www.nationalsmartcardprojec t.org.uk www.scnf.org.uk National Smartcard Project Work Package 8 – Risk Register

Transcript of Www.nationalsmartcardproject.org.uk National Smartcard Project Work Package 8 – Risk Register.

Page 1: Www.nationalsmartcardproject.org.uk  National Smartcard Project Work Package 8 – Risk Register.

www.nationalsmartcardproject.org.uk

www.scnf.org.uk

National Smartcard Project

Work Package 8 – Risk Register

Page 2: Www.nationalsmartcardproject.org.uk  National Smartcard Project Work Package 8 – Risk Register.

Risk Register

Identifies key risks particular to a Smartcard Scheme

Uses: Evaluation of a proposed Scheme Assessing potential risks Allocation of liability and risk Dealing with problems once the Scheme is live

Insurance may also be available

Page 3: Www.nationalsmartcardproject.org.uk  National Smartcard Project Work Package 8 – Risk Register.

Layout of Risk Register

Organised into nine volumes:1. Introduction

2. Development, implementation and timing: General

3. Card Infrastructure

4. Cards

5. Software Applications

6. E-money

7. Branding

8. Procurement

9. Regulatory: information law, health and safety, disability discrimination, competition, financial services

Page 4: Www.nationalsmartcardproject.org.uk  National Smartcard Project Work Package 8 – Risk Register.

How to use the Risk Register

Four columns:

1. “Types of risk”

2. “Consequences of risk”

3. “Risk apportionment”

4. “Relevant contract”

Page 5: Www.nationalsmartcardproject.org.uk  National Smartcard Project Work Package 8 – Risk Register.

“Types of risk”

Starting point is to locate the risk or event in question by referring to the relevant volume.

The “Types of risk” column sets out problem scenarios which could arise in the context of a Smartcard Scheme

Page 6: Www.nationalsmartcardproject.org.uk  National Smartcard Project Work Package 8 – Risk Register.

“Consequences of risk”

Once the type of risk has been identified, read across the Register to the “consequences of risk” column

This column sets out the potential effects of the risk or event

Does not account for unusual or unforeseen circumstances

Page 7: Www.nationalsmartcardproject.org.uk  National Smartcard Project Work Package 8 – Risk Register.

“Risk apportionment”

Who bears primary responsibility at law for the risk?

How, if at all, might the risk be mitigated?

Can responsibility be moved to a third party?

If so, who is that third party likely to be?

Is the third party likely to accept the risk?

Page 8: Www.nationalsmartcardproject.org.uk  National Smartcard Project Work Package 8 – Risk Register.

“Relevant contracts”

Identifies those contracts (if any) that may be used to effect contractual protection for the Card Issuer

The contracts are the same as those set out in more detail in the Commercial Conditions Checklist

Full list of contracts on next slide

Page 9: Www.nationalsmartcardproject.org.uk  National Smartcard Project Work Package 8 – Risk Register.

“Relevant contracts”

i. Card Issuer / Card Supplier

ii. Card Issuer / Technology Supplier

iii. Card Issuer / Secondary Service Provider

iv. Card Issuer / brand or design advisor

v. Card Issuer / Card Issuer

vi. Card Issuer / Project Manager

vii. Card Issuer / Technical Administrator

viii. Card Issuer / Scheme Administrator

ix. Card Issuer / Card User

x. Secondary Service Provider / Card User