EPC in Austria
Reinhard Ungerböck, Graz Energy Agency
29.09.2015, Folie 2
The priciple of EPC
"We will leave a steam engine free
of charge to you. We will install
these and will take over for five
years the customer service.
We guarantee you that the coal for
the machine costs less, than you
must spend at present at fodder
(energy) on the horses, which do
the same work.
And everything that we require of
you, is that you give us a third of
the money, which you save."
James Watt, 18th century
29.09.2015, Folie 3
200 years later:
• EPC projects for ~15 years
• several initiatives:
• BIG-initiative: >300 buildings
• Graz Energy Agency: : >30
tenders
• 15 to 20 ESCOs offering EPC services.
5 ESCOs cover about 70 to 80 % of all EPC-contracts
• DECA: Lobbying organization for EPC, ESCO-driven
EPC in Austria
29.09.2015, Folie 4
• quality standard for tendering energy services
• standard EPC:
• HVAC in buildings
• street lighting
• traffic lights
• advanced EPC:
• comprehensive refurbishment
• IEC: combination with energy supply contracting
• re-commissioning
by GEA
29.09.2015, Folie 5
EPC as an implementation model
Why are so many measures
not being implemented?
1. no time
2. no money
3. lack of know-how
4. lack of trust
the ESCO:
designs and implements
invests money
is an expert
guarantees performance
29.09.2015, Folie 6
Added value of EPC
29.09.2015, Folie 7
Added value of EPC
29.09.2015, Folie 8
no rebound-effect through
Performance-Guarantee
ESCO bears experience of
dozens of facilities
owner/user can concentrate
on his core business
Added value of EPC
29.09.2015, Folie 9
best practice: Wr. Neustadt
initial reason for EPC:
need for investment in the
swimming center
but no financing available
why EPC?
no budget occupation for
investment
outsourcing of technical and
economic risks
professional, performance
orientated maintenance and
monitoring
29.09.2015, Folie 10
best practice: Wr. Neustadt
results project 1 (10 year contract):
savings-guarantee: 214.000 €/a (33%)
investment : 1,45 Mio €
compared to in-house-solution:
savings 15% higher, investment
€370.000 lower
results project 2 (15 year contract):
savings-guarantee: 101.000 €/a (27%)
investment : 1,00 Mio €
9 buildings (6 schools, theater,
museum, kindergarden)
29.09.2015, Folie 11
Client: City of Graz
Project implementation GEA with Thermoprofit contracting
Retrofitting of 190 traffic lights on LED
Total investment costs 2,3 Mio. € (inkl. USt.)
Energy cost savings: 185.000 €/a (68%)
Total savings: 339.000 €/a (75%)
CO2 savings :
460 t/a (68%)
Conversion of Grazer LED lights to LED
Grazer Energieagentur Kaiserfeldgasse 13/I 8010 Graz www.grazer-ea.at
0316 - 811848 -
Direkt zur Homepage!
17
Reinhard Ungerböck, Graz Energy Agency
Thank you for your attention!