Breaching the Mahar Regional School Dam Presentation to Ralph
C. Mahar Regional School Committee GZA GeoEnvironmental, Inc.
February 9, 2011
Slide 2
Presentation Outline Introductions Derek Schipper, P.E. and
Greg Hunt GZA GeoEnvironmental, Inc., Norwood, MA Existing Site
Information Project Background Summary of Dam Breach Feasibility
Study Proposed Dam Breach Design Permitting & Construction
Preliminary Cost Estimate Timeline Example Project Questions
Slide 3
Existing Site
Slide 4
Existing Dam Pond / Impoundment Dam Spillway & Low- level
Outlet with Culvert through Dam Concrete Core Wall Around
Spillway
Slide 5
Dam Information Mahar Regional School Dam: Dam Size: Small
Hazard Rating: Significant Condition: Poor Main Deficiencies:
Growth of trees throughout dam Erosion on top of dam and near
waterline Embankment seepage
Slide 6
Project Background 1950s: Dam constructed 1960: Dam repaired
following spillway damage 2005: New MA Dam Safety Regulations go
into effect 2008: DCR Office of Dam Safety (DCR/ODS) ordered that
dam be inspected by professional engineer July 2009: GZA performed
Phase I Inspection/ Evaluation of Dam; found dam to be in Poor
condition Sept. 2009: School District ordered by DCR/ODS to repair,
breach, or remove dam by March 11, 2011and continue to have dam
inspected every 6 months.
Slide 7
Project Background (Cont.) 2009 present: GZA has performed
three 6-month inspections, dam found to be in similar condition
2010: School Committee approves plan to address condition of dam
through dam removal/breach 2010: GZA prepares Dam Breach
Feasibility Study to evaluate potential dam breach
Slide 8
Dam Breach Feasibility Study GZA Scope of Work: Extension
request from DCR/ODS (11/30/2012 New Date) Field Work Site Survey,
Wetland Resource Evaluation, Sediment Analysis Technical Analysis
Hydrologic & Hydraulic Modeling, Conceptual Breach Design
Permitting Investigation Estimate of project impacts and required
local, state, and federal permits Cost Estimate & Funding
Sources Cost estimate to perform dam breach & potential
grants
Proposed Conditions Conceptual Design Restored Gulf Brook
Stream Channel Excavated Section of Dam for Breach Channel Concrete
Core Wall to Remain Below Ground Stone Erosion Protection Grassed
Slopes
Slide 12
Permitting & Construction Environmental Permitting:
Numerous Local, State, and Federal permits required to work in
wetland resource areas Permit process will likely lasts 9 months 1
year Final Design and Specifications: Prepare final design plans
and specifications suitable for contractor bidding and construction
Construction: Once Final Design is complete and permits are in
place, work awarded to Contractor to perform breach work
Construction to take about 4 weeks
Slide 13
Preliminary Cost Estimate Permitting & Final Design
Engineering $ 85,000 Construction Work$ 170,000 Construction
Contingency (25%)$ 43,000 Construction Engineering (5 weeks)$
35,000 Total Estimated Cost$ 333,000
Slide 14
Preliminary Timeline Spring 2011: Submit Environmental
Permitting Summer 2011: Final Engineering Design &
Specifications Spring 2012: Award Construction Contract Summer
2012: Perform Dam Breach Work Fall 2012 - 2013: Revegetation
Monitoring & Maintenance by Contractor Note: Under current
timeline, dam breach work must be completed by November 30, 2012,
and Six-Month Follow-Up Inspections of Dam must continue until work
is completed.
Slide 15
Questions?
Slide 16
Before Dam Breach One Year After Dam Breach Example Project:
Champlin Pond Dam Breach