www.vita.virginia.gov
Commonwealth Project Management: CPGAT
Pat ReynoldsProject Management Division
www.vita.virginia.gov 1
D R A F T
www.vita.virginia.gov
Concepts to know• CPGAT “fine tunes” (not too much or too little) project:
– Governance & Oversight– Documentation requirements– Approval levels
• Based on four levels - - NOT two: (major, non-major)
• “Major IT Project” is simply a label for ITIM/ITSP purposes.
• May reduce the ‘paperwork burden’ of many projects– Remember that “it’s not about the paperwork”!...– Documentation is merely evidence that the agency and PM
went through the mental process of initiating, planning, executing & controlling and closing out the project.
www.vita.virginia.gov
CPGA Categories
Risk High Medium LowComplexity High
Medium Low High
Medium Low High
Medium Low
Category 1 2 3 4
www.vita.virginia.gov
CPGA Changes to ProSight (CTP)No more:• Major and Non-major projects
– Governance & Oversight is applied in accordance with the CPGA Risk/Complexity Category
• ITIB– Secretary of Technology is the highest approval authority
• Pre-Select Investment Analysis– Replaced by CPGA Pre-Select Risk/Complexity Assessment
• Project Analysis Worksheet (PAW)– Previously was optional– Under CPGA, the Business Case & Alternatives Analysis (BCAA)
incorporates much of the information and analysis previously found in the PAW
www.vita.virginia.gov
CPGA Changes to ProSight (CTP)No more:• Project Proposal
– Under CPGA, the Project Charter and the Business Case & Alternatives Analysis (BCAA) incorporate much of the information and analysis previously found in the Project Proposal
• Excel-Macro Cost-Benefit Analysis worksheet– Now CBA is an integrated form in ProSight
• Preliminary Risk Assessment– Replaced by CPGA Planning Risk/Complexity Assessment
• Project Complexity– Replaced by CPGA Project Initiation Approval Risk/Complexity Assessment and
CPGA Category Matrix
• User Acceptance Report – The UA Report is now incorporated into the Closeout Report
www.vita.virginia.gov
CPGA Changes to ProSight (CTP)New ProSight Forms:
• CPGA Pre-Select Risk/Complexity Assessment• CPGA Project Initiation Approval Risk/Complexity Assessment• CPGA Planning Risk/Complexity Assessment• CPGA Event-Driven Risk/Complexity Assessment• Business Case & Alternatives Analysis (BCAA)• Cost-Benefit Analysis• Organizational Change Management Plan (upload, Ph. 2)• Closeout Report (updated, incl. O&M cost planning)
www.vita.virginia.gov
CPGA Changes to ProSight (CTP)New ProSight Procedures:• Every new project > $250,000 requires more robust justification
through the use of Business Case & Alternatives Analysis and Cost-Benefit Analysis.– Capture costs of current process– Compare alternative solutions, including ‘do nothing’– Justify the selected alternative
• Incorporate Risk/Complexity Assessment discussions/activities: – Initial– Periodic– Cumulative– Changeable
www.vita.virginia.gov
CPGA Changes to ProSight (CTP)New ProSight Procedures:
• Refer to CPGA Risk/Complexity Category for:– Documentation requirements– Approval levels– IV&V requirements– Status reporting requirements– Oversight committee requirements– Scope, schedule, budget accuracy thresholds– Post-Implementation Review requirements
Project Business Alignment Biennium Funding
Project Business Alignment Biennium Funding
Project Business Alignment
Project Business Alignment
Pre-Select & Select
IBC – Investment Business
Case Approval
PMD Project**
Evaluation
PMD Project**
Evaluation
ITIM verifies
Agcy has Certified Strategic
Plan
ITIM verifies
Agcy has Certified Strategic
Plan
ITIM drafts decision
package to CIO
ITIM drafts decision
package to CIO
IPP – Identified
for Preliminary Planning***
CPGAPre-Select
R/C* Assessment
CPGAPre-Select
R/C* Assessment
Investment Business
Case
Investment Business
Case
Signed by: - AITR - Agcy Hd.
Agency contacts
ITIM Office
NOTE: As part of the RTIP cycle, projects approved in the RTIP report = IPP or IBC approval.
PMD Recom-
mendation & Approval
– Strat. Planning
PMD Recom-
mendation & Approval
– Strat. Planning
** Projects are evaluated with consideration to:PMD: Strategic Plan, Business Case, Funding, RiskEnt. Arch: Technical Feasibility, Re-UseEnt. Appl: Collaboration, EADSupply Chain: APR, RFP, Statewide Contract
Determines CPGA
Category
Red shading = new or revised form.
Agency
Strategic
Plan
Business Need
*** Proposed Project statuses:
IPP: CIO recognizes the business need; needs further analysis before IBC
IBC: CIO authorizes agency to spend funds on developing a project Charter
Note: Both IPP and IBC proposed projects are included in the Agency IT Strategic Plan
- or -
* R/C: Risk & Complexity
www.vita.virginia.gov
Pre-Select & Select: Differences by CPGAT Category
Category > > > > 1 2 3 4Project Business
AlignmentRequired Required Required Required
Project Business Alignment Biennium
FundingRequired Required Required Required
CPGA Pre-Select R/C Assessment
Required Required Required Required
Investment Business Case
Required Required Required Required
Investment Business Case Approval Level
AITR > AgcyHd > PMD > CIO
AITR > AgcyHd > PMD > CIO
AITR > AgcyHd > PMD > CIO
AITR > AgcyHd > PMD > CIO
PMD Project Evaluation Required Required Required RequiredPMD Project Evaluation
Passing Score70 70 70 49
PMD Recommendation & Approval – Strategic
PlanningRequired Required Required Required
DetailedPlanning
Control
IBC – Investment Business
Case Approval
Project Initiation
Approval*
Control Project
Detailed Planning Approval
Initiate Execute & Control Closeout
Closeout Report
Deliver Product or
Service
Status Report
**NOTE: Contract may only be signed AFTER Project Initiation Approval.
Procurement
Procure-ment as needed:
- APR
- RFP
- - Contract*
**NOTE: Projects are designated “active” upon Project Initiation Approval.
Project Analysis
Worksheet (optional)
Project Analysis
Worksheet (optional)
1 Preliminary Risk
Assess-ment
Preliminary Risk
Assess-ment
2
PMD Balanced Scorecard
PMD Balanced Scorecard
PMD Decision
Brief
PMD Decision
Brief
Control: Initiate
APP – Approved
for Planning
Approved for Development
PMD calls for SOC*
review
PMD drafts
decision package for CIO
CIO Develop-
ment Approval
letter
CIO Develop-
ment Approval
letter
ITIB 5-day review**
CIO recommendation**
**CIO recommendation and ITIB review/approval for Major IT projects only
NOTE: Initiation steps are required for both Major and NON-Major projects except where noted.
*Secretariat Oversight Committee (SOC) review/recommendation for Major IT projects only
SOC recommendation*
Cost & Benefit
Analysis
Cost & Benefit
Analysis
3
Project Manager Qualifi-cation
(optional)
Project Manager Qualifi-cation
(optional)
4
Project Proposal
Project Proposal
5
Project Charter
Project Charter
6
Signed by: - Proj. Mgr. - Bus. Sponsr. - Agcy Hd
Signed by: - CIOSigned by: - CIO
Signed by: - Deputy Secretary*
Procurement
Procure-ment as needed:
- APR
- RFP
- Contract*
**
***APR, RFP and Contract require CIO approval. Contract may only be signed AFTER
Development Approval.
CPGA Project
Initiation R/C
Assessment
CPGA Project
Initiation R/C
Assessment
5
B C A A *B C A A *
1
PMD Balanced Scorecard
PMD Balanced Scorecard
PMD Decision
Brief
PMD Decision
Brief
Control: Initiate
IBC – Investment Business
Case Approval
Project Initiation Approval
PMD calls for SOC**
review
CIO Project
Initiation Approval
letter
CIO Project
Initiation Approval
letter
NOTE: CPGAT assessment determines documentation and approval level requirements.
SOC recommendation**
Cost & Benefit
Analysis
Cost & Benefit
Analysis
2
Project Manager Qualifi-cation
(optional)
Project Manager Qualifi-cation
(optional)
3
***APR, RFP and Contract require CIO approval. Contract may only be signed AFTER Project
Initiation Approval.
* BCAA = Business Case & Alternatives Analysis
Procurement
Procure-ment as needed:
- APR
- RFP
- Contract*
**
** SOC = Secretariat Oversight Committee approval as necessary
Re-determines CPGA
Category
Org. ChartOrg. Chart
4.a
Project Charter
Project Charter
4
Procuremt. Plan
Procuremt. Plan
6
Project Initiation
Transition Checklist
Project Initiation
Transition Checklist
7
www.vita.virginia.gov
Initiation: Differences by CPGAT Category
Category > > > > 1 2 3 4Business Case &
Alternatives Analysis (BCAA)
Required Required Required Required
Cost/ Benefit AnalysisRequired Required Required
Summarize in BCAA & Charter
Project Manager Qualification Form
Optional Optional Optional Optional
Project Manager Qualification
Major IT Projects
Major IT Projects
Major IT Projects
Non-major IT Projects
Full-time Project Manager?
Shall, or by exception
Shall, or by exception
Shall, or by exception
Full-time not required
Procurement Plan As Needed As Needed As Needed As Needed
www.vita.virginia.gov
Initiation: Differences by CPGAT Category (Cont’d.)
Category > > > > 1 2 3 4
CPGA Project Initiation Approval Risk /
Complexity Assessment
Required Required Required Required
Charter, with Project Org. Chart
Required Required Required Required
Internal Agency Oversight Committee
(IAOC)?
Required, with PMD
Required, with PMD
Required, with PMD
None; Agcy PM Team only
Balanced Scorecard
Required; Delphi
Required; Delphi
Required; Delphi
No; use Transition Checklist
Project Initiation Transition Checklist
Optional Optional Optional Required
Project Initiation Approval Level
Sponsor > AgcyHd > SOC > PMD > CIO >
SoTech
Sponsor > AgcyHd > SOC > PMD > CIO
Sponsor > AgcyHd > SOC > PMD > CIO
Sponsor > AgcyHd
www.vita.virginia.gov
CPGA Changes to ProSight (CTP)Focus On: Business Case & Alternatives Analysis (BCAA)• Describe the Business Problem• Project Scope, Objectives, Constraints, Business Alignment• Describe 3 different solution alternatives:
– Solution description, Project description, Intangible benefits– Business Process Impact, Technical Feasibility, Maturity of Solution– Estimate Resources: Funding, Project Team, Facilities, Equipment, etc.– Constraints, CBA summary, ROI analysis
• Solution comparison:– Decision Criteria and scores, CBA Comparison, Chosen solution– Recommended Solution Justification
• Project Sponsor Approval
www.vita.virginia.gov
CPGA Changes to ProSight (CTP)• Focus On: Cost-Benefit Analysis (CBA)• Current Operational Expenditures
– Internal Staff Labor (# of people)– Expenditures: Staff costs, Services, Software, Facilities, etc.
• Solution 0 (As-Is): Impact of maintaining the current business process to meet the new problem/opportunity.– Ongoing People, Other costs – Tangible benefits and Revenue
• Solution 1 - 3: Impact of conducting a various projects to meet the new problem/opportunity.– Project Costs– Ongoing People, Other costs – Tangible benefits and Revenue
• Summary & Comparison
Proj. Scope &
Bus. Objective Wksht.
Proj. Scope &
Bus. Objective Wksht.
2
Control: Plan
BOLD indicates REQUIRED form;
Complete other forms based on Project Complexity Model
Approved for Development
NOTE: For NON-Major projects, planning steps described are not required, but recommended.
Project Complex-
ityModel
Project Complex-
ityModel
1
Work Breakdown Structure
Work Breakdown Structure
3
Org. Work Breakdown Structure
Org. Work Breakdown Structure
4
Activity Definition & Sequence.
Wksht.
Activity Definition & Sequence.
Wksht.
5
Resource Plan
Resource Plan
6Project
Schedule
Project Schedule
7Risk Mgmt. Plan
Risk Mgmt. Plan
8
Quality Mgmt. &
IV&V Plan
Quality Mgmt. &
IV&V Plan
11
Project Plan
Summary
Project Plan
Summary
15
Change & Config.
Plan
Change & Config.
Plan
12
Procuremt. Plan
Procuremt. Plan
9
Communi-cation Plan
Communi-cation Plan
10
Perform-ance Plan
Perform-ance Plan
13
Project Plan Approval
Project Oversight
Plan
Project Oversight
Plan
Budget Plan
Budget Plan
14Signed by:PMD (on behalf of CIO)
Signed by: - Bus. Sponsor or - Agcy Hd.
FIRST required IV&V *
* First IV&V required at completion of the detailed project plan and before execution begins.
Proj. Planning Transition Checklist
Proj. Planning Transition Checklist
16
Proj. Scope &
Bus. Objective Wksht.
Proj. Scope &
Bus. Objective Wksht.
1
Control: Detailed Planning
Project Initiation Approval
Work Breakdown Structure (upload)
Work Breakdown Structure (upload)
2
Org. Work Breakdown Structure (upload)
Org. Work Breakdown Structure (upload)
3
Activity Definition & Sequence.
Wksht. (upload)
Activity Definition & Sequence.
Wksht. (upload)
4
Resource Plan
Resource Plan
5Project
Schedule
Project Schedule
6
RiskMgmt. Plan
RiskMgmt. Plan
7
Project Plan
Summary
Project Plan
Summary
15
Communi-cation Plan
Communi-cation Plan
8
Quality Mgmt. &
IV&V Plan
Quality Mgmt. &
IV&V Plan
9
Detailed Planning Approval
Project Oversight
Plan
Project Oversight
Plan
Signed by:PMD (on behalf of CIO)
CPGA Planning
R/C Assessment
CPGA Planning
R/C Assessment
14
Change & Config.
Plan
Change & Config.
Plan
10
Budget Plan
Budget Plan
13
Org. Change
Mgt. Plan (upload)
Org. Change
Mgt. Plan (upload)
11
Perform-ance Plan
Perform-ance Plan
12
Re-determines CPGA
Category
Signed by: - Project Sponsor (IAOC) - Agcy Hd.
www.vita.virginia.gov
Detailed Planning: Differences by CPGAT Category
Category > > > > 1 2 3 4Project Scope &
Business Objective Worksheet
Required Required Required Required
Work Breakdown Structure
Required Required Required Optional
Organization Work Breakdown Structure
Required Required Optional Optional
Activity Definition & Sequencing Worksheet
Required Optional Optional Optional
Resource Plan Required Required Optional OptionalProject Schedule Required Required Required Required
Risk Management Plan(incl. biennium risk
costs)Required Required Required Optional
Communication Plan Required Required Required Optional
www.vita.virginia.gov
Detailed Planning: Differences by CPGAT Category (Cont’d.)
Category > > > > 1 2 3 4Quality Management &
IV&V PlanRequired Required Required Optional
Change & Configuration Management Plan
Required Required Required Optional
Organizational Change Management Plan
Required Required Required Optional
Performance Plan Required Required Required OptionalBudget Plan Required Required Required Required
Project Plan (Summary) Required Required Required Required
CPGA Planning Risk / Complexity Assessment
Required Required Required Required
www.vita.virginia.gov
Detailed Planning: Differences by CPGAT Category (Cont’d.)
Category > > > > 1 2 3 4Appointment of a Risk
Manager (other than the Project Manager)
Strongly Recommended
Strongly Recommended
PMD reviews and approves the Detailed
Project Plan on behalf of the CIO.
Required Required Required
Detailed Planning Approval - up to 10%
additional chartered scope, schedule, budget;
approved by -
IAOC > Sponsor > AgcyHd. >
PMD
IAOC > Sponsor > AgcyHd. >
PMD
IAOC > Sponsor > AgcyHd. >
PMDSponsor (20%)
Change Control Request required for
scope, schedule, budget baseline -
> 10% > 10% > 10% > 20%
Project Oversight Plan Required Required Required RequiredProject Planning
Transition ChecklistOptional Optional Optional Optional
PMD Decision
Brief(>10%)
PMD Decision
Brief(>10%)
Issue Mgmt.*
Issue Mgmt.*
User Acceptance
Report*
User Acceptance
Report*
Control: Execute & Control
Signed by: - User Rep. - Proj. Mgr. - Bus. Sponsor - Agcy Hd.
Project Plan Approval
Control Project (Scope
Cost Schedule)
Rebaseline** Deliver Product or
Service
Status Reports
(monthly after
Development Approval)
Status Reports
(monthly after
Development Approval)
Status Report
Change Control Request
Change Control Request
> 10%Signed by: - Proj. Mgr. - Bus. Sponsor (IAOC) - SOC (Major Proj. Only)
- CIO< 10%Signed by: - Proj. Mgr. - Bus. Sponsor (IAOC)
**Rebaseline if necessary.
NOTE: For NON-Major projects, execute & control steps described are not required, but recommended.
Additionally, NON-Major projects must submit a Change Control Request when scope, schedule or budget exceeds 20%.
*If required per Project Complexity Model.
PERIODIC IV&V *
CPGA Event-Driven
R/C Assessment
CPGA Event-Driven
R/C Assessment
PMD Decision
Brief
PMD Decision
Brief
Issue Mgmt.
Issue Mgmt.
Control: Execute & Control
Detailed Planning Approval
Control Project (Scope,
Cost, Schedule)
Rebaseline* Deliver Product or
ServiceStatus Report
Status Report
Status Report
Change Control Request
Change Control Request
*Rebaseline if necessary.
PERIODIC IV&V
Independent Agency
Oversight Committee Meetings
PMD Balanced Scorecard
PMD Balanced Scorecard
Proj. Exec. & Cntrl.
Transition Checklist
Proj. Exec. & Cntrl.
Transition Checklist
Re-determines CPGA
CategorySigned by: - Proj. Mgr. - Sponsor (IAOC) - SOC - CIO
Event-Driven IV&V
www.vita.virginia.gov
Execute & Control: Differences by CPGAT Category
Category > > > > 1 2 3 4
IAOC Project meetingsMonthly, incl.
PMDMonthly, incl.
PMDQuarterly, incl.
PMDNone;
Agcy PM Team
In-progress IV&V, scheduled to coincide with the completion of
each project phase
1 IV&V in first 6 mo.; then
annual IV&V if project > 12 mo.
duration
1 IV&V in first 6 mo.; then
annual IV&V if project > 12 mo.
duration
1 IV&V in first 6 mo.; then
annual IV&V if project > 12 mo.
duration
None
Issue LogMonthly upload Monthly upload
Upload w/ Status Report
Upload w/ Status Report
Status ReportMonthly Monthly
Start, and Quarterly
Start, and each January and
July
Status Report Assessment / Input /
Review / Approval
PM > AgcyHd > SOC > PMD >
CIO (Qtrly: SoTech)
PM > AgcyHd > SOC > PMD >
CIO (Qtrly: SoTech)
PM > AgcyHd > SOC > PMD >
CIO (Qtrly: SoTech)
PM > AgcyHd > SOC > PMD >
CIO (Qtrly: SoTech)
Change Control Request cumulative threshold; (baseline
changes approved by IAOC & Sponsor only)
10% 10% 10% 20%
www.vita.virginia.gov
Execute & Control: Differences by CPGAT Category (Cont’d.)
Category > > > > 1 2 3 4Change Control
Request required for scope, schedule, budget baseline -
> 10% > 10% > 10% > 20%
Review/Approval of Baseline change above
threshold
IAOC > SOC > CIO
IAOC > SOC > CIO
IAOC > SOC > CIO
Sponsor > AgcyHd
Balanced Scorecard for Change Control
RequestRequired Required Required
IV&V Review due to Baseline change request
above thresholdRequired Required Required Optional
CPGA Event-Driven (ED) Risk / Complexity
Assessment above threshold
Required Required Required Required
Project Execution & Control Transition
ChecklistOptional Optional Optional Optional
Control: Closeout
Product or Service
DeliveredCloseout Report
Proj. Exec. & Cntrl.
Transition Checklist
Proj. Exec. & Cntrl.
Transition Checklist
Closeout Report
Closeout Report
Category > > > > 1 2 3 4System Operation &
Maintenance documentation (budget, staffing, technology and
operational)
Required; IAOC, Sponsor & PMD
review
Required; IAOC, Sponsor & PMD
review
Required; IAOC, Sponsor & PMD
review
Required; IAOC, Sponsor & PMD
review
Project Closeout ReportRequired Required Required Required
Project Closeout Transition Checklist
Optional Optional Optional Optional
Review/Approval of Closeout Report
IAOC > Sponsor > AgcyHd >
PMD > CIO > SoTech
IAOC > Sponsor > AgcyHd > PMD > CIO
IAOC > Sponsor > AgcyHd > PMD > CIO
PM > Sponsor > AgcyHd > PMD
> CIO
Closeout IV&V