Wind farm Baku
Transcript of Wind farm Baku
2009 1
Wind farm Baku
50 Megawatts renewable energy
in co-operation of
2009 2
Project scope
• Turn key delivery of 50 MW Wind farm – 20x 2,5 MW Wind energy converter (WEC) up to 80m hub height
– Project will involve:
• Finance structuring
• Design
• Procurement
• Construction
• Commissioning
• Training of customers employees
• Logistics / DDU
• Management (Project, Quality, Construction)
– Project duration: 16 months (Sept. 09 – Dec.10; dependent of L/C)
2009 3
Project stakeholders
Turn key delivery of 50 MW Wind farm
The project will involve
– financing by two European banks with the support and warranty of
International Bank of Azerbaijan
– an innovative financing structure developed by Mitaki project GmbH
Hamburg (Germany) with great support of the federal Republic of
Germany which grants an export credit insurance through its state-owned
insurance agency Euler Hermes Kreditversicherung
– approximately 15 German and European companies for engineering,
design, logistics and manufacturing of equipment as well as 10 Azeri
companies for construction works, local logistics and management under
the leadership of the general supplier airwerk GmbH, Essen (Germany)
2009 4
Organizational structure
Financing
Consulting
Legal advice
Airwerk: System responsible
engineering
logistics
Key partner
WECTrans-former
Tower Construction others
Customer: Caspian Management System & Aztorq
Owner Operation Maintenance Energy supply
2009 5
General information
Location of pilot
Wind farm
Wind energy potential in the Absheron economical region about 1000 Megawatts
2009 6
Location „Yeni Yashma“
Highway
Sumgayit
WEC
Co ordinates of land boundary
1
2
3
2009 7
Scope & Interfaces pilot wind farm “Yeni
Yashma”
transformer
transformer
transformer
transformer
public
Electrical network
Main Power line: 110 kV
Connection cabling
Approx. 200 m
690 V
Low voltage
20 kV medium voltage level
Redundant 31,5 MVA
Transformer station
Hand over / Connection to
public electrical network
provision
by purchaser
deliverables
supplier
Internal park communication
ISDN
Public telephone
network
Modem
50MW: 20x 2,5 MW WEC
2009 8
2009 9
Turbine production
2009 10
Transport of blades
2009 11
Hub with blades
2009 12
Hub with blades
2009 13
Future view “Yeni Yashma”
2009 14
Future view “Yeni Yashma”
2009 15
Thank you
2009 16
1:Location „Yeni Yashma“ North View
2009 17
2: Location „Yeni Yashma“ canal
2009 18
3:Location „Yeni Yashma“ East View