Technical Submission for Pipework.
Issued by: London Office Tech-submission No.
Job Reference Number:Project:
For the attention of:Copy to:
From Completed By: Stephen Keen
Manufacturer Model Ref. Number QuantityMechanical & Pipework Fabrications n/a n/a n/aPipework Engineering Services n/a n/a n/a
Note: All equipment sourced only from LPC listed/approved contractors, where appropriate.
Equipment Particulars
Information provided: From Suppliers Data Sheets
Document Ref: EN 10255 Tube Weights / Certificates Attached Not Applicable
Description of application Areas to be usedAll Fire Protection Pipework All sprinkler ranges & mains
Clients specification used:
Statement of compliance to specification – Compliant not applicable
If non-compliant give details:
STATUS
Approved Approved with comments Rejected – Re-submit
Comments:
Date Issued Approval required by Date approval received00/00/2018 00/00/2018
We will be using the following pipework:Assembly & Installation:
All pipework will be fabricated off site and installed on site to a construction issued pre-fabrication drawing. All pipework is fabricated with identification numbers for ease of identification when installing and to reduce installation time.
Pipe weights are as follows:
Maintenance:
Quarterly Checks - Pipework should be checked for corrosion in accessible areas and to gauge the overall integrity of the pipework.
Testing
All pipework will be pressure tested to the following pressures as per BS EN 12845
15 Bar or 1.5 times the working pressure (whichever is higher) for 2 hours.
Certificates of Conformity