Phase 2AIn this slide show:

West Canopy & Interior Work

July 8, 2011

Page 2: 7.6.11 West Canopy & Interior Work

New west side canopy completed with all lighting installed.

Page 3: 7.6.11 West Canopy & Interior Work

New copper gutter installed on north canopy adjacent to Plaza.

Page 4: 7.6.11 West Canopy & Interior Work

A large roll-up door installed on the west wall.

Page 5: 7.6.11 West Canopy & Interior Work

The future baggage area gets a new door with brass fixtures and restored windows that allow plenty of light.

Page 6: 7.6.11 West Canopy & Interior Work

This beautiful marble counter was reinstalled.

Page 7: 7.6.11 West Canopy & Interior Work

The freshly refurbished grand staircase steps and new stainlessness rail.

Page 8: 7.6.11 West Canopy & Interior Work

Mechanical systems under the plaza in the final stage of installation.

Page 9: 7.6.11 West Canopy & Interior Work

Communications equipment room under construction.

Page 10: 7.6.11 West Canopy & Interior Work

Staircase and lift door (right of stair) to mezzanine space above future Amtrak offices.

Page 11: 7.6.11 West Canopy & Interior Work

At the mezzanine level this area will serve as restrooms and locker rooms.

Page 12: 7.6.11 West Canopy & Interior Work

Future Amtrak break room on the mezzanine level.

Page 13: 7.6.11 West Canopy & Interior Work

Additional interior partitions installed for future use.

Page 14: 7.6.11 West Canopy & Interior Work

This space, under the northeast corner of the plaza, will be the recycling room. Metallic, automatic roll-up doors provide convenient access.

Page 15: 7.6.11 West Canopy & Interior Work

A new steel guard plate installed to protect Jackson Street structural wall.

Page 16: 7.6.11 West Canopy & Interior Work

On the station’s west side crews installed 31 additional geothermal wells expanding the efficient, sustainable heating and cooling systems.