Bongkot Booster Compressors Project Phase 4
WP16-Offshore Construction
Contract No. ECM-12-0500
WP16-Offshore Construction
Thai Nippon Steel & Sumikin Engineering & Construction Corp.,Ltd
![Page 2: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/2.jpg)
Agenda
1. Scope of Work
2. Planning & Project Schedule
3. Work Method
4. Project Highlights
2
![Page 3: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/3.jpg)
Booster Compressor (BC) Package Modification Works at WP16
� Demolition and relocation of structural elements at lower and upper deck
� Installation of Deck Extensions at west side of Lower & Upper Deck
� Install hand rail/ beam members/ deck plate/ doublers plate for BC skid base support
� Lifting and positioning of BC package
1. Scope of Work
3
� Lifting and positioning of BC package� BC package assembly, leveling, alignment and full
welding of skid base to the doublers support plate� Installation of loose items for BC package� Tie-in BC Package to platform System� Pressure testing� Installation and modification of relevant Electrical
and Instrument systems� Pre- commissioning and commissioning� Power brushing and touch up painting
![Page 4: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/4.jpg)
2. Planning & Project Schedule
� Key Dates & Milestones
Key Dates Event Date
1 WP16 Structural fabrication completion 21-Mar-14
2 Work barge alongside at WP16 5-Jul-14
3 WP16 Deck extension installation completion 29-Jul-14
4 WP16 Booster compressor package installation complete 19-Jul-14
4
4 WP16 Booster compressor package installation complete 19-Jul-14
5 WP16 Offshore work completion 8-Aug-14
6 Final documentation 8-Sep-14
Note : This schedule is base on accommodation barge along-side at WP16 between 5-Jul-14 to 8-Aug-14
![Page 5: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/5.jpg)
Offshore Schedule
5
![Page 6: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/6.jpg)
Upper Deck
Stair
3. WORK METHOD (WP16)
Lower Deck
![Page 7: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/7.jpg)
Deck Extension for
Header manifold
![Page 8: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/8.jpg)
Lower Deck West Side.
Lower Deck North Side.
![Page 9: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/9.jpg)
3.1 PREPARATORY WORKS
1. Set up, install personnel access Gangway betweenaccommodation Barge and WP16 Platform @ upperdeck and lower deck
2. Install hanging scaffolding access @ upper deck andlower deck
3. Install hot work shielding/habitat @ upper deck andlower deck
9
3. Install hot work shielding/habitat @ upper deck andlower deck
4. Demolish of existing handrail and obstruct item outfrom work area at lower deck and upper deck @ upperdeck and lower deck
5. Prepared of new joint and install stopper support atinterconnecting for install new deck extension @ upperdeck and lower deck
![Page 10: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/10.jpg)
PIPING TIE-IN POINT
10
![Page 11: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/11.jpg)
To be modify support6”-CG-26B3-F48
TIP-01
TIP-02
TIP-01
TIP-02
6”-CG-26AD-F48 (existing)
6”-CG-26AD-F48 (existing)
4”-CG-26A3-F48
![Page 12: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/12.jpg)
6”-CG-26HK-F48 (existing)
TIP-03
TIP-04
6”-CG-26D3-F48
4”-CG-26C3-F48
6”-CG-26BE-F48 (existing)
TIP-03
TIP-04
![Page 13: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/13.jpg)
6”-CG-26CF-F48 (existing)
TIP-05 TIP-06
TIP-05
TIP-06
6”-CG-26LM-F48 (existing)
4”-CG-26C3-F48
4”-CG-26C3-F48
![Page 14: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/14.jpg)
TIP-07
TIP-08
TIP-08
TIP-07
6”-CG-2612-F48 (existing)
6”-CG-2612-F48 (existing)
6”-CG-2671-F48
![Page 15: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/15.jpg)
TIP-10
TIP-10
4”-CG-2652-F48
TIP-09
TIP-09
6”-CG-2612-F48 (existing)
![Page 16: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/16.jpg)
TIP-12
8”-AV-2617-B03 (existing)
TIP-12
TIP-13TIP-13
8”-AV-2617-B03
![Page 17: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/17.jpg)
TIP-14
TIP-14
8”-AV-2617-B03
8”-AV-2617-B03 (existing)
![Page 18: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/18.jpg)
8”-AV-2651-B03 (existing)
1”-AV-26100-B03
6”-AV-2651-B03 (existing)
TIP-15A TIP-15B
TIP-15A TIP-15B
![Page 19: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/19.jpg)
6”-AV-26112-F48
TIP-16
3”-CD-2647-F48
3”-CD-2647-F48 (existing)
TIP-16
![Page 20: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/20.jpg)
TIP-17A
3”-DO-2678-F48 (existing)
2”-CD-26110-B03
3”-DO-2678-F48 (existing)
TIP-17A
TIP-17B
TIP-17B
3”-DO-2678-F48 (existing)
![Page 21: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/21.jpg)
3”-IG-2553-B03 (existing)
2”-IG-2553-B03 (existing)
2”-IG-2682-B03
TIP-18
![Page 22: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/22.jpg)
3”-OD-2543-B91 (existing)
2”-OD-26110-B91
TIP-19
![Page 23: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/23.jpg)
TIP-20
2”-OD-26113-B91
2”-OD-26113-B91 (existing)
TIP-20
![Page 24: BC4-Bongkot WP16 PRESENTATION - Rev.01](https://reader030.fdocuments.us/reader030/viewer/2022032506/55cc9267bb61eb54578b4725/html5/thumbnails/24.jpg)
4. Project Highlights
� CY boat runs for the mobilization will be directed from Petra Lyra (WP16) at Bongkot Field
� A shutdown is planned by 1-Aug-14 until 3-
24
A shutdown is planned by 1-Aug-14 until 3-Aug-14 for WP15