ZXSDR BS8700 Step by Step Commissioning Guide
-
Upload
bstoan5050 -
Category
Documents
-
view
294 -
download
13
Transcript of ZXSDR BS8700 Step by Step Commissioning Guide
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
1/29
ZXSDR BS8700 Step by StepCommissioning Guide
GSM Product Support Dept.
Wireless Network Service Center
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
2/29
ZXSDR BS8700 Step by Step Commissioning Guide
LEGAL INFORMATION
By accepting this certain document of ZTE CORPORATION you agree to the following terms. If you
do not agree to the following terms, please notice that you are not allowed to use this document.
Copyright 2013 ZTE CORPORATION. Any rights not expressly granted herein are reserved. This
document contains proprietary information of ZTE CORPORATION. Any reproduction, transfer,
distribution, use or disclosure of this document or any portion of this document, in any form by any
means, without the prior written consent of ZTE CORPORATION is prohibited.
and are registered trademarks of ZTE CORPORATION. ZTEs company name, logo
and product names referenced herein are either trademarks or registered trademarks of ZTE
CORPORATION. Other product and company names mentioned herein may be trademarks or trade
names of their respective owners. Without the prior written consent of ZTE CORPORATION or the
third party owner thereof, anyones access to this document should not be construed as granting, by
implication, estopped or otherwise, any license or right to use any marks appearing in the document.
The design of this product complies with requirements of environmental protection and personal
security. This product shall be stored, used or discarded in accordance with product manual,
relevant contract or laws and regulations in relevant country (countries).
This document is provided as is and as available. Information contained in this document is
subject to continuous update without further notice due to improvement and update of ZTECORPORATIONs products and technologies.
ZTE CORPORATION
Address: NO. 55
Hi-tech Road South
ShenZhen
P.R.China518057
Website: http://support.zte.com.cn
Email: [email protected]
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. I
http://support.zte.com.cn/mailto:[email protected]:[email protected]://support.zte.com.cn/ -
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
3/29
ZXSDR BS8700 Step by Step Commissioning Guide
Revision History
Product Version Document Version Serial Number Reason for Revision
R1.0 First published
Author
Date Document Version Prepared by Reviewed by Approved by
2010-5-7 R1.0 Bai Guowei Cai Kai
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. II
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
4/29
ZXSDR BS8700 Step by Step Commissioning Guide
About This Document
Applicable to: ZXSDR BS8700 BTS
Intended for: Supervisor, commissioning engineer
This document aims to guide the commissioning task of site engineer after the
completion of BS8700 installation and acceptance test. For detailed information of
installation procedure and installation check, please refer to the related documents.
Summary
Chapter Description
1 Overview Commissioning flow, manpower projection and skillsrequired
2 Product Introduction Introduction about BBU and RRU
3 Preparations Before OnsiteOperation
Prerequisites, tools and documents required forcommissioning
4 Commissioning Checking hardware, cables, power-on/power-off andrunning status of BTS
5 BTS Test CS service test, PS service test, handover test, filling oftest report
6 Site Cleaning Items to be cleaned on site
Error: Reference source not foundError: Reference source not found
Appendix
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. III
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
5/29
ZXSDR BS8700 Step by Step Commissioning Guide
TABLE OF CONTENTS
1 Overview 11.1 Introduction...................................................................................................................11.2 BTS Commissioning Flowchart..................................................................................... 11.3 Manpower Projection....................................................................................................11.4 Required Skills..............................................................................................................2
2 Product Introduction..................................................................................................... 22.1 BBU (B8200) ................................................................................................................22.2 BBU Boards (B8200) ....................................................................................................3
2.3 BBU External Cable Connection (B8200) .....................................................................42.4 RRU (R8860) ............................................................................................................... 5
3 Preparations Before Onsite Operation......................................................................... 63.1 Checking Onsite Commissioning Conditions ................................................................63.2 Preparing Tools............................................................................................................. 63.3 Preparing Documents................................................................................................... 7
4 Commissioning..............................................................................................................74.1 Checking Hardware....................................................................................................... 74.1.1 Checking Configuration and Model of BBU and RRU...........................................74.1.2 Checking SA Jumpers.......................................................................................... 9
4.1.3 Checking Power Supply..................................................................................... 114.1.4 Checking BTS Transmission..............................................................................124.1.5 Checking Cable Connection...............................................................................144.1.6 Checking Power-on/Power-off of BTS................................................................154.1.7 Checking BTS Running Status...........................................................................17
5 BTS Test 185.1 Commissioning Test....................................................................................................185.1.1 CS Service Test................................................................................................. 185.1.2 PS Service Test..................................................................................................205.1.3 Handover Test.................................................................................................... 205.2 BTS Commissioning Test Report (Completed on Site)...............................................21
6 Site Cleaning................................................................................................................ 22
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. IV
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
6/29
ZXSDR BS8700 Step by Step Commissioning Guide
FIGURES
Figure 1-1 BTS Commissioning Flowchart.....................................................................1
Figure 2-2 ZXSDR B8200 GU360 Configuration...............................................................2
Figure 2-3 Appearance of R8860..................................................................................... 5
Figure 2-4 RRU interfaces................................................................................................6
Figure 4-5 Board Slot Configuration...............................................................................7
Figure 4-6 Factory Bar Code of CC Board......................................................................8
Figure 4-7 Position of the SA Jumper...........................................................................10
Figure 4-8 Cable Connection of BTS............................................................................. 15
TABLES
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. V
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
7/29
ZXSDR BS8700 Step by Step Commissioning Guide
Table 1-1 Manpower Projection........................................................................................1
Table 2-2 ZXSDR B8200 Board List................................................................................. 3
Table 2-3 Description of B8200 External Cable Connection..........................................4
Table 4-4 Checklist of BBU and RRU Product Configurations and Models.................8
Table 4-5 Setting of X5 Jumper [1, 0] ..............................................................................9
Table 4-6 Setting of X5 Jumper [3, 2]..............................................................................9
Table 4-7 Setting of X6 jumpers..................................................................................... 11
Table 4-8 Checklist of Input Power Supply................................................................... 12
Table 4-9 BTS Transmission Checklist.........................................................................12
Table 4-10 75 E1 Cable Sequence ...............................................................................13
Table 4-11 120 E1 Cable and 120 T1 Cable Sequences..........................................13
Table 4-12 Cable Connection Checklist........................................................................14
Table 4-13 Description of B8200 Board Status in Normal Working Status................17
Table 5-14 BTS Commissioning Test Report................................................................21
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. VI
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
8/29
ZXSDR BS8700 Step by Step Commissioning Guide
1 Overview
1.1 Introduction
This guide focuses on the commissioning of ZXSDR BS8700, including SDR
commissioning flow and procedure.
Please conduct commissioning according to this guide after equipment installation
and check. For equipment installation information, please refer to the following
documents.
ZXSDR BS8700 (V4.00.30) Hardware Installation Guide (BBU)
ZXSDR BS8700 (V4.00.30) Hardware Installation Guide (RRU)
ZXSDR BS8700 (V4.00.30) Hardware Description
1.2 BTS Commissioning Flowchart
Figure 1-1 BTS Commissioning Flowchart
1.3 Manpower Projection
Table 1-1 Manpower Projection
Position Responsibilities
BTScommissioning engineer
Prepare and check BTS commissioning, and assist theiBSC&RNC commissioning engineer in finishing BTScommissioning.
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 1
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
9/29
ZXSDR BS8700 Step by Step Commissioning Guide
Position Responsibilities
Supervisor Be responsible for the whole process of commissioning
iBSC&RNC
commissioning engineer
Perform data synchronization between BTS and OMCR, andtrace BTS related signaling in the course of BTS commissioning.
1.4 Required Skills
The person responsible for BS8700 commissioning should know about the following
knowledge:
ZXSDR BS8700 products (boards, cables and system infrastructure), as well as
installation and checking modes.
Types, sequences and connection methods of SDR transmission cables.
Basic (speech and data) commissioning skills of SDR.
2 Product Introduction
ZXSDR BS8700 is of distributed structure, which includes baseband unit (BBU) and
remote radio unit (RRU).
2.1 BBU (B8200)
ZXSDR B8200 GU360 is also named indoor GSM/UMTS dual-mode baseband pool.
Figure 2-2 ZXSDR B8200 GU360 Configuration
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 2
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
10/29
ZXSDR BS8700 Step by Step Commissioning Guide
2.2 BBU Boards (B8200)
Table 2-2 ZXSDR B8200 Board List
Abbreviation Full name Description
PM0 Power ModuleIt provides power to the other boards.One module is configured by default;1+1 backup configuration is optional.
SA Site Alarm Module
This board integrates the functions ofenvironment monitoring and E1interface, providing 6 incoming and 2outgoing lines of dry contact monitoringand 8 lines of E1/T1 interfaces. Besides,it provides one line of RS232 and one
line of RS485.
CC0/CC1Control and ClockModule
Its functions include switching of mediastream and control stream, processingclocks and managing subracks.
The panel provides GE interface(optional for optical and electrical) fortransmission over Iub, and it alsoprovides antenna interface. Only onemodule is configured by default. 1+1backup configuration is optional. TheREF interface supports import of BITSsignal source.
FSFabric SwitchModule
This board focuses on IQ signalswitching. Each supports 6 fiberinterfaces to connect with the RRUmodule. Two FSs at the maximum inloading sharing mode can be configured.
BPCBasebandProcessing BoardType C
Baseband board for WCDMA
UBPGGSM BasebandProcessor
UBPG is the baseband board of GSM.One UBPG supports 12 TRXs.
FA FAN ModuleIt is on the right side of the subrack,,which is used for heat dissipation.
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 3
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
11/29
ZXSDR BS8700 Step by Step Commissioning Guide
2.3 BBU External Cable Connection (B8200)
Table 2-3 Description of B8200 External Cable Connection
B8200 External Cable Connection
NoCablename
Media/type
UsageLocal end
connected toPeer end
connected to
1GPSantennacable
It receives GPSsignals
REF port onthe CC boardof B8200
GPS lightningarrester
2B8200powercable
Blueandblackpower
cables
B8200 powercable
Powerinterface onthe PM board
of B8200
-48V DC powersupply
3SA panelcable
It connects E1DB44connector
E1 cable studout of the DDF
It connectsRS232/RS485serial port cable
DB9connector
Externalcommissioningdevice
It connectsexternal alarmcable
DB25connector
Parts to bemonitored
4Iub/Abisinterface
2M
coaxialcable
Iub/Abis interface
E1 interfaceon the SAboard ofB8200
iBSC/RNC
5
Iub/Abisinterfaceand GEelectricalportcables
RJ45suppercategory 5/6twisted-pair
It connects theEthernetinterfacebetween BBUand iBSC/RNC.This interfaceprovides opticalinterface andelectricalinterface of theEthernet on thepanel(10M/100M/1000M self-adaptive)
ETH0interface onthe CC boardof B8200(electricalport)
The IP networkof iBSC/RNC
6
Iub/Abisinterfaceopticalport
Fiber
It connectsoptical portbetween BBUand iBSC/RNC
Optical porton the CCboard ofB8200
The IP networkconnecting toRNC/Abis (notin use becauseof technicallimitations)
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 4
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
12/29
ZXSDR BS8700 Step by Step Commissioning Guide
B8200 External Cable Connection
NoCablename
Media/type
UsageLocal end
connected toPeer end
connected to
7CPRIinterfacecable
Single-modefiber
It connects BBUand RRU totransmit IQsignals
Optical porton the FSboard ofB8200
CPRI interfaceon the RRU
8
RRUcommissioningcable
RMBinterface cableandinterface board
It connects RRUforcommissioning
Monitorinterface onthe RRU
RMB board
9
RRU
antenna
7/8''
feeder Feeder
Antenna
interface onthe RRU Cell antenna
10
EXT externaltelecommunication interface,connectingexternal receiver;
EXT interfaceon the CCboard ofB8200
2.4 RRU (R8860)
R8860 is an outdoor macro remote radio unit (RRU).
Figure 2-3 Appearance of R8860
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 5
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
13/29
ZXSDR BS8700 Step by Step Commissioning Guide
Figure 2-4 RRU interfaces
1. (LC1) Interface between BBU and RRU/RRU cascading interface2. (LC2) Interface between BBU and RRU/RRU cascading interface3. (AISG) AISG equipment interface4. (Mon) Interfaces for external devices (such as monitoring, LMT, etc.)5. (DCIN) Power interface6. Interface for Rx diversity RF cable
7. (Interface for RX/TX) Main RF cable8. (RXout) Frequency extension interface9. (Rxin) Frequency extension interface10. (GND) Grounding
3 Preparations Before Onsite Operation
3.1 Checking Onsite Commissioning Conditions
Please refer to the following steps to see if the site is available for commissioning:
Make sure the equipment has been installed properly on site, and items in
installation acceptance test have been passed;
Find out the transmission type of the BTS;
Check whether transmission and power supply are ready for commissioning;
You need to get the confirmation of the project manager upon the completion of the
above three steps.
3.2 Preparing Tools
A laptop;
(Both cross and flathead) screwdrivers, wrenches, multi-meter, and other
commonly used tools;
Two testing handsets supporting the services to be tested and related data cables;
The SIM cards supporting the services to be tested.
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 6
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
14/29
ZXSDR BS8700 Step by Step Commissioning Guide
3.3 Preparing Documents
You can find all of the following documents on TSM website (log on to
ecc.zte.com.cn and then click Technical Support), or ask the engineers in the localoffice for the documents.
ZXSDR B8200&R8860 Commissioning Test Record
ZXSDR B8200&B8860 Test Guide
4 Commissioning
4.1 Checking Hardware
4.1.1 Checking Configuration and Model of BBU and RRU
Purpose
Check the configuration and model of the BTS to be commissioned to ensure it isconsistent with what is planned.
Record the factory bar code of the PCB on CC board, and send it to iBSC&RNCcommissioning engineer for data synchronization.
Procedure (BBU)
1. Check the following items according to the Figure 4 -5:
1. Check whether the site has been configured with boards as planned;
2. Check whether the boards are all in correct slots;
Figure 4-5 Board Slot Configuration
2. The BTS commissioning engineer records the factory bar code on the PCB of CC1
board as shown in Figure 4 -6, and sends it to the RNC&iBSC commissioning
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 7
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
15/29
ZXSDR BS8700 Step by Step Commissioning Guide
engineer for data synchronization.
Figure 4-6 Factory Bar Code of CC Board
Procedure (RRU)
1. Check the nameplate on the left of RRU to see whether it is consistent with what is
planned;
2. Check the nameplate on the left of RRU to see whether its power and frequency
range are consistent with what is planned;
Criteria
Table 4-4 Checklist of BBU and RRU Product Configurations and Models
Item Contents Result Remarks
Check BBU andRRU productconfigurationsand models
Whether the site has beenconfigured with boards asplanned
Yes No
Whether the boards are in correctslots
Yes No
Whether RRU product models areconsistent with what is planned
Yes No
Whether RRU product power andfrequency range are consistentwith what is planned
Yes No
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 8
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
16/29
ZXSDR BS8700 Step by Step Commissioning Guide
4.1.2 Checking SA Jumpers
Purpose
Check transmission type and networking type on site:
Check transmission mode of Iub/Abis interface circuit (X1, X5)
Check cabinet No. in the case of BBU cascading (X6)
Procedure
1. Change the settings of X1 and X5 jumpers with jumper cap. Figure 4 -7 shows the
position of jumpers, and Table 4 -5 and Table 4 -6 show their functions. Short circuit
means that there is a jumper cap, and Open circuit means there is not.
1. Work modes of uplink/downlink links
2. Matching impedance
Table 4-5 Setting of X5 Jumper [1, 0]
X5 jumper position [1, 0] E1/T1 mode
[short circuit, short circuit] Reserved
[short circuit, open circuit] T1, 100
[open circuit, short circuit] E1, 120 (open circuit, and the SA board isclose to the jumper at the panel, as shown inFigure 4 -7
[open circuit, open circuit] E1, 75 (default value)
3. E1/T1, and combination of long cable (more than 1000 meters) and short
cable (less than 1000 meters)
Table 4-6 Setting of X5 Jumper [3, 2]
X5 jumper position [3, 2] Mode
[open circuit, open circuit] uplink short, downlink short
[short circuit, short circuit] uplink long, downlink long
[open circuit, short circuit] uplink short, downlink long
[short circuit, open circuit] uplink long, downlink short
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 9
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
17/29
ZXSDR BS8700 Step by Step Commissioning Guide
Figure 4-7 Position of the SA Jumper
Reference
Uplink represents the transmission from BBU to iBSC/RNC, and downlink
represents the reverse;
Long/short cable refers to the receiving mode of E1. Use the long cable if E1
transmission distance is longer than 1km, and use the short if otherwise.
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 10
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
18/29
ZXSDR BS8700 Step by Step Commissioning Guide
2. Change the setting of X6 jumper with the jumper cap in the case of BBU cascading.
At most 8 sets of BBU (from 000 to 111, as shown in Table 4 -7) can be cascaded.
The default value is 000.
Table 4-7 Setting of X6 jumpers
Position of X6 jumper [2,1,0] BBU cabinet No.
[open circuit, open circuit, open circuit] 0
[open circuit, open circuit, short circuit] 1
[open circuit, short circuit, open circuit] 2
[open circuit, short circuit, short circuit] 3
[short circuit, open circuit, open circuit] 4
[short circuit, open circuit, short circuit] 5
[short circuit, short circuit, open circuit] 6
[short circuit, short circuit, short circuit] 7
4.1.3 Checking Power Supply
Purpose
To ensure the power supply of the BTS is normal for subsequent commissioning.
Procedure
1. Wear the anti-statistic wrist;
2. Check the cable tag, and check the polarity of BBU and RRU input power;
3. Measure input voltage of BBU and RRU with the multi-meter:
1. Normal range of DC power supply: -40V DC to -57V DC;
2. Normal range of AC power supply: 200V AC to 240V AC,
Note:
BBU only supports DC power supply, so it is necessary to use PSU module for AC-
DC conversion in the case of AC power supply.
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 11
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
19/29
ZXSDR BS8700 Step by Step Commissioning Guide
Criteria
Table 4-8 Checklist of Input Power Supply
Item Content and criteria Result Remarks
Checkpowersupply
Whether the polarities of the BBUs andRRUs power supply are correct
Yes No
Whether input voltage of BBU and RRU isnormal
Yes No
4.1.4 Checking BTS Transmission
Purpose
To ensure the BTS transmission is normal for commissioning.
Procedure
E1 cables:
1. Identify each pair of E1 cables by cable sequence and color spectrum shown in
Table 4 -10 and Table 4 -11;
2. Perform self-loop for each pair of E1 cables;
3. Contact BSC engineer to make sure if E1 /T1 transmission is normal.
FE cables:
1. Connect both RJ-45 connectors of the FE cable to the FE cable detector, and
check whether the FE cable is correctly made based on indicators on the FE cable.
If the 8 indicators flash in sequence, it shows the connection is correct.
Criteria
Table 4-9 BTS Transmission Checklist
Item Contents and criteria Result Remarks
BTStransmission
Whether connection between E1 cableand DDF rack is correct
Yes No
Whether connection between FE cableand switch is correct
Yes No
Reference
E1 cable description:
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 12
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
20/29
ZXSDR BS8700 Step by Step Commissioning Guide
75 E1 cable:
8 pairs of 75 E1 are often used in China. One end of it is the DB44 connector, and
the other end is divided into 2 cables (the connectors are made on site). Each of the
two has 8 cores (1-8), which support 4 pairs of E1. The labeled cables are the 1 st-4th
pairs of E1, while the unlabeled ones are the other 4 pairs. The E1 labeled with 1
and 2 are the first pair, those with 3 and 4 are the second pair, and so on. See the
following table for the cable sequence description.
Table 4-10 75 E1 Cable Sequence
Signaldefinition
RX0 RX0+ TX0 TX0+ RX1 RX1+ TX1 TX1+
Pin at EndA
22 23 24 25 1 2 3 4
Cable colorspectrum
11extern
al
11intern
al
12extern
al
12intern
al
13extern
al
13intern
al
14extern
al
14intern
al
Signaldefinition
RX4 RX4+ TX4 TX4+ RX5 RX5+ TX5 TX5+
Pin at EndA
13 14 43 44 39 40 41 42
Cable colorspectrum
21extern
al
21intern
al
22extern
al
22intern
al
23extern
al
23intern
al
24extern
al
24intern
al
11internal, 11external represents the internal or external conductor of thecoaxial cable identified with 1.
120 E1 cable and 100 T1 cable
120 E1 and 100 T1 are divided into 4 pairs of E1/T1 and 8 pairs of E1/T1. One
end of it is the DB44 connector, and each cable has 16 cores (1-16), which supports
4 pairs of E1/T1, the labeled ones are the 1 st-4th pairs of E1, and the unlabeled ones
are the 5th-8th E1/T1. See the following table for cable sequence.
Table 4-11 120 E1 Cable and 120 T1 Cable Sequences
Signaldefinition
RX0 RX0+TX0
TX0+ RX1 RX1+ TX1 TX1+
Pin at End A 22 23 24 25 1 2 3 4
Cable colorspectrum
blue/1red
blue/1black
pink/1red
pink/1black
green/1red
green/1black
yellow/1red
yellow/1black
Signaldefinition
RX4 RX4+TX4
TX4+ RX5 RX5+ TX5 TX5+
Pin at End A 13 14 43 44 39 40 41 42
Cable color yellow yellow/ gray/ gray/2 blue/3 blue/3b pink/3 pink/3bl
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 13
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
21/29
ZXSDR BS8700 Step by Step Commissioning Guide
Signaldefinition
RX0 RX0+TX0
TX0+ RX1 RX1+ TX1 TX1+
spectrum /2red 2black 2red black red lack red ack
Blue/1 red means that there is 1 red flag on the blue cable; pink /2 red means
there are 2 red flags on the pink cable.
4.1.5 Checking Cable Connection
Items
Table 4-12 Cable Connection Checklist
Item Description Result Remarks
Checkcableconnection of therack
Whether the fiber between the FS boardand RRU is correct, or whether the SFPhigh speech cable connection is correct.
Yes No
CheckIub/Abisinterfaceconnection
If the FE cable is used, check whether itsconnection from the switch to the CCboard is correct.
Yes No
If the E1 cable is used, check whether itsconnection from the DDF rack to the SAcable of BTS is correct.
Yes No
Checkothercables
Whether the cables of dry contacts, theSerial Ports 232 and 485 are connectedcorrectly.
Yes No
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 14
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
22/29
ZXSDR BS8700 Step by Step Commissioning Guide
Figure 4-8 Cable Connection of BTS
4.1.6 Checking Power-on/Power-off of BTS
Purpose
To ensure BBU and RRU can work normally.
Procedure (BBU)
1. Power-on Procedure:
1. Plug out all of the boards of B8200 carefully, and keep the PM (power module)in the slot.
2. After the BTS is powered on, check whether the RUN indicator of the PM
module is ON, and the ALM indicator is OFF.
3. Check whether the FAN module is running normally (the PWR indicator is
ON, and the ALM indicator is OFF. If the FAN module is in normal operation,
please insert the CC, BPC, UBPG, FS and SA one by one.
2. Power-off Procedure:
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 15
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
23/29
ZXSDR BS8700 Step by Step Commissioning Guide
1. Shut down the power supply system directly.
Reference
After the PM module or any board is just powered on, the ALM indicator flashes,
which shows the board has not been started. If the SA board is not inserted, the
ALM indicator on the FA panel will be ON. Hot plug-out/in of the power cables is
forbidden.
The handle bar on the left of a board has three gears, and that on the right is fixed.
Please gear the handle bar to the outmost before plugging out the board, and gear
the handle bar to the inmost before plugging in the board.
To remove the fan subrack, firstly please push the lock-switch on the panel on the
right before plugging out the fan subrack.
Procedure (RRU)
1. Power-on Procedure:
1. Special power cables have been delivered together with the RRU to connect
with -48VDC power cabinet or AC power cabinet. Please ensure the power
cables and PGND cables are correctly connected before using the fuse.
2. Power-off Procedure:
1. Shut down the power supply of RRU:
When the RRU is installed indoors, switch off the RRU air-switch of the
AC/DC power distribution box;
When the RRU is installed outdoors, switch off the RRU air-switch of the
indoor/outdoor DC lightning protection box;
Note:
After all of the above procedure, the BTS commissioning engineer should feed back
the BTS status to the iBSC&RNC commissioning engineer, who will then conduct
version upgrade and data synchronization accordingly. Follow-up operations are not
allowed until the iBSC&RNC commissioning engineer completes the job and sends
a notice.
Ensure that the iBSC&RNC has finished BTS version upgrade and data
synchronization before the subsequent procedures.
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 16
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
24/29
ZXSDR BS8700 Step by Step Commissioning Guide
4.1.7 Checking BTS Running Status
Prerequisites
1. SDR version is completely loaded.
2. SDR data synchronization between foreground and background is completed.
3. SDR is reset and restarted normally.
Purpose
1. To make sure BTS hardware work normally.
2. To make sure the current versions in the BTS are correct.
3. To make sure SDR data synchronization between foreground and background is
completed.
Procedure (BBU)
1. After the BTS is reset and restarted, all of the boards can resume working normally
in 5 minutes.
2. Check the status of indicators on the boards according to Table 4 -13.
3. Contact the BSC engineer to check the running status of the current version.
4. Contact the BSC engineer to see whether the running status of BBU boards is
consistent with what the indicators show. Indicator in green means normal status.
Table 4-13 Description of B8200 Board Status in Normal Working Status
Board RUN Indicator (Green) ALM Indicator (Red)
FM Flashing at 1Hz OFF
SA Flashing at 1Hz OFF
CC Flashing at 1Hz OFF
FS Flashing at 1Hz OFF
UBPG Flashing at 1Hz OFF
FA module Flashing at 1Hz OFF
Reference
When the BTS is restarted and reset, ALM indicators of PM and the boards may
keep flashing for a while. It is a normal status because the boards have not been
started.
If the board indicators are in abnormal status, please contact the iBSC&RNC
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 17
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
25/29
ZXSDR BS8700 Step by Step Commissioning Guide
commissioning engineer for help.
Procedure (RRU)
1. After the BTS is reset and restarted, RRU resumes working normally in 10 minutes;
2. Contact BSC engineer to see whether the RRU boards work normally in OMC.
Indicator in green means normal status.
Warning:
It is forbidden to open the front panel of RRU to see its running status.
5 BTS Test
5.1 Commissioning Test
Prerequisites
Before the test of each item, please notify BSC engineer to make sure the
equipment works normally and the configuration related to the test is completed.
Tools
Two testing handsets (with frequency lock and forced handover functions);
Two SIM cards;
Data cables for testing handsets (to test PS service, optional)
Test computer (to test PS service, optional)
5.1.1 CS Service Test
5.1.1.1 Dial Test of CS Service
Procedure
1. BSC engineer selects a cell for the test;
2. Lock the frequency of testing handsets at the BCCH frequency of the tested cell.
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 18
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
26/29
ZXSDR BS8700 Step by Step Commissioning Guide
Note:
The commissioning engineers should know how to perform frequency lock.Otherwise please refer to the guide of testing handsets or consult BSC engineer.
3. Local MS user (the calling party) initiates a call. The called party answers. The
calling party hangs up first.
4. Local MS user (the calling party) initiates a call. The called party answers. The
called party hangs up first.
5. The calling party initiates a call. Local MS user (the called party) answers. The
calling party hangs up first.
6. The calling party initiates a call. Local MS user (the called party) answers. The
called party hangs up first.
End of procedures
Acceptance Criteria
1. The calling party can hear ring-back tone.
2. The called party answers successfully.
3. Conversation is in good quality.
4. Both the calling party and the called party can hang up normally.
5.1.1.2 Dial Test for the Services in Channels
Procedure
1. Notify BSC engineer before the test.
2. After BSC engineer completes the settings for the test, lock the frequency of thetesting handset at BCCH frequency of the tested cell.
3. Perform dial test.
4. Notify BSC engineer to observe the status of reserved (unblocked) TS.
5. Repeat steps 1-4 to test the other TSs in the BTS.
End of procedures
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 19
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
27/29
ZXSDR BS8700 Step by Step Commissioning Guide
Acceptance Criteria
All TCHs of the BTS support CS service.
5.1.2 PS Service Test
Procedure
1. Set the IP address and gateway of the data server according to the parameters
provided by the operator.
Note:
The commissioning engineer should know how to set the IP address and gateway of
data server. Otherwise please consult BSC engineer.
2. Input WAP address into the testing handset to log on to WAP website.
Note:
The commissioning engineers should have the skill of WAP browsing with testing
handset. Otherwise please consult BSC engineer.
3. Record WAP average login time and WAP login success rate.
4. Refresh WAP webpage on testing handset. Record WAP refresh success rate.
End of procedures
Acceptance Criteria
WAP login success rate is above 90%. Webpage can be logged in normally.
5.1.3 Handover Test
Procedure
1. Select a cell of the BTS and lock the frequency of the testing handset at BCCH
frequency of the cell.
2. Establish a call.
3. Observe the parameters of neighbor cells with testing handset to find anther cell in
the same BTS as the target cell. The received level of the target cell should be
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 20
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
28/29
ZXSDR BS8700 Step by Step Commissioning Guide
above ReLevMin, and near or higher than the level of the frequency in the
conversation.
4. Set handover function of the testing handset to perform forced handover.
End of procedures
Acceptance Criteria
The testing handset can be handed over to the target cell while the conversation
remains normal.
5.2 BTS Commissioning Test Report (Completed on
Site)
Table 5-14 BTS Commissioning Test Report
Item Content Result Remark
Local MS user asthe calling party
Number of dial times:
Number of success times:
Number of failure times:
Number of poor-quality calltimes:
Service quality:Normal Silence
One-way audio Cross
talk
Echo Background noise
Intermittent voice
Yes
No
Local MS user asthe called party
Number of dial times:
Number of success times:
Number of failure times:
Number of poor-quality calltimes:
Service quality:
Normal Silence
One-way audio Cross
talk
Echo Background noise
Intermittent voice
YesNo
TS dial test
Number of dialed TSs:
Number of normal TSs:
Number of abnormal TSs:
Yes
No
ZTE Confidential Proprietary 2013 ZTE CORPORATION. All rights reserved. 21
-
7/22/2019 ZXSDR BS8700 Step by Step Commissioning Guide
29/29
ZXSDR BS8700 Step by Step Commissioning Guide
Item Content Result Remark
WAP test
WAP average login time
WAP login success rate:
WAP refresh success rate
Yes
No
Handover test
Handover times: ______
Success times: _______
Failure times: ________
Yes
No
6 Site Cleaning
Clean the site upon the completion of BTS commissioning.
1. Clean up the useless stuffs in the equipment.
2. Check if the equipment door is closed and locked.