Zaid AlAnber_Finalproject

download Zaid AlAnber_Finalproject

of 44

Transcript of Zaid AlAnber_Finalproject

  • 8/14/2019 Zaid AlAnber_Finalproject

    1/44

    Final Project Report

    Project Title

    (in arabic and english)

    SOLVENT ROCOVERY AND WASTEWATER TREATMENTSTUDY IN KILANI PAINT MANUFACTURING INDUSTRY

    ParticipantName

    (in arabic and english)

    Zaid Ahmed Al-Anber

    Company Name(in arabic and english)

    Kilani Paints Industrial Commercial est.

    Sponsor

    Dec. 1 2009

    Faculty

    For

    Factory

  • 8/14/2019 Zaid AlAnber_Finalproject

    2/44

    Table of Contents

    SUMMARY (in Arabic and English). .1

    1.0 Section 1.....................................................................................................3

    INTRODUCTION

    2.0 Section 2 .....................................................................................................8

    PROBLEM STATEMENT AND OBJECTIVES

    3.0 Section 3 11

    POLLUTION PREVENTION POTENTIAL

    4.0 Section 4........................................................................ ..13

    DESCRIPTION OF THE PROCESSES OF WASHED SOLVENT

    5.0 Section 5....................................................................................................23

    DESCRIPTION OF THE PROCESSES OF WASTWATER

    6.0 Section 6....................................................................................................30

    ECONOMIC EVALUATION

    7.0 Section 7....................................................................................................33

    CONCLUSION

    8.0 Section 8....................................................................................................34

    SUSTAINABILITY STUDY FOR SOLVENT RECOVERY

    9.0 Section 9....................................................................................................37APPENDICES

    Appendices 1: Physical properties of solvents

    Appendices 2: AttachmentsA. Approvals and Acceptance letter of the project output

    B. Poster < in the FFF format>

    C. Faculty and Factory surveysD. Approval of the 20% payment

  • 8/14/2019 Zaid AlAnber_Finalproject

    3/44

    KILANIS PRODUCTS

  • 8/14/2019 Zaid AlAnber_Finalproject

    4/44

    SUMMARY

    At the beginning of the study, I was concentrated on crucial problem which

    is the recovering and reusing of solvent (such as Toluene) in the Kilani

    factory. But during my visiting to the Kilani Factory, I found another

    problem which is the wastewater. Therefore, I included the treatment of

    paint industrial wastewater in this study as well.

    Actually the solvents and paint wastewater were discarded into the public

    sewerage network. These cause environmental and economic problems.Therefore, reducing and recovering the quantity of solvents waste and

    treatment of paint wastewater are beneficial for the owner of the plant as

    well as for the environment.

    Our objectives were handled these problems by minimizing and recovering

    the solvents wastes and treatment of paint wastewater.

    The purpose of the solvent recovery process is to separate the solvent

    from paints and impurities to produce a solvent can be reused for the

    original application and different purposes in Kilani factory. Our process was

    involved a physical treatment which is sedimentation followed by

    distillation of solvent.

    Based on our experimental results the installation of a distillation unit can provide at least

    90% solvent recovery from waste of solvent. We can an approximate, save of $20,000 per

    year.

    The purpose of paint wastewater treatment is to separate the water from paints and impurities

    to produce water can be reused in different industrial purposes in Kilani factory. Our process

    was only involved a physical treatments which are sedimentation and then coagulation

  • 8/14/2019 Zaid AlAnber_Finalproject

    5/44

    process. About 85% of water was recovered by coagulation process. We can an approximate,

    save of $4000 per year.

    ) ( . ,

    ( )

    .

    ..

    .

    .

    .

    .

    . 90. %

    $ 20000 .

    .

    .

    85$ %4000

  • 8/14/2019 Zaid AlAnber_Finalproject

    6/44

    SECTION 1

    INTRODUCTION

    COMPANY BACKGROUND

    Kilani paints Company is owned by official Jordanian organizations. It is located in

    Mafraq with 45000 m2 land. 200 employees in over 10 locations around in the Middle East

    are joining the Kilani Paints. The production of paints began effectively in 1974 in Jordan.

    The Kilani vision is to operate successfully in all the Middle East markets through:

    Customers are our partners of success.

    Change is an opportunity.

    Continuous improving of our employees, knowledge and processing capabilities.

    Competence through innovative products and operational excellence.

    Finally commitment to sustainable development.

    Kilani History as follow:

    1974 paint Co. establish to distribute paints in Jordan.

    1978 contribution in a local paints factory

    1980 established a distribution in Irbid.

    1984 established a distribution in Zarka.

    1994 kilani paint lunched powder coating to be the first powder coating plant in

    Jordan and the third in the Middle East, under the license of Croda Paints England.

    1996 Kilani Paints launched auto and industrial paints.

    1997 established in Palestine

    1998 established in Sudan.

    2002 kilani paint opened a regional office in Iraq.

  • 8/14/2019 Zaid AlAnber_Finalproject

    7/44

    2006 Kilani paints opened a showroom in Zarka, Irbid and Amman to launch the

    special effects paints

    In general, Kilani paints produce the following:

    Water based paints

    Decorative paints

    Oil based paints

    Insulation and production paints

    Auto paints

    Synthetic paints

    Auxiliary paints

    Powder coating paint

    Nitrocellulose paints

    Special effect powder.

    Champion Glue, white spirit, Adhesive, Sperto, and others

    KILANIS PAINT PROCESS

    Paints are manufactured in batch blending tanks according to specific recipes. The Paint

    Factory Production facility inKilanican be separated into two distinct areas:

    Water Based

    Solvent Based such as Toluene, Xylene, Methyl ethyl ketone, Methyl isobutyl ketone,

    Acetone, and Methylene chloride. The physical properties of some of these solvent are

    presented in the Appendix A.

    1. Water Based

  • 8/14/2019 Zaid AlAnber_Finalproject

    8/44

    The water based acrylic area has two blending tanks where specific acrylic paint recipes are

    produced. The general ingredients for these types of paints are water, pigment, resin, additives

    and biocides (anti fungal/bacterial agents). The pigment is added to the blending tank in a

    powder form. To prevent pigment dust emanating throughout the factory, vacuum extraction

    units are used. Any residual pigment dispersing out of the blending tank is drawn up into the

    extraction unit, which then passes through a number of filters. The filtered residual powder is

    collected as solid waste.

    After a batch of paint was produced the blending tank and all associated tools used with

    that batch (eg. agitator) need to be cleaned. Before the cleaner production initiatives the

    blending tanks were cleaned by a low-pressure water rinse technique. All wastewater was

    then stored in underground sludge-holding tank. This is the first problem is facing the

    Kilanis Paints.

    2. Solvent Based

    Solvent-based paints contain essentially the same core ingredients as acrylic paints besides

    the distinction in base. Solvent-based paints are not susceptible to fungi and bacteria therefore

    no biocide is required.

    In general, solvent-based paint is produced by mixing chemicals (primarily resins, dry

    pigment, and pigment extenders) in a container equipped with a high-speed mixer. Solvents

    and drying oils also are added during this step. After mixing, the batch may be transferred to a

    millfor additional grinding and mixing. Next, the paint base or concentrate is transferred to a

    tank where the tints, thinner (usually a volatile naphtha or blend of solvents), and the balance

    of the resin are added and mixed. Upon reaching the proper consistency, the paint is filtered to

    remove any non-dispersed pigment and transferred to a loading hopper. From the hopper, the

    paint is poured into cans, labelled, packed, and stored in the appropriate location. Figure 1

    illustrates the specific production processes for paint production in the plant.

  • 8/14/2019 Zaid AlAnber_Finalproject

    9/44

    The blending tank cleaning process is done with a solvent. This is the second problem is

    facing the Kilanis Paints.

    Solvent required cleaning the mixing and dispensing equipments and tanks between batches is

    the major source of solvent waste in the manufacture of solvent-borne paint. Information from

    company records and from interviews with key staff was gathered to determine the volume of

    wash solvent (mineral spirits) diverted from the waste stream by implementation of the reuse

    program at Kilani

    The volume of wash solvent diverted from the waste stream could vary from year to year,

    depending on the product mix and the annual production. This low-tech system has, however,

    produced an appreciable reduction in solvent waste at Kilani. Production figures and

    background information collected during site visits to Kilani indicate that Kilani diverted

    about 12000 gal of solvents per year.

  • 8/14/2019 Zaid AlAnber_Finalproject

    10/44

    Fig. 1. General flow scheme of paint production.

  • 8/14/2019 Zaid AlAnber_Finalproject

    11/44

  • 8/14/2019 Zaid AlAnber_Finalproject

    12/44

    OUR OBJECTIVES

    Depends on the above, our objectives are:

    1) Evalute the pollution prevention. Evalute the amount of solvent and water diverted

    from the wastestream.

    2) Constuct and built up a unit which has a cabability to recover the solvent from

    washed-solvent in order to produce a solvent that can be reused for the original

    application or a lower grade solvent which can be used for different purposes.

    3) Constuct and built up a unit to treat the wastewater in the factory.

    4) Evalute the economics. Evalute the costs and cost saving of this pollution preventing

    project.

    5) And finally evaluet the product quality. Evalute the quality of the paint formulated

    with wash solvent to ensure product quality.

    To do so, the project will be carried out with the following strategic objectives:

    Random choice of cleaning solvent will be replaced by an evaluation process, leading

    to a choice of one single solvent for all tank and equipment cleaning;

    Manufacturing procedures will be modified to minimize the use of wash solvent and

    wastewater.

    Create a solvent recovery model to recover weekly batches of such solvent for using

    and recycling in the paints applications.

    Create a wastewater treatment model.

    Evaluate the economic viability

    Reduce environmentally harmful

  • 8/14/2019 Zaid AlAnber_Finalproject

    13/44

  • 8/14/2019 Zaid AlAnber_Finalproject

    14/44

  • 8/14/2019 Zaid AlAnber_Finalproject

    15/44

    Kilani paint informs me that they used about 25-30 gal of solvent to clean equipment between

    batches of production. As I found in the factory, 0% of the wash solvent is reused or

    recovered in paint processes. They disposed all the wash solvent.

    I also found that the annual solvent waste as shown in the following table. This information

    based on 2008.

    Kilani production dataNumber of batches

    ( estimated)/year

    400 batches

    Quantity of solvent used to clean

    tanks

    30 gal.

    Solvent required for cleanup only 12000 gal.Solvent reuse/recover Zero gal.Waste reduction Zero

    The volume diverted from the waste stream could vary from year to year depending on the

    product mix and the annual production. It should be noted that the waste reduction is zero in

    Kilani Paint factory.

    This wash solvent is labelled and stored in 1 m3 tank for addition back into the same or very

    similar paint production with three months.

    As first step, we advised the employees at Kilani paint make a conscious effort to minimize

    the amount of solvent required for cleaning by techniques such as:

    Scraping the mix tanks to remove many paint solids before solvent cleaning.

    Minimize cleanup of work areas and equipment by taking care when adding

    raw materials and dispending finished batches.

    WASTE VOLUME REDUCTION FOR WASTWATER

    Our main aims were, to investigate wastewater characteristics, to examine possible treatment

    methods, to suggest ways to reduce wastewater production and select the most appropriate

    waste minimization options to advice to the Kilani paint factory.

  • 8/14/2019 Zaid AlAnber_Finalproject

    16/44

    A Waste Minimization Opportunity Assessment is a systematic procedure for identifying

    ways to reduce or eliminate waste water. The assessment consists of a careful review of a

    Kilani paint factorys operations and wastewater streams and the selection of specific areas to

    assess. After a particular wastewater stream or area is established, a number of options with

    the potential to minimize waste are developed.

    The main sources of wastewater in Kilani factory is the cleaning wastes such as the cleaning

    of the reactors, tank and other equipments. I found that the total amount of discharged

    wastewater in the Kilani plant is approximated 10-20 m3/d .Therefore to give treatment of

    these amounts of wastewater and to state pollution prevention options appropriate for this

    industry; we carried out a laboratory works such as coagulation process and some tests.

    SECTION 4

    DESCRIPTION OF THE PROCESSES OF WASHED

    SOLVENT

    I classified the process of washed (or waste) solvent in Kilani factory as follow:

    Class one:

    I must emphasize that our processes only work because the company employees were

    involved from the beginning; the problem and its ramifications was explained to them,

    and their cooperation made, and makes, the program work well.

    Class two:

    Then I went to the second step which is the process. Here we divided the process into

    three part processes:

    First process (Storage area) :

  • 8/14/2019 Zaid AlAnber_Finalproject

    17/44

    In the storage area, I marked the used solvent as groups (for example group 1, group 2

    etc). Group 1 is washed solvent from white, group 2 is washed solvent from clear

    paint, and group 3 is washed solvent from gray paint and so on.

    This process is eliminated the need for substantial volumes of solvents needed for

    tank rinsing and flushing after each batch. Then, whenever possible, thesolvents used

    for mill wash and filter flushing was either used in that batch or held inmarked drums

    for the next batch of the same or similar color. See the Figure below.

    Second process (Initial Treatment):

    Wash solvents generated in other areas that were not amenable for reuse in the

    production process was, and is, collected in others drums/tanks. This material is

    allowed to sit and settle undisturbed for several days. High level of suspended solid

    may be separated from solvent by sedimentation or gravity settling. At that time, the

    clear, thin solvent is decanted from the top of the drum/tank and is used as the first

    wash on specified mills, some portable tubs, filling machines, etc. This process of

    settling and decanting continues until the material in the drum/tank becomes too thick

    or heavy to be usable as a wash solvent. The drum/tank is then labeled and dated as a

    hazardous material and set aside for treatment as shown in the third process. See

    Figure 3.

  • 8/14/2019 Zaid AlAnber_Finalproject

    18/44

    Figure 3: Tanks in Kilani factory

    Third process (recovery process):

    It is the treatment process. We design and construct a process for solvent recovery.

    This process is consisting distillation unit which capable of handling 120 tons per year

    of dirty (washed) solvent.

    The distilled solvent is, in most cases, about 96-97% pure. Initially, it will be intended

    to use the distilled solvent, but even 3-4% dilution significantly reduced cleaning

    efficiency. It will be trialed as a partial replacement for purchased solvent in several

    blended thinner formulations which Kilani paints will find to be satisfactory in many

    of the products. By using the distilled solvent to replace new solvent, it will be easily

    converted to a relatively cheap solvent that can be sold.

    DESCRIPTIONOFTHE DISTILLATIONPROCESS

    As shown in the figure 4:

    A. Feed Tank Reservoir. A stainless steel tank with a sloping bottom for proper

    drainage

  • 8/14/2019 Zaid AlAnber_Finalproject

    19/44

    B. Reboiler. Cylindrical glass with a capacity of, approximately, 3.8 - 4.0 gal at

    operating level. The boiler, covered with foam rubber insulating material. The main

    heating element is a stainless steel heated bayonet-type 3-phase electric heater with a

    nominal power rating of 15 Kilowatts at 240 VAC. The power to the heating elements

    is controlled by an electronic switch which operates by cycling the heater on and off in

    1 to 3 seconds intervals. The relative times the heaters are on or off determine the

    amount of power supplied to the reboiler. The reboiler also has a drainage stop-cock.

    C. Column. Consist of sections each assembled from a 3-inch ID glass pipe section.

    Each section contains process fittings for feed, pressure and temperature measurement.

    The column, when assembled, is approximately 31 inches in height, bolted to the

    boiler at its bottom and to the vapor riser at its upper end by means of a bell reducing

    coupling section and a flexible Teflon expansion joint.

    D. Condenser. A glass shell-and tube type heat exchanger, which contains the

    equivalent of 1.3 sq. ft. of spiral-tube heat exchange surface. The tube side coolant is

    water from the municipal water supply. Thermocouples are placed in the tube side to

    monitor the inlet and outlet temperatures of the cooling water. The spiral condensing

    tube is 160 inches long coiled to a length of 18 inches. The tube is 3/8-inch OD, with

    0.019-inch wall. The shell side condensate drains through a 3/8-inch line to the

    distillate receiver. The cooling water supply to the condensed is equipped with a flow-

    switch that will cut the power to the reboiler if there is a loss of water flow to the unit.

    E. Feed Pumps. A stainless steel pumps are used for the feed.

    F. Distillate Receiver. A 3-inch OD by 12-inch long Pyrex glass tube that is flanged top

    and bottom with stainless steel caps. Condensate enters from the condenser through a

    3/8-inch tube into the top, which is fitted with a thermocouple. There is a valve drain

    at the bottom.

  • 8/14/2019 Zaid AlAnber_Finalproject

    20/44

    G. Feed Preheaters. Cartridge-type rated at 1500 Watts at 240 VAC and sealed in a

    stainless steel type enclosure. Peheater is controlled from an ONOFF type

    temperature controller.

    H. Thermocouples. Thermocouples are installed at various locations throughout the

    distillation column system. These thermocouples are connected to a digital scale for

    monitoring and dataloging. These thermocouples are slow to respond to temperature

    changes and record temperatures that are slightly lower than the stream inside the

    column. All temperature values are displayed and saved to file in degrees Celcius.

    Figure shows a typical continuous distillation column. The washed-solvent (paint and

    solvent) mixture is fed to the column at one or more points along the column. liquid

    runs down the column due to gravity while the vapour runs up the column. The vapour

    is reduced by partial vaporization of the liquid reaching the bottom of the column. The

    remaining liquid is withdrawn from the column as bottom product rich in heavy

    component. The vapour reaching the top of the column is partially or fully condensed.

    PROCEDUREAND METHODOLOGY

    A. Distillation Column Start-Up Procedure.

    Turn on the cooling water to condenser. Check that water flows to the drain from the cooling

    water outlets in the rear of the column . Do not start any operation until cooling water flow

    is visible in drains. Note that the reboiler heater will not turn ON unless there is flow in the

    cooling water line.

    1. Fill the reboiler with washed solvent. To charge the boiler, open the feed bypass ball

    valve F-5, (located near the reboiler quick connect port Q-1).

  • 8/14/2019 Zaid AlAnber_Finalproject

    21/44

    2. Trace the feed line from the reservoir tank through the feed pump and then connect the

    flexible tubing feed line to any desired feed port.

    3. Turn the main power switch "on", then the feed pump switch.

    4. Observe the liquid level in the boiler.

    5. Shut feed pump off when the reboiler is full (drain light turns on)

    6. Set proportional power control switch for the boiler to the desired heating rate value to

    expedite the start-up. Generally, it is best to turn full power on until boiling begins, then

    reduce the power to the desired value.

    7. Turn the boiler power switch on; a pilot light should indicate heat input. The System

    should heat up and begin boiling in 10 to 15 minutes if full power is applied.

    8. While the System is heating up, open the distillate receiver overflow. The distillate drain

    valve should be closed.

    9. When boiling starts and condensate starts to form in the condenser, turn the feed pump on .

    Adjust the feed flow to the desired flow rate.

    A. Distillation Column Shut-Down Procedure. (See Figure 4):

    1. Turn boiler power switch off.

    2. Turn off feed preheater.

    3. Turn off feed pump.

    4. Shut off cooling water to condenser and pumps.

    5. Do not drain the hot paint from the reboiler. The reboiler can only be drained when it is

    cool.

    RESULTS AND OUTPUT

    The amount of solvent recovery by using distillation process is shown in the following table.

    Our results based on 4 gal as basis of washed solvent.

  • 8/14/2019 Zaid AlAnber_Finalproject

    22/44

    Kilani production dataNumber of batches

    ( estimated)/year

    400 batches

    Quantity of solvent used to cleantanks 30 gal.

    Solvent required for cleanup only 12000 gal.Solvent reuse/recover

    (90%*12000 gal)

    10800 gal.

    Waste reduction 1200 gal.

    It can be observed that the percentage of solvent recovery is

    Percentage = 10800/12000= 90%One site sample collection and testing

    Different wasted solvent of Toluene after the cleaning of tanks were collected after the

    batches of production. The sample was taken at the end of the tank washing. We used the

    washed solvent that used in the cleaning of black tanks, which is the difficult one to be

    handed. This sample was pumped as the feed of distillation unit. Most the solvent was

    vaporized and condensed at the top of the column and paints was collected in bottom of the

    boiler as shown in the figure below. The condensed solvent was analysed using gas

    chromatography and viscometer. The following results that we obtained:

    Property Value ( our results) Literature

    Assay 96% 99 %Boiling point 108 C 110 C Density 0.859 g/cm 3 0.862 g/cm3

    From our results, we can see that the most of the disposal washed solvent can be recovered

    and recycled. Also, on comparing these results with those values of the literature, we see that

    a good agreements between them. It means that, even if we use the distillated Toluene

    (recovered Toluene) in the production of paints, we expect that the properties of paints will

    not be changed.

    Also we have to concentrate on the other important point which is the solid waste that

    remaining in the boiler after the distillation process. These solid are paint constituents and

  • 8/14/2019 Zaid AlAnber_Finalproject

    23/44

    can be reuse it again in the manufacturing of the paints. This part needs more studies and

    research. Therefore, I advised the Kilani factory to concentrate on this point in another

    studies.

  • 8/14/2019 Zaid AlAnber_Finalproject

    24/44

    CondenserDistillate ReceiverReboilerDistillation columnCooling WaterFeed

  • 8/14/2019 Zaid AlAnber_Finalproject

    25/44

    Figure 4 : Distillation Column

    Condenser

    Feed

  • 8/14/2019 Zaid AlAnber_Finalproject

    26/44

    SECTION 5

    DESCRIPTION OF THE PROCESSES OF

    WASTWATER

    Water Problem

    The major hazardous wastewater sources are process water, cleaning residue mixed with

    water, and spills that occur when paint is inadvertently discharged in the production area. The

    total amount of discharged water in the plant is approximated 10-20 m3/d. Although this

    amount is quite low in comparison to other industries, the cost of treating and disposing of

    this wastewater is significant.

    White paint washings currently constitutes over 50% of wastewater produced during

    cleaning operations. The other 50% comes in the form of other colours wash water. These

    other colours washings are also discharged into other tanks. See Figure 5.

  • 8/14/2019 Zaid AlAnber_Finalproject

    27/44

    Figure 5. Washing tank by water

    DESCRIPTION OF THE PROCESS

    In this part we used a simple process to treat the wastewater which is called coagulation

    process.

    COAGULATIONPROCESS

    Coagulation and flocculation processes are an important part of water and waste water

    treatment. The processes of coagulation and flocculation are employed to separate suspended

    solids from water. The particles are essentially coated with a chemically sticky layer that

    allows them to flocculate and settle in a reasonable period of time.

    In wastewater of paint, in general, coagulation precedes chemical or biological processes

    which are pre-treatment for the removal of suspended solids, foam and high molecular weight

    compounds. Coagulation is also used for the removal of turbidity , water clarification

    and organic load abatement (COD , BOD).

  • 8/14/2019 Zaid AlAnber_Finalproject

    28/44

    Destabilization of a colloidal suspension results in joining of minute particles by

    physical and chemical processes which presented by neutralizing the forces that keep the

    colloids apart. Cationic coagulants provide positive electric charges to reduce the negative

    charge (zeta potential) of the colloids. When the coagulant added to the water numerous

    species of hydroxyl metallic complexes are formed because the complexes, which are

    hydrolysis products.

    Wastewater Samples

    Wastewater samples are collected from the discharges of Kilani paint factory. The wastewater

    is mainly characterized by its color variation and high load of Chemical Oxygen Demand

    (COD). The characteristics of the raw wastewater (RW) are as shown in the table below

    Parameter concentration

    pH 7.35Conductivity, ms/cm 2.35Turbidity (NTU) 26.98COD, mg/l 9600BOD, mg/l 16324Total phosphorus, mg/l 7.52Chloride, mg/l 266Sulphate, mg/l 2389

    Methodology and Procedure

    In this part, we carried out the work based on the lab scale. Four equal-volume beakers are

    used; 500 ml of paint wastewaters was taken in a 1000 ml worked volume beaker and, after

    addition of coagulant aid, mixed for 5 min at 150 rpm to insure complete dispersion. See

    figure 6.

  • 8/14/2019 Zaid AlAnber_Finalproject

    29/44

  • 8/14/2019 Zaid AlAnber_Finalproject

    30/44

    Color measurement: Prior to color measurement, the sample is filtered through

    a membrane filter (0.45m) to prevent turbidity. Color measurements are

    carried out with a spectrophotometer.

    Since the wastewater contains different kinds of pigments (depending on the

    production), the traditional method of applying the maximum absorbance is not

    used. Color content is determined using a UVvis (Model 7800UVvis

    spectrophotometer) by measuring the absorbance at three wavelengths (436,

    540 and 660 nm) and taking the sum of these absorbencies.

    Amount of sludge: The volume of decanted sludge is estimate by the

    volumetric method using the graduated cylindrical. Once the experiment has

    been performed, the beaker contents are transferred to special graduated

    cylindrical. After 1 h of settling, the sludge production is determined by direct

    reading as ml of sludge/l of wastewater treated.

    RESULTS AND OUTPUT

    Treatment efficiency is evaluated in term of the recovery of treated water and pollutant

    removals (turbidity, COD and color) as well as in terms of sludge production. We determined

    the optimal operating conditions as follow:

    The percentage of the recovery was calculated based on the amount of wastewater

    used and the amount of water treated. About 425 ml was recovered, therefore

    Percentage recovery = 425/500

    = 85 %

    The pH solution is an important factor in the coagulation process. The use of

    coagulant at its optimum pH displays maximum pollutant removal. To optimize the

    pH of the coagulation process, a known volume of prepared coagulant aid solution is

    added to 500 ml of wastewater at different pH value adjusted with concentrated

  • 8/14/2019 Zaid AlAnber_Finalproject

    31/44

    H2SO4 and NaOH. The mass of coagulant aid was 600 mg/l. I found that the turbidity

    removal is most effective at a pH range between 8 and 9. See figure 7

    I also studied the effect of the coagulant aid dosage on the COD and

    color removal by varying the amount of coagulant in the paint

    wastewater, while keeping other conditions constant (pH 8.5). I

    observed that for the quantitative removal of 82% of COD and 94%

    of colorings matter, a minimum dosage of 600 mg/l of coagulant aid

    is required. I also observed that a further increase in the coagulant

    dosage does not produce better removal rate.

    Amount of sludge was estimated by graduated cylinder as shown in Figure 8. I found

    that the volume of the sludge production is 50 ml.

    I also optimized the cost of the paint wastewater treatment; I found that the operating

    cost of 1 m3 is 0.15 JD

    The remaining solid waste after the coagulation process is mainly paintcomposition. We suggest that these wastes must to be studied and reused in thepaint production

  • 8/14/2019 Zaid AlAnber_Finalproject

    32/44

    Figure 7: pH readings

    Figure 8: Treated water and sludge

    the summary of an interesting point. You can position the text box anywhere in the document. Use the Text Box Tools tab to change the form

    Sludge production

    reated water

  • 8/14/2019 Zaid AlAnber_Finalproject

    33/44

    SECTION 6

    ECONOMIC EVALUTION

    The objective of economic estimation is to locate a payback period and cost reduction

    associated with implementation of this technology for reducing the solvent waste stream and

    paint wastewater. Economic estimations for evaluating the technology are based on capital

    and operating costs.

    CAPITAL COSTS FOR WASH-SOLVENT REUSE SYSTEM

    The wash solvent reuse system used by Kilani Paint did not have significant capital cost. No

    equipments were purchased, no addition storage area was need, and addition energy supply

    was needed. Total expenditure to implement the system is estimated by us to be less $2000

    ($1500 +$500).

    OPERATING COSTS

    The major operating costs associated with the washed solvent reuse system are shown in the

    table below. It can be seen that the labour cost are the same weather wash solvent is disposed

    of or stored for reuse. The washed solvent must be collected in tanks in both cases. Electricity

    is required and it is considered within the operating costs.

  • 8/14/2019 Zaid AlAnber_Finalproject

    34/44

    I. Washed solvent (Toluene)

    CAPITAL

    COST

    $1500

    OPERATING

    COST

    Cost item Annualamount

    Unitcost

    Annualcost

    Solvent waste disposal 12000 gal $

    2/gal

    $ 24000

    Total without reuse $ 24000

    Solvent not reused 1200 gal $

    2/gal

    $ 2400

    Electricity $1600

    Total with reuse $ 2400

    Annual saving of

    wash solvent

    $20000

    II. Wastewater

    CAPITAL

    COST

    $500 JD

    OPERATING

    COST

    Cost item Annual

    amount

    Unit

    cost

    Annual

    cost

    Waste water disposal 6000 m3 $1/m3 $ 6000

  • 8/14/2019 Zaid AlAnber_Finalproject

    35/44

    Coagulant aids $ 0.2 $0.2/

    m3

    $1200

    Total $ 6200

    Treated water

    (6000*85%)

    5100 m3 $1/m3 $5100

    Annual saving $4000

    Economic Evaluation of Washed Solvent

    A simple payback period calculation for this project evaluation can be performed with the

    capital cost and operation costs. The cost saving in this system comes from the reduction of

    disposal charges and the reduction of solvent purchases.

    Payback=capital costs/ saving in annual operating costs

    Capital costs for solvent recovery in Kilani paints including material, labour and others simple

    equipments are $1500. The total operating saving are $ 21600, this include saving on both

    waste disposal and material purchased based on the 2008. Operating costs are affected by

    reducing the volume of new solvent purchased. Because solvent prices fluctuates with the

    market and the volume purchased, these saving vary somewhat.

    The recovery of 10800 gal of wash solvent for reuse in paint manufacturing reduces solvent

    raw material purchased by that amount. Based on the cost of $ 2 per gal for solvent, this

    represents a saving of about 21600$.

    The payback period of implantation of the wash solvent recovery system at Kilani paint was

    approximate one month.

    Payback=1500/21600= 1 month

  • 8/14/2019 Zaid AlAnber_Finalproject

    36/44

  • 8/14/2019 Zaid AlAnber_Finalproject

    37/44

    Inlet Washed SolventEvaporator

    SECTION 8

    SUSTAINABILITY STUDY FOR SOLVENT RECOVERY

    Depend on our results as created in the small scale process, we (The owner of Kilani and I)

    decided to go to industrial scales or large scales to recover the solvents. To do that, we bought

    some equipment; these equipments are consists of evaporator, heat exchanger, vessel, pumps

    and pipes as shown in the following figures:

  • 8/14/2019 Zaid AlAnber_Finalproject

    38/44

    Outlet of sludge

  • 8/14/2019 Zaid AlAnber_Finalproject

    39/44

    Heat ExchangerCover of Heat Exchanger

    This part is already built in the Kilani Paint Factory for few days ago. We

    are now in running way to collect others parts like vessels, heat

    exchangers, pumps and with its pipings. See the following Figures.

    Vessel

  • 8/14/2019 Zaid AlAnber_Finalproject

    40/44

    We expect that the installation of all parts will befinished by the end of the Dec 2009, while theoperation process will be started at thebeginning of Jan 2010.

    Methodology

    The feed of washed solvent will be pumped from the vessel to the pointof feed in the evaporator.

    The washed solvent will be heated using an external heating thatwrapped around the evaporator.

    The vapour of solvent will be condensed by the heat exchanger. The sludge of washed solvent will be drained at the bottom of

    evaporator.

    SECTION 9

    APPENDICES

    Appendix A: Physical properties of solvents

    Toluene

  • 8/14/2019 Zaid AlAnber_Finalproject

    41/44

    Property value

    Molecular weight 92.14

    Boiling point 110.62C

    Vapor pressure 28.5 Torr at 20C

    Freezing point -94.99C

    Refractive index 1.4969 at 20C

    Density 0.8623 g/mL (7.196 lb/gal) at 25C

    Xylene

    Property value

    Molecular weight 106.167

    Boiling point 144.41 C

    Vapor pressure 0.7 Kpa at 20C

    Freezing point -25.182 C

    Refractive index 1.5054 at 20C

    Density 0.8802, g/cm3 at 25C

    Appendix B: Approvals and Acceptance letter of the project

    output

  • 8/14/2019 Zaid AlAnber_Finalproject

    42/44

    Appendix C: Poster

  • 8/14/2019 Zaid AlAnber_Finalproject

    43/44

    Appendix D: Faculty and Factory surveys

  • 8/14/2019 Zaid AlAnber_Finalproject

    44/44