WP8 - Project Management
description
Transcript of WP8 - Project Management
1
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
WP8 - Project Management
• 2nd Cost Statement– Bank transfers processed on September 6th
– TECNO “virtual” debit apportionment
• Final Cost Statement– Final Cost statement simulation
– Read carefully EC comments to the 2nd Cost Statement
2
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
WP8 – 2nd Cost StatementVirtual payment Debit compensation Amount to be paid
UGDIE 29,705.90 -95.14 29,610.76
SCIRO 108,709.60 -348.15 108,361.45
IVU 103,789.29 -332.40 103,456.89
EDC 23,494.48 -75.24 23,419.24
NTUA 60,874.28 -194.96 60,679.32
SIGMA 14,490.62 -46.41 14,444.21
CP 11,006.95 -35.25 10,971.70
PI 12,393.72 -39.69 12,354.03
TECNO -1,167.24 1,167.24 0.00
TOTAL 363,297.60 0.00 363,297.60
On the occasion of the final payment the amount anticipated by the Partners will be deducted from
the payment of TECNO and redistributed
3
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
WP8 – Payment summary
Ceiling (85%) = 54,435 • 0.85 46,269 Euro
Delta with respect to the ceiling 1,167 Euro
Maximum EC Protection of co-financing knowledge (50%)
UGDIE 116,354.39 138,218.00 0.00 21,863.61
SCIRO 320,826.44 389,393.00 3,900.00 64,666.56
IVU 204,666.89 247,458.00 3,895.50 38,895.61
EDC 68,808.35 99,672.00 4,000.00 26,863.65
NTUA 186,677.82 246,356.00 0.00 59,678.18
SIGMA 59,853.41 80,000.00 0.00 20,146.59
CP 51,044.82 66,289.00 0.00 15,244.18
PI 52,139.43 78,180.00 0.00 26,040.57
TECNO 47,436.99 54,435.00 0.00 6,998.01
1,400,001.00TOTAL 1,107,808.54
Organisation Received
11,795.50
Available
280,396.96
It represents the amount of money still available for each Partner on the occasion of the Final Payment (budget foreseen
for Protection of knowledge have been deducted)
Such data represent the amount of money a Partner would receive on the occasion of the Final Payment, should have he claimed, for instance, costs coincident with the budget and
should have the EC judged all those costs eligible
It’s included the amount of money anticipated to cover the debit of TECNO on the occasion of the payment of the 2nd CS
4
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
WP8 – Deadlines for the Final CS
• Preparation of Excel effort tables covering July-September within October 15th
• Preparation of the first draft of the Final CS within October 29th and submission to the Coordinator for a preliminary feedback
• Preparation of the official Final CS within November 12th
Please fulfil the deadlines as 8-12 months are usually needed for the EC payment
5
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
• Report man-hours fully compliant with the quarterly effort tables (01 October 2003 – 30 September 2004)
• Claim co-financing for Travel and Subsistence• Claim depreciation for Durable equipment (12 months)• Claim co-financing for Other specific costs• Provide invoices for the purchase of new equipment
(OBTs and sensors), or suitable documentation for other costs (communication, …)
• Take carefully into account the official feedback of the EC to the 2nd CS, providing the required documentation
WP8 – Filling the Final CS
6
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
WP8 – Filling the CS forms (details)COST STATEMENT: Details by Category (euro/ currency)
for the period from 01/10/03 to 30/09/04 Cost basis1: FC
Project Title: F-MANContract No: IST-2000-29542Name of principal contractor / assistant contractor 2: Università degli Studi di GenovaCurrency (euro/currency) in which account is kept: Euro
(reporting period No 3 )
We certify that- the above costs are derived from the resources employed which were necessary for the work under the contract,- such costs have been incurred and fall within the definition of eligible costs specified in the contract,- any necessary permissions of the Commission have been obtained, and- full supporting documentation to justify the costs hereby declared, including time sheets as referred to in Article 23(1)(a), third subparagraph of Annex II to the contract, is available for audit by the Commission and its authorised representatives or the Court of Auditors and reflects the costs actually incurred.
We certify that any necessary adjustments, for any reason, to costs reported in previous cost statements have been incorporated in the above statement6.
Date: xx/10/2004 Date: xx/10/2004
Name of person in charge of the work: Name of duly authorised responsible Financial Officer:
Stefano Savio Maurizio Mazzucchelli
Please update
Please check the names
7
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
WP8 – Filling the CS forms (details)TRAVEL AND SUBSISTENCE
Coo3 Name4 Destination Purpose of Travel Amount12
(City, Country)Stefano Savio Brussels Belgium 1st Annual Review 21 October 2002Stefano Savio Berlin Germany Project meeting 23-24 J anuary 2003
Marco Giannettoni Berlin Germany Project meeting 23-24 J anuary 2003Marco Giannettoni Crete Greece Project meeting 10-11 April 2003
Total
OTHER SPECIFIC COSTS
Coo3 Description and supplier name if applicable Amount12
Total
Organisation of the Project Board Meeting held in Genoa on 17-18 J uly 2003 (Capurro Ricevimenti s.a.s.)
Please insert official dates only
Please insert all available details
8
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
Cost Figure Accepted Budget Final CS forecast Difference
Personnel 361679.08 473592.00 111467.12 445.80
Overheads 96304.27 126112.00 29678.29 129.44
Travel 17536.95 18100.00 5171.52 -4608.47
Subcontracting 89860.67 120000.00 32669.92 -2530.59
Equipment 5562.64 7609.00 2781.12 -734.76
Other costs 0.00 25575.00 18055.84 7519.16
TOTAL 570943.61 770988.00 199823.81 220.58
Final CS forecast - SCIRO
Perfect – Just an internal shift required
9
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
Final CS forecast - IVU
Cost Figure Accepted Budget Final CS forecast Difference
Personnel 188646.30 242044.00 60574.50 -7176.80
Overheads 154703.70 198469.00 49675.50 -5910.20
Travel 11893.08 26720.00 3887.46 10939.46
Subcontracting 0.00 0.00 0.00 0.00
Equipment 157.45 2292.00 314.91 1819.64
Other costs 4368.00 17600.00 12010.74 1221.26
TOTAL 359768.53 487125.00 126463.11 893.36
Perfect – Just an internal shift required
10
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
Final CS forecast - EDC
Cost Figure Accepted Budget Final CS forecast Difference
Personnel 52075.72 80299.00 44150.84 -15927.56
Overheads 41660.58 64239.00 35320.67 -12742.25
Travel 3756.54 14807.00 2160.79 8889.67
Subcontracting 0.00 0.00 0.00 0.00
Equipment 0.00 0.00 0.00 0.00
Other costs 762.25 32000.00 11446.69 19791.06
TOTAL 98255.09 191345.00 93078.99 10.92
Perfect - an internal shift required
11
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
Final CS forecast - NTUA
Cost Figure Accepted Budget Final CS forecast Difference
Personnel 104413.83 169254.00 74000.00 -9159.83
Overheads 24536.32 41060.00 16040.00 483.68
Travel 18267.82 36042.00 6200.00 11574.18
Subcontracting 0.00 0.00 0.00 0.00
Equipment 0.00 0.00 0.00 0.00
Other costs 0.00 0.00 0.00 0.00
TOTAL 147217.97 246356.00 96240.00 2898.03
Perfect - an internal shift required
12
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
Final CS forecast - SIGMA
Cost Figure Accepted Budget Final CS forecast Difference
Personnel 88361.00 142229.00 62409.60 -8541.60
Overheads 0.00 0.00 0.00 0.00
Travel 4638.39 17771.00 3532.00 9600.61
Subcontracting 0.00 0.00 0.00 0.00
Equipment 0.00 0.00 0.00 0.00
Other costs 0.00 0.00 0.00 0.00
TOTAL 92999.39 160000.00 65941.60 1059.01
Perfect – Just an internal shift required
13
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
Final CS forecast - CP
14
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
Final CS forecast - PI
Cost Figure Accepted Budget Final CS forecast Difference
Personnel 34884.04 64117.00 34935.00 -5702.04
Overheads 27856.40 51294.00 27928.00 -4490.40
Travel 11382.92 21533.00 6360.00 3790.08
Subcontracting 0.00 0.00 0.00 0.00
Equipment 2010.91 3917.00 1020.28 885.81
Other costs 0.00 15500.00 9357.00 6143.00
TOTAL 76134.27 156361.00 79600.28 626.45
Perfect – Just an internal shift required
15
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
Final CS forecast - UGDIECost Figure Accepted Budget Final CS forecast Difference
Personnel 147335.96 172918.00 50385.00 -24802.96
Overheads 40923.65 67901.00 12241.00 14736.35
Travel 12644.88 28750.00 7000.00 9105.12
Subcontracting 0.00 0.00 0.00 0.00
Equipment 3477.74 4785.00 1738.00 -430.74
Other costs 552.00 2082.00 0.00 1530.00
TOTAL 204934.23 276436.00 71364.00 137.77
Perfect – Just an internal shift required
16
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
UGDIE 276436.00 276298.23 137.77
SCIRO 770988.00 770767.42 220.58
IVU 487125.00 486231.64 893.36
EDC 191345.00 191334.08 10.92
NTUA 246356.00 243457.97 2898.03
SIGMA 160000.00 158940.99 1059.01
CP 132579.00 132579.00 0.00
PI 156361.00 155734.55 626.45
TOTAL 2421190.00 2415343.88 5846.12
Partner Budget Claimed Saving
Project Coordination (Oct - Nov 2004)
Coordination activities to be completed after 30/09/2004:
Issue of Deliverable D16 – Final report Management of Final Cost Statement process Issue of 3rd Progress Report Preparation of the on-site Final Review
17
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
WP8 – Reporting
• Management Reporting– 11th QMR submitted on 28 July 2004
– 3rd Progress Report to be issued on the occasion of the Final CS
• Deliverables submission– Deliverable D10 submitted on 28 July 2004 (available on the Web)
– Deliverable D15 (e-TIP) submitted on 14 September 2004
– Deliverables D11.2 and D13 to be submitted within 8 October 2004
– Deliverable D16 to be submitted within 8 November 2004
18
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
WP8 - Project deadlines
WP5 completion – Deliverable D11.2 on 08 October 2004
Project completion – Deliverable D16 – Milestone M5 on 08 November 2004
WP6 completion – Deliverable D13 on 08 October 2004
WP7 completion on 30 September 2004 (Deliverable D15 on 14 September 2004)
19
UGDIE
PROJECT MEETINGAthens – 23-25 September 2004
Mandatory deadlines
Document Issuer Draft version Final issue
D11.2 – Verification report CP September, 20th October, 8th
D13 – Evaluation results UGDIE September, 20th October, 8th
D16 – Final report SCIRO October, 15th November, 8th
Effort tables (07/04 – 09/04) All – October, 15th
Final Cost Statement All October, 29th November, 12th