ZDC Status, 9th December ‘07
• Fitting in the TAN slot
• Getting in and out of the TAN
• Schedule
• TriggerYasar Onel (Michael Murray) for ZDC group
2
Several problems fitting in TAN1. bumps in the ZDC, biggest bumps flattened
& threaded rods were inserted through the empty screw holes in the 2 hadronic modules
2. Poor assembly of TAN improved3. The slope of the LHC, the bottom of the ZDCs
has been bevelled 4. Limitations of crane; Paul and Ianos have
come up with a much better design that should be much cheaper than option proposed by CERN. (See ZDC_crane.ppt for full details)
3
Partial Vertical Extraction
Twin Lead screws (not shown) located vertically between each end of the
Lift frame and outer frame pull ZDC from slot..
4
Full Extraction
5
Partial RotationClever Bell assembly is rotated slightly upward and out toward transport side of tunnel. Motion is again by a pair of lead screws which spanbetween each set of fixed and rotating leaves.
6
“Clever Bell” mated to Shielding Pig
Clever Bell assembly mates on alignment pins to pig. Alignment blocks
on sideof TAN allow accurate pre-placement of pig.
7
ZDC Fully lowered into Pig
Human intervention then to disconnect ZDC fromcrane. Pig is removed,
pig containing copper bars put in place, affixed to crane and procedure
reversed. Copper bar module must be built to duplicate the manner in
which ZDC attaches to lift frame.
8
Schedule
• Right hand ZDC will most likely be installed sometime in weeks 7,8 or 9, left sometime between Feb 24 and Apr 9
• Getting crane approved and built by then is a great challenge but everyone on ZDC team will work on this
• KU, Iowa will cover these times but we could do with help
9
Trigger
• ZDC has very simple “on”, “off” contributions to trigger that will be used for beam tuning, diffraction and heavy ion.
• Need to start programming frim-ware for this. One student coming to CERN for 3 months, perhaps he could learn how to do this.
10
ZDC => LHCC
• We have not yet presented ZDC project to LHCC. Skuja approved the the report but we are trying to improve its “look and feel”
• Oleg and David d’Enterrira are working on this