Palladium...Palladium.com. Palladium Hotels and Resorts PalladiumHotels ...
ZA PSMP presentation at palladium forum 2012
-
date post
13-Sep-2014 -
Category
Business
-
view
304 -
download
1
description
Transcript of ZA PSMP presentation at palladium forum 2012
ADSSC Partners and Stakeholders
Management Programme - PSMP
Presentation @
Palladium Partners and Stakeholders
Management Road-show
31st May 2012
by
Zillay Ahmed, ADSSC Business Support
ADSSC Background and Service Delivery Model
ADSSC currently
services 1.3 million
inhabitants, after
completion of its CIP
will serve a population
base of 1.7 million
Established in June 2005.
Owned by the Government
of Abu Dhabi
Over US $ 6 billion
Capital Investment
Projects (CIP) in
progress
Sewer tunnel project
(STEP); 41 kms length,
up to 5.5 m in diameter,
commissioning planned
for 2014, with capacity to
handle 1.6 million cubic
meters by 2030
510 employees
work at
ADSSC. O & M
is 100 %
outsourced
3
ADSSC Assets
4 www.adssc.ae
ADSSC Whole of Government Outcomes:
Reliable, secure, safe and cost effective provision of sewerage services
Sewerage network that complies with environmental regulations and standards
What’s our
contribution to
AD Vision?
Our Mission: “To achieve excellence in the provision of high quality, cost effective, safe and environmentally compliant sewerage
services in the Emirate of Abu Dhabi.”
Why do we
exist?
V2: Ensure Customer Satisfaction V1: Increase efficiency of ADSSC What “Value” do
we need to
deliver during
the next 5
years?
External Stakeholder Collaboration
I6: Ensure regulatory compliance
Where should
we focus our
efforts in order
to deliver this
Value?
Service Delivery
I1: Effectively manage overloaded asset base
I3: Realistic planning and
efficient delivery of CAPEX
Customer Focus
Organisational Excellence
E1: Attract qualified & experienced staff
E3: Ensure complete IT segregation from ADWEA
E4: Enhance communication
capabilities
E5: Implement best-practice frameworks
E2: Motivate & retain human capital
What will
enable us to
execute all
these
challenges?
I4: Improve management of Trade Effluent customers
I5: Enhance domestic customer service
PSMP linkage to ADSSC Strategy Map 2011-2015
I2: Strengthen value-added partnerships with suppliers, contractors and consultants
I7: Enhance co-ordination with developers I8: Ensure alignment and co-ordination
with relevant governmental entities
Stakeholder
Collaboration
theme and 4-
priorities
5 www.adssc.ae
Customer Focus
ADSSC Whole of Government Outcomes:
Reliable, secure, safe and cost effective provision of sewerage services
Sewerage network that complies with environmental regulations and standards
What’s our
contribution to
AD Vision?
Why do we
exist?
V2: Ensure Customer Satisfaction V1: Enhance Cost Efficiency
What “Value” do
we need to
deliver during
the next 5
years?
External Stakeholder Collaboration
I5: Comply with Regulatory Requirements I6: Coordinate and Collaborate with External Stakeholders
Where
should we
focus our
efforts in
order to
deliver this
Value?
Service Delivery
I2: Plan and Deliver CAPEXI1: Manage Overloaded Asset
Base
Organizational Excellence
E1: Attract, Motivate & Retain Human Capital E2: Deploy technology enablement E3: Implement Best-Practice Frameworks
What will
enable us to
execute all
these
challenges?
I3: Facilitate Implementation of Trade Effluent Regulations
I4: Facilitate Transition Towards Tariff Regime
Vision: “To be recognized by communities, businesses and regulators as a world leader in the provision of sewerage services by
2020”
Mission: “To achieve excellence in the provision of high quality, cost effective, safe and environmentally compliant sewerage
services in the Emirate of Abu Dhabi.”
PSMP linkage to ADSSC Strategy Map 2012-2016
Stakeholder
Collaboration
theme and 2-
priorities
6
What is PSMP?
ADSSC Partners & Stakeholders Management Program reviews & improves:
• Relationship
• Engagement
• Management
• Satisfaction
PSMP focuses on ADSSC stakeholders, including:
• Contractors
• Consultants
• Government entities
• Developers
• Suppliers
PSMP excludes the following stakeholders, included under separate initiatives:
• Employees
• Customers
7
Why PSMP?
Strategic Planning framework mandated by Abu Dhabi Executive Council includes:
• Strategic Stakeholder Mapping
• Stakeholder Needs Analysis
• Stakeholder Interactions
Abu Dhabi Government Excellence Award (EFQM model) stresses on Stakeholder:
• Engagement
• Consultation
• Partnerships
• Technological collaboration
Abu Dhabi Executive Council Performance Management Framework includes:
• Whole-of-Government Outcomes
• Inter-dependencies & Inter-linkages
• Alignment with Abu Dhabi Vision
8
How did we proceed?
Internal Assessment, Planning and Actions:
• Stakeholder Prioritization
• Verification of process interfaces and touch points
• Review of existing procedures, forms, technology deployment
• Design of Stakeholder customized questionnaire
• Issuance of participation invitation via MD office
Engagement Options:
• 1-2-1
• Focus Groups
Outcomes and Next Steps:
• Communication (3-iterations)
• Internal Improvement Projects
• Integration with ADSSC Strategic Planning and Performance Management
Scorecards
9 www.adssc.ae
PSMP
Engagement
Satisfaction
Management
Relationship
• Participation invitation by MD
• 1-2-2 interviews
• Focus group sessions
• Report back via formal MD letter
• Contractual Ts’ & Cs’
• SLAs
• Technological interface
• Partnership opportunities
• Identification of concerns &
process improvement
opportunities
• Action planning
• Implementation
Stakeholder PerceptionsWhy do /don’t you
agree?What should be done by ADSSC? Who should do it?
When should it be
done?Rank
1. Slow response time and
decision making
Agree, this was the case
when we were apart of
ADWEA (in the MOUs)
We are appointing our legal advisor to
review all MOUs and revisit the IDAs
(removing Power and Water). Consider
communicating this to Developers
Assets Already underway 3
2. Lack of empowerment Don’t agree regarding internal empowerment –
feel this is a legacy issue
from ADWEA
As above Assets Already underway 3
3. Slow and inefficient communication
Yes, this is an existing problem. Communication
channels and procedure is
not clear . Responses tend
to be reactive (query
specific)
Clearly indicate the required protocol (e.g., use overseeing consultants)
Clear contact points on website (query)
Implement strong reception system
Business Support Immediately – quick win
1
4. No clear contact point As above As above Business Support Immediately - next 3 months
1
5. Stakeholder not clear on
ADSSC internal roles and responsibilities
No need to know internal roles as long as contact
points are clearly identified
Clearly communicate relevant points of contact
Business Support Immediately - next 3 months
1
6. Limited / no availability of TSE Agree that this is a concern but this is something that is
out of our hands
A letter has been sent to all developers communicating that a Higher
Committee for Water & Agricultural
Strategy is deciding on the correct policy
and use
Continue to keep developers updated on
status
Assets Already underway 2
ADSSC PSMP Framework
• Structured interview Q &A
• Tailored surveys
• Objective analysis
10 www.adssc.ae
Workshop conducted to identify areas of improvement
2010 2011
Government
Entities, 5
Contractors, 5
Consultants, 5
Developers, 3
Participants
Launch of the programme
1-2-1 interviews with selected stakeholders (18)
Action plans implementation
Enhanced approach with increased number of
participants (64)
Customized surveys & analysis for each stakeholder
group Open discussions in focus group setting
Execution & monitoring framework for actions to be
taken
Approach : Approach :
PSMP – Comparison between 2-cycles
11 www.adssc.ae
Interviews
• Eighteen 1-2-1 interviews were done with stakeholders from all identified strategic stakeholder groups
Workshops
• Workshops were conducted to understand stakeholders’ perception and to identify areas requiring change
Management Presentation
• Feedback presentation was made to Management of ADSSC
Action Plans
• An implementation framework has been developed along with the relevant Action Plans
2010
Ap
pro
ach
2010 External Stakeholders Feedback
• An acknowledgment of the continuous efforts made to
improve the partnership between ADSSC and O&M
Contractors.
• ADSSC communication and reporting lines were seen to be
defined and clear.
• Transparency and access to higher management is seen
to be amongst the positive attributes resulting in higher
satisfaction results.
Areas of improvement were mostly focused on the
following :
• Contract terms and conditions
• Scoping
• Bid bonds
• Variation orders
• HSE
PSMP – Cycle 1 2010
Project initiated in January 2010 and completed in April 2010
12 www.adssc.ae
Rank Identified Issue Action Taken
1
Contract monitoring and
implementation on-site
• New O & M contracts are performance based, with specific HSE KPIs’
2
HSE culture
• Effective implementation of an Integrated Management System (IMS)
resulted in achievement of the ADSSC IMS Certification in May 2010
• HSE Specialist has been brought on-board
3
Contracts Ts’ & Cs’
• New contracts are performance based
•Terms and conditions aligned to FIDIC
4
Variations Management
and timelines
• End-to-end process review and re-design
5
Sharing of Bid Outcomes
• Relevant policy review is under consideration (changed in 2012)
PSMP – Cycle 1 2010 – Outcomes
All areas of concern were addressed and reported back to stakeholders
13
PSMP – Cycle II Details
Stakeholders Involvement – 64 external organizations:
• 18 Government entities
• 8 Developers
• 14 Suppliers
• 12 Contractors (Projects)
• 5 Contractors (O & M)
• 7 Consultants
Engagement Method:
• Customized questionnaire
• 6 Focus Groups (1-2 guests invited from each stakeholder entity)
Focus Group details:
• ADSSC MD, Executive Management team and relevant staff attended
• Survey results presented
• Discussion and lunch
14 www.adssc.ae
ADSSC PSMP Cycle II – Government Entities
15 www.adssc.ae
ADSSC PSMP Cycle II – O&M Contractors
General Construction Comp.
ADSSC PSMP Cycle II – Consultants
ADSSC PSMP Cycle II - Developers
Additionally 14 Suppliers
participated, representing the full
spectrum, in terms of volume of
business and strategic importance for
ADSSC
16 www.adssc.ae
• Frequency of Interaction
• Perception of ADSSC: − Professionalism
− Social Responsibility
− Technology
− Service Delivery
− Bureaucracy
− Responsiveness
− Leadership
− Values
SECTIONS
1 & 2
• Overall Satisfaction on General
Issues: − Quality and Timeliness of
Communication Material
− Professionalism, Knowledge and
Responsiveness of ADSSC
Personnel
− Clarity of Communication Channel
− Contribution to Government
Outcomes
− Frequency of interaction
SECTION 3 SECTION 4
• Overall Satisfaction on
Technical Issues: − The Bidding Process
− Contractual Terms and
Conditions
− On-Site Coordination
− Integrated Management
System
− The Handover Process
− The Variation Process
− The Payment Process
PSMP – Cycle II Questionnaire Design
17 www.adssc.ae
Higher Satisfaction Rates
Lower Satisfaction Rates
Moderate Satisfaction Rates
Based on the results of the survey … … we’ve built a “heat map” of the technical aspects
of the interaction between ADSSC & the Consultants
to identify major improvement areas:
High
Satisfaction
LEGEND:
Moderate
Satisfaction Areas to
improve
Feedback Review and Analysis – typical example
18
PSMP – Cycle II Outcomes
Four Improvement Projects identified, related to:
• Bidding
• Consultant Effectiveness
• Internal Divisional Coordination
• Handover
What was done:
• Internal multi-divisional teams formed
• Maximum 6-month timeline per team
• 4 concurrent projects
• Monthly update to Management
• Feedback to stakeholders at PSMP Cycle III planned for October 2012
PSMP Cycle III Options:
• Repeat Cycle I or II methodology
• Do collective Focus Group
• Invite relevant stakeholders in joint session/s
19
PSMP – Tips for Success
Design and Planning stage:
• Drill down to smallest details
• Ensure that stakeholder selection is representative of the group
• Develop interview/survey methodology in coordination with relevant internal divisions
• Leave 6-7 weeks window for receipt of participants feedback (reminders @W3/4/5)
Interaction stage:
• Prepare well and stick to schedule
• Brief executive management team prior to meeting
• Deploy professional facilitation during workshop as interactions can get messy
• Recognize / reward stakeholders
Analysis and Report back stage:
• Capture all discussion notes
• Communicate your action plans to stakeholders
• Engage executive management in periodic review of agreed action plans / outcomes
20 www.adssc.ae
ADSSC PSMP Focus Groups in Session
21 www.adssc.ae
Appreciation Certificates
22
ADSSC Organizational Excellence –
Sharing Best Practice Sessions
1. Western Region Development Council (WRDC) – March 2012 @ADSSC
2. DU Telecom – February 2012 @ADSSC
3. Regulation & Supervision Bureau (RSB) Abu Dhabi – January 2012 @ADSSC
4. Roads & Transport Authority Dubai (RTA) – June 2011 @ADSSC
5. Region of Peel, Mississauga, Canada - February 2011
6. Abu Dhabi Distribution Company – November 2010, at ADDC Head Office
7. Calgary Water, City of Calgary, Canada – October 2010
8. ETISALAT – October 2010 @ADSSC
9. Department of Transport (DoT) Abu Dhabi – July 2010 @ADSSC
23
1. “ADSSC Partners and Stakeholders Management Programme - PSMP”
presentation at Palladium Round Table Workshops in May 2012, Abu Dhabi
2. “Organizational Excellence @ ADSSC: An integrated Approach” paper
presentation at Balanced Scorecard Forum in April 2012, Dubai
3. “A Practical Guide to Performance Benchmarking” workshop (full-day) presentation
at Balanced Scorecard Forum in April 2012, Dubai
4. “Benchmarking UAE Style” paper presentation at 6th International Benchmarking
Conference, March 2012, Dubai
5. “International Innovation: Globally Leveraging a Canadian Best Practice” paper
published in American Public Works Association (APWA), June 2011 issue
6. “Benchmarking Sewerage Services in Abu Dhabi” paper published in IWA Utility
Water Management International, June 2011 issue
ADSSC Organizational Excellence –
Presentations and Publications
24
7. “Strategic Performance Management @ ADSSC” paper presentation at NWWBI
Conference in Banff, Canada, April 2011
8. “Risk Management @ADSSS” paper presentation at MENA ERM conference in April
2011, Dubai
9. “ADSSC ARP Case Study” paper published by QPR in April 2011
10. “Using Process Benchmarking to Leverage Best Practices in the Establishment
of a Functional and Dynamic Balanced Scorecard-based Performance
Measurement System” paper presentation at IWA Benchmarking Conference,
Valencia, Spain – January 2011
11. “Rapid Growth – an Abu Dhabi Perspective” paper presentation at WSAA
Conference in Sydney, Australia – October 2008
ADSSC Organizational Excellence –
Presentations and Publications
25
Thank you.