Www.senergyworld.com The Super Smart Windy Grid – The Offshore Option Presentation by Peter...
-
Upload
haley-barnett -
Category
Documents
-
view
224 -
download
4
Transcript of Www.senergyworld.com The Super Smart Windy Grid – The Offshore Option Presentation by Peter...
www.senergyworld.com
The Super Smart Windy Grid – The Offshore Option
Presentation by Peter McGarleyRenewableUK 2010
Glasgow SECC 3rd November
Senergy Econnect
• International consultants and advisors in renewable energy and grid integration
• Over 50GW of grid integration studies for wind with ~3GW projects connected
• Services include:
• Electrical engineering
• On-site generation
• Grid connection feasibility
• Grid code compliance
• Due diligences
• Commercial & regulatory
• Geophysical and geotechnical
consultancy
• Cable routing and burial protection
indices
• Consultancy
• Smartgrid products
• Electrical design
• Technical adviser
• Technical services
• Strategic services
• Foundation design,
construction and installation
assessment
EU OffshoreGrid
• PROJECT DNA• Techno-economic study
• Coordinator 3E, 8 partners, consultancy & applied research
• Budget: 1.4 million euros
• Funding: 75% from Intelligent Energy Europe (Contract IEE/08/780/SI2.528573)
• May 2009 to October 2011
Consortium Members
• CONSULTANTS
• 3E: strategy, techncial coordination, management
• Senergy Econnect: Grid design optimisation
• IEO: thorough knowledge on wind power policy
• dena: power markets and regulatory situation
• APPLIED RESEARCH
• Sintef: power market model and TradeWind experience
• Uni Oldenburg: energy meteorology
• NTUA: wind energy in the Mediterranean
• INDUSTRY ASSOCIATION
• EWEA: communication and technical review
• STAKEHOLDER INPUT / REVIEW
EU OffshoreGrid
• GENERAL OBJECTIVES• Recommendations on topology and capacity choices
• Guideline for investment decision & project execution
• Trigger a coordinated approach for the Mediterranean ring
• SPECIFIC OBJECTIVES• A selection of blueprints for an offshore grid
• Business figures for investments and return
• Insight in interaction of design drivers and techno-economic parameters
• Representative wind power time series
• Feedback from & acceptance by stakeholders
EU OffshoreGrid
• Senergy Econnect scope:
• To provide the technical design for an integrated offshore transmission network allowing connection of offshore wind and marine renewables and interconnection between the countries of the Baltic and North Seas for the purposes of arbitrage where justified
• Technical design is integrated in to a power market model of the European grid produced by SINTEF to assess power flows on offshore grid – iterative process
• To provide a cost estimate for such a network or networks
EU OffshoreGrid Reference
• Planned offshore wind and marine
CountryOffshoreGrid offshore scenario
2020 2030
Belgium 1 994 3 794
Denmark 2 329 3 799
Estonia 0 1 600
Finland 590 3 190
France 2 510 4 914
Germany 10 249 26 553
Ireland 1 055 3 780
Latvia 0 900
Lithuania 0 1 000
Netherlands 4 622 12 122
Norway 957 9 667
Poland 500 5 300
Russia 0 500
Sweden 2 983 10 522
UK 15 303 38 146
Total Northern EU 42 135 115 620
Total OffshoreGrid 43 093 125 787
EU OffshoreGrid Reference
• ENTSO-E - TYNDP
Radial Scenario
• Initial step – define radial scenario
• Each project connected radially to selected onshore connection point
• Appropriate technology solution selected based on project capacity, timing and connection distance, e.g.
• HVAC technology ineffective beyond 80km• Projects <2020 use technology commercially available today• Projects >2030 use evolved technologies
• Connection distance determined by GIS plots around subsea obstacles
Key Design Assumptions
• OffshoreGrid technology used to be evolutionary rather than revolutionary
Pre 2010 150kV HVAC 3 core subsea cable
+/- 150kV 400MW HVDC Voltage Source Converters
2010 2020 220kV HVAC 3 core subsea cable
+/-320kV 1000MW HVDC Voltage Source Converters
320kV XLPE subsea HVDC cable
2020 2030 380kV HVAC 3 core subsea cable
+/-500kV 2000MW HVDC Voltage Source Converters
500kV XLPE subsea HVDC cable
HVDC Circuit Breakers
Radial Scenario
Radial Scenario
• Statistics:
• Total Connected Capacity = 129GW
• Total Cost = €83.201bn
• €643k/MW
• Total length of cable = 31,500km
• 294 HVDC VSC converter stations
Hubs
• 1st stage of Offshore Grid
• Group projects into hubs and share export cables
• Cost effective
• Less cabling
• Fewer cables at landfall
• Risk of stranded assets
Case Study German Hubs
• Total Connected Capacity = 26.6GW• Hubs
• Total Cost = € 18,650m (€15,280m excluding onshore cables)
• €702k/MW (€575k/MW excluding onshore cables)
• Base Case Comparison• Total Cost = € 28,069m (€20,116m excluding onshore
cables)
• €1057k/MW (€758k/MW excluding onshore cables)
Meshed OffshoreGrid
• Connect +/- 320kV and +/-500kV hubs
• Defined by prototype Grids
• Justified by further need for arbitrage between countries
• Capacity for interconnection to be established from market model iterations
Meshed OffshoreGrid
• Comparison:• Look at Additional
Direct Links• Higher capital cost
• No constraint
• Key – determine balance of cost and constraint from modelling
EU OffshoreGrid Challenges
• Technical• Onshore bottlenecks• Technology e.g. different voltages used
• Market• Planning uncertainties• Risk & financing• Variable generation vs long-term contract on cable
• Regulatory• Different regulatory schemes• Slow permitting procedures• Unclear cost allocation & allowed profit margins
• Policy• Renewable energy support schemes• Political priorities
EU OffshoreGrid
• Stakeholder Meetings
• We want your input
• Held twice per year
• Next meeting:• 22nd November 2010• Berlin• See details on www.offshoregrid.eu or me afterwards
Senergy Econnect
Thank You
Peter McGarley
+44 (0)191 238 7300