Bongkot Booster Compressors Project Phase 4
WP16-Offshore Construction
Contract No. ECM-12-0500
WP16-Offshore Construction
Thai Nippon Steel & Sumikin Engineering & Construction Corp.,Ltd
Agenda
1. Scope of Work
2. Planning & Project Schedule
3. Work Method
4. Project Highlights
2
Booster Compressor (BC) Package Modification Works at WP16
� Demolition and relocation of structural elements at lower and upper deck
� Installation of Deck Extensions at west side of Lower & Upper Deck
� Install hand rail/ beam members/ deck plate/ doublers plate for BC skid base support
� Lifting and positioning of BC package
1. Scope of Work
3
� Lifting and positioning of BC package� BC package assembly, leveling, alignment and full
welding of skid base to the doublers support plate� Installation of loose items for BC package� Tie-in BC Package to platform System� Pressure testing� Installation and modification of relevant Electrical
and Instrument systems� Pre- commissioning and commissioning� Power brushing and touch up painting
2. Planning & Project Schedule
� Key Dates & Milestones
Key Dates Event Date
1 WP16 Structural fabrication completion 21-Mar-14
2 Work barge alongside at WP16 5-Jul-14
3 WP16 Deck extension installation completion 29-Jul-14
4 WP16 Booster compressor package installation complete 19-Jul-14
4
4 WP16 Booster compressor package installation complete 19-Jul-14
5 WP16 Offshore work completion 8-Aug-14
6 Final documentation 8-Sep-14
Note : This schedule is base on accommodation barge along-side at WP16 between 5-Jul-14 to 8-Aug-14
Offshore Schedule
5
Upper Deck
Stair
3. WORK METHOD (WP16)
Lower Deck
Deck Extension for
Header manifold
Lower Deck West Side.
Lower Deck North Side.
3.1 PREPARATORY WORKS
1. Set up, install personnel access Gangway betweenaccommodation Barge and WP16 Platform @ upperdeck and lower deck
2. Install hanging scaffolding access @ upper deck andlower deck
3. Install hot work shielding/habitat @ upper deck andlower deck
9
3. Install hot work shielding/habitat @ upper deck andlower deck
4. Demolish of existing handrail and obstruct item outfrom work area at lower deck and upper deck @ upperdeck and lower deck
5. Prepared of new joint and install stopper support atinterconnecting for install new deck extension @ upperdeck and lower deck
PIPING TIE-IN POINT
10
To be modify support6”-CG-26B3-F48
TIP-01
TIP-02
TIP-01
TIP-02
6”-CG-26AD-F48 (existing)
6”-CG-26AD-F48 (existing)
4”-CG-26A3-F48
6”-CG-26HK-F48 (existing)
TIP-03
TIP-04
6”-CG-26D3-F48
4”-CG-26C3-F48
6”-CG-26BE-F48 (existing)
TIP-03
TIP-04
6”-CG-26CF-F48 (existing)
TIP-05 TIP-06
TIP-05
TIP-06
6”-CG-26LM-F48 (existing)
4”-CG-26C3-F48
4”-CG-26C3-F48
TIP-07
TIP-08
TIP-08
TIP-07
6”-CG-2612-F48 (existing)
6”-CG-2612-F48 (existing)
6”-CG-2671-F48
TIP-10
TIP-10
4”-CG-2652-F48
TIP-09
TIP-09
6”-CG-2612-F48 (existing)
TIP-12
8”-AV-2617-B03 (existing)
TIP-12
TIP-13TIP-13
8”-AV-2617-B03
TIP-14
TIP-14
8”-AV-2617-B03
8”-AV-2617-B03 (existing)
8”-AV-2651-B03 (existing)
1”-AV-26100-B03
6”-AV-2651-B03 (existing)
TIP-15A TIP-15B
TIP-15A TIP-15B
6”-AV-26112-F48
TIP-16
3”-CD-2647-F48
3”-CD-2647-F48 (existing)
TIP-16
TIP-17A
3”-DO-2678-F48 (existing)
2”-CD-26110-B03
3”-DO-2678-F48 (existing)
TIP-17A
TIP-17B
TIP-17B
3”-DO-2678-F48 (existing)
3”-IG-2553-B03 (existing)
2”-IG-2553-B03 (existing)
2”-IG-2682-B03
TIP-18
3”-OD-2543-B91 (existing)
2”-OD-26110-B91
TIP-19
TIP-20
2”-OD-26113-B91
2”-OD-26113-B91 (existing)
TIP-20
4. Project Highlights
� CY boat runs for the mobilization will be directed from Petra Lyra (WP16) at Bongkot Field
� A shutdown is planned by 1-Aug-14 until 3-
24
A shutdown is planned by 1-Aug-14 until 3-Aug-14 for WP15