West App Factsheet

download West App Factsheet

of 2

Transcript of West App Factsheet

  • 8/14/2019 West App Factsheet

    1/2

    Work on the West Approach is one o a series o seismic saety projects to strengthen the B

    Bridge. Seismic retrot work on the bridges West Span was completed in 2004. Work to complet

    replace the original eastern span started in 2002. Replacing it will be a dramatic Sel-Anchor

    Suspension (SAS) span, a 1.2-mile long Skyway and a touchdown near the Oakland Toll Plaza

    temporary transition structure at Yerba Buena Island will be required, to allow trafc to saely u

    the existing bridge and tunnel while the tie-in to the new bridge is completed. Ater these seism

    saety projects are completed, the original eastern span will be demolished.

    Seismic safety work involves completelyremoving and replacing this one-mile sectionof freeway in its original footprint, as 280,000

    vehicles continue to travel over it each day!

    PROJECT OVERVIEWhe West Approach reers to a one-mile stretch

    Interstate 80 linking San Francisco to the Bay

    ridge. It is delineated by Fith Street and the

    an Francisco anchorage on Beale Street. Seis-

    mic saety work on the West Approach involves

    ompletely removing and replacing this one-

    mile section o reeway in its original ootprint,

    s 280,000 vehicles continue to use the bridge

    ach day!

    Key Facts

    ProjectStartDate:2003

    AnticipatedCompletionDate:2009

    ConstructionContractor:Tutor-SalibaCorporation

    YearthattheSanFrancisco-OaklandBayBridgeopenedtotrafc:1936

    West Approach West Span Yerba Buena IslandTransition

    SAS Skyway OaklaTouchd

    As part o this $429 million retrot-by-replace-

    ment project to rebuild the West Approach, the

    double-deck roadways rom 3rd Street to the an-

    chorage are being rebuilt so that each deck will

    have independent columns and oundations.

    CONSTRUCTION ELEMENTSO the many seismic retrot projects planned

    or the Bay Bridge, eorts to rebuild the West

    Approach occur in the most densely populated

    area. Some o the work, which has mobilized

    enormous demolition and construction equip-

    ment rom all over the country, takes place within

    eet (or even inches!) o apartment buildings and

    ofces South o Market Street in San Francisco. In

    an eort to keep trafc moving and to minimize

    neighborhood disruptions, the project is being

    perormed through a series o six highly complex

    phases o demolition and construction.

    A WHOLE NEW APPROACH

    A one-mile stretch o I-80 approaching thebridge, and two on- and three o-ramps, will be

    demolished and completely rebuilt. The work

    West Approach

    For more information aout the West Approach, visit www.ayridgeinfo.org

    F A C T S H E E T

    required to rebuild the West Appr

    is being perormed through elabor

    choreographed stages, as each se

    o the one-mile reeway is demol

    and rebuilt one section at a time. To

    sure public saety, the work oten req

    major lane recongurations, trafc s

    and temporary deck closures. Vehicle

    detoured onto temporary roadways a

    original structures are demolished an

    built. When the new structures are pleted, trafc is once again shited an

    temporary structure is demolished.

  • 8/14/2019 West App Factsheet

    2/2

    SCHEDULING IS KEYMost o the major demolition and construc-

    on work is scheduled at a time when it will

    e least disruptive to the 280,000 vehicles

    rossing the bridge each day. However, as

    with any project o this magnitude, trafc

    ackups and neighborhood impacts are likely

    o occur. Bridge builders continue to go to ex-reme lengths to minimize these impacts by

    cheduling work over weekends and at night.

    ometimes it means consolidating work into

    condensed time rame. Oten, hundreds o

    workers must toil around-the-clock to get the

    ob done beore heavy commute-hour trafc

    egins.

    LAbOR DAY CLOSUREhe most challenging work on the West Ap-

    roach occurred over Labor Day weekend in

    006, when a 1,000-oot segment o roadway

    n the upper deck was removed in just 77

    ours. The roadway is being replaced with

    new, seismically upgraded structure. This

    required the erection o a system o steel

    beams and columns to support 400 eet o

    the lower deck; the removal o steel and con-

    crete reinorcements, including 25-ton struc-

    tural steel bolsters and 22-ton steel columns;

    the processing o concrete and steel; and the

    removal o many tons o debris. Extensive

    plans were also made or dust control, saety

    monitoring, milestone tracking, and risk mitiga-

    tion. The work also involved the cooperation

    o numerous transportation agencies, airports,

    emergency service providers and many cities

    and counties.

    KEEPING EVERYONE INFORMEKeeping neighbors, motorists, and the

    eral public inormed has been key d

    major demolition and construction wo

    the West Approach. Outreach eorts inc

    community meetings, door-to-door can

    ing, the stafng o a project hotline, mai

    public service announcements, and m

    and legislative outreach.

    The work on the West Approach over L

    Day weekend required the projects mos

    tensive outreach campaign, beginning s

    al weeks in advance o the closure and i

    siying as it neared. The campaign exte

    rom Mendocino to Bakerseld. It incl

    television, radio, and print announcem

    the distribution o nearly one million

    sheets to airports, hotels, hospitals and o

    venues; and extensive canvassing o res

    tial and commercial neighborhoods.Because o this comprehensive public outr

    motorists avoided the bridge over Labor

    weekend, and workers were able to nis

    enormous task on time!

    Bike and pedestrian path to Yerba Buena Island

    PS0304

    bAY bRIDGE PUbLIC INFORMATION OFFICE311 Burma Road, Oakland, CA 94607

    Tel: (510) 286-7167email: [email protected]

    This is one in a series o act sheets availableon the San Francisco-Oakland Bay BridgeSeismic Saety Projects published by the