    ZXSDR BS8700 Step by StepCommissioning Guide

    GSM Product Support Dept.

    Wireless Network Service Center

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    2/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    LEGAL INFORMATION

    By accepting this certain document of ZTE CORPORATION you agree to the following terms. If you

    do not agree to the following terms, please notice that you are not allowed to use this document.

    Copyright 2013 ZTE CORPORATION. Any rights not expressly granted herein are reserved. This

    document contains proprietary information of ZTE CORPORATION. Any reproduction, transfer,

    distribution, use or disclosure of this document or any portion of this document, in any form by any

    means, without the prior written consent of ZTE CORPORATION is prohibited.

    and are registered trademarks of ZTE CORPORATION. ZTEs company name, logo

    and product names referenced herein are either trademarks or registered trademarks of ZTE

    CORPORATION. Other product and company names mentioned herein may be trademarks or trade

    names of their respective owners. Without the prior written consent of ZTE CORPORATION or the

    third party owner thereof, anyones access to this document should not be construed as granting, by

    implication, estopped or otherwise, any license or right to use any marks appearing in the document.

    The design of this product complies with requirements of environmental protection and personal

    security. This product shall be stored, used or discarded in accordance with product manual,

    relevant contract or laws and regulations in relevant country (countries).

    This document is provided as is and as available. Information contained in this document is

    subject to continuous update without further notice due to improvement and update of ZTECORPORATIONs products and technologies.

    ZTE CORPORATION

    Address: NO. 55

    Hi-tech Road South

    ShenZhen

    P.R.China518057

    Website: http://support.zte.com.cn

    Email: [email protected]

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. I

    http://support.zte.com.cn/mailto:[email protected]:[email protected]://support.zte.com.cn/
  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    3/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    Revision History

    Product Version Document Version Serial Number Reason for Revision

    R1.0 First published

    Author

    Date Document Version Prepared by Reviewed by Approved by

    2010-5-7 R1.0 Bai Guowei Cai Kai

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. II

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    4/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    About This Document

    Applicable to: ZXSDR BS8700 BTS

    Intended for: Supervisor, commissioning engineer

    This document aims to guide the commissioning task of site engineer after the

    completion of BS8700 installation and acceptance test. For detailed information of

    installation procedure and installation check, please refer to the related documents.

    Summary

    Chapter Description

    1 Overview Commissioning flow, manpower projection and skillsrequired

    2 Product Introduction Introduction about BBU and RRU

    3 Preparations Before OnsiteOperation

    Prerequisites, tools and documents required forcommissioning

    4 Commissioning Checking hardware, cables, power-on/power-off andrunning status of BTS

    5 BTS Test CS service test, PS service test, handover test, filling oftest report

    6 Site Cleaning Items to be cleaned on site

    Error: Reference source not foundError: Reference source not found

    Appendix

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. III

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    5/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    TABLE OF CONTENTS

    1 Overview 11.1 Introduction...................................................................................................................11.2 BTS Commissioning Flowchart..................................................................................... 11.3 Manpower Projection....................................................................................................11.4 Required Skills..............................................................................................................2

    2 Product Introduction..................................................................................................... 22.1 BBU (B8200) ................................................................................................................22.2 BBU Boards (B8200) ....................................................................................................3

    2.3 BBU External Cable Connection (B8200) .....................................................................42.4 RRU (R8860) ............................................................................................................... 5

    3 Preparations Before Onsite Operation......................................................................... 63.1 Checking Onsite Commissioning Conditions ................................................................63.2 Preparing Tools............................................................................................................. 63.3 Preparing Documents................................................................................................... 7

    4 Commissioning..............................................................................................................74.1 Checking Hardware....................................................................................................... 74.1.1 Checking Configuration and Model of BBU and RRU...........................................74.1.2 Checking SA Jumpers.......................................................................................... 9

    4.1.3 Checking Power Supply..................................................................................... 114.1.4 Checking BTS Transmission..............................................................................124.1.5 Checking Cable Connection...............................................................................144.1.6 Checking Power-on/Power-off of BTS................................................................154.1.7 Checking BTS Running Status...........................................................................17

    5 BTS Test 185.1 Commissioning Test....................................................................................................185.1.1 CS Service Test................................................................................................. 185.1.2 PS Service Test..................................................................................................205.1.3 Handover Test.................................................................................................... 205.2 BTS Commissioning Test Report (Completed on Site)...............................................21

    6 Site Cleaning................................................................................................................ 22

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. IV

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    6/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    FIGURES

    Figure 1-1 BTS Commissioning Flowchart.....................................................................1

    Figure 2-2 ZXSDR B8200 GU360 Configuration...............................................................2

    Figure 2-3 Appearance of R8860..................................................................................... 5

    Figure 2-4 RRU interfaces................................................................................................6

    Figure 4-5 Board Slot Configuration...............................................................................7

    Figure 4-6 Factory Bar Code of CC Board......................................................................8

    Figure 4-7 Position of the SA Jumper...........................................................................10

    Figure 4-8 Cable Connection of BTS............................................................................. 15

    TABLES

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. V

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    7/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    Table 1-1 Manpower Projection........................................................................................1

    Table 2-2 ZXSDR B8200 Board List................................................................................. 3

    Table 2-3 Description of B8200 External Cable Connection..........................................4

    Table 4-4 Checklist of BBU and RRU Product Configurations and Models.................8

    Table 4-5 Setting of X5 Jumper [1, 0] ..............................................................................9

    Table 4-6 Setting of X5 Jumper [3, 2]..............................................................................9

    Table 4-7 Setting of X6 jumpers..................................................................................... 11

    Table 4-8 Checklist of Input Power Supply................................................................... 12

    Table 4-9 BTS Transmission Checklist.........................................................................12

    Table 4-10 75 E1 Cable Sequence ...............................................................................13

    Table 4-11 120 E1 Cable and 120 T1 Cable Sequences..........................................13

    Table 4-12 Cable Connection Checklist........................................................................14

    Table 4-13 Description of B8200 Board Status in Normal Working Status................17

    Table 5-14 BTS Commissioning Test Report................................................................21

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. VI

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    8/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    1 Overview

    1.1 Introduction

    This guide focuses on the commissioning of ZXSDR BS8700, including SDR

    commissioning flow and procedure.

    Please conduct commissioning according to this guide after equipment installation

    and check. For equipment installation information, please refer to the following

    documents.

    ZXSDR BS8700 (V4.00.30) Hardware Installation Guide (BBU)

    ZXSDR BS8700 (V4.00.30) Hardware Installation Guide (RRU)

    ZXSDR BS8700 (V4.00.30) Hardware Description

    1.2 BTS Commissioning Flowchart

    Figure 1-1 BTS Commissioning Flowchart

    1.3 Manpower Projection

    Table 1-1 Manpower Projection

    Position Responsibilities

    BTScommissioning engineer

    Prepare and check BTS commissioning, and assist theiBSC&RNC commissioning engineer in finishing BTScommissioning.

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 1

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    9/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    Position Responsibilities

    Supervisor Be responsible for the whole process of commissioning

    iBSC&RNC

    commissioning engineer

    Perform data synchronization between BTS and OMCR, andtrace BTS related signaling in the course of BTS commissioning.

    1.4 Required Skills

    The person responsible for BS8700 commissioning should know about the following

    knowledge:

    ZXSDR BS8700 products (boards, cables and system infrastructure), as well as

    installation and checking modes.

    Types, sequences and connection methods of SDR transmission cables.

    Basic (speech and data) commissioning skills of SDR.

    2 Product Introduction

    ZXSDR BS8700 is of distributed structure, which includes baseband unit (BBU) and

    remote radio unit (RRU).

    2.1 BBU (B8200)

    ZXSDR B8200 GU360 is also named indoor GSM/UMTS dual-mode baseband pool.

    Figure 2-2 ZXSDR B8200 GU360 Configuration

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 2

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    10/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    2.2 BBU Boards (B8200)

    Table 2-2 ZXSDR B8200 Board List

    Abbreviation Full name Description

    PM0 Power ModuleIt provides power to the other boards.One module is configured by default;1+1 backup configuration is optional.

    SA Site Alarm Module

    This board integrates the functions ofenvironment monitoring and E1interface, providing 6 incoming and 2outgoing lines of dry contact monitoringand 8 lines of E1/T1 interfaces. Besides,it provides one line of RS232 and one

    line of RS485.

    CC0/CC1Control and ClockModule

    Its functions include switching of mediastream and control stream, processingclocks and managing subracks.

    The panel provides GE interface(optional for optical and electrical) fortransmission over Iub, and it alsoprovides antenna interface. Only onemodule is configured by default. 1+1backup configuration is optional. TheREF interface supports import of BITSsignal source.

    FSFabric SwitchModule

    This board focuses on IQ signalswitching. Each supports 6 fiberinterfaces to connect with the RRUmodule. Two FSs at the maximum inloading sharing mode can be configured.

    BPCBasebandProcessing BoardType C

    Baseband board for WCDMA

    UBPGGSM BasebandProcessor

    UBPG is the baseband board of GSM.One UBPG supports 12 TRXs.

    FA FAN ModuleIt is on the right side of the subrack,,which is used for heat dissipation.

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 3

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    11/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    2.3 BBU External Cable Connection (B8200)

    Table 2-3 Description of B8200 External Cable Connection

    B8200 External Cable Connection

    NoCablename

    Media/type

    UsageLocal end

    connected toPeer end

    connected to

    1GPSantennacable

    It receives GPSsignals

    REF port onthe CC boardof B8200

    GPS lightningarrester

    2B8200powercable

    Blueandblackpower

    cables

    B8200 powercable

    Powerinterface onthe PM board

    of B8200

    -48V DC powersupply

    3SA panelcable

    It connects E1DB44connector

    E1 cable studout of the DDF

    It connectsRS232/RS485serial port cable

    DB9connector

    Externalcommissioningdevice

    It connectsexternal alarmcable

    DB25connector

    Parts to bemonitored

    4Iub/Abisinterface

    2M

    coaxialcable

    Iub/Abis interface

    E1 interfaceon the SAboard ofB8200

    iBSC/RNC

    5

    Iub/Abisinterfaceand GEelectricalportcables

    RJ45suppercategory 5/6twisted-pair

    It connects theEthernetinterfacebetween BBUand iBSC/RNC.This interfaceprovides opticalinterface andelectricalinterface of theEthernet on thepanel(10M/100M/1000M self-adaptive)

    ETH0interface onthe CC boardof B8200(electricalport)

    The IP networkof iBSC/RNC

    6

    Iub/Abisinterfaceopticalport

    Fiber

    It connectsoptical portbetween BBUand iBSC/RNC

    Optical porton the CCboard ofB8200

    The IP networkconnecting toRNC/Abis (notin use becauseof technicallimitations)

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 4

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    12/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    B8200 External Cable Connection

    NoCablename

    Media/type

    UsageLocal end

    connected toPeer end

    connected to

    7CPRIinterfacecable

    Single-modefiber

    It connects BBUand RRU totransmit IQsignals

    Optical porton the FSboard ofB8200

    CPRI interfaceon the RRU

    8

    RRUcommissioningcable

    RMBinterface cableandinterface board

    It connects RRUforcommissioning

    Monitorinterface onthe RRU

    RMB board

    9

    RRU

    antenna

    7/8''

    feeder Feeder

    Antenna

    interface onthe RRU Cell antenna

    10

    EXT externaltelecommunication interface,connectingexternal receiver;

    EXT interfaceon the CCboard ofB8200

    2.4 RRU (R8860)

    R8860 is an outdoor macro remote radio unit (RRU).

    Figure 2-3 Appearance of R8860

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 5

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    13/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    Figure 2-4 RRU interfaces

    1. (LC1) Interface between BBU and RRU/RRU cascading interface2. (LC2) Interface between BBU and RRU/RRU cascading interface3. (AISG) AISG equipment interface4. (Mon) Interfaces for external devices (such as monitoring, LMT, etc.)5. (DCIN) Power interface6. Interface for Rx diversity RF cable

    7. (Interface for RX/TX) Main RF cable8. (RXout) Frequency extension interface9. (Rxin) Frequency extension interface10. (GND) Grounding

    3 Preparations Before Onsite Operation

    3.1 Checking Onsite Commissioning Conditions

    Please refer to the following steps to see if the site is available for commissioning:

    Make sure the equipment has been installed properly on site, and items in

    installation acceptance test have been passed;

    Find out the transmission type of the BTS;

    Check whether transmission and power supply are ready for commissioning;

    You need to get the confirmation of the project manager upon the completion of the

    above three steps.

    3.2 Preparing Tools

    A laptop;

    (Both cross and flathead) screwdrivers, wrenches, multi-meter, and other

    commonly used tools;

    Two testing handsets supporting the services to be tested and related data cables;

    The SIM cards supporting the services to be tested.

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 6

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    14/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    3.3 Preparing Documents

    You can find all of the following documents on TSM website (log on to

    ecc.zte.com.cn and then click Technical Support), or ask the engineers in the localoffice for the documents.

    ZXSDR B8200&R8860 Commissioning Test Record

    ZXSDR B8200&B8860 Test Guide

    4 Commissioning

    4.1 Checking Hardware

    4.1.1 Checking Configuration and Model of BBU and RRU

    Purpose

    Check the configuration and model of the BTS to be commissioned to ensure it isconsistent with what is planned.

    Record the factory bar code of the PCB on CC board, and send it to iBSC&RNCcommissioning engineer for data synchronization.

    Procedure (BBU)

    1. Check the following items according to the Figure 4 -5:

    1. Check whether the site has been configured with boards as planned;

    2. Check whether the boards are all in correct slots;

    Figure 4-5 Board Slot Configuration

    2. The BTS commissioning engineer records the factory bar code on the PCB of CC1

    board as shown in Figure 4 -6, and sends it to the RNC&iBSC commissioning

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 7

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    15/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    engineer for data synchronization.

    Figure 4-6 Factory Bar Code of CC Board

    Procedure (RRU)

    1. Check the nameplate on the left of RRU to see whether it is consistent with what is

    planned;

    2. Check the nameplate on the left of RRU to see whether its power and frequency

    range are consistent with what is planned;

    Criteria

    Table 4-4 Checklist of BBU and RRU Product Configurations and Models

    Item Contents Result Remarks

    Check BBU andRRU productconfigurationsand models

    Whether the site has beenconfigured with boards asplanned

    Yes No

    Whether the boards are in correctslots

    Yes No

    Whether RRU product models areconsistent with what is planned

    Yes No

    Whether RRU product power andfrequency range are consistentwith what is planned

    Yes No

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 8

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    16/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    4.1.2 Checking SA Jumpers

    Purpose

    Check transmission type and networking type on site:

    Check transmission mode of Iub/Abis interface circuit (X1, X5)

    Check cabinet No. in the case of BBU cascading (X6)

    Procedure

    1. Change the settings of X1 and X5 jumpers with jumper cap. Figure 4 -7 shows the

    position of jumpers, and Table 4 -5 and Table 4 -6 show their functions. Short circuit

    means that there is a jumper cap, and Open circuit means there is not.

    1. Work modes of uplink/downlink links

    2. Matching impedance

    Table 4-5 Setting of X5 Jumper [1, 0]

    X5 jumper position [1, 0] E1/T1 mode

    [short circuit, short circuit] Reserved

    [short circuit, open circuit] T1, 100

    [open circuit, short circuit] E1, 120 (open circuit, and the SA board isclose to the jumper at the panel, as shown inFigure 4 -7

    [open circuit, open circuit] E1, 75 (default value)

    3. E1/T1, and combination of long cable (more than 1000 meters) and short

    cable (less than 1000 meters)

    Table 4-6 Setting of X5 Jumper [3, 2]

    X5 jumper position [3, 2] Mode

    [open circuit, open circuit] uplink short, downlink short

    [short circuit, short circuit] uplink long, downlink long

    [open circuit, short circuit] uplink short, downlink long

    [short circuit, open circuit] uplink long, downlink short

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 9

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    17/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    Figure 4-7 Position of the SA Jumper

    Reference

    Uplink represents the transmission from BBU to iBSC/RNC, and downlink

    represents the reverse;

    Long/short cable refers to the receiving mode of E1. Use the long cable if E1

    transmission distance is longer than 1km, and use the short if otherwise.

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 10

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    18/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    2. Change the setting of X6 jumper with the jumper cap in the case of BBU cascading.

    At most 8 sets of BBU (from 000 to 111, as shown in Table 4 -7) can be cascaded.

    The default value is 000.

    Table 4-7 Setting of X6 jumpers

    Position of X6 jumper [2,1,0] BBU cabinet No.

    [open circuit, open circuit, open circuit] 0

    [open circuit, open circuit, short circuit] 1

    [open circuit, short circuit, open circuit] 2

    [open circuit, short circuit, short circuit] 3

    [short circuit, open circuit, open circuit] 4

    [short circuit, open circuit, short circuit] 5

    [short circuit, short circuit, open circuit] 6

    [short circuit, short circuit, short circuit] 7

    4.1.3 Checking Power Supply

    Purpose

    To ensure the power supply of the BTS is normal for subsequent commissioning.

    Procedure

    1. Wear the anti-statistic wrist;

    2. Check the cable tag, and check the polarity of BBU and RRU input power;

    3. Measure input voltage of BBU and RRU with the multi-meter:

    1. Normal range of DC power supply: -40V DC to -57V DC;

    2. Normal range of AC power supply: 200V AC to 240V AC,

    Note:

    BBU only supports DC power supply, so it is necessary to use PSU module for AC-

    DC conversion in the case of AC power supply.

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 11

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    19/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    Criteria

    Table 4-8 Checklist of Input Power Supply

    Item Content and criteria Result Remarks

    Checkpowersupply

    Whether the polarities of the BBUs andRRUs power supply are correct

    Yes No

    Whether input voltage of BBU and RRU isnormal

    Yes No

    4.1.4 Checking BTS Transmission

    Purpose

    To ensure the BTS transmission is normal for commissioning.

    Procedure

    E1 cables:

    1. Identify each pair of E1 cables by cable sequence and color spectrum shown in

    Table 4 -10 and Table 4 -11;

    2. Perform self-loop for each pair of E1 cables;

    3. Contact BSC engineer to make sure if E1 /T1 transmission is normal.

    FE cables:

    1. Connect both RJ-45 connectors of the FE cable to the FE cable detector, and

    check whether the FE cable is correctly made based on indicators on the FE cable.

    If the 8 indicators flash in sequence, it shows the connection is correct.

    Criteria

    Table 4-9 BTS Transmission Checklist

    Item Contents and criteria Result Remarks

    BTStransmission

    Whether connection between E1 cableand DDF rack is correct

    Yes No

    Whether connection between FE cableand switch is correct

    Yes No

    Reference

    E1 cable description:

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 12

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    20/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    75 E1 cable:

    8 pairs of 75 E1 are often used in China. One end of it is the DB44 connector, and

    the other end is divided into 2 cables (the connectors are made on site). Each of the

    two has 8 cores (1-8), which support 4 pairs of E1. The labeled cables are the 1 st-4th

    pairs of E1, while the unlabeled ones are the other 4 pairs. The E1 labeled with 1

    and 2 are the first pair, those with 3 and 4 are the second pair, and so on. See the

    following table for the cable sequence description.

    Table 4-10 75 E1 Cable Sequence

    Signaldefinition

    RX0 RX0+ TX0 TX0+ RX1 RX1+ TX1 TX1+

    Pin at EndA

    22 23 24 25 1 2 3 4

    Cable colorspectrum

    11extern

    al

    11intern

    al

    12extern

    al

    12intern

    al

    13extern

    al

    13intern

    al

    14extern

    al

    14intern

    al

    Signaldefinition

    RX4 RX4+ TX4 TX4+ RX5 RX5+ TX5 TX5+

    Pin at EndA

    13 14 43 44 39 40 41 42

    Cable colorspectrum

    21extern

    al

    21intern

    al

    22extern

    al

    22intern

    al

    23extern

    al

    23intern

    al

    24extern

    al

    24intern

    al

    11internal, 11external represents the internal or external conductor of thecoaxial cable identified with 1.

    120 E1 cable and 100 T1 cable

    120 E1 and 100 T1 are divided into 4 pairs of E1/T1 and 8 pairs of E1/T1. One

    end of it is the DB44 connector, and each cable has 16 cores (1-16), which supports

    4 pairs of E1/T1, the labeled ones are the 1 st-4th pairs of E1, and the unlabeled ones

    are the 5th-8th E1/T1. See the following table for cable sequence.

    Table 4-11 120 E1 Cable and 120 T1 Cable Sequences

    Signaldefinition

    RX0 RX0+TX0

    TX0+ RX1 RX1+ TX1 TX1+

    Pin at End A 22 23 24 25 1 2 3 4

    Cable colorspectrum

    blue/1red

    blue/1black

    pink/1red

    pink/1black

    green/1red

    green/1black

    yellow/1red

    yellow/1black

    Signaldefinition

    RX4 RX4+TX4

    TX4+ RX5 RX5+ TX5 TX5+

    Pin at End A 13 14 43 44 39 40 41 42

    Cable color yellow yellow/ gray/ gray/2 blue/3 blue/3b pink/3 pink/3bl

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 13

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    21/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    Signaldefinition

    RX0 RX0+TX0

    TX0+ RX1 RX1+ TX1 TX1+

    spectrum /2red 2black 2red black red lack red ack

    Blue/1 red means that there is 1 red flag on the blue cable; pink /2 red means

    there are 2 red flags on the pink cable.

    4.1.5 Checking Cable Connection

    Items

    Table 4-12 Cable Connection Checklist

    Item Description Result Remarks

    Checkcableconnection of therack

    Whether the fiber between the FS boardand RRU is correct, or whether the SFPhigh speech cable connection is correct.

    Yes No

    CheckIub/Abisinterfaceconnection

    If the FE cable is used, check whether itsconnection from the switch to the CCboard is correct.

    Yes No

    If the E1 cable is used, check whether itsconnection from the DDF rack to the SAcable of BTS is correct.

    Yes No

    Checkothercables

    Whether the cables of dry contacts, theSerial Ports 232 and 485 are connectedcorrectly.

    Yes No

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 14

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    22/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    Figure 4-8 Cable Connection of BTS

    4.1.6 Checking Power-on/Power-off of BTS

    Purpose

    To ensure BBU and RRU can work normally.

    Procedure (BBU)

    1. Power-on Procedure:

    1. Plug out all of the boards of B8200 carefully, and keep the PM (power module)in the slot.

    2. After the BTS is powered on, check whether the RUN indicator of the PM

    module is ON, and the ALM indicator is OFF.

    3. Check whether the FAN module is running normally (the PWR indicator is

    ON, and the ALM indicator is OFF. If the FAN module is in normal operation,

    please insert the CC, BPC, UBPG, FS and SA one by one.

    2. Power-off Procedure:

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 15

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    23/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    1. Shut down the power supply system directly.

    Reference

    After the PM module or any board is just powered on, the ALM indicator flashes,

    which shows the board has not been started. If the SA board is not inserted, the

    ALM indicator on the FA panel will be ON. Hot plug-out/in of the power cables is

    forbidden.

    The handle bar on the left of a board has three gears, and that on the right is fixed.

    Please gear the handle bar to the outmost before plugging out the board, and gear

    the handle bar to the inmost before plugging in the board.

    To remove the fan subrack, firstly please push the lock-switch on the panel on the

    right before plugging out the fan subrack.

    Procedure (RRU)

    1. Power-on Procedure:

    1. Special power cables have been delivered together with the RRU to connect

    with -48VDC power cabinet or AC power cabinet. Please ensure the power

    cables and PGND cables are correctly connected before using the fuse.

    2. Power-off Procedure:

    1. Shut down the power supply of RRU:

    When the RRU is installed indoors, switch off the RRU air-switch of the

    AC/DC power distribution box;

    When the RRU is installed outdoors, switch off the RRU air-switch of the

    indoor/outdoor DC lightning protection box;

    Note:

    After all of the above procedure, the BTS commissioning engineer should feed back

    the BTS status to the iBSC&RNC commissioning engineer, who will then conduct

    version upgrade and data synchronization accordingly. Follow-up operations are not

    allowed until the iBSC&RNC commissioning engineer completes the job and sends

    a notice.

    Ensure that the iBSC&RNC has finished BTS version upgrade and data

    synchronization before the subsequent procedures.

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 16

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    24/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    4.1.7 Checking BTS Running Status

    Prerequisites

    1. SDR version is completely loaded.

    2. SDR data synchronization between foreground and background is completed.

    3. SDR is reset and restarted normally.

    Purpose

    1. To make sure BTS hardware work normally.

    2. To make sure the current versions in the BTS are correct.

    3. To make sure SDR data synchronization between foreground and background is

    completed.

    Procedure (BBU)

    1. After the BTS is reset and restarted, all of the boards can resume working normally

    in 5 minutes.

    2. Check the status of indicators on the boards according to Table 4 -13.

    3. Contact the BSC engineer to check the running status of the current version.

    4. Contact the BSC engineer to see whether the running status of BBU boards is

    consistent with what the indicators show. Indicator in green means normal status.

    Table 4-13 Description of B8200 Board Status in Normal Working Status

    Board RUN Indicator (Green) ALM Indicator (Red)

    FM Flashing at 1Hz OFF

    SA Flashing at 1Hz OFF

    CC Flashing at 1Hz OFF

    FS Flashing at 1Hz OFF

    UBPG Flashing at 1Hz OFF

    FA module Flashing at 1Hz OFF

    Reference

    When the BTS is restarted and reset, ALM indicators of PM and the boards may

    keep flashing for a while. It is a normal status because the boards have not been

    started.

    If the board indicators are in abnormal status, please contact the iBSC&RNC

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 17

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    25/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    commissioning engineer for help.

    Procedure (RRU)

    1. After the BTS is reset and restarted, RRU resumes working normally in 10 minutes;

    2. Contact BSC engineer to see whether the RRU boards work normally in OMC.

    Indicator in green means normal status.

    Warning:

    It is forbidden to open the front panel of RRU to see its running status.

    5 BTS Test

    5.1 Commissioning Test

    Prerequisites

    Before the test of each item, please notify BSC engineer to make sure the

    equipment works normally and the configuration related to the test is completed.

    Tools

    Two testing handsets (with frequency lock and forced handover functions);

    Two SIM cards;

    Data cables for testing handsets (to test PS service, optional)

    Test computer (to test PS service, optional)

    5.1.1 CS Service Test

    5.1.1.1 Dial Test of CS Service

    Procedure

    1. BSC engineer selects a cell for the test;

    2. Lock the frequency of testing handsets at the BCCH frequency of the tested cell.

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 18

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    26/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    Note:

    The commissioning engineers should know how to perform frequency lock.Otherwise please refer to the guide of testing handsets or consult BSC engineer.

    3. Local MS user (the calling party) initiates a call. The called party answers. The

    calling party hangs up first.

    4. Local MS user (the calling party) initiates a call. The called party answers. The

    called party hangs up first.

    5. The calling party initiates a call. Local MS user (the called party) answers. The

    calling party hangs up first.

    6. The calling party initiates a call. Local MS user (the called party) answers. The

    called party hangs up first.

    End of procedures

    Acceptance Criteria

    1. The calling party can hear ring-back tone.

    2. The called party answers successfully.

    3. Conversation is in good quality.

    4. Both the calling party and the called party can hang up normally.

    5.1.1.2 Dial Test for the Services in Channels

    Procedure

    1. Notify BSC engineer before the test.

    2. After BSC engineer completes the settings for the test, lock the frequency of thetesting handset at BCCH frequency of the tested cell.

    3. Perform dial test.

    4. Notify BSC engineer to observe the status of reserved (unblocked) TS.

    5. Repeat steps 1-4 to test the other TSs in the BTS.

    End of procedures

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 19

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    27/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    Acceptance Criteria

    All TCHs of the BTS support CS service.

    5.1.2 PS Service Test

    Procedure

    1. Set the IP address and gateway of the data server according to the parameters

    provided by the operator.

    Note:

    The commissioning engineer should know how to set the IP address and gateway of

    data server. Otherwise please consult BSC engineer.

    2. Input WAP address into the testing handset to log on to WAP website.

    Note:

    The commissioning engineers should have the skill of WAP browsing with testing

    handset. Otherwise please consult BSC engineer.

    3. Record WAP average login time and WAP login success rate.

    4. Refresh WAP webpage on testing handset. Record WAP refresh success rate.

    End of procedures

    Acceptance Criteria

    WAP login success rate is above 90%. Webpage can be logged in normally.

    5.1.3 Handover Test

    Procedure

    1. Select a cell of the BTS and lock the frequency of the testing handset at BCCH

    frequency of the cell.

    2. Establish a call.

    3. Observe the parameters of neighbor cells with testing handset to find anther cell in

    the same BTS as the target cell. The received level of the target cell should be

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 20

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    28/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    above ReLevMin, and near or higher than the level of the frequency in the

    conversation.

    4. Set handover function of the testing handset to perform forced handover.

    End of procedures

    Acceptance Criteria

    The testing handset can be handed over to the target cell while the conversation

    remains normal.

    5.2 BTS Commissioning Test Report (Completed on

    Site)

    Table 5-14 BTS Commissioning Test Report

    Item Content Result Remark

    Local MS user asthe calling party

    Number of dial times:

    Number of success times:

    Number of failure times:

    Number of poor-quality calltimes:

    Service quality:Normal Silence

    One-way audio Cross

    talk

    Echo Background noise

    Intermittent voice

    Yes

    No

    Local MS user asthe called party

    Number of dial times:

    Number of success times:

    Number of failure times:

    Number of poor-quality calltimes:

    Service quality:

    Normal Silence

    One-way audio Cross

    talk

    Echo Background noise

    Intermittent voice

    YesNo

    TS dial test

    Number of dialed TSs:

    Number of normal TSs:

    Number of abnormal TSs:

    Yes

    No

    ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 21

  • 7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide

    29/29

    ZXSDR BS8700 Step by Step Commissioning Guide

    Item Content Result Remark

    WAP test

    WAP average login time

    WAP login success rate:

    WAP refresh success rate

    Yes

    No

    Handover test

    Handover times: ______

    Success times: _______

    Failure times: ________

    Yes

    No

    6 Site Cleaning

    Clean the site upon the completion of BTS commissioning.

    1. Clean up the useless stuffs in the equipment.

    2. Check if the equipment door is closed and locked.