Progress report from ALICE ITS3 WP3 -4-5

17
Progress report from ALICE ITS3 WP3-4-5 Giacomo Contin Università di Trieste and INFN Sezione di Trieste EIC Silicon Consortium meeting – July 26 th 2021

Transcript of Progress report from ALICE ITS3 WP3 -4-5

Page 1: Progress report from ALICE ITS3 WP3 -4-5

Progress report from ALICE ITS3 WP3-4-5

Giacomo ContinUniversità di Trieste and INFN Sezione di Trieste

EIC Silicon Consortium meeting – July 26th 2021

Page 2: Progress report from ALICE ITS3 WP3 -4-5

Main ongoing activities within ITS3 WP3-4-5

• MLR1 Testing campaign plans• ALPIDE-based DUT Testbeams• Larger-size chip Thinning,

Bending and Interconnections• Mechanics development

2021-07-26 ITS3 Update @ EICSC - [email protected] 2

Page 3: Progress report from ALICE ITS3 WP3 -4-5

MLR1 testing plans• Test system components under production

• First batch of boards ready between now and end of August• Firmware/software being finalized

• MLR1 wafers ready• Dicing is ongoing• Picking will follow• Wire-bonding of samples planned

• Process under study on pad wafers• Chip distribution is under discussion

• First samples to institutes involved in silicon and test system design• After first feedback, larger distribution of samples

• Plans:• Start MLR1 lab testing as soon as chips and test systems are available• Irradiation of MLR1 chips • Beam test of MLR1:

• 18 Oct - 6 Nov @ PS• 10 - 15 November @ SPS• 29 Nov - 6 Dec @ DESY

2021-07-26 ITS3 Update @ EICSC - [email protected] 3

Page 4: Progress report from ALICE ITS3 WP3 -4-5

Bent MLR1 testing plans

2021-07-26 ITS3 Update @ EICSC - [email protected] 4

Original single TS carrier

Large chip including multiple TSs

Wire bonding 1• Surface mounted curved base• Board traces re-routed• Long wires

Wire bonding 2• Curved base underneath board• Shorter wires

SpTAB bonding• Surfaced mounted curved base• Microcable re-routing the lines

Bend and characterize test structures• Bend a large area (3.2 x 2.4 cm2) chip• Adhesive tape and/or kapton layer• Detailed curvature measurement of 1.5 x 1.5 mm2 TS

Page 5: Progress report from ALICE ITS3 WP3 -4-5

Bent ALPIDE-based DUT testbeams

23-07-2021

PreliminaryFrancesca Carnesecchi,Lukas Lautner,Manuel ColocciWP3 @ ITS3 Plenary

WP3 meeting – Sergey Senyukov

2021-07-26 5ITS3 Update @ EICSC - [email protected]

Page 6: Progress report from ALICE ITS3 WP3 -4-5

SPS July 2021

6

µITS with 6 chipsµITS with 6 chips+ Cu target

Chip tested in Dec 2020 new orientation

W-shaped chipFlat chip

WP3 meeting – Sergey Senyukov

2021-07-26 ITS3 Update @ EICSC - [email protected]

Page 7: Progress report from ALICE ITS3 WP3 -4-5

Large-size chip bending and interconnectionsALPIDE Super-chips• Idea: cut out large “super chips” from a wafer• about the area of 1/2 ITS3 half-layer 0

• ~140 x 60 mm• 9 x 2 chips

• 9 interconnection areas in z-direction• need individual connections:

• no interconnections on wafer-level• SpTAB or wire-bonding

2021-07-26 ITS3 Update @ EICSC - [email protected] 7

Page 8: Progress report from ALICE ITS3 WP3 -4-5

• Dummy-super-ALPIDE (using mini-pad)• Exoskeleton• Exo-FPC• Wire-bonding

2021-07-26 ITS3 Update @ EICSC - [email protected] 8

Super-ALPIDE mock-up assembly

ITS3 WP4 meeting - Domenico Colella

Page 9: Progress report from ALICE ITS3 WP3 -4-5

Super-ALPIDE mock-up assemblyR&D on:• Handling and bending large area chip• Gluing procedure FPC on exoskeleton• Wire-bonding in complex and curved geometry

2021-07-26 ITS3 Update @ EICSC - [email protected] 9

ITS3 WP4 meeting - Domenico Colella

Page 10: Progress report from ALICE ITS3 WP3 -4-5

Super-ALPIDE Edge-FPC• First prototype of the final front-edge ITS3 interconnections – in production

2021-07-26 ITS3 Update @ EICSC - [email protected] 10

ITS3 WP4 meeting - Domenico Colella

Page 11: Progress report from ALICE ITS3 WP3 -4-5

ALICE ITS3 WP5Super-ALPIDE: MuLtiPourpose JIG design compatibility

CAD scheme with super-ALPIDE chip

138.2mm

Super-ALPIDE

S-Alpide : jig for bending/ foam gluing/ wire bonding…compatibility

FPC (temporary approach)

@INFN BARI

DESIGN provided by INFN Bari:Compatibility verified

Full size jig design developed Reduced size jig (S-Alpide) on going

Jig production next

with Bending and Foam gluing

11

ITS3 WP5 meeting – Massimo Angeletti

2021-07-26 ITS3 Update @ EICSC - [email protected]

Page 12: Progress report from ALICE ITS3 WP3 -4-5

ALICE ITS3 WP5EM1: Chip held in position by Kapton mask

Carbon foam

Impregnated fleece Siliconkapton

HLS equipped with edge Kapton tape that after bending hold the chip in position 12

ITS3 WP5 meeting – Massimo Angeletti

2021-07-26 ITS3 Update @ EICSC - [email protected]

Page 13: Progress report from ALICE ITS3 WP3 -4-5

ALICE ITS3 WP5MultiPurpose JIG , Full size Design HOLDING IN POSITION

Kapton tape

Or vacuum mandrel

JIG design for full size chip 13

ITS3 WP5 meeting – Massimo Angeletti

chip

mylar foil

2021-07-26 ITS3 Update @ EICSC - [email protected]

Page 14: Progress report from ALICE ITS3 WP3 -4-5

ALICE ITS3 WP5

HLS Full scale mandrels in productionAssembly EM2 (Silicon) and Super-ALPIDEAim EM2: Verify the obtained assembly precision using mandrels and carbon foam supports with quality similar to the final ones

EM2: Chip held in position by Kapton mask

14

Large bending test with Kapton

Carbon foam

Impregnated fleece

SiliconKapton

3-4mm

D 40mm

@CERN, P. Ijzermans

Silicon 40 µm

ITS3 WP5 meeting – Massimo Angeletti

2021-07-26 ITS3 Update @ EICSC - [email protected]

Page 15: Progress report from ALICE ITS3 WP3 -4-5

Plans for the upcoming weeks

• Testing and characterization• Continue analysis of bent ALPIDEs beam test. Paper in preparation.• Start MLR1 testing in lab and beam

• Thinning, bending and interconnections• Super-ALPIDE wire-bonding: exoskeleton and edge-FPC• SpTAB bonding• Mechanical characterization of bent structures

• Mechanics• FOAM/glue characterization• Vacuum mandrel development

2021-07-26 ITS3 Update @ EICSC - [email protected] 15

Page 16: Progress report from ALICE ITS3 WP3 -4-5

Backup

2021-07-26 ITS3 Update @ EICSC - [email protected] 16

Page 17: Progress report from ALICE ITS3 WP3 -4-5

17

ALPIDE chips and superchips testing

~1 year toprepare the next

test system

<6 months forMLR1 test system

~2 years for the “final” test system

MLR1testing ER1 testing

Full-scale chip testing Final chip testing

* Testing periods are approximate

ITS3 project timeline: testing

2021-07-26 ITS3 Update @ EICSC - [email protected]