1
1.1 Name of the infrastructure: Navarra CSTechnical characteristics 38 MW
1.2 Name of the responsible TSO: Enagás S.A1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) Yes
Spain-France: 0
France-Spain:Max:100
Min: 50(W) / 40 (S)
2.1 Initial Planning 2.2 Updated forecast
Starting operation date 2009 May-09
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Apr-2004 May-2005
3.2 Environmental Assessment Jun-2007
3.3 Final (Authorisation for starting construction) Dec-2006 Nov-2007
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 100% 100%
4.2 Procurement 100% 100%
4.3 Construction 100% 100%
4.4 Commissioning 100% 100%
Causes of delays (if applied)
1
2
3
4
5
COMMISSIONED
1. Larrau investments
2
1.1 Name of the infrastructure: Pipeline Lemona – HaroTechnical characteristics 92 km / 26"
1.2 Name of the responsible TSO: Enagás S.A1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) Yes
Spain-France: 0
France-Spain:Max:100
Min: 30(W) / 20 (S)
2.1 Initial Planning 2.2 Updated forecast
Starting operation date 2009 Ago-09
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Mar-2006 Apr-2006
3.2 Environmental Assessment Sep-2007
3.3 Final (Authorisation for starting construction) May-2006 Dec-2007
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 100% 100%
4.2 Procurement 100% 100%
4.3 Construction 100% 100%
4.4 Commissioning 100% 100%
Causes of delays (if applied)
1
2
3
4
5
COMMISSIONED
1. Larrau investments
3
1.1 Name of the infrastructure: Reinforcement of Haro CSTechnical characteristics 23 MW
1.2 Name of the responsible TSO: Enagás S.A1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) Yes
Spain-France: 0
France-Spain:Max:100
Min: 30(W) / 20 (S)
2.1 Initial Planning 2.2 Updated forecast
Starting operation date 2009 Ago-09
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Mar-2006 Jul-2006
3.2 Environmental Assessment Apr-2007
3.3 Final (Authorisation for starting construction) Sep-2006 Dec-2007
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 100% 100%
4.2 Procurement 100% 100%
4.3 Construction 100% 100%
4.4 Commissioning 100% 100%
Causes of delays (if applied)
1
2
3
4
5
COMMISSIONED
1. Larrau investments
4
1.1 Name of the infrastructure: Pipeline Castelnou – Tivisa (loop)Technical characteristics 91 km / 26"
1.2 Name of the responsible TSO: Enagás S.A1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) YesSpain-France: 30(W) / 50 (S)
France-Spain: 100
2.1 Initial Planning 2.2 Updated forecast
Starting operation date 2009 Sep/Oct-09
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Mar-2006 Feb-2007
3.2 Environmental Assessment Mar-2007 Apr-2009
3.3 Final (Authorisation for starting construction) Mar-2007 Oct-2009
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 100% 100%
4.2 Procurement 100% 100%
4.3 Construction 0% 100%
4.4 Commissioning 0% 100%
Causes of delays (if applied)
1
2
3
4
5
COMMISSIONED
1. Larrau investments
5
1.1 Name of the infrastructure: Villar de Arnedo CSTechnical characteristics 35 MW
1.2 Name of the responsible TSO: Enagás S.A1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) YesSpain-France: 110(W) / 100 (S)
France-Spain: 100
2.1 Initial Planning 2.2 Updated forecast
Starting operation date 2010 Feb-11
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Apr-2006 Feb-2008
3.2 Environmental Assessment Nov-2008
3.3 Final (Authorisation for starting construction) Jul-2008 Mar-2010
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 81% 100%
4.2 Procurement 61% 100%
4.3 Construction 0% 100%
4.4 Commissioning 0% 100%
Causes of delays (if applied)
1
2
3
4
5
COMMISSIONED
1. Larrau investments
6
1.1 Name of the infrastructure: Pipeline Tivisa – Paterna (loop)Technical characteristics 235 km / 40"
1.2 Name of the responsible TSO: Enagás S.A1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) YesSpain-France: 30(W) / 50 (S)
France-Spain: 100
2.1 Initial Planning 2.2 Updated forecast
Starting operation date 2009 Nov-2011
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Mar-2006 May-2007
3.2 Environmental Assessment Jun-2007 Jul-2009
3.3 Final (Authorisation for starting construction) Jun-2007 Jan-2011
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 100% 100%
4.2 Procurement 98% 100%
4.3 Construction 69% 100%
4.4 Commissioning 100% 100%
Causes of delays (if applied) The pipeline is divided in 3 tranches (i.e North, Central, South). The 3 tranches are already commissioned
1
2
3
4
5
COMMISSIONED
1. Larrau investments
7
1.1 Name of the infrastructure: Pipeline Zarza de Tajo - YelaTechnical characteristics 106 km / 30"
1.2 Name of the responsible TSO: Enagás S.A1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) YesSpain-France: 110(W) / 100 (S)
France-Spain: 100
2.1Initial Planning 2.2 Updated forecast
Starting operation date 2010 4Q2013
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Apr-2006 Dec-2007
3.2 Environmental Assessment Apr-2011 Nov-2011
3.3 Final (Authorisation for starting construction) May-2008 pending
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 70% 70%
4.2 Procurement 35% 95%
4.3 Construction 0% 0%
4.4 Commissioning 0% 0%
Causes of delays (if applied) Pending Final Authorisation for starting construction
1
2
3
4
5
1. Larrau investments
8
1.1 Name of the infrastructure: Pipeline Yela – Villar de ArnedoTechnical characteristics 251 km / 30"
1.2 Name of the responsible TSO: Enagás S.A1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) YesSpain-France: 110(W) / 100 (S)
France-Spain: 100
2.1Initial Planning 2.2 Updated forecast
Starting operation date 2010 Dec-12
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Apr-2006 Jun-2008
3.2 Environmental Assessment May-2006 Nov-2010
3.3 Final (Authorisation for starting construction) Jul-2008 Dec-2010
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 100% 100%
4.2 Procurement 22% 90%
4.3 Construction 0% 63%
4.4 Commissioning 0% 0%
Causes of delays (if applied)
1
2
3
4
5
1. Larrau investments
9
1.1 Name of the infrastructure: CS at the borderTechnical characteristics To be defined
1.2 Name of the responsible TSO: Application made by Enagás S.A for authorisation1.3 Additional capacity from existing infrastructure (GWh/day)
1.4 Investment approved by TSO (YES/NO) YesSpain-France: 60
France-Spain: 0
2.1 Initial Planning 2.2 Updated forecast
Starting operation date 2015 2015
Administrative milestones A) Application Date B) Concession Date
3.1 Initial (promoter choice) Jun-2008
3.2 Environmental Assessment
3.3 Final (Authorisation for starting construction)
Current project advance A) In previous review (%) B) Total (%)
4.1 Engineering 0% 0%
4.2 Procurement 0% 0%
4.3 Construction 0% 0%
4.4 Commissioning 0% 0%
Causes of delays (if applied)
1
2
3
4
5
1. Biriatou investments