WP3 Report

7
Telefónica Móviles España WP3 Report 2.5 -3G Communication Infrastructure February 02 - April 03

description

WP3 Report. 2.5 -3G Communication Infrastructure February 02 - April 03. Telefónica Móviles España. Communication infrastructure: Installation and configuration of the BE systems in TME, Telia and UT Configuration of secure connections with the technical support staff and the hospitals - PowerPoint PPT Presentation

Transcript of WP3 Report

Page 1: WP3 Report

Telefónica Móviles España

WP3 Report2.5 -3G Communication

InfrastructureFebruary 02 - April 03

Page 2: WP3 Report

2

Activities and Results• Communication infrastructure:

– Installation and configuration of the BE systems in TME, Telia and UT

– Configuration of secure connections with the technical support staff and the hospitals

– Tests of the system with the trial owners

– Analysis of the measurement strategy

• Security:– Development and tests of security mechanisms

– Integration of the security mechanisms in the BE systems

• Collaboration with:– WP1 and WP5: Technical evaluation of the trials

– WP2: Integration of the BAN into the communication infrastructure

• Deliverable D3.1: ”Trial ready GPRS and UMTS networks”

• First draft of Deliverable D3.2: “MobiHealth system”

• Weekly WP3 e-meetings of follow-up

Page 3: WP3 Report

3

Future work• Communication architecture:

– Providing technical support and maintenance before and during the trials

– Implementation of the measurement strategy

– UMTS testbeds

• Collaboration with:

– WP2: Configuration of BAN for the trials

Security mechanisms

– WP4: Ready GPRS and UMTS networks for and during the trials.

– WP5: Technical evaluation of the trials

Measurement strategy

• Deliverable D3.2: ”MobiHeatlh System”

• Dissemination activities: Update WP3 section in MobiHealth website

Page 4: WP3 Report

4

Resources used and planned resources usage

Ericsson GSCOUT Telia LTU UT TMSI Yucat TME UPF CMG

4 4 5 4 6 3 1 10 4 5

WP3: 2.5 - 3G COMMUNICATION INFRASTRUCTURE

PROJECT PLANNED MAN-MONTHS (IN CONTRACT)

Resources used (man hours)May 02 - October 02

18570

150256

375

48113

286

653

Ericss

on

GSCOUTTe

lia LTU UT

Yucat

TME

UPFCM

G

Resources used (man hours)November 02 - April 03

120 90

320443

756

232? 325 ? ?

Erics

son

GSCOUTTe

liaLT

U UTTM

SI

Yucat

TME

UPFCMG

Page 5: WP3 Report

5

Critical issues

• UMTS testbeds:

– Possible testsbeds in different areas of the trial sites

– Available functionalities?

– Use of prototype UMTS terminals

• Technical support and maintenance of the

communication infrastructure is required during the

trials:

– Time extension of WP3

– Task in WP4

Page 6: WP3 Report

6

Activity Planning

• Deployment of security mechanisms End of

May 2003

• Sending of Deliverable D3.2 to EC June 2003

• Implementation of the measurement strategy

During the trials

• Technical support before (and during) the trials

Page 7: WP3 Report