTOS