WEEK 4 Introduction to Project Management 1. Communication Plan Objectives Objective is to...
-
Upload
lizbeth-rodgers -
Category
Documents
-
view
213 -
download
0
Transcript of WEEK 4 Introduction to Project Management 1. Communication Plan Objectives Objective is to...
2
Communication Plan ObjectivesObjective is to determine:
◦Who needs to know what?
◦How will they be told?
◦When will they be told and how
often?
5
Purpose of SchedulingShows relationships of each activity
to others in the whole projectIdentifies the precedence relations
among activitiesEncourages the setting of realistic
time and cost estimates for each activity
Helps make better use of people, money, and material resources by identifying “critical bottlenecks” in the project
6
In any project there will be 1or more bottlenecks that can spoil the successful
completion of the project.◦ i.e. getting the resource you need, failing to
complete a “critical task” on time One of the important responsibilities of a PM is to ID
the bottlenecks of the project and to figure out how to eliminate them or minimize their impact.
When you eliminate a bottleneck, it often frees up time
When you build a project plan, schedule the tasks conservatively to help insure you can complete them on time.◦ i.e. If you think it will take 60 days for a contractor to
complete a task, schedule 90 days to ensure that the total project will come in on time
BOTTLENECKS
7
Common tools
Gantt charts
Project calendars
Milestones charts
Critical Path Method (CPM)
the sequence of project activities which
determines the shortest time possible to
complete the project.
Program Evaluation and Review Technique
(PERT)
a method to estimate TASK DURATION ,
using optimistic, pessimistic, and most likely
time frames
Scheduling Techniques
9
ALL the tasks that determine the end date in your project schedule.
The critical path is the longest PATH, through the “AON” NETWORK (Activity On Node-explanation on 2nd slide from this one—slide # 13) Longest path of planned activities to the end of
the project Longest time in (days/weeks/months) To be started and completed exactly as
scheduled to ensure the project is completed by a certain date
ONE activity can NOT be done before the previous activity is completed
CRITICAL PATH
10
CRITICAL PATH cont. The critical path is the shortest possible TIME
in which the ENTIRE project can be completed• BECAUSE all activities are CONTINGENT upon a
PREDECESSOR (a PREVIOUS “ACTIVITY” getting completed)
Any DELAY in ANY of the “CRITICAL PATH” ACTIVITIES DELAYS the project
All “Critical Path” activities have to be in sequence”
“Critical” does NOT refer to how important the task is, but rather the IMPACT the SCHEDULING of these tasks has on the FINISH date of the project
11
CRITICAL PATH SUMMARYDIFFERENCE BETWEEN:1. The entire PROJECT completion date versus 2. the "AON" network:
The critical path is the SHORTEST possible TIME
in which the ENTIRE project can be completed.
Every “CRITICAL” activity must be completed.
The critical path is the LONGEST PATH through the
"AON" network.
◦ You need to add up all the activity times (days/weeks/ months). Whichever path is the longest (takes the most time) is the “Critical Path”.
12
FRAME OF HOUSE
FOUNDATION WALLS ROOF
PIPES IN HOUSE
SHOWER STALL
SHOWER HEAD
DRY WALLERS
Activity on Node (AON) Explained
FLOORING
14
RESOURCE PlanningQuestions to be answered when planning
resources:◦What needs to be done?◦Who or what can do the work?◦ Is this resource available?◦How will this resource affect schedules
and costs?◦RACI (Responsible, Accountable,
Consulted, Informed) Chart
◦Estimating would be completed here but we are not going to get into this in this course
15
Activities 1-4
PM Director
Service Mgr
Legal Dept
A1 R A
A2 A C I
A3 RA (responsible & Accountable)
I C
A4 A R C
R = Responsible
A = Accountable (or Approve)
C = ConsultedI = InformedProject
Manager does not necessarily have a role in every activity
RACI Chart
16
RACI ModelSteps in a RACI process
◦Identify all the activities◦Identify the roles◦Complete the cells accordingly
(R,A,C,I)◦Resolve overlaps & gaps
Every process should contain only one “R”
17
INDIVIDUAL ASSIGNMENTDo PRECEDENCE TABLE:
BLACKBOARD > WEEKLY LESSONS > Week #4-Planning Phase Part 2 > PRECEDENCE TABLE "DIGITAL ACTIVITY"
GROUP Work ActivityEach group is to create the following for the
“INTERNATIONAL Fundraiser”:(1) Communication Plan, (2) Precedence
Table (3) AON: Activity On Node and Critical Path (4)RACI Chart
R = ResponsibleA = Accountable (or Approve)C = Consulted I = Informed
R = ResponsibleA = Accountable (or Approve)C = Consulted I = Informed
COMMUNICATION PLAN
RACI
18
GROUP Work Activity cont.
1.“Communication Plan” will become page #2 of the MS WORD
portion of your Group Assignment (page #1 is your “Cover Page”)
2.“Precedence Table” will become slide #5 in your PowerPoint Presentation) (slides #3 & #4 will be the “Risk Identification Plan” covered in Week 05,) 19
GROUP Work Activity cont.
3. “AON: Activity On Node” AND “Critical Path” will become slide #6 in your PowerPoint Presentation)
4. “RACI Chart” will become page #3 of the MS WORD portion of your Group Assignment
20
21
G
E
F
H
CA
Start
DB
“Arrows” Show Precedence Relationships
AON
5 W3 W
4 W
2 W
2 W
BUILD INTERNAL COMPONENTS
2 W
4 W
3 W
MODIFY ROOF & FLOOR
POUR CONCRETE & INSTALL FRAME
CONSTRUCT COLLECTION STACK
BUILD HIGH TEMP BURNER
INSTALL POLLUTION CONTROL SYSTEM
INSTALL AIR POLLUTION DEVICE
INSPECT & TEST