WorkPlan Improve Postharvest Practices on Vegetables in Cambodia EM HUY Deputy chief MSc....

9
WorkPlan Improve Postharvest Practices on Vegetables in Cambodia EM HUY Deputy chief MSc. Agricultural Resources and Economic Consultancy experiences: ADB project: National Postharvest/Marketing Specialist WB Project: National Rural Livelihood Specialist

Transcript of WorkPlan Improve Postharvest Practices on Vegetables in Cambodia EM HUY Deputy chief MSc....

WorkPlan

Improve Postharvest Practices on Vegetables in Cambodia

EM HUYDeputy chief

MSc. Agricultural Resources and Economic

Consultancy experiences: ADB project: National Postharvest/Marketing Specialist

WB Project: National Rural Livelihood Specialist

Rationale

Why need to promote best postharvest practices ?

• Status of current mis-practices of postharvest • Severe situation of Fresh produces being

contaminated,• Situation that consumers pay for unwanted

hazards coming along with fresh produces purchased.

Objectives

• To promote best postharvest practices to producers and marketers,

• To help improve safety and quality of vegetables for consumption,

• To help gain more value added from fresh produces marketed

Expected Outputs

Progress indicators

Activities Timetable/duration

Inputs/Resources

Budget Responsible Persons

At least 10 farmers and 10 marketers apply the knowledge transferred

- 100 copies of Postharvest Practice manual

- 30 vegetable farmers and 20 marketers

-Permission from Dept - Design the training modules of postharvest

Practice, - Get the training manual

copied- Select target locationsand places for training(Svay BraTeal and KienSvay, Kandal province)- Mobile trainees - Print out trainingmaterials, posters, and

postcards

15 July – 30 August, 2012

- PC, printer,motorcar/car - Two support staffs

1400 (for only gasoline and copy)

Em Huy

- 2 trainings (50 trainees)- 25 trainees for each

training

- Provide training to the selected trainees

2 days (two times) in September, 2012

- Motorcare/car- Papers, notebook,pens, pencils, markers, flipcharts, trainee bags, PC, printer, LCD projector, snack, and

lunch, - Two support staffs

850$ (PC, printer, LCD projector excluded)

Em Huy

Result and Report

- 2 times of follow-up- 1 report - Follow-up

- Make a final reportSeptember to October, 2012

motorcar/car, PC, printer, papers, camera

100$ (for only gasoline)

Em Huy

Total estimated budget (USD) 2,350.00