West Virginia Department of Education Office ... - sba.wv.gov

33
Executive Summary Page 1 of 1 West Virginia Department of Education Office of School Operations & Finance – School Facilities Introduction: The McDowell County Board of Education requests approval of an amendment to their current 2020-2030 Comprehensive Educational Facilities Plan (CEFP). Changes: The McDowell County Board of Education requests approval to change how Sandy River Middle School is classified in the 2020-2030 CEFP. In the current version, Sandy River is slated for closure by 2026, with the students being moved into River View HS as a consolidated 6-12 school. This amendment is to reclassify Sandy River Middle as a relocation, with the school being moved and operated distinctly as a 6-8 school at the existing River View High School facility. River View High School will continue to serve grades 9-12 and these two schools would operate with autonomous administrations. This amendment also moves the date of this action to the conclusion of the 2020-2021 school year. Once Sandy River Middle School is relocated to River View High School campus, the remaining building will first be offered for auction and if there is no successful purchaser, McDowell County Schools may donate the building to a community based nonprofit organization. If the building is not auctioned or donated to a 501-c3 organization, then the building will be slated for demolition. Impact: This change will allow the middle school students to have access to courses that are not currently available, access to mentoring and extensive counseling and limited transitioning from middle school to high school because of no campus change. The students would also have access to improved athletic facilities. The budget would be positively impacted by a yearly cost savings of $424,474.54.

Transcript of West Virginia Department of Education Office ... - sba.wv.gov

Page 1: West Virginia Department of Education Office ... - sba.wv.gov

Executive Summary

Page 1 of 1

West Virginia Department of Education Office of School Operations & Finance – School Facilities

Introduction: The McDowell County Board of Education requests approval of an amendment to their current 2020-2030 Comprehensive Educational Facilities Plan (CEFP). Changes: The McDowell County Board of Education requests approval to change how Sandy River Middle School is classified in the 2020-2030 CEFP. In the current version, Sandy River is slated for closure by 2026, with the students being moved into River View HS as a consolidated 6-12 school. This amendment is to reclassify Sandy River Middle as a relocation, with the school being moved and operated distinctly as a 6-8 school at the existing River View High School facility. River View High School will continue to serve grades 9-12 and these two schools would operate with autonomous administrations. This amendment also moves the date of this action to the conclusion of the 2020-2021 school year. Once Sandy River Middle School is relocated to River View High School campus, the remaining building will first be offered for auction and if there is no successful purchaser, McDowell County Schools may donate the building to a community based nonprofit organization. If the building is not auctioned or donated to a 501-c3 organization, then the building will be slated for demolition.

Impact: This change will allow the middle school students to have access to courses that are not

currently available, access to mentoring and extensive counseling and limited transitioning from middle

school to high school because of no campus change. The students would also have access to improved

athletic facilities. The budget would be positively impacted by a yearly cost savings of $424,474.54.

Page 2: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.021 Application for Amendment[McDowell County Schools]100.021 CEFP APPLICATION FOR AMENDMENTInstructions: Please provide details regarding the request for amendment for any part of the CEFP.COUNTY McDowellDATE 2/18/2021AMENDMENT TYPE OVERALL PLANAMENDMENT # 1DATE AMENDMENT APPROVED BY LEASIGNATURE-COUNTY SUPERINTENDENT See last page for signed letter.

Briefly describe the nature of the amendment and/or scope of work to be completed:This amendment is to change how Sandy River Middle School is classified in the 2020-2030 CEFP. Inthe current version, Sandy River is slated for closure by 2026, with the students being moved intoRiver View HS as a consolidated 6-12 school. This amendment is to reclassify Sandy River Middle as arelocation, with the school being operated separately as a 6-8 school at the existing River View HighSchool, that will continue to serve grades 9-12. These two schools would operate independently, withtwo administrations and separate reporting functions. This amendment also moves the date of thisaction to the conclusion of the 2020-2021 school year.Once Sandy River Middle School is relocated to River View High School campus, the remainingbuilding will first be offered for auction and if there is no successful purchaser, McDowell CountySchools may donate the building to a community based nonprofit organization. If the building is notauctioned or donated to a 501-c3 organization, then the building will be slated for demolition.

A. BUDGET AMENDMENTS FOR PREVIOUSLY APPROVED PROJECT WITHIN THE CURRENT CEFPInclude a revised CEFP finance plan summary sheet and any other altered CEFP pages with revision dateas per Section E to specifically reflect the project expenditures requested in this amendment. Brieflydescribe the need to adjust the present budget.BUDGET ITEM BUDGET AMOUNTTOTAL PROJECT BUDGET APPROVED BY CEFP $No Change to Finance Plan*A. SBA GRANTB. OTHER (DESCRIBE) $$AMENDMENT TO THIS PROJECT BUDGET(+/-) $No Change to Finance Plan*A. SBA GRANTB. OTHER (DESCRIBE) $$TOTAL PROJECT AMOUNT IF AMENDMENT APPROVED $No Change to Finance Plan*

Page 3: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.021 Application for Amendment

* There will be no need to adjust the present budget in the CEFP, as no new costs will be incurred bymoving the Sandy River Middle School campus.B. AMENDMENT TO EXISTING OR NEW PROJECT (Complete information on additionalpages if 2, 3, or 4 are checked below)REVISE THE SCOPE OF AN EXISTING PROJECT X

ADD A NEW PROJECT NOT CURRENTLY IN CEFP ☐

NEW ADDITION OR RENOVATION PROJECT ☐

TECHNOLOGY AND/OR BLDG. INFRASTRUCTURE IMPROVEMENTS ☐

Provide a revised budget in Part A for the project(s) affected by this amendment. Also, providereplacement sheets for the current approved plan on file in the SBA and WVDE offices for all chapters ofthe plan affected by the amendment. Include revision dates on all replacement sheets as per Section E.There will be no need to adjust the present budget in the CEFP, as no new costs will be incurred bymoving the Sandy River Middle School campus.C. OVERALL PLAN AMENDMENT (Complete Information on additional pages)Amendments to the overall plan are defined as those changes that alter the educational delivery models(grade configuration, delivery system, etc.) or dramatically affect the major elements of the CEFPidentified in WVBE 6200, Chapter 1, Handbook on Planning Schools or Goals and Objectives of the SBA(West Virginia Code §18-9D-15). Provide replacement sheets for the current approved plan on file in theSBA and WVDE offices for all chapters of the plan affected by the amendment, including revisions dateson all replacement sheets as per Section E.The relocation of Sandy River Middle School will not alter the educational delivery models ordramatically affect the major elements of the CEFP. Sandy River Middle will still operate separately asa 6-8 school at the existing River View High School that will continue to serve grades 9-12.D. AMENDMENT JUSTIFICATION AS REQUIRED IN WEST VIRGINIA CODE §18-9D-15(Attachment additional backup information, if required)1. Describe how the amendment alters the current ten-year comprehensive educational facilities plan,project, finance plan, and changes in the scope of the project.This amendment changes the time line of relocating of the Sandy River students to the River ViewHigh School Campus to the end of the 2020/2021 school year.2. Provide the impact of this amendment upon the educational opportunities of students and thebudget of the LEA.The impact on educational opportunities will be access to courses that are not currently available,access to mentoring and extensive counseling and limited transitioning from middle school to high

Page 4: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.021 Application for Amendmentschool because of no campus change. The students would also have access to improved athleticfacilities.The budget would be positively impacted by the total cost savings of $424,474.54. Those savings arebroken down as follows: Utilities $133,777.36, Personnel $98,790.00, Maintenance $131,249.03, andTransportation $60,658.15.

3. Describe how the existing facility plan does not and the proposed amendment does meet thefollowing goals of the SBA as described in WV Code §18-9D-16:

a. Student health and safety including, but not limited to, critical health and safety needsRiver View High School has a Tug River Health Clinic on site that provides services to RHVS students.Sandy River Middle School will have daily access to the clinic when it is relocated to the RHVS campus.Transfer buses will no longer be needed, making transportation time shorter and safer. The SandyRiver Middle School campus has a water treatment plant that is need of costly upgrades to continueproviding safe drinking water to students. Relocating them to the RVHS campus reduces the need foron-going boil water advisories.

b. Economies of Scale, including compatibility with similar schools that have achieved the mosteconomical organization, facility use, and pupil-teacher ratiosMoving the Sandy River Middle School campus into the River View High School campus will improveeconomies of scale and building program capacity. Teacher pupil-ratios will not change; however,both River View High School and Sandy River Middle School will benefit from being able to shareresources and arts certified staff.

c. Reasonable Travel Time and practical means of addressing other demographic considerationsTravel time will be reduced for many of the Sandy River Middle School Students living near theBradshaw area. Travel time will remain the same for others due to not having to unload/load transferbuses at the middle school campus. The travel time will also be reduced for the River View HighSchool students riding transfer buses.

d. Multi-County and regional planning to achieve the most effective and efficient instructionaldelivery systemGiven the location of the two schools, multi-county and regional planning cannot be considered.

e. Curriculum improvements and diversification, including the use of instructional technology,distance learning and access to advanced courses in science, mathematics, language arts, and socialstudiesSandy River Middle School students will have access to courses that are not currently available.Opportunities will exist for early enrollment into our RVHS CTE programs.

f. Innovations in Education

Page 5: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.021 Application for AmendmentHaving Sandy River Middle School on the high school campuses increases opportunities for innovationthrough an increase in the availability of funds by operating buildings at a desirable program capacity.These funds may be used to create STEAM labs and other innovations such as virtual reality and cloudcomputing.

g. Adequate Space for projected student enrollmentsThe RVHS campus and SRMS campus have low program utilization. River View High School’s programutilization is currently 39% resulting in ample space for the relocation of SRMS into one section of theRVHS campus, thus improving program capacity. The following table breaks down River View HighSchool’s program utilization:

Number Of Maximum Pupils/ Total ProgramClassroom Types Classroom Types x Class Capacity = Capacity

General PurposeClassrooms

24 25 600

Science Classrooms 5 25 125

Driver’s Ed 1 25 25

Computer Lab 1 20 20

Art 1 25 25

Music 1 40 40CTE 2 20 40P.E. 1 70 70

P.E. Aux Gym 1 50 50Sp. Ed. Self-Contained 2 12 24

Sp. Ed. 5 10 50TOTALS: 35 1069

Program Utilization = _______415__________ divided by _________1069__________ =Current Enrollment Total Program Capacity

PROGRAM UTILIZATION = 39% Desirable Program Capacity = 85%

Sandy River Middle School’s current enrollment is 261 students and their five year projectedenrollment is 225. Combined enrollment based on current enrollment numbers will be 676 students.The 5th year projected combined enrollment will 716. Using the projected enrollment numbers of716, the program capacity will be 67% with both schools on the RVHS campus.

h. The history of efforts taken by the LEA to propose or adopt local school bond issues or speciallevies to the extent constitutionally permissible

Page 6: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.021 Application for AmendmentMcDowell County voters have approved the continuation of our excess levy since 1942. Up until thespring of 2019, the county had met and often exceeded its levy call. With the continued decline inthe coal mining industry, for the first time, 2020 tax revenues were unable to sustain the levy call,leaving a gap in the educational needs of the county. With our current economy, tax revenuescontinue to decline in the current year, leaving no hope that our economy can sustain the currentlevy or any type of bond.

i. Regularly scheduled preventive maintenancePreventative maintenance efforts will be improved through the elimination of the SRMS campus.

j. How the project will assure the prudent and resourceful expenditure of state funds andachieve the purposes of this article for constructing, expanding, renovating or otherwise improving andmaintaining school facilities for a thorough and efficient educationImproving and maintaining one facility will be cost efficient and provide additional resources to SRMSstudents.

E. SUBMISSION OF REVISED CEFP PAGESList the page numbers changed in the CEFP by this amendment, attach the altered pages to this form,place the revision date (revised [date]) on the bottom right hand corner of each revised page, andsubmit one copy to both the SBA and the WVDE. If additional pages are required, use the page numberfrom the preceding page in the CEFP and add successive letters, i.e., 47, 47a, 47b, 48.100.014.2 (Page 2), 100.016.1 (pages 5, 6 ), 100.016.2 (page 5) and 100.016.3 pages (1,2,7,10)

FOR WVDE AND SBA USE ONLY

WVDE Signature: ________________________ SBA Signature: ____________________________WVDE Approval Date: _____________________ SBA Approval Date: ________________________

Page 7: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.021 Application for Amendment

Page 8: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.016.1 Translating Educational Needs OverviewMcDowell County Schools100.016.1 Translating Educational Needs OverviewExecutive SummaryExecutive SummaryThe McDowell County Comprehensive Educational Facilities Plan (CEFP) is intended to serve the countyschool system in making decisions related to school facilities over the next ten-year period, and whenimplemented will result in this county having the best possible public school facilities within theparameters of available financial resources.The architectural division of The Thrasher Group, Inc. engaged to facilitate the development of theComprehensive Educational Facilities Plan for the years 2020-2030 consistent with the requirements ofWest Virginia Department of Education and the West Virginia School Building Authority.The CEFP was developed using the following sources: Collection of demographic information, historicand projected enrollments, school facility evaluations and other pertinent data. The problem consistent, inmost if not all counties, is not having enough money for all the school building needs to meet twenty-firstcentury educational standards and the educational needs of all students as well as providing a healthy,safe learning environment for students and staff.Many issues related to school facilities are extremely sensitive, and there are many points of view to beconsidered in developing the plan. Therefore, McDowell County CEFP Committee was established andprovided an opportunity for a diverse group of individuals to contribute their ideas and opinions to theplan. The intention was to develop CEFP Goals & Objectives, understand educational and physicalrequirements, program needs and requirements and to develop a strategic plan.Members of the CEFP Committee, 25 individuals, worked as a whole and in subcommittees during theplanning period to develop the content of the plan. The Committee also kept the McDowell CountyBoard of Education up-to-date with 0n their progress. This committee’s efforts produced group consensusand resulted in a plan that was found to be acceptable to the Grant County Board of Education.The data collected for this CEFP is provided in the Phase I section entitled Community Analysis, Goalsand Objectives, Education Plan, Evaluation of the 2010 – 2020 CEFP and Facilities Assessments.Consideration must be given to this data in translating educational needs into facility needs for McDowellCounty Schools over the ten-year period 2020 to 2030.The Community Analysis revealed McDowell County as primarily a rural county. The county’s economyis driven by mining, timber and recreation. Since 2005 the potential for commercial / industrial growth,has declined with the decline in the coal industry. McDowell County’s population, as in many WestVirginia counties, is declining. According to the 2010 Census, McDowell County’s population was22,113. The 2018 population had declined by 3,890. Reference the Community Analysis section fordetails.The Goals and Objectives revealed that the total school enrollment for the ten-year period will decrease.The West Virginia University’s Bureau of Business and Economic Research Office has provided county-wide school enrollment projections that also indicates a downward trend. This section identifies currentand future curriculum, facility, and over all educational needs for staff and students. Reference the Goalsand Objectives section for details.

Page 9: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.016.1 Translating Educational Needs OverviewThe Education Plan developed for McDowell County assures the delivery of high quality of programs andstate of the art technology to McDowell County students for this ten-year CEFP cycle. Reference theEducational Plan section for details.There are two high school attendance areas, in McDowell County. Mount View High School, includes,Mount View Middle School, Fall River Elementary, Kimball Elementary and Welch Elementary. TheMcDowell County Board of Education will be evaluating / considering the consolidation of these threeelementary schools, into one new elementary school. River View High School, that includes, Sandy RiverMiddle School, Bradshaw Elementary, Iaeger Elementary, and Southside PreK-8 School. McDowellCounty was devastated by flooding in 2002 resulting in the closure of several schools. With School BuildingAuthority and Army Corp of Engineers funding in 2002 five new schools were constructed in the county.Through the efforts of the county’s maintenance department and the school’s custodial staff all the schoolsare well maintained. Upgrades and renovations to all schools will be needed over the next ten-year CEFPcycle totaling an estimated. An estimated $47,561,215.00 will be needed for exterior / interior maintenanceand upgrades. Building renovations and additions, as determined by the CEFP committee, are not includedin this estimate.The Evaluation of the 2010 – 2020 CEFP revealed that McDowell County continues to have considerablefacility needs. McDowell County will endeavor to address these needs for their students to have theopportunity to attend schools in facilities that are conducive to learning and the delivery of educationbased upon the best practices supported by research. Reference the Evaluation section for details.The aforementioned information is consistent with the primary purpose of the ComprehensiveEducational Facilities Plan for 2020 to 2030 which is to establish an organized systematic approach toproviding educational facilities that will support the McDowell County School System in the delivery ofthe best possible education to its students within the parameters of available resources.

InstructionsPrior to determining the recommendations for each facility, a review of the gathered information mustbe completed, and a study of the high school feeder summary must be performed. In addition to thistemplate, please complete the supporting template for your county, Translating Educational Needs intoFacility Needs-Building ReviewComplete a chart for each high school attendance area. To add additional schools and their grade levelsin the chart, click anywhere on the chart and use the pop-up to add the school name and grade levels. Toadd the Current Enrollment numbers, double click into the Enrollment box. In addition to the chartbelow, complete the information in the table following for each school within the high school attendancearea.

Page 10: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.016.1 Translating Educational Needs Overview

Mt. View High School Attendance Area Overview

Mt. View High School Attendance AreaPlease Reference the Analytics Section on Dude Solutions 360 TM to pull in the values for the ProgramUtilization, Facility Condition Index (FCI) and Energy Usage Index (EUI).

Program Utilization: Preferred method of calculation where enrollment of each school is divided by thenumber of “seats” available at a given time throughout the day. Facility Condition Index (FCI): Calculated as the backlog of Needs for the Building/Location, divided by theCRV (Current Replacement Value). ( Backlog / CRV ) x 100 Energy Usage Index (EUI): The amount of energy consumed divided by the gross area, in square feet.

Data Mt. View MS – 6-8 / HS – 9-12School Number 060527Date of Original Construction 1978Number of Additions 25th Year Projected Enrollment 571Building Program Capacity 951Program Utilization (%) 70%Cost to Bring Facility up to Current Codes &Standards ($) 14,472,299Replacement Cost (SBA Formula $) 39,441,600Facility Condition Index (FCI) 36.69Energy Usage Index (EUI) 36

Page 11: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.016.1 Translating Educational Needs Overview

Data Fall River PreK-5 Kimball PreK-5School Number 060210 060217Date of Original Construction 1978 1954Number of Additions 0 15th Year Projected Enrollment 143 183Building Program Capacity 163 210Program Utilization (%) 93% 94%Cost to Bring Facility up to CurrentCodes & Standards ($) 1,519,318 4,192,538Replacement Cost (SBA Formula $) 7,787,976 10,212,048Facility Condition Index (FCI) 19.51 41.05Energy Usage Index (EUI) 38 67

Data Welch PreK-5School Number 060222Date of Original Construction 1954Number of Additions 25th Year Projected Enrollment 284Building Program Capacity 348Program Utilization (%) 82%Cost to Bring Facility up to CurrentCodes & Standards ($) 1,969,132Replacement Cost (SBA Formula $) 13,078,200Facility Condition Index (FCI) 15Energy Usage Index (EUI) 21

Page 12: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.016.1 Translating Educational Needs OverviewRiver View High School Attendance Area Overview

River View High School Attendance AreaPlease Reference the Analytics Section on Dude Solutions 360 TM to pull in the values for the ProgramUtilization, Facility Condition Index (FCI) and Energy Usage Index (EUI).

Program Utilization: Preferred method of calculation where enrollment of each school is divided by thenumber of “seats” available at a given time throughout the day. Facility Condition Index (FCI): Calculated as the backlog of Needs for the Building/Location, divided by theCRV (Current Replacement Value). ( Backlog / CRV ) x 100 Energy Usage Index (EUI): The amount of energy consumed divided by the gross area, in square feet.

Data River View HS 9-12School Number 060520Date of Original Construction 2010Number of Additions 05th Year Projected Enrollment 491Building Program Capacity 1069Program Utilization (%) 46%Cost to Bring Facility up to Current Codes &Standards ($) 3,990,000Replacement Cost (SBA Formula $) 33,766,200Facility Condition Index (FCI) 11.82Energy Usage Index (EUI) 59

Page 13: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.016.1 Translating Educational Needs Overview

Data Sandy River MS 6-8 Southside PreK-8School Number 060304 060223Date of Original Construction 1999 2008Number of Additions 0 05th Year Projected Enrollment 225 303Building Program Capacity 443 493Program Utilization (%) 55% 70%Cost to Bring Facility up to CurrentCodes & Standards ($) 2,490,188 4,924,023Replacement Cost (SBA Formula $) 11,347,952 13,429,760Facility Condition Index (FCI) 21.94 36.67Energy Usage Index (EUI) 62 88

Data Bradshaw PreK-5 Iaeger PreK-5School Number 060206 060213Date of Original Construction 2010 2002Number of Additions 0 05th Year Projected Enrollment 492 257Building Program Capacity 300 184Program Utilization (%) 94% 93%Cost to Bring Facility up to CurrentCodes & Standards ($) 1,343,034 153,091Replacement Cost (SBA Formula $) 12,986,100 12,757,078Facility Condition Index (FCI) 10.34 1.2Energy Usage Index (EUI) 90 70

Data McDowell Career CenterSchool Number 060731Date of Original Construction 1945Number of Additions 05th Year Projected Enrollment 300Building Program Capacity 641Program Utilization (%) 50%Cost to Bring Facility up to Current Codes &Standards ($) 9,528,476Replacement Cost (SBA Formula $) 28,814,424Facility Condition Index (FCI) 33.07Energy Usage Index (EUI) 60.10

Page 14: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.016.2 Translating Educational Needs-Building Review

1

McDowell County Schools100.016.2 Translating Educational Needs-Building ReviewBuilding Review and Recommendations Report, compiled by High School attendance areas.

Mount View High School Attendance Area

Mount View Middle / High SchoolDescribe Existing Facility: A 6 – 8 grade middle school and 9 – 12 grade high school located east ofWelch. This school was constructed in 1978 with two additions in 2002 and 2005. The building is a180,836 square feet masonry load bearing structure. The facility is well maintained but needs bothexterior and interior upgrades. Upgrades include; walks replacement, site paving, window replacement,exterior door/frame/hardware replacement, HVAC/HVAC controls, electrical, toilet renovations, andinterior finishes. This facility adequately meets the objectives of Phase I criteria.

Describe Existing Facility Site: The school sits on a 53-acre reclaimed surface mine site, east of Welch.The site is not in a flood plain. The site is accessed off US Rt. 52. Bus loading and access is average. Thesite does meet the WVDE suggested site size.

Recommendations for Future Use of Existing Facility: The committee’s recommendation is to maintainthe facility as a 6 – 8 middle school and 9 – 12 grade high school.

Cost Estimates for Recommendations: The estimated replacement cost, by SBA formula, is$39,441,600.00 The CEFP proposes future consideration for an addition to replace the four-story part ofthe existing building.Proposed addition to replace existing four-story part of building.293 students x 154sq.ft. / student = 45,122sq.ft. x $325/sq.ft. = $14,664,650

Estimated cost for maintenance and upgrades, to current standards, is $14,472,299 to include thefollowing:

· Site upgrades including parking, roads, and bus loading· Exterior windows and doors· Interior finishes· Interior door replacement· HVAC upgrades· Toilet renovations· Sprinkler System upgrades

Page 15: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.016.2 Translating Educational Needs-Building Review

2

Fall River Elementary SchoolDescribe Existing Facility: A PreK–5 elementary school located in the Roderfield community. This schoolwas constructed in 1978. The main building is a 38,285 square feet masonry load bearing structure. Thefacility is well maintained but needs both exterior and interior upgrades. Upgrades include; new 6 inchwater service, window replacement, exterior door/frame/hardware replacement, and interior lighting.This facility adequately meets the objectives of Phase I criteria.

Describe Existing Facility Site: The school sits on a 20-acre site accessed off County Rt. 7. The site is notin a flood plain. Bus loading and access is average. Play areas are average. The site does meet the WVDEsuggested site size.

Recommendations for Future Use of Existing Facility: The committee’s recommendation is to classifythis facility as a F - Functional school (Closing in the last 5 years of this CEFP). With the closing andconsolidation of Welch Elementary, Fall River Elementary, and Kimball Elementary schools, this facility,with renovations / additions, will later be transitioned into being the Career Technical Center.

Cost Estimates for Recommendations: Estimated cost for maintenance and upgrades, to currentstandards is $1,519,318 to include the following:· Site upgrades· Exterior windows, doors, and roofing· Interior finishes· Interior door replacement· Sprinkler System upgrades

SBA funding formula for a new consolidated PK – 5 elementary school (8th year projected enrollmentfor Fall River 145, Kimball 185, Welch 278 = 608 student elementary).608x100sq.ft./student=60,800sq.ft.x$307/sq.ft.=$18,665,600.

Page 16: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.016.2 Translating Educational Needs-Building Review

3

Kimball Elementary SchoolDescribe Existing Facility: A PreK–5 elementary school located in Welch. This school was constructed in1954 with one addition in 1978. The main building is a 48,986 square feet masonry load bearingstructure. The facility is well maintained but needs both exterior and interior upgrades. Upgradesinclude; new 6 inch water service, walks replacement, site paving, windows replacement, roofreplacement, exterior door/frame/hardware replacement, roof replacement, new HVAC/HVAC controls,electrical and interior lighting. This facility does not meet the objectives of Phase I criteria.

Describe Existing Facility Site: The school sits on a 6 - acre site accessed off US Rt. 52. The site is in aflood plain. Bus loading and access is below average. Play areas are below average. The site does meetthe WVDE suggested site size.

Recommendations for Future Use of Existing Facility: The committee’s recommendation is to classifythis facility as a F - Functional school (Closing in the last 5 years of this CEFP). This consolidationconsideration is the result of county wide declining enrollment and the cost of maintaining theseschools. The schools recommended for closing and consolidation are Welch Elementary, Fall RiverElementary, and Kimball Elementary.

Cost Estimates for Recommendations: Estimated cost for maintenance and upgrades, to currentstandards, is $4,192,538 to include the following:· Site upgrades including parking, roads, and bus loading· Exterior windows and roofing· HVAC upgrades· Sprinkler System upgrades

SBA funding formula for a new consolidated elementary school (8ty year projected enrollment for FallRiver 145, Kimball 185, Welch 278 = 608 student elementary).608x100sq.ft./student=60,800sq.ft.x$307/sq.ft.=$18,665,600.

Page 17: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.016.2 Translating Educational Needs-Building Review

4

Welch Elementary SchoolDescribe Existing Facility: A PreK–5 elementary school located in Welch. This school was constructed in1954 with one addition in 1980. The main building is a 53,975 square feet masonry load bearingstructure. The facility is well maintained but needs both exterior and interior upgrades. Upgradesinclude; site drainage, parking, site access improvements, new 6 inch water service, exterior - interiordoor/frame/hardware replacement, roof replacement, new HVAC/HVAC controls and interior lightingand interior finishes. This facility does not meet the objectives of Phase I criteria.

Describe Existing Facility Site: The school sits on a 3 - acre site accessed off WV Rt. 16. The site is in aflood plain. Bus loading and access is below average. Play areas are below average. The site does notmeet the WVDE suggested site size.

Recommendations for Future Use of Existing Facility: The committee’s recommendation is to classifythis facility as a F - Functional school (Closing in the last 5 years of this CEFP). This consolidationconsideration, is the result of county wide declining enrollment and the cost of maintaining theseschools. The schools recommended for consolidation are Welch Elementary, Fall River Elementary, andKimball Elementary.

Cost Estimates for Recommendations: Estimated cost for maintenance and upgrades, to currentstandards, is $1,969,132 to include the following:· Site upgrades· Exterior doors and roofing· Interior finishes including toilet renovations· HVAC upgrades· Elevator· Sprinkler System upgrades· Kitchen Equipment

SBA funding formula for a new consolidated elementary school (8th year projected enrollment for FallRiver 145, Kimball 185, Welch 278 = 608 student elementary).608x100sq.ft./student=60,800sq.ft.x$307/sq.ft.=$18,665,600.

Page 18: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.016.2 Translating Educational Needs-Building Review

5

River View High School Attendance Area

River View High SchoolDescribe Existing Facility: A 9 – 12 grade high school located in the Bradshaw community. This schoolwas constructed in 2010. The building is a 140,000 square feet masonry load bearing structure. Thefacility is well maintained. Because of the facility’s recent construction, limited exterior and interiorupgrades, are needed, over the ten-year CEFP cycle. Upgrades include; roof replacement, and interiorlighting. This facility adequately meets the objectives of Phase I criteria.

Describe Existing Facility Site: The school sits on a 11-acre site, west of Bradshaw. The site is not in aflood plain. The site is accessed off WV Rt. 80 (Mingo Hwy.). Bus loading and access is above average.The site does not meet the WVDE suggested site size. This site with the adjoining Bradshaw Elementarysite were developed as replacement schools from the 2002 flood that devastated McDowell County.

Recommendations for Future Use of Existing Facility: The committee’s recommendation is to move theSandy River Middle School 6 – 8 students to River View High School as a 6 – 12 middle/high school theRiver View High School campus. Sandy River Middle School will remain its own entity inside of the RiverView campus.Cost Estimates for Recommendations: Estimated cost for maintenance and upgrades, to currentstandards, is $3,990,000 to include the following:

· New Roof· Lighting upgrades

Sandy River Middle SchoolDescribe Existing Facility: A 6 – 8 grade middle school located in the Big Creek community. This schoolwas constructed in 1999. The main building is a 53,850 square feet masonry load bearing structure. Thefacility is well maintained but needs both exterior and interior upgrades. Upgrades include; exteriordoor/frame/hardware replacement, HVAC/HVAC controls and interior lighting. This facility adequatelymeets the objectives of Phase I criteria.

Describe Existing Facility Site: The school sits on a 15-acre site accessed off WV Rt. 80 (Mingo Hwy.). Thesite is not in a flood plain. Bus loading and access is above average. Play areas are above average. Thesite does meet the WVDE suggested site size.

Recommendations for Future Use of Existing Facility: The committee’s recommendation is to classifythis facility as P/T (A school that is Permanent and in Transition).C-Closure (A school facility that isprojected for closure before the fifth year of the ten year planning period). This proposed closure Thisproposed relocation of the Sandy River 6 – 8 students to River View High Schoolcampus as their own school. as a 6 – 12 middle/high school. Revised 2-18-21

Page 19: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.016.2 Translating Educational Needs-Building Review

6

Cost Estimates for Recommendations: Estimated cost for maintenance and upgrades, to currentstandards, is $2,490,188 to include the following:· Exterior doors/frames· HVAC· Lighting· Sprinkler System upgrades

Southside Elementary – Middle SchoolDescribe Existing Facility: A PreK - 8 elementary / middle school located in War. This school wasconstructed in 2008 to replace the schools, in War, lost in the 2002 flood that devastated McDowellCounty. The main building is a 72,618 square feet masonry load bearing structure. The facility is wellmaintained. Because of the facility’s recent construction limited exterior and interior upgrades areneeded, over the ten-year CEFP cycle. Upgrades include; Roof replacement, HVAC/HVAC controls,lighting and electrical. This facility adequately meets the objectives of Phase I criteria.

Describe Existing Facility Site: The school sits on a 11-acre site accessed off State Rt. 16. The site is notin a flood plain. Bus loading and access is above average. Play areas are above average. The site doesmeet the WVDE suggested site size.Recommendations for Future Use of Existing Facility: The committee’s recommendation is to maintainthe facility as a PK-5 elementary school, 6 – 8 grade middle school.Cost Estimates for Recommendations: Estimated cost for maintenance and upgrades, to currentstandards, is $4,924,023 to include the following:

· New Roof· HVAC upgrades· Sprinkler System upgrades

Bradshaw Elementary SchoolDescribe Existing Facility: A PreK–5 elementary school located in Bradshaw. This school was constructedin 2010 to replace the school lost in the 2002 flood. The main building is a 37,400 square feet masonryload bearing structure. The facility is well maintained. Because of the facility’s recent constructionlimited exterior and interior upgrades are needed, over the next ten - year CEFP cycle. Upgrades include;roof replacement, HVAC controls, and lighting. This facility adequately meets the objectives of Phase Icriteria.

Describe Existing Facility Site: The school sits on a 5-acre site accessed off WV Rt. 80 (Mingo Hwy.). Thesite is not in a flood plain. Bus loading and access is above average. Play areas are above average. Thesite does meet the WVDE suggested site size.

Page 20: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.016.2 Translating Educational Needs-Building Review

7

Recommendations for Future Use of Existing Facility: The committee’s recommendation is to maintainthe facility as a PK-5 elementary school.

Cost Estimates for Recommendations: Estimated cost for maintenance and upgrades, to currentstandards, is $1,343,034 to include the following:· New Roof· HVAC Controls· Sprinkler System upgrades

Iaeger Elementary SchoolDescribe Existing Facility: A PreK–5 elementary school located in the Iaeger. This school was constructedin 2015 replacing Iaeger Elementary that was lost in the 2002 flood, that devastated McDowell County.The main building is a 47,105 square feet masonry load bearing structure. The facility is well maintained.Because of the facility’s recent construction there are no upgrades, identified, to be needed over thenext ten-year CEFP cycle. Maintenance of equipment, HVAC system, fire alarm – sprinkler systems,security system, etc., will be needed. This facility adequately meets the objectives of Phase I criteria.

Describe Existing Facility Site: The school sits on a 7-acre site, developed for this new school to beconstructed, out of the flood plain, replacing the old Iaeger Elementary School lost in the 2002 flood.Bus loading and access is above average. Play areas are above average. The site does meet the WVDEsuggested site size.

Recommendations for Future Use of Existing Facility: The committee’s recommendation is to maintainthe facility as a PK-5 elementary school.

Cost Estimates for Recommendations: Estimated cost for maintenance and upgrades, to currentstandards $153,091 to include the following:· Fire Alarm upgrades· Sprinkler System upgrades

McDowell County Career and Technical CenterDescribe Existing Facility: The county’s career and technical center is located in Welch. This school wasconstructed in 1945 with two additions in 1967 and 1968. The building is a 95,412 square feet masonryload bearing structure. The facility is well maintained but needs both exterior and interior upgrades.Upgrades include; walks replacement, site paving, roof replacement, window replacement, exteriordoor/frame/hardware replacement, HVAC/HVAC controls, electrical and technology. This facilityadequately meets the objectives of Phase I criteria.

Page 21: West Virginia Department of Education Office ... - sba.wv.gov

McDowell County Schools CEFP 2020100.016.2 Translating Educational Needs-Building Review

8

Describe Existing Facility Site: The facility sits on a 3-acre site accessed off WV Rt. 16 on Stadium Drive.Buss loading and access is average. The site is partially in a flood plain. The limited site size, geographicrestrictions, and location partially in a flood plain, eliminates any future additions to the facility.

Recommendations for Future Use of Existing Facility: The committee’s recommendation is to maintainthe facility as the county’s career and technical center. Toward the end of this cycle, if the consolidationof Welch Elementary, Fall River Elementary, and Kimball Elementary schools occurs, the closed Fall Riverfacility would transition into being the Career Technical Center.

Cost Estimates for Recommendations: Estimated cost for maintenance and upgrades, to currentstandards, is $9,528,476 to include the following:· Site upgrades· HVAC upgrades· Sprinkler System upgrades

Page 22: West Virginia Department of Education Office ... - sba.wv.gov

1

McDowell County Schools100.016.3 Translating Educational Needs into Facility NeedsA. A Feeder School Summary Report

Instructions: For each High School Attendance Area within the county, complete a new chart todisplay what it will look like after all changes are implemented.Mt. View High School Attendance Area

River View High School Attendance Area

Revised 2-18-21

415

261

Page 23: West Virginia Department of Education Office ... - sba.wv.gov

2

B. A feeder school summary report narrativeIn coordination with the feeder school summary, compile a list alphabetically by high school attendancearea to provide an analysis of feeder schools and any systematic changes that are proposed to occur in thenext planning cycle. Provide the facility name, whether it’s a re-designation or a closure and the date ofthe change below for each High School Attendance area.

Mt. View High School Attendance AreaFacility Name Re-designation/Closure Proposed Date Change

Fall River ES Closure (Facility to PotentiallyBecome Career TechnicalCenter after consolidation)2028

Kimball ES Closure 2028Welch ES Closure 2028

River View High School Attendance AreaFacility Name Re-designation/Closure Proposed Date Change

Sandy River MS Closure Re-designationSchool to be relocated toRiver View High Schoolfacility and it will operate asa separate school.

2025 2021

C. A High School Attendance Area Facility ReportCompile a list alphabetically by high school attendance area to provide an analysis of necessary andproposed improvements in each community. Mark all that apply with an X for each school. Add columnsfor each additional school. There are separate charts for each school type.

Page 24: West Virginia Department of Education Office ... - sba.wv.gov

3

Mt. View High School Attendance Area

Building Use Mt. View MS 6-8 / Mt. View HS 9-12Functional SchoolContinued School XClosed SchoolTransitional SchoolNew School (ReplacementConsolidated School

Building ImprovementsNew Construction (Addition)Site Improvements XBuilding RepairBuilding Envelope Renovation (NewComp)Interior Remodeling (Sp Imp)New Interior Finishes XWindow Replacement XDoors & Frame Replacement XPlumbing RenovationsHeating/Ventilation Improvement XAir ConditioningSpecial Use Space Improvements(Technology, Media etc.) XRoof RepairAccessibility ImprovementsHealth & Safety Improvements XFurnishing & EquipmentImprovementsPortable Replacement

Revised 2-18-21

Page 25: West Virginia Department of Education Office ... - sba.wv.gov

4

Building Use Fall River ES - PreK-5 Kimball ES - PreK-5Functional School X (Part of a new consolidatedFall River, Kimball, WelchElementary School)

(Facility would becomeCareer Technical Center afterconsolidation)

X (Part of a newconsolidated Fall River,Kimball, WelchElementary School)

Continued SchoolClosed SchoolTransitional SchoolNew School (ReplacementConsolidated School

Building ImprovementsNew Construction (Addition)Site Improvements X XBuilding RepairBuilding Envelope Renovation (NewComp)Interior Remodeling (Sp Imp)New Interior Finishes XWindow Replacement XDoors & Frame Replacement X XPlumbing RenovationsHeating/Ventilation Improvement XAir ConditioningSpecial Use Space Improvements(Technology, Media etc.)Roof Repair X XAccessibility ImprovementsHealth & Safety Improvements X XFurnishing & EquipmentImprovementsPortable Replacement

Page 26: West Virginia Department of Education Office ... - sba.wv.gov

5

Building Use Welch ES - PreK-5Functional School X (Part of a new consolidatedFall River, Kimball, WelchElementary School)Continued SchoolClosed SchoolTransitional SchoolNew School (ReplacementConsolidated School

Building ImprovementsNew Construction (Addition)Site Improvements XBuilding Repair XBuilding Envelope Renovation (NewComp)Interior Remodeling (Sp Imp)New Interior Finishes XWindow ReplacementDoors & Frame Replacement XPlumbing Renovations XHeating/Ventilation Improvement XAir ConditioningSpecial Use Space Improvements(Technology, Media etc.) XRoof Repair XAccessibility ImprovementsHealth & Safety Improvements XFurnishing & EquipmentImprovements XPortable Replacement

Total Estimated Expenditures in This Attendance Area: $ 30,775,408 Prioritized Projects

NOTE: Complete a series of charts for each High School Attendance Area

Page 27: West Virginia Department of Education Office ... - sba.wv.gov

6

River View High School Attendance Area

Building Use River View HS 9-12Functional SchoolContinued School XClosed SchoolTransitional SchoolNew School (ReplacementConsolidated School

Building ImprovementsNew Construction (Addition)Site ImprovementsBuilding Repair XBuilding Envelope Renovation (NewComp)Interior Remodeling (Sp Imp)New Interior Finishes XWindow ReplacementDoors & Frame ReplacementPlumbing RenovationsHeating/Ventilation ImprovementAir ConditioningSpecial Use Space Improvements(Technology, Media etc.)Roof RepairAccessibility ImprovementsHealth & Safety ImprovementsFurnishing & EquipmentImprovementsPortable Replacement

Page 28: West Virginia Department of Education Office ... - sba.wv.gov

7

Building Use Sandy River MS 6-8 Southside PreK-8Functional SchoolContinued School XClosed School X (Move students to RiverView 6-8 MS / 9-12 HS)Transitional School X (Relocate 6-8 students toRiver View HS campus andoperate Sandy River MS as aseparate school)New School (ReplacementConsolidated School

Building ImprovementsNew Construction (Addition)Site ImprovementsBuilding RepairBuilding Envelope Renovation (NewComp)Interior Remodeling (Sp Imp)New Interior Finishes XWindow ReplacementDoors & Frame Replacement XPlumbing RenovationsHeating/Ventilation Improvement X XAir ConditioningSpecial Use Space Improvements(Technology, Media etc.)Roof Repair XAccessibility ImprovementsHealth & Safety Improvements X XFurnishing & EquipmentImprovementsPortable Replacement

Page 29: West Virginia Department of Education Office ... - sba.wv.gov

8

Building Use Bradshaw ES PreK-5 Iaeger ES PreK-5Functional SchoolContinued School X XClosed SchoolTransitional SchoolNew School (ReplacementConsolidated School

Building ImprovementsNew Construction (Addition)Site ImprovementsBuilding RepairBuilding Envelope Renovation (NewComp)Interior Remodeling (Sp Imp)New Interior Finishes XWindow ReplacementDoors & Frame ReplacementPlumbing RenovationsHeating/Ventilation Improvement XAir ConditioningSpecial Use Space Improvements(Technology, Media etc.) XRoof Repair XAccessibility ImprovementsHealth & Safety Improvements X XFurnishing & EquipmentImprovementsPortable Replacement

Total Estimated Expenditures in This Attendance Area: $ 9,028,190 Prioritized Projects

NOTE: Complete a series of charts for each High School Attendance Area

Revised 2-18-21

Page 30: West Virginia Department of Education Office ... - sba.wv.gov

9

McDowell Career & Technical Center

Building Use McDowell Career & Technical CenterFunctional School X (If consolidation happens, the closed Fall River ESfacility would be converted into the Career TechnicalCenter)Continued SchoolClosed SchoolTransitional SchoolNew School (ReplacementConsolidated School

Building ImprovementsNew Construction (Addition)Site Improvements XBuilding Repair XBuilding Envelope Renovation (NewComp)Interior Remodeling (Sp Imp)New Interior FinishesWindow ReplacementDoors & Frame Replacement XPlumbing RenovationsHeating/Ventilation Improvement XAir ConditioningSpecial Use Space Improvements(Technology, Media etc.) XRoof RepairAccessibility ImprovementsHealth & Safety Improvements XFurnishing & EquipmentImprovementsPortable Replacement

Total Estimated Expenditures: $ 5,774,632 Prioritized Projects

Page 31: West Virginia Department of Education Office ... - sba.wv.gov

10

D. A countywide facility classificationList each facility within the county and its classification per the Building Review and RecommendationReport of this document.

Facility Name Classification If Transitional, Describe Future UseMt. View MS/HS PFall River ES F If the proposed consolidation is funded, this closedfacility would be renovated to become the CareerTechnical CenterKimball ES FWelch Es FRiver View HS T Becomes 6-8 MS / 9-12 HSSandy River MS C P/T Projected for closure by 2026 - students move toRiver View 6-8 MS / 9-12 HSStudents will be relocated to River View HS campusat the end of 2020-2021 school year. Sandy Riverwill continue to operate as a separate school.Southside PreK-8 PBradshaw ES PIaeger ES PCareer Technical Center P/T School location changes if new consolidated ES isfunded / constructed. CTC would move to theclosed Fall River ES facility.School Classification Categories:P = Permanent A School facility that is to be utilized throughout the ten-year planning period without achange in its present use or grade configuration.T = Transitional A school facility that is projected to be utilized throughout the ten-year planning cyclebut will experience a change in its configuration or use.F = Functional A school facility that is projected for closure between the fifth and tenth year during theten-year planning periodC = Closure A school facility that is projected for closure before the fifth year of the ten-yearplanning period.E. School SafetyProvide a school access safety repair and renovation schedule for each school.

School Repair / Renovations Budgeted Cost AnticipatedRevised 2-18-21

Page 32: West Virginia Department of Education Office ... - sba.wv.gov

11

CompletionSouthside PreK-8 Safe Security Entrance 200,000 2022Mt View HS Safe Security Entrance 350,000 2022River View HS Safe Security Entrance 150,000 2022Career & Tech Ctr Safe Security Entrance 350,000 2022

F. Project Priority ListProvide a prioritized list of projects from the facility recommendations above. Also include a ten-yeartimeline to indicate the anticipated completion of each of these projects.

Priority Facility Name Project Name Budgeted Cost ($) AnticipatedCompletion (YR)1 Mt. View HS Replace Windows 308,000 2024

Safe Security Entrance 350,000 2024HVAC Controls 5,422,080 2024Toilet Renovations 360,000 2025

Career & Tech Ctr Exterior Doors 115,500 2022Safe Security Entrance 350,000 2022Fire Alarm 238,500 2022

River View HS Safe Security Entrance 150,000 2023Southside PK-8 Safe Security Entrance 150,000 2023New ConsolidatedES 18,665,600 2028

Priority Facility Name Project Name Budgeted Cost ($) AnticipatedCompletion (YR)2 Bradshaw ES HVAC Controls 149,600 2026

Southside Communications/Tech 1,452,360 2027HVAC Controls 2,178,540 2027Lighting 363,090 2027

Mt. View HS Communications/Tech 1,085,016 2028Interior Doors 1,021,500 2028Exterior Doors 275,000 2028

Career & Tech Ctr Roof Replacement 1,908,240 2027Communications/Tech 572,472 2027Interior Doors 355,560 2027HVAC Controls 1,431,180 2028Walks 18,120 2028Paving 72,000 2028

Page 33: West Virginia Department of Education Office ... - sba.wv.gov

12

Lighting 477,060 2028

Priority Facility Name Project Name Budgeted Cost ($) AnticipatedCompletion (YR)3 Bradshaw ES Roof Replacement 748,000 2030Lighting 336,600 2030Mt. View HS Site Work 214,000 2030Ceiling Finishes 2,170,032 2030Lighting 904,180 2030River View HS Roof Replacement 2,800,000 2030Lighting 700,000 2030Career/Tech Ctr Replace Windows 236,000 2030

GRAND TOTAL 45,578,230

Use additional rows if necessary.