Download - Format Rfi for Base Plate Stc1

Transcript

ENGINEERING & PROJECT MANAGEMENTDoc. No.:EPM-PM-00-03

Department:Planning and ControlRev. No.:00

Section/System:TQMRev. Date:01-01-2013

Document Title:Document Control ProcedurePage No.:Page 2 of 2

ENGINEERING & PROJECT MANAGEMENTSITE PROJECTS DEPARTMENT

REQUEST FOR INSPECTION

Project Title :UPGRADATION OF POWER STACK FAN IN DR MODULE A & B15-Feb-15

Project No. :AF-1221089Project Type : Affiliate : HADEEDRev. :00

Contractor Contact PersonNORMAN MORALESTel:053-1841298RFI NoM-036

Inspection Date16/02/15Time:1400HRSPlace of InspectionCAMERON FAB SHOP

SSRS No.:Network No:

Discipline:CIVIL MECH. ELECT. INSTR.

S No.Item to be InspectedQuantityDrawings No. / Remarks

6.2.3FINAL DIMENSIONAL INSPECTION OF STC1,RD1&STC2 STACK B

SEE ATTACHED DIMENSIONAL REPORTS4509-S00160-F6-001 REV.B4509-S00160-F6-002 REV.B

4509-S00160-F6-003 REV.A4509-S00160-F6-004 REV.C

4509-S00160-F6-009 REV.A4509-S00160-F6-010 REV.A

4509-S00160-F6-007 REV.B4509-S00160-F6-008 REB.A

Results|_|Satisfactory

|_|Unsatisfactory

Comments

QA/QC Engineer / Inspector NameSignature Date

Construction Supervisor / Project EngineerSignature Date

ContractorNORMAN MORALESSignature Date

PROPRIETARY & CONFIDENTIALThis document and the information contained herein is SABICs proprietary know-how. This document or any part thereof should not be reproduced, stored in a retrieval system or transmitted by any means, electronic or otherwise, or divulged without prior written permission of SABIC.

EPM-SPD-PC-F-008 Rev. No.: 00 Page 1 of 2Ref Doc.: EPM-SPD-PC-P-004