MIMIC WP 3Identification and assessment of security-related risks
Kick off 5.-6.9.2011, Helsinki
Mirva SalokorpiResearch manager, seafaring and logistics
KyUAS | KymiTechnology | Mirva Salokorpi 2
Project personnel and other partners
Part-time Project manager will start in early October
Recruitment process for a full-time Project specialist on going, the application deadline 8.9.
Research manager (Mirva Salokorpi): responsibility of project establishing and supervising, participate in some tasks, if needed
Project secretary (Päivi Piira)
UTARTU
Finnish ”METO-group”
4.9.2011
KyUAS | KymiTechnology | Mirva Salokorpi 3
The Main Goal (in the project plan)
The main goal is to define security related threats of maritime oil transportation in the Baltic Sea, and to evaluate their impact on the total safety concept. IMO's adopted FSA (formal safety assessment) is the key procedure here.
4.9.2011
KyUAS | KymiTechnology | Mirva Salokorpi 4
Background
”Finnish maritime stakeholders (auhtorities) group” (METO-group: The Finnish Transport Agency, Finnish Transport Safety Agency, The Finnish Border Guard, Ministry of Defence, The Finnish Navy, Ministry of Transport and Communication) is the driving force behind will be as an Advisory Board for wp 3
Preliminary study (METO-group, Aalto, VTT and KyAMK) was completed 2010 (not published), oulined the total safety concept
4.9.2011
KyUAS | KymiTechnology | Mirva Salokorpi 5
Background/purpose/need/aim
To get more information and tools for authorities to develop co-operation and preparing for security threats in the Baltic Sea
Comprehensive approach, basic knowledge about security and safety chains, where these threats and risks can be encounterd
The essential question/challenge: how to model security threats?
4.9.2011
KyUAS | KymiTechnology | Mirva Salokorpi 6
Main tasks
1. state of the art of the security issues related to oil transportation;
2. identification of threats using FSA procedure;
3. recommendations for using best available risk control options and instruments in the Baltic Sea
4.9.2011
KyUAS | KymiTechnology | Mirva Salokorpi 7
Tasks and milestones
I MilestoneMay-Aug 2011
• ”O-result”
II MilestoneSep-Deg 2011
• Start• Literature
review (task1)• First
brainstorming session (task1)
• Subcontracted study will be ordered (task2)
III MilestoneJan-Apr 2012
• First report will be published (task1)
• Project seminar (results of task1, other wp:s and kick off of task3)
• 2 x brainstorming sessions (task2)
• Subcontracted study will be finished
• Web-based questionnaire
IV MilestoneMay-Aug 2012
• Preliminary report (task2)
• Presenting the results of the task 1
• List of identified threats and their ranking (task2)
• Preliminary plan for Risk Control Options (task3)
4.9.2011
KyUAS | KymiTechnology | Mirva Salokorpi 8
Tasks and milestones (2)
V MilestoneSep-Deg 2012
• Final report of the task 2
• The results for the different stakeholders for information and comments
• Preliminary findings of the task 3
VI MilestoneJan-Apr 2013
• Developing the Web Service (UTARTU) (security risk assessment maps)
• Preliminary report (task3)
VII MilestoneMay-Aug 2013
• Closure of the task3
• Testing and using of the Web tool
• Meetings with stakeholders (results and future)
• Writing final report
VIII MilestoneSep-Deg 2013
• Closing period
• Final report (for financier)
4.9.2011
KyUAS | KymiTechnology | Mirva Salokorpi 9
Questions/discussion
Any other connections to other WP:s or participants?
Presentation of the project in Finnish Russian Maritime Assembly 12-14 October 2011 (Ust Luga), call Russian oil companies and ports to participate to the project
+358 44 702 8513