Warrell Creek to Nambucca Heads upgrade, Information for ... · Warrell Creek to Nambucca Heads...
Transcript of Warrell Creek to Nambucca Heads upgrade, Information for ... · Warrell Creek to Nambucca Heads...
Warrell Creek to Nambucca Heads upgrade, Information for Independent review- Road Ecologist
1. Background to Project The New South Wales (NSW) Roads and Maritime Services (Roads and Maritime) propose to upgrade approximately 19.5 kilometres of the Pacific Highway starting at the northern end of the Allgomera deviation south of Warrell Creek to Old Coast Road, west of Nambucca Heads, refer Attachment A – Figure 1. The upgrade (WC2NH) would comprise a motorway style dual carriageway and would include a number of significant structures including seven bridges, crossing of the Nambucca River and Warrell Creek floodplain and underpasses for both traffic and fauna. The project is the Stage 2 of the larger Warrell Creek to Urunga (WC2U) project and the approved Environmental Assessment covers both projects.
2. Consultation with Agencies
In addition to the consultation detailed in the EA and, Submissions and Preferred Project Report 2010 Roads and Maritime further developed the fauna crossing for WC2NH consultation with Environmental Protection Authority (EPA) then OEH. Correspondence includes
• Letter from OEH now EPA- 10/5/2011- Attachment B • Letter and table of structures (May2011) to DOP now DoPI- 23/5/2011
Attachment C • Follow up Letter and table of structures (June 2011) to DOP detailing
additional consultation with OEH- 01/06/2011- Attachment D • Site inspection of crossing structures with EPA on 26/11/2013 –
Attachment E
The current agreed table of Fauna Crossing as approved by DP&I is detailed in Table 4.1 below. Attachment I also displays the crossing and fauna fence locations.
Table 4.1: Fauna Crossing Structure and Fish Passage Requirements (extract from SWTC Appendix 4)
Location Fauna Crossing Structure Type
Structure Form1
Number and Dimensions
Fish Passage Requirements Additional Requirements
Chainage
42km500
Combined Bridge (-) Class 1 waterway3 Minimum 3 metre wide fauna
passage required at each abutment
Chainage
43km325
Combined Box culvert Minimum 5 no. x
3600mm x 1500mm
high
Class 2 waterway3
Set one culvert cell 200mm
(minimum) below existing bed level
Continue low flow channel through
scour protection
Fauna passage only required for
Giant Barred Frog
Two outside cells must provide dry
passage in accordance with Appendix
5 of the SWTC
No refuge poles required
Approximate culvert length is 47m.
Chainage
44km905
Fish passage Box culvert Minimum 3300 mm
wide x 1800 mm high
Class 3 waterway3
Include low flow channel 200mm
(minimum) below existing bed level
and 450mm wide
Continue low flow channel through
scour protection
Waterway realignment must ensure
bed stability; and maintain existing
flow velocity
Chainage
45km525
Incidental Box culvert Minimum 7 no. x
4200 mm wide x
Class 3 waterway3
Set one culvert cell 200mm
(minimum) below existing bed level
Waterway realignment must ensure
bed stability; minimise increasing or
decreasing existing waterway length;
Location Fauna Crossing Structure Type
Structure Form1
Number and Dimensions
Fish Passage Requirements Additional Requirements
3600 mm high Continue low flow channel through
scour protection
and maintain existing flow velocity
Chainage
47km000
Fish passage Bridge (-) Class 3 waterway3
Chainage
47km525
Incidental Box culvert Minimum 3000 mm
wide x 1200 mm high
Class 3 waterway3
Include low flow channel 200mm
(minimum) below existing bed level
and 450mm wide
Continue low flow channel through
scour protection
Must extend under Existing Highway
Chainage
48km085
Dedicated Bridge (-) Fauna corridor listed is under
southern end span of bridge.
Minimum 3 metre wide fauna
passage required
Chainage
48km215
Dedicated Bridge (-) Class 1 waterway3
Chainage
48km275
Dedicated Bridge (-) Fauna corridor listed is under
northern end span.
Minimum 3 metre wide fauna
passage required
Location Fauna Crossing Structure Type
Structure Form1
Number and Dimensions
Fish Passage Requirements Additional Requirements
Chainage
49km880
Incidental Box culvert Minimum 2400 x
1200 mm
No Must provide water connectivity
across Main Carriageways
Chainage
50km215
Incidental Box culvert Minimum 14 no. x
3600 x 1800 mm
No
Chainage
50km985
Incidental Box culvert Minimum14 no. x
3600 x 2100 mm
No
Chainage Combined Box culvert Minimum 2400 x No Approximate length of culvert under
55km115 2400 mm Main Carriageway is 54m and under
Old Coast Road is 29m2 .
Koala included as target species
Chainage
56km415
Combined Box culvert Minimum 2400 x
1200 mm
No Approximate culvert length under
Main Carriageway is 45m and under
Old Coast Road is 28m2 .
Koala included as target species
Chainage
58km465
Combined Box culvert Minimum 2 no. x
3600 x 2400 mm
Class 3 waterway3
Include low flow channel 200mm
(minimum) below existing bed level in
one cell
Approximate culvert length is 106m.
Koala included as target species
Location Fauna Crossing Structure Type
Structure Form1
Number and Dimensions
Fish Passage Requirements Additional Requirements
Low flow channel width to be
consistent with existing low flow
channel width
Continue low flow channel through
scour protection
Chainage
59km040
Combined Box culvert Minimum 2400 x
1500 mm
No Approximate culvert length is 93m.
Koala included as target species
Chainage
59km565
Dedicated Box culvert Minimum 3000 x
3000 mm
No Approximate culvert length is 44m.
Koala included as target species
Chainage
60km390
Northbound
Main
Carriageway
and 60km565
Southbound
Main
Carriageway
Combined Box culvert Minimum 2400 x
2400 mm
No Approximate culvert length is 40m for
Northbound Main Carriageway and
30m for Southbound Main
Carriageway. Carriageway separation
is approximately 55m.
Koala included as target species
Chainage Incidental Pipe culvert Minimum 825 mm No
Location Fauna Crossing Structure Type
Structure Form1
Number and Dimensions
Fish Passage Requirements Additional Requirements
61km195
1 A bridge may be provided in lieu of a box culvert provided that the total width between the intersection of the scour protection and the
finished ground level of the bridge is at least equivalent to the total clear width of the cells of the replaced box culvert.
2 Separate fauna crossing structures must be provided for the Main Carriageways and Service Road to provide daylight between the Main
Carriageways and Service Road structures.
3 Classification identified in consultation with DPI (Fisheries Conservation and Aquaculture)
3. Monitoring
DP&I Ministers Condition of Approval B10 requires an Ecological Monitoring Program to de developed and implemented. The Program is currently in draft form however the below is extracted from the draft Program to provide a summary.
Fauna underpasses and exclusion fencing Monitoring
Subject to the availability of suitable control sites, monitoring of the fauna underpasses and exclusion fencing will employ a Before-After Control Versus Impact (BACI) design. The BACI design allows for monitoring to occur on treated and untreated sites both before and after the subject mitigation measures have been installed or implemented
The selection criteria for fauna underpass monitoring include a continuous underpass length greater than 90 metres (excludes bridges and arches) and/or location of the structure within an area of suitable habitat for one or more of the target threatened species (ie. koala, brush-tailed phascogale, spotted-tailed quoll or giant barred frog). It was agreed with EPA that bridge underpasses will not require monitoring given that such structures have been demonstrated to provide effective fauna movement on other similar road projects.
The timing of fauna underpass/exclusion fence monitoring has been selected to coincide with the breeding seasons and likely dispersal periods of threatened fauna species targeted by the underpass structures (Table 3.4). Fauna movements are expected to be more frequent and extensive during the breeding seasons and dispersal periods due to expansion of home ranges and movement of juveniles away from natal areas. Therefore, these periods are likely to represent peaks in fauna movement, resulting in higher rates of fauna underpass usage, hence higher detection rates and sample sizes.
Table 3.4: Breeding seasons and likely dispersal periods of threatened fauna species targeted by the fauna underpass structures.
Scientific Name
Common Name
Breeding Season Likely Dispersal Periods
Dasyurus maculatus Spotted-tailed Quoll
Late May to early August (Belcher et al. 2008).
Spring and summer.
Phascolarctos cinereus
Koala Spring and summer (Martin et al. 2008). Spring and summer.
The monitoring will commence after the vegetation clearing phase of the project has been completed, but before the underpass structures become operational. The impacts resulting from vegetation clearing are not relevant to assessing the effectiveness of fauna underpass or exclusion fence mitigation measures. Therefore, it will be necessary to collect the baseline monitoring data after the vegetation clearing phase in order to eliminate or control this variable so that its effects cannot be confused or confounded with those of the independent variable (ie. impacts of underpasses and exclusion fencing)
Monitoring of the selected fauna underpasses will involve sampling within each underpass structure and its entrances, in retained habitats adjacent to the fauna underpass and in the areas isolated by exclusion fencing leading into the underpass structures. Monitoring should involve the use of several fauna census techniques including:
• sand pad sampling (eight sampling nights per sand pad per monitoring event);
• hairtube sampling (minimum 20 sampling nights per hairtube per monitoring event);
• detection with automated cameras (minimum 40 sampling nights per camera per monitoring event);
• scat and track searches; and • use of artificial groundcover (e.g. corrugated iron or plywood sheeting).
Due to the potential risk of inundation, the use of automated cameras is not recommended at combined drainage/ fauna underpass structures.
Monitoring is currently planned for Winter and Spring of Year 2 of Construction and Years 2, 3 and 5 of Operation.
4. Fauna Underpass Use
Koala In NSW, the Roads and Maritime has commissioned several long-term studies involving radio-tracking of Koalas pre-construction, during and post-construction to investigate the effectiveness of underpasses and exclusion fencing incorporated into the Pacific Highway Upgrade. Surveyed sections include at Lindsays Cutting (Moon, 1998) and Pine Creek State Forest, near Coffs Harbour, at Raymond Terrace and Bulahdelah, north of Newcastle, and along the Yelgun to Chinderah realignment in north-eastern NSW and Bonville Upgrade (AMBS, 2011). These studies have demonstrated the effectiveness of underpasses (minimum 2.4 x 2.4 metres) for Koalas crossing the highway. This includes observations of three Koalas observed to use a steel arch structure 2.8 metres wide under a dual carriageway at Taree on the NSW mid north coast (AMBS, 2002a) and several complete Koala passages of a 4 x 10 metre span bridge, 3 x 10 metre span bridge and 2.4 x 1.2 metre Reinforced Concrete Box Culvert (RCBC) at Brunswick on the NSW far north coast (Taylor and Goldingay 2003 in AMBS, 2012). Three complete Koala passages were also recorded from an RCBC structure at the Yelgun to Chinderah Upgrade (AMBS, 2012). Two Koalas used underpasses along the Bulahdelah to Coolongolook section of the Pacific Highway. The Raleigh box culvert underpass was used on three possibly four occasions by koalas. Since 1999 the fauna movement structures at Bonville/ Raleigh were used at least 30 times by Koalas in the Bonville study area with at least 12 successful crossings. A 2003 report by Taylor and Goldingay recorded 2 crossings by Koalas (unradiocollared) at Brunswick Heads via a 2.4 metre wide x 1.2 metre high box culvert.
In addition to the above an RMS unpublished document detailing fauna use of fauna structures from 2009 is included in Attachment J.
Spotted Tailed Quoll An unpublished document detailing fauna use of fauna structures from 2009 is included in Attachment J. This document aids in the following summary of underpass success with regard to Spotted Tailed Quolls and Koalas. The Spotted-tailed Quoll has been recorded using underpass structures, including large box culverts and purpose-built structures. To date there is no evidence of Spotted Tailed Quolls using overpass structures. Quolls along with wombats and bats are the only taxa not to have been recorded using bridge underpasses. The Spotted-tailed Quoll would use 3 metre x 3 metre box culverts and fauna tunnels with ten records of complete passage for separate locations. Studies conducted by the RTA have also demonstrated use of fauna underpass structures by prey species of the Spotted-tailed Quoll, including possums and other medium sized mammals that comprise 75% of their diet. Increased crossing success by suitable prey species such as medium sized mammals (i.e. Brush-tailed Possum and Common Ringtail Possum) may also have an indirect beneficial impact on the Spotted-tailed Quoll. Whilst there is no supportive data, it is possible that a reduction in roadside carrion may result in a decrease in opportunistic roadside foraging by the Spotted-tailed Quoll and consequently reduce the potential for road mortality as a result of vehicle strike.
Giant Barred Frog Whilst native frogs have been recorded using a variety of types of underpass structures, there is limited data available for threatened, cryptic frogs such as the Green-thighed Frog (Litoria brevipalmata), the Green and Golden Bell Frog (Litoria aurea) and the Giant Barred Frog. To date, there have been 57 records of native frogs and Cane Toads (Rhinella marina) using underpasses during the monitoring of these structure. Further detail can be seen in Attachment J. The confirmed location of Giant Barred frog at Upper Warrell Creek will provide crossing and habitat provision through the high bridge structure.
5. Design and Construct Contract Requirements
Roads and Maritime is currently in the process of defining a preferred contractor to undertake the detailed design and construction of the WC2NH project. The below details the requirement in relation to connectivity with the contract documents
5.1 Fauna Passage
Documents within the contract that refer to mitigation for fauna connectivity include Scope and Technical Works Criteria (SWTC) Appendix 4, Table 4.1 above. Table 4.1 details the agreed minimum culvert size and numbers, approximately length based on concept design, culvert type (ie dedicated, combined fauna and drainage or incidental).
Dedicated culverts will not include drainage in the design and as such will always be a dry culvert for dedicated fauna crossing. Combined culverts are located in areas where drainage is required but at locations where fauna crossing will benefit. These culverts will have dry fauna passage in a 1 in 1 year ARI 3 day hour storm event and must not have wet sections that retain water for longer than three days. Combined culverts will also provide fish passage where required. One culvert is nominated as Fish Passage. This culvert is primarily drainage with potential for aiding fish passage
Table 1 of the extract of SWTC Appendix 5 details the design fauna related aspects of the culvert and bridge structures. Included is design, internal and external furniture, drainage timings, bridge requirements, and landscaping requirements. Attachment F is the extracted information from SWTC Appendix 5.
5.2 Fauna Fence Figure 14.1 from Appendix 14 (Attachment I) details current nominated locations for Fauna Fencing. During detailed design this location may be modified in consultation with EPA as detailed in section 5.4 SWTC Appendix 5 (Attachment F) Attachment F also details the general requirements for fauna fencing in Section 5.4. Attachment G details typical Fauna fence design.
5.3 Clearing Procedures Section 5.2.3 of SWTC Appendix 5 (Attachment F) details the requirements for pre-clearing and clearing.
5.4 Ecological Monitoring
SWTC Appendix 4.15 and 14.9 details the Contractors requirements in relation to the Ecological Monitoring Program. (Attachment H) contains the relevant extracts from Appendix 4 and 14).
References
AMBS 2002a, Fauna Underpass Monitoring Stage Two, Episode Five, Taree. Unpublished Report to the NSW Roads and Traffic Authority.
AMBS 2012, Investigation of the Impact of Roads on Koalas. Report prepared for the NSW Roads and Traffic Authority by Australian Museum Business Services, Sydney.
Australian Museum Business Services (AMBS) (2011), Investigation of the Impact of Roads on Koalas. Final report prepared for the NSW Roads and Traffic Authority by Australian Museum Business Services, Sydney. AMBS Reference: 98001
FERRY
STREET
TAYLORS ARM ROAD
WIRRIMBI ROAD
HIG
HST
REET
VALL
ARO
AD
RIVER STREET
SCOTTS HEAD ROAD
GUMMA ROAD
BELLWOOD ROAD
JA CK S R I DG EROAD
CLA
YHOL
ES
ROA
D
ROSEWO
OD
ROADCORONATION ROAD
GRA
SS
Y ROAD
NURSERY ROAD
UPP
ER
WAR RELL
CREEK
ROAD
SWAMPY CREEK
ROSEW OOD CREEK
WAYWA
YCREE K
BIG CREEK
SWIMMING CREEK
B L A CKBUTTCREE K
SNA KEYCR
EEK
TAYLORS ARM
MIDDLE H EAD CRE EKC HANNELS CREEK
WILLIAMSONS CREEK MOR G ANSGU
LLY
T ILLYWILLY
CREEK
BELLWOOD CREEK
BUTCHERS CREEK
S TARLIGHT CREEK
NEWE
ECREE
K
WATT CREEK
NAMBUCCA RIVER
SLEDG
ELINE
GUL LY
TAYLO
RSCRE
EK
STONY CREEK
BRIANS CREEK
PARK INS GU LLY
WARR
ELLCREEK
BOGGY CREEK
EXIS
TIN
GH
IGH
WAY
EXISTINGHIGHWAY
WAYWAY
WARRELLCREEK
DONNELLYVILLE
SCOTTSHEAD
MACKSVILLE GUMMA
CONGARINNINORTH
WIRRIMBI
TEWINGA
NAMBUCCAHEADSUPPERNEWEECREEK
NSW
SPA
TIA
L - G
IS M
AP fi
le :
EN
0416
4_G
IS_E
PBC
_F00
1_r2
v1_A
-1
Road boundary Existing highway
Railway
Waterway
G:\Technical\Spatial\GIS\GIS_Directory\ArcMap\Figures\EPBC\EN04164_GIS_EPBC_F001_r2v1_A-1.mxd
Attachment A Figure 1 Overview of locality
EPBC REFERRALUpgrade of the Pacific Highway, Warrell Creek to Nambucca Heads
EUNGAICREEK
STUARTSPOINT
WARRELLCREEK
SCOTTSHEAD
CONGARINNI MACKSVILLE
BELLWOOD
BOWRAVILLENAMBUCCA
HEADS
VALLABEACH
DATA SOURCESESRI basemaps 2013, Roads and Maritime Services 2010, 2013, LPMA 2010
0 4 km
Office of Environment NSW &HeritageGOVERNMENT
Our reference: DOC 11/22122 Contact: Simone Garwood
Scott Lawrence RTA Pacific Highway Office PO Box 546 Grafton 2460.
Dear Mr Lawrence,
Re: Biodiversity Connectivity- Warrell Creek to Urunga Pacific Highway Upgrade
Thank you for the opportunity to meet with yourself on the 151 April and 6 May 2011 to discuss biodiversity connectivity associated with the Warrell Creek to Urunga Pacific Highway Upgrade.
In regards to our most recent meeting on the 6 May 2011, the Office of Environment and Heritage (OEH) reiterates the importance of strategically designing and positioning biodiversity connectivity structures to increase the probability that they will be effective.
Where the likely effectiveness of some of these connectivity structures is questionable (eg. colocated with small drainage structures), OEH agrees that it will be more beneficial to minimise the investment in these structures and transfer those cost savings to the construction of a bridge at Dalhousie Creek. OEH considers a bridge at Dalhousie Creek will optimise biodiversity connectivity in a high conservation area (on the understanding that adequate fauna passage will be provide between the mean high water flow and toe of the scour protection).
In relation to the structures located at the chainages listed below, OEH therefore supports the proposal to revert back to the original design parameters as outlined in the attachment of your e-mail dated 5 May 2011 (EN02286_Fauna_crossing_culverts May 2011), in order to deliver cost savings which can be reinvested in a bridge at Dalhousie Creek:
• Chainage 17205; • Chainage 19820; • Chainage 30855; and • Chainage 40500.
OEH considers that the structures at the above locations are not likely to provide optimal biodiversity connectivity due to their length (>100m) and the restricted opportunity to substantially increase the height and width of these structures.
In accordance with the discussions on the 6 May 2011, OEH understands that the RTA will also be investigating opportunities to implement the following mitigation strategies:
The Department of Environment, Climate Change and Water is now known as the Office of Environment and Heritage, Department of Premier and Cabinet
Locked Bag 914, Colts Harbour NSW 2450 Federation House level?, 24 Moonee Street,
Colts Harbour NSW 2450 Tel: (02) 6651 5946 Fax: (02) 6651 6187
ABN 30 841 387 271 W\Wt.environment.nsw.gov.au
Page2
• to increase the height of the structure at Chainage 28565 preferably to 3m, but as a minimum 2.4m and adopt this as a minimum design standard;
• to increase the size of the culvert located south of chainage 9350; • on the basis that the length of the crossing at Chainage 17720 is less than 50m, OEH
considers that a 3m x 3m box culvert would be sufficient thus reducing the need for an arched culvert; and
• the opportunity to remove the dedicated underpass at Chainage 32780 and revise the design of the next drainage structure to the north as a combined 9m x 4m arched fauna/drainage culvert. However, OEH highlights that the hydrology at this location would need to be reviewed in order to determine the adequacy of dry fauna passage on the ledges within the arched culvert.
OEH confirms that the inclusion of a bridge structure at Dalhousie Creek is the priority biodiversity connectivity strategy and if this cannot be achieved OEH would appreciate the opportunity to revisit the location and design of all fauna connectivity structures associated with the project.
If you have any questions, or wish to discuss this matter further please do not hesitate to contact Simone Garwood on 66598219.
Yours sincerely
~~:~::s:-?> 3::J .c;: _____ _
BRETT NUDD Manager North Coast Region Environment Protection and Regulation Group Office of Environment and Heritage Department of Premier and Cabinet
,b -v'l·-t 2.A It
Table 1: Update to Submissions Report Warrell Creek to Urunga ‐ Fauna crossings comparison/ revisions May 2011
Page 1 of 9
Submissions report (November 2010) Proposed crossings after discussion with DECCW
Approximate Chainage
Fauna crossing type
Proposed structure
Indicative size and configuration
Approximate Chainage
Proposed structure
Indicative size and configuration
Comments
3760 Incidental Culvert over Stony Creek
3 x 3600 x 3600
3800 Box Culvert 7 x 4200 x 3600 Increased opening. Size revised to meet hydraulic requirements. Current location coincides with watercourse.
5760 Incidental Box Culvert 3000 x 1200 5760 Box Culvert 3000 x 1200 No change.
6320 Dedicated Fauna corridor under bridge over Warrell Creek
Bridge 230m total length
6320 Bridge 230m total length No change. Corridor listed is under southern end span of bridge. Unhindered passage is provided (refer to Note 1).
6450 Dedicated Bridge over Warrell Creek
Bridge 6450 Bridge (‐) No change. Northern span of bridge over Warrell Creek detailed above. Unhindered passage is provided (refer to Note 1).
6510 Dedicated Fauna corridor under bridge over Warrell Creek
Bridge 6510 Bridge (‐) Location is part of bridge over Warrell Creek detailed above. No change. Corridor listed is under northern end span. Unhindered passage is provided (refer to Note 1).
8115 Incidental Box Culvert 2400 x 1200 8115 Box Culvert 2400 x 1200 No change.
Table 1: Update to Submissions Report Warrell Creek to Urunga ‐ Fauna crossings comparison/ revisions May 2011
Page 2 of 9
Submissions report (November 2010) Proposed crossings after discussion with DECCW
Approximate Chainage
Fauna crossing type
Proposed structure
Indicative size and configuration
Approximate Chainage
Proposed structure
Indicative size and configuration
Comments
8450 Incidental Box Culvert 14 x 3600 x 1800
8450 Box Culvert 14x3600x1800 No change.
9220 Incidental Box Culvert 14 x 3600 x 2100
9220 Box Culvert 14 x 3600 x 2100 No change.
13285 Combined Box Culvert 2400 x 1200
13285 Box Culvert 2400x2400 Culvert height increased for improved fauna connectivity. Fill height approximately 7m. Length of culvert under highway is 54 m and under Old Coast Road is 29m. Daylight between highway and Old Coast Road.
14555 Combined Box Culvert 2400 x 1200
14555 Box Culvert 2400x1200 No change. Fill height is approximately 3m to road level. The culvert height has not been increased to 2400, as this would require lifting the road level. Culvert length under highway (approximately 45m) and Old Coast Road is approximately 73m in total. Daylight between highway and Old Coast Road.
16630 Combined Box Culvert 3x3600x1200
16630 Box Culvert 2x 3600x2400 Size increased for improved fauna connectivity. Fill height is approximately 15m and requires verges at lower tier. Culvert length is approximately 106m. Reduction in length is not achievable without 15 high retaining walls, so has not been adopted.
17205 Combined Box Culvert 2400 x 1500
17205 Box Culvert 2400x1500 No change Fill height is approximately 15m and culvert is running at around 70 degrees to match the existing watercourse. Length approximately 93m. Reduction in length is not achievable without 15m high retaining walls, so
Table 1: Update to Submissions Report Warrell Creek to Urunga ‐ Fauna crossings comparison/ revisions May 2011
Page 3 of 9
Submissions report (November 2010) Proposed crossings after discussion with DECCW
Approximate Chainage
Fauna crossing type
Proposed structure
Indicative size and configuration
Approximate Chainage
Proposed structure
Indicative size and configuration
Comments
has not been adopted. 17720
Dedicated Box Culvert 2400 x 2400
17720 Box Culvert 3000 X 3000 Culvert size increased for improved fauna connectivity. Fill height is approximately 6.5m. Length is approximately 44m.
18515 Combined Box Culvert 2400 x 1200
18515 northbound and 18695 southbound
Box Culvert 2400x2400 Culvert size increased. Fill height approximately 8m. Length is 40m northbound and 30m southbound. Carriageway separation is about 55m. Culvert across southbound carriageway moved to 18695 to minimise number of culverts and improve culvert skew. Increased length of fauna fencing is required between northbound and southbound culverts.
19350 Incidental Circular Culvert
750 19350 Pipe Culvert 750 No change.
19820 Combined Box Culvert 5 x 2400 x 2100
19820 Box Culvert 5 x 2400 x 2100
No Change Fill height is approximately 14 m, requiring verges at lower tier. Culvert length is approximately 97 m across proposed highway and 30m across existing highway with daylight in between. Reduction in length is not achievable without 14 m high retaining walls, so has not been adopted.
20880 Dedicated Fauna corridor under bridge over Boggy Creek
Bridge 20800 Bridge Total length 96m No change. Bridges over Boggy Creek. Fauna corridor under southern end span. Unhindered passage is provided (refer to Note 1)
Table 1: Update to Submissions Report Warrell Creek to Urunga ‐ Fauna crossings comparison/ revisions May 2011
Page 4 of 9
Submissions report (November 2010) Proposed crossings after discussion with DECCW
Approximate Chainage
Fauna crossing type
Proposed structure
Indicative size and configuration
Approximate Chainage
Proposed structure
Indicative size and configuration
Comments
20880 Dedicated Bridge over Boggy Creek
Bridge 20880 Bridge Total length 96m No change. Bridge over Boggy Creek. Fauna corridor under northern end span. Without creek re‐alignment it is unlikely to achieve 3m unhindered passage on the northern abutment. Bridge pier layout has been designed to avoid placing piers directly into the ‘low flow’ watercourse. To achieve 3m unhindered passage on the northern abutment the piers would be required to be placed into the ‘low flow’ watercourse (assuming the creek was not realigned). Detail on the exact pier configuration and passage whether 3m unhindered fauna passage can be achieved on the northern abutment will be finalised as part of the detailed design in consultation with DPI (Fisheries) and Office of Environment & Heritage (OEH)
21740 Dedicated Fauna corridor under bridge over Cow Creek
Bridge 21740 Bridge Total length 122m No change. Fauna corridor under northern and southern end span. Unhindered passage is provided (refer to Note 1).
21740 Dedicated Bridge over Cow Creek
Bridge 21740 Bridge Total length 122m No change. Fauna corridor under northern and southern end span. 1m wide unhindered fauna passage would be required.
23040 Dedicated Fauna corridor under bridge over Deep Creek
Bridge 23040 Bridge Bridge over Deep Creek
No change. Unhindered passage is provided (refer to Note 1).
Table 1: Update to Submissions Report Warrell Creek to Urunga ‐ Fauna crossings comparison/ revisions May 2011
Page 5 of 9
Submissions report (November 2010) Proposed crossings after discussion with DECCW
Approximate Chainage
Fauna crossing type
Proposed structure
Indicative size and configuration
Approximate Chainage
Proposed structure
Indicative size and configuration
Comments
24305 Incidental Box Culvert 2700 x 900 24305 Box Culvert 2700x900; crosses local service road not upgrade.
No change.
25255 Combined Box Culvert 2400 x 2400
25255 Box Culvert 2400x2400 Not continued under local service road.
No change. Fill height is approximately 4.6m. Length is 42m under highway and 37m under existing highway with daylight in between. Underpass cannot continue under the local service road, unless the service road is regraded. This would need an adjustment of the proposed boundary. Therefore it is not proposed to have the underpass extend under the local road.
26535 Combined Box Culvert 5 x 3600 x 1200
26535 Box Culvert 4 x 3600 x 1200 Plus 1 x 3600 x 2400
Increase one cell to 2400 height for improved fauna connectivity. Fill height is approximately 4.5m. Length approximately 18m and 52m day light between highway and local service road. Minor level adjustment required to local service road to accommodate increased height.
27845 Incidental Pipe Culvert
4X1200 27848 Pipe Culvert 4x 1200 No Change
Table 1: Update to Submissions Report Warrell Creek to Urunga ‐ Fauna crossings comparison/ revisions May 2011
Page 6 of 9
Submissions report (November 2010) Proposed crossings after discussion with DECCW
Approximate Chainage
Fauna crossing type
Proposed structure
Indicative size and configuration
Approximate Chainage
Proposed structure
Indicative size and configuration
Comments
28275 Incidental Pipe Culvert
3x 1200 28275 Pipe culvert 2x1800 Increased height. Culvert modified to 2x1800 because of drainage considerations
28565 N/A N/A 2 x 2400 x 1200
28565 Box Culvert 3600x3000 Originally 2 x 2400 x 1200 box culvert (for drainage) this structure has been increased to 3600 x3000 box culvert to serve as a combined fauna/drainage structure. Fill height is approximately 5.0m. Length is approximately 53m long. Not feasible to daylight in the median without significant cost (narrow median width) Fauna fence would be provided to assist usage of this structure
29650 N/A N/A N/A 29650 Bridge over McGraphs Creek Floodplain No.1
Approximate length 100m
Unhindered fauna passage is able to be provided on the northern and southern banks (refer to Note 1) Fauna fence would be provided to assist usage of this structure
30855 Combined Box Culvert
2100 x 900
30855 Box Culvert 2100 x 900 No change Fill height is approximately 12 m. Length is approximately 110 m. Culvert located in transition zone to wider separations and batters overlap, as a result there is no opening in the median. Due large fill heights it is not possible to daylight culverts in the median. Because of large fill heights retaining walls would be required to reduce culvert length this is not considered a reasonable option at this location given larger fauna crossing structure (bridge) at CH 31510
Table 1: Update to Submissions Report Warrell Creek to Urunga ‐ Fauna crossings comparison/ revisions May 2011
Page 7 of 9
Submissions report (November 2010) Proposed crossings after discussion with DECCW
Approximate Chainage
Fauna crossing type
Proposed structure
Indicative size and configuration
Approximate Chainage
Proposed structure
Indicative size and configuration
Comments
31510 Combined Box Culvert 4 x 2100 x 1200
31510 Bridge over Dalhouse Creek
Minimum 15.0m span
Replace box culverts with Bridge to improve fauna connectivity. Unhindered fauna passage is likely to be provided on the northern and southern banks (refer to Note 1)
32075
Combined Box Culvert
2400 x 1200
31930 Northbound 31750 Southbound
Box Culvert
2400 x 2400 Culvert size increased to improve fauna connectivity Design modified to utilise wide separation between carriageways for open drain and culvert crosses the northbound and southbound carriageway separately, because the existing watercourse runs in the median. Fill height is approximately 6m. Length of culvert is approximately 50m across each carriageway.
32780 Dedicated Box Culvert 2400 x 2400
32930 Arch Minimum height 4.0m Minimum span 9.0m
Replaced box culvert with arch structure. Location moved to 32930 Fill height approximately 10 m. Length is approximately 62m. Hydrology at this location would need to be reviewed to confirm dry passage for most times of the year is available for fauna.
33395 Incidental Circular Culvert
3 x 1200 33395 Box Culvert 3000x2400 Size increased for drainage purposes
33880 Incidental Box Culvert 2400 x 1200 33940 Box Culvert 2400x1200 Note the location shift to avoid the spider orchid. No change in size.
34380
Combined Box Culvert 3 x 2700 x 1200
34450 Box Culvert 3600 x 2400 Single cell box culvert adopted with increased height to suit combined crossing for fauna. Note the location shift to avoid the spider orchid. Fill height is approximately 8m. Length is approximately 68m.
Table 1: Update to Submissions Report Warrell Creek to Urunga ‐ Fauna crossings comparison/ revisions May 2011
Page 8 of 9
Submissions report (November 2010) Proposed crossings after discussion with DECCW
Approximate Chainage
Fauna crossing type
Proposed structure
Indicative size and configuration
Approximate Chainage
Proposed structure
Indicative size and configuration
Comments
34380
Combined Box Culvert 3 x 2700 x 1200
34450 Box Culvert 3600x3600 Culvert height increased to improve fauna connectivity Fill height is approximately 8m. Length is approximately 68m.
34380
Combined Box Culvert 3 x 2700 x 1200
34450 Box Culvert 3000x3000 Culvert height increased to improve fauna connectivity Fill height is approximately 8m. Length is approximately 68m.
34615 Incidental Box Culvert 3 x 2700 x 1200
34780 Box Culvert 3600 x 2100 Single cell box culvert adopted for drainage purposes Note the location shift to avoid the spider orchid. Increased height is benefit to fauna crossing. Culvert length approximately 56m. Fill height approx 6m
35095 Combined Box Culvert 23 x 3600 x 3000
35095 Box Culvert 23x3600x3000 No change. Culvert length approximately 50m.
36905 Combined Box Culvert 2 x 2400 x 1200
36905 Box Culvert 2x2400x1200 No change. Fill height is approximately 3m. Fill height would need to be increased to accommodate a higher culvert. Culvert length is approximately 53m.
37950 Dedicated Dry corridor
2400 x 2400
37950 Bridge 15 m minimum length
Placement of a bridge at this location. Unhindered passage is provided (refer to Note 1).
38330 Combined Box Culvert 2 x 3000 x 1500
38330 Box Culvert 2x3000x1500 No change. Fill height is approximately 1m. Fill height would have to be increased for the northbound carriageway to accommodate a higher culvert. Carriageways have wide separation. Culvert length is approximately 28m across southbound carriageway and
Table 1: Update to Submissions Report Warrell Creek to Urunga ‐ Fauna crossings comparison/ revisions May 2011
Page 9 of 9
Submissions report (November 2010) Proposed crossings after discussion with DECCW
Approximate Chainage
Fauna crossing type
Proposed structure
Indicative size and configuration
Approximate Chainage
Proposed structure
Indicative size and configuration
Comments
37m across southbound carriageway.
39990 Incidental Box Culvert 17 x 3300 x 2100
39990 Box Culvert 17x3300x2100 No change.
40500 Combined Box Culvert 9 x 3000 x 2100
40500 Box Culvert 9 x 3000 x 2100
No change Fill height approximately 3.5m Length of culvert is approximately 48m under proposed highway and 17m under existing highway realignment, with daylight t in between. Uncertain whether dry passage would be able to be achieved for most of the year at this location.
Notes: SKM has prepared this information in accordance with the scope of work outlined by the RTA. The indicative size and configuration of culverts would be further refined during the detailed design phase. SKM assumes no responsibility for any inaccuracies or omissions in the data or for use of this data in any other context or for any other purpose or by third parties.
1) The bridges detailed above appear to have a 3m unhindered passage for fauna, with the exception of the northern abutment at Boggy Creek. Note that this has been determined from limited survey data and will need to be confirmed during the detailed design.
2) Multiple culverts with non‐matching cell heights impacts on the construction cost. The optimum construction cost scenario includes an odd number of cells maximising the use of link slabs.
3) For incidental crossing some rationalisation of the culvert configurations was undertaken following the initial design to eliminate smaller multiple pipes susceptible to blockage in preference to single larger size pipe or box culverts.
Minutes Page 1 of 3
MEETING MINUTES
Warrell Creek to Nambucca Heads – Fauna underpass Name of meeting:
Location of meeting: Project site
Meeting facilitator: Andrew Cook (RMS)
9.00 – 15:00 Date: 26/11/13 Time:
Tammie Tribe (RMS), Andrew Cook (RMS), Craig Harré (EPA) Attendees:
Apologies:
Discussion/Comments Action/Response
General • Inspection was planned to concentrate on the Fauna crossing identified in
Table 4.1 of SWTC. • Discussion was had on the early consultation with EPA (OEH) in 2011
which had involved another member of the EPA team
• Nil
Upper Warrell Creek bridge (Chainage 42km500/EA 735) - No issues raised by EPA- Discussion had on the requirement for 3m
wide fauna passage on either side of the waterway - Discussion had on the fencing setup for the Giant Barred Frog at
Upper Warrell Creek
• Nil
Butchers Creek (Chainage 43km325/EA 1560) • Discussion had on fauna fencing at this location was targeting Giant
Barred Frog and that the Fauna Passage requirements were also targeted for Giant Barred Frog (is dry passage required but no refuge poles)
• Nil
Stony Creek (Chainage 45km525/ EA Chainage 3760) • Limited vegetation here, short top for Craig’s orientation.
• Nil
Williamson Creek (Chainage 47km000) • Limited vegetation at this location. • Discussed the Microbat Management Strategy and possible changes
based on not forcing exclusion at this and other locations.
• RMS to following up additional consultation with EPA regarding changes to the Microbat Management Plan.
Unnamed drainage line (Chainage 47km525/ EA Chainage 5760) • Inspection had on both up stream and downstream. A stream blockage
with a farm crossing constructed of large rocks was observed downstream.
• Further examination of the project plans show this farm crossing to be removed
• Nil
Warrell Creek bridge • EPA commented on the importance of this crossing as part of the larger
• Comments noted.
regional fauna corridor, with particular emphasises on the southern bank.
Unnamed drainage line (Chainage 49km880/ EA Chainage 8115) • It was noted this waterway crossing was on the southern side of the Grey
headed Flying fox colony • The fauna fence in the current design based on the EA was discussed.
Possible opportunity for further discussion during detailed design removing this fencing based on inundated area not likely to provide habitat for high numbers of mammal which would fauna fence would be targeting towards. Flying foxes would not be influenced by the fauna fence.
• EPA to further consider and discuss during detailed design.
Nambucca River • Not inspected
•
Unnamed drainage line (Chainage 55km115/ EA Chainage 13285) • It was noted Koala was a target species at this location as detailed in
Table 4.1 Appendix 4 SWTC • The height of the structure was discussed with Craig commenting more
height would achieve better passage
• RMS has consulted with EPA previously regarding the dimensions of the combined fauna underpasses as part of the complete Warrell Creek to Urunga project. It is noted that the dimensions are considered the minimum dimensions.
Unnamed drainage line (Chainage 56km415/ EA Chainage 14555) • Not inspected
•
Unnamed drainage line (Chainage 58km465/ EA Chainage 16630) • The concept design shows two 3600 mm wide x 2400 mm high box
culvert. Concept shows this culvert to be approximately 106m long. • Comments were made on the height of the structure considering the
height of fill (approximately 15 m). • Craig commented a reduction in the skew would shorten the culvert length• It was noted Koala was a target species at this location as detailed in
Table 4.1 Appendix 4 SWTC •
• Refer to response above for Chainage 55km115 regarding culvert dimensions and fill height.
• EPA to raise with Construction contractor during detailed design
Unnamed drainage line (Chainage 59km040/ EA Chainage 17205) • The concept design shows one 2400 mm wide x 1500 mm high box
culvert. • Comments were made on the height of the structure considering the
height of fill (approximately 15 m). • Comments were also made on reducing culvert skew to potentially reduce
culvert length. • It was noted Koala was a target species at this location as detailed in
Table 4.1 Appendix 4 SWTC
• Refer to response above for Chainage 55km115 regarding culvert dimensions and fill height.
• Opportunities to reduce culvert skew would be investigated during detailed design.
Minutes Page 2 of 3
Unnamed drainage line (Chainage 59km565/ EA Chainage 17720) • It was noted this is the only dedicated culvert on WC2NH and Koala was
a target species at this location as detailed in Table 4.1 Appendix 4 SWTC
• Inspection of culvert area saw good vegetation around the site with some weeds
• No issues raised with culvert •
• Nil
Unnamed drainage line (Chainage 60km390 and 60km565/ EA Chainage 18515 and 18695) • It was noted that this location is associated with the widened median
section of the project. • The concept design shows one 2400 mm wide x 2400 mm high box
culverts under each carriageway with a run of fauna fence required to join • Craig commented that reducing the run length would benefit crossing
success. •
• Opportunities to reduce run length through the widened median would be investigated during detailed design.
Unnamed drainage line (59km195/ EA Chainage 19350) • Not inspected due to incidental classification
• Nil
Minutes Page 3 of 3
Pacific Highway upgrade – Warrell Creek to Nambucca Heads Provisions for Fauna
5.2.3 Clearing Procedures
The fauna rescue procedure must address the control of all clearing operations to
minimise fauna injury and must include procedures to reduce risks from vehicle
impacts to fauna in newly cleared areas.
The fauna rescue procedure must address, as a minimum, the following
requirements:
(a) The contact details for the project ecologist must be identified and kept at a
convenient location on the Construction Site and must be available to the
relevant Contractor’s management and supervisory personnel at all locations
where clearing is being undertaken, to enable quick contact and access with
the project ecologist.
(b) Prior to undertaking clearing at any location or time, a pre-clearing
assessment must be undertaken by the project ecologist to identify the
presence or evidence of the presence (including fresh scats, scratches and
remains of prey) of fauna, including threatened species. The assessment
must include processes and actions to protect or rescue the identified fauna,
including koalas, bat colonies and roosts, glider dens and frogs.
(c) All hollow bearing trees, potential hollow bearing trees and all other fauna
containing habitat trees, including trees with nests, dreys and termitaria likely
to be occupied by fauna, must be marked at least 7 days prior to the
commencement of clearing in a manner which clearly identifies and
demarcates the trees.
(d) The Contractor must identify and mark all habitat features, which consist of all
large fallen logs (greater than 300 mm diameter and not in advanced stage of
decay) and bush rocks, in a manner which clearly identifies and demarcates
the feature. The Contractor must relocate these habitat features to areas
adjacent to the clearing footprint and within the Construction Site.
(e) The Contractor must implement a two stage approach to clearing. Non-
habitat trees must be removed at least 48 hours before habitat trees are
removed, unless otherwise agreed with EPA, to allow fauna an opportunity to
move from habitat trees and allow time to concentrate rescue efforts on the
trees that are most likely to be inhabited. All habitat trees must be felled
under the supervision of the project ecologist. Felled trees must be left for a
Scope of Works and Technical Criteria Page 3 Appendix 5 RFT
Pacific Highway upgrade – Warrell Creek to Nambucca Heads Provisions for Fauna
short period of time, determined by the project ecologist, on the ground to
give any fauna trapped in the trees an opportunity to escape.
(f) An assessment of habitat trees and the handling of the fauna affected by the
clearing activities must be undertaken. The assessment must address all
elements of the implementation, outcomes and effectiveness of the fauna
rescue procedure, including:
(i) the identification and assessment of habitat trees affected by the
clearing activities, including details on the checks by the project
ecologist on trees for fauna, nests and the like, and the
implementation of the fauna rescue procedure; and
(ii) shocked and injured animal care and handling.
(g) Procedures for the relocation of non-injured fauna from clearing areas and
operations, including the identification of appropriate locations, timings and
weather conditions for the relocation of non-injured fauna.
(h) Procedures for handling injured fauna from clearing areas and operations,
including details on liaison with wildlife rescue groups, veterinary surgeons
and any other appropriate organisations or individuals.
5.2.4 Structures
The Contractor must assess all bridge and culvert structures to be removed for the
presence of native fauna, including fauna such as bats that may be present in gaps
in structures or scuppers. If native fauna are found, a fauna rescue procedure must
be prepared in consultation with EPA. The Contractor must prepare the fauna
rescue procedure and recommend appropriate mitigation measures and monitoring.
The fauna rescue procedure must be prepared by degree qualified and experienced
ecologists, with expertise in fauna rescue for the relevant fauna species.
5.2.5 Water extraction and dewatering
Where the construction of the Project Works requires the Contractor to infill dams or
dewater waterways for the construction of drainage structures, the Contractor must
develop and implement a dewatering procedure. The dewatering procedure must be
implemented under the direct control of the Project Ecologist and must address the
following requirements:
Scope of Works and Technical Criteria Page 4 Appendix 5 RFT
Pacific Highway upgrade – Warrell Creek to Nambucca Heads Provisions for Fauna
(a) restriction of the initial drawdown of water to a manageable level for the
survey, capture and relocation of aquatic fauna, including native fish, turtles
and eels (approximately 500 mm depth of water remaining);
(b) following initial drawdown, management of the survey, capture and relocation
of aquatic fauna, including native fish, turtles and eels, to nearby recipient
sites that are:
(i) not directly impacted by the Contractor’s Work; and
(ii) part of the same sub-catchment so as to avoid the inadvertent
dispersal of native vertebrates into unsuitable habitat;
(c) procedures to euthanase any exotic fish and any other fish that cannot be
appropriately identified (native or not), in consultation with DPI (Fishing and
Aquaculture); and
(d) in Giant Barred frog habitat development in accordance with requirements of
section 14.6 of Appendix 14 of the Scope of Works and Technical Criteria.
5.2.6 Reporting
Following the completion of clearing operations and any bridge and culvert structures
removal, the Contractor, in consultation with the project ecologist, must prepare a
report that:
(a) details the assessment of habitat trees and the handling of the fauna affected
by the clearing activities undertaken in accordance with the requirements of
section 5.2.3 of this Appendix;
(b) details the clearing and structures removal operations, including procedures,
dates, areas and information on the fauna specialist(s) present during the
clearing and structures removal operations;
(c) details any live animals that were sighted, captured, released, injured or
shocked;
(d) details dead animals that were found as a result of clearing and structures
removal operations and fauna rescue;
(e) details trees being used for breeding or roosting by fauna, including their
species, locations, sizes, heights and depths of hollows in trees;
Scope of Works and Technical Criteria Page 5 Appendix 5 RFT
5.3
Pacific Highway upgrade – Warrell Creek to Nambucca Heads Provisions for Fauna
(f) details any bridge or culvert structure being used for breeding or roosting by
fauna, including their species, locations, sizes, gap heights and depths;
(g) includes photo images of rescued fauna;
(h) includes records of road kill during the clearing period and for one month
following clearing;
(i) includes an analysis of the effectiveness of the clearing methods and fauna
rescue procedures adopted by the Contractor; and
(j) includes recommendations for future pre-clearing assessments and/or fauna
rescue procedures.
Fauna Underpasses
Fauna underpasses must comply with the requirements of Table 1. The design of
fauna underpasses must be undertaken in consultation with EPA and Fisheries. The
Contractor must address the fauna underpass requirements identified in Table 1 in
the Design Documentation. The Contractor must also prepare and keep records of
all agreements reached with agencies and include these records in the Design
Documentation.
Scope of Works and Technical Criteria Page 6 Appendix 5 RFT
Pacific Highway upgrade – Warrell Creek to Nambucca Heads Provisions for Fauna
Table 1 Fauna Underpass Requirements
Fauna Underpass Requirement
Issue
Design, location • Underpasses must be located as close as possible to, or
and installation of within, recognised fauna movement corridors and / or
dedicated fauna adjacent to areas of key habitat.
underpasses • Underpasses must provide an unobstructed view, for fauna
using an underpass, of the habitat or horizon on the other
side of the underpass. The location of the underpasses in
the embankment fills must be optimised to provide these
views.
• The design must ensure that fauna can view the entrance to
underpasses by careful placement of vegetation and other
features.
• Underpasses must be located and installed so that entrance
slopes are not steeper than 3:1 H:V nor rocky and must
provide suitable fauna passage.
• Clearance of natural vegetation adjacent to underpasses
must be minimised during construction.
• Scour protection associated with the entries and exits to
underpasses must accommodate and provide for the safe
and effective passage of fauna as detailed in Figure 5.3, be
constructed with the smallest reasonably possible rock size,
be as level as possible and have minimal gaps between the
rocks. Consideration must be given to the use of concrete
paths or other suitable surfaces in the scour protection to
provide for the safe and effective passage of fauna.
• Except for dedicated fauna underpasses under twin bridges
over Warrell Creek, dedicated fauna culvert underpass floors
and exit / entry points must provide dry fauna passage in 1
in 100 year average recurrence interval (ARI) events.
• Dedicated fauna underpasses under twin bridges over
Warrell Creek must maintain existing flood immunity.
Scope of Works and Technical Criteria Page 7 Appendix 5 RFT
Pacific Highway upgrade – Warrell Creek to Nambucca Heads Provisions for Fauna
Fauna Underpass
Issue
Requirement
Internal furniture • Durable refuge poles / horizontal poles must be installed features of inside underpasses where required by the Environmental dedicated fauna Documents and in underpasses that may be frequented by underpasses fauna species which are likely to use the structures. The
refuge poles must be designed to provide safe refuge for
fauna from predators and to encourage use of the
underpasses by smaller fauna species. The poles must be
located to one side of the underpasses. The structures must
be upright. Cross legged supports which block views and
access must not be used in the structures. Forks must be
installed at the top of refuge poles to provide a rest area for
fauna.
• The preferred medium on floors of dedicated fauna
underpasses is mulch.
External furniture • Durable refuge poles must be provided outside of features of underpasses, within 4 metres of the ends of the dedicated fauna underpasses. Flood impacts must be assessed and underpasses considered in determining the location of refuge poles.
Refuge poles must be 4 metres above ground with
diameters no greater than 25 cm at ground level.
• Unless otherwise agreed with EPA, cleared stumps / logs
must not be used at the ends of underpasses, as they can
be a fauna barrier and / or provide hiding areas for predatory
fauna and / or obstruct the view of habitat at the end of the
underpass.
Design • Combined underpass floors and exit / entry points must considerations for provide dry fauna passage during a 1 in 1 year ARI 3 day combined hour storm event and must not have wet sections that retain drainage and water for longer than three days. fauna
underpasses • Combined underpasses must be located and installed so
Scope of Works and Technical Criteria Page 8 Appendix 5 RFT
Pacific Highway upgrade – Warrell Creek to Nambucca Heads Provisions for Fauna
Fauna Underpass
Issue
Requirement
that entrance slopes are not steeper than 3:1 H:V nor rocky
and must provide suitable fauna passage.
• Scour protection associated with the entries and exits to
combined drainage / fauna underpasses must accommodate
and provide for the safe and effective passage of fauna as
detailed in Figure 5.3, be constructed with the smallest
reasonably possible rocksize, be as level as possible and
have minimal gaps between the rocks. Consideration must
be given to the use of concrete paths or other suitable
surfaces in the scour protection areas to provide for the safe
and effective passage of fauna.
• Durable refuge poles / horizontal poles must be installed
inside combined underpasses where required by the
Environmental Documents and in combined underpasses
that may be frequented by fauna species which are likely to
use the structures. The refuge poles must be designed to
provide safe refuge for fauna from predators and to
encourage use of the underpasses by smaller fauna
species. The poles must be located to one side of the
underpasses. The structures must be upright. Cross legged
supports which block views and access must not be used in
the structures. Forks must be installed at the top of refuge
poles to provide a rest area for fauna.
• Durable refuge poles must be provided outside of combined
underpasses, within 4 metres of the ends of the
underpasses. Flood impacts must be assessed and
considered in determining the location of refuge poles.
Refuge poles must be 4 metres above ground with
diameters no greater than 25 cm at ground level.
Design
considerations for
Main Carriageway
• Clearance of natural vegetation adjacent to the Main
Carriageway bridges must be minimised during construction.
Scope of Works and Technical Criteria Page 9 Appendix 5 RFT
Pacific Highway upgrade – Warrell Creek to Nambucca Heads Provisions for Fauna
Fauna Underpass
Issue
Requirement
bridges which are • Where a Main Carriageway bridge traverses a local road, it required to must provide dry, safe and effective passage of fauna. provide fauna
passage under • Scour protection associated with the entries and exits to
the bridge Main Carriageway bridges must accommodate and provide
for the safe and effective passage of fauna as detailed in
Figure 5.3, be constructed with the smallest reasonably
possible rock size, be as level as possible and have minimal
gaps between the rocks. Consideration must be given to the
use of concrete paths or other suitable surfaces in the scour
protection areas to provide for the safe and effective
passage of fauna.
Landscaping
within approaches
to dedicated fauna
underpasses,
combined
drainage and
fauna
underpasses and
Main Carriageway
bridges where
provisions must
be made for fauna
passage under
the bridge
• Clearing of existing vegetation near underpasses and
combined underpasses and bridges must be minimised.
• Revegetation near dedicated underpasses and combined
underpasses and bridges must be commenced as soon as
practicable after clearing of existing vegetation and within 3
months of completion of construction of each fauna
underpass and combined underpass and bridge.
• The density of vegetation planting or seeding must match
the surrounding natural habitat.
• Vegetation planted or seeded within an approach to either
an underpass or combined underpass and bridge must:
o not obstruct access to the underpass or bridge;
o be endemic and representative of the
surrounding natural habitat;
o be designed to attract native fauna species to the
structure, except where fauna exclusion fences
are not present; and
Scope of Works and Technical Criteria Page 10 Appendix 5 RFT
5.4
Pacific Highway upgrade – Warrell Creek to Nambucca Heads Provisions for Fauna
Fauna Underpass
Issue
Requirement
o not obstruct the views through, or disguise, the
entrance to the underpass or bridge.
Fauna Fences
The fauna fencing requirements of this Appendix 5 must be identified and addressed
within the Flora and Fauna Management Plan. The design of fauna fencing must be
undertaken and finalised in consultation and agreement with EPA. The fauna fencing
must be designed where required by the Environmental Documents to provide a
barrier to reptiles, snakes and frogs. The Contractor must comply with the fauna
fencing requirements identified in Table 2 and Table 3 and address these
requirements in the Design Documentation. The Contractor must also prepare and
keep records of all agreements reached with Authorities and include these records in
the Design Documentation.
5.4.1 Standard Fauna Fences
Standard fauna fencing must comply with the standard requirements detailed in
Table 2.
Table 2 Standard fauna fencing requirements
Fauna Fencing
Issue
Requirement
Type of fauna
fencing • Fauna fencing must be a heavily galvanised, floppy-top
mesh fauna fence designed in accordance with the drawing
MD.R201.D02.A and Appendix 15 of the Scope of Works
and Technical Criteria and must be unobtrusive. Plastic
coated fencing is not permitted.
• The extension of wire chain-lock mesh above the tops of
galvanised pipe posts must be sufficiently ‘floppy’ to prevent
climbing fauna from climbing over the fence. The floppy
extensions must face the fauna locations away from the road
carriageway.
Scope of Works and Technical Criteria Page 11 Appendix 5 RFT
Pacific Highway upgrade – Warrell Creek to Nambucca Heads Provisions for Fauna
Fauna Fencing
Issue
Requirement
Installation of
fauna fencing • Along the length of the fence, mesh one metre wide must be
attached to the base of the fauna fencing and laid over the
ground away from the carriageway to provide an effective
barrier to burrowing animals. The mesh must be pinned to
the ground with metal pins at least every metre without any
gaps between the mesh and the ground.
• The alignment of fauna fencing must not contain corners
with internal angles less than 135 degrees in order to
minimise the risk of fauna being trapped by predators.
• Fauna fencing must be designed and installed without sharp
edges which may cause injury to fauna or humans.
• Fauna fence returns must be provided to restrict fauna going
around the ends of fauna fencing, particularly where access
roads are located near to the ends of the fauna fencing.
Returns in fauna fences must:
o connect to the ends of fauna fences as defined in
Appendix 4 of the Scope of Works and Technical
Criteria; and
o extend a minimum 25 metres past the defined
ends of the fencing and must be curved away
from the road carriageways.
Location of fauna
fencing and visual
and urban design
issues
• Fauna fencing must be provided, as a minimum, where there
is an identified fauna movement corridor and in accordance
with the Environmental Documents and Scope of Works and
Technical Criteria.
• Fauna fences must be installed as close as possible to the
road, taking into account the visual and urban design
principles in Appendix 15 of the Scope of Works and
Technical Criteria, in order to:
Scope of Works and Technical Criteria Page 12 Appendix 5 RFT
Pacific Highway upgrade – Warrell Creek to Nambucca Heads Provisions for Fauna
Fauna Fencing
Issue
Requirement
o avoid drains, operational basins, rough
topography and the like which could be potential
fauna access points. Crossing drains must be
avoided wherever possible;
o provide maintenance access;
o provide greater revegetated habitat for fauna;
o allow fauna access to available fauna watering
points, including constructed wetlands; and
o avoid large trees which could fall across and
damage fences and thereby provide an avenue
for fauna to cross the fences.
• Where the fauna fences are installed on fills, the fences
must be set down below the top of the fills so that they are
less visible from vehicles but are easy to maintain. Tops of
fauna fences may be set at just below safety barrier levels
on fills so that they are unobtrusive. Fauna fences must be
located in less visible locations wherever possible.
• Fauna fences may be installed on the highest fill bench and
lowest cut batter bench to locate the fences closer to the
road. Fencing on cut batter benches must blend into the
surroundings and high quality landscaping must be provided
to screen the fences. Design of landscaping in the vicinity of
fauna fences must avoid vegetation with the potential to
grow to a size that overhangs the fencing, and prevents
fauna from entering the road way.
Fauna escape
mechanisms in
areas with fauna
fencing
• In areas where there are long distances of fauna fence,
provision must be made, in consultation with EPA, for fauna
escape points where practical. Escape points must prevent
fauna access into the road reserve area. The design of
Scope of Works and Technical Criteria Page 13 Appendix 5 RFT
Pacific Highway upgrade – Warrell Creek to Nambucca Heads Provisions for Fauna
Fauna Fencing
Issue
Requirement
escape points must take into account fauna species and
safe drop heights for fauna.
• Escape point design solutions may include:
o joining fauna fences up to structure wing walls,
allowing a small drop for fauna escape; and
o ramp structures with a drop for fauna as detailed
in Figure 5.1.
Fauna fencing at • Fauna fences must be installed between dual carriageway fauna bridges and culverts where there are gaps between underpasses and structures to prevent fauna accessing the median strip. combined fauna
underpasses and • Fauna exclusion fencing at underpass entrances must have
bridges wide angled openings to encourage usage by fauna. Fauna
fencing must be placed above fauna culvert structures or
join bridge structures as high as possible at the abutment
while locating the top of the fauna fence below the top of the
traffic barrier.
• Fauna fences must be joined to fauna underpass structures
without any gaps.
Fauna fencing
across drains, at
gates and at
detention ponds
and basins
Fauna fencing provided across drains and gates must prevent
fauna access.
Access to fauna
fencing Access must be provided to and along fauna fences for fence
maintenance and vegetation control. This access must be
suitable for a 2.5 metre wide vehicle.
Gates Access gates through the fauna fencing must be provided
without any gaps or holes that would allow fauna access when
shut. Gates must have a locking mechanism. Gates must be
Scope of Works and Technical Criteria Page 14 Appendix 5 RFT
Pacific Highway upgrade – Warrell Creek to Nambucca Heads Provisions for Fauna
Fauna Fencing
Issue
Requirement
located and sized to provide suitable access in the operational
phase. The floppy extensions in the fauna fencing must be
continuous over the gates.
Revegetation in • Native tree and shrub seeding and planting stock must not the vicinity of be used within 3 metres of fauna fences during the fauna fencing revegetation process.
• The Contractor must design revegetation to reduce vines
and heavy vegetation / grass growth in and adjacent to
fauna fences and suitable measures must be implemented
to reduce the extent of regrowth and maintenance. The
Contractor must provide in the Design Documentation
details of design and installation measures to address this
issue.
Maintenance and
inspections of the
fauna fencing
• Inspections and maintenance of the fauna fencing must be
addressed in the Flora and Fauna Management Plan.
• Fauna fencing must be designed and installed to facilitate
access for maintenance of the fauna fencing, including the
provision of access tracks and access to benches, gates and
any other fence infrastructure.
• Within 3 months prior to opening any section of the Works to
traffic, all fauna fences along the section of Works which is
to be opened to traffic must be installed and must be
inspected by the Contractor for:
o gaps in fauna fencing at drains, gates and other
areas;
o adequate pinning down of mesh;
o any vegetation located within 3 metres of the
fauna fencing which could allow fauna across the
fence; and
Scope of Works and Technical Criteria Page 15 Appendix 5 RFT
Pacific Highway upgrade – Warrell Creek to Nambucca Heads Provisions for Fauna
Fauna Fencing
Issue
Requirement
o any trees or branches located across the fence.
• A report on the inspection must be provided to RMS
Representative, including resolution of any issues arising
from the inspection
5.4.2 Frog Fauna Fences
Frog fauna fencing must comply with the requirements detailed in Table 3.
Table 3 Frog fencing requirements
Frog Fencing
Issue
Requirement
Type of fencing • Frog fencing is a separate fence to the standard fauna
fencing detailed in Table 2 and must include 1.5 mm
neoprene rubber sheeting running along the bottom half of
the fence with a length of pressed steel or aluminium
attached horizontally at the top of the rubber in accordance
with Figure 5.2.
Installation of • The rubber sheeting must extend flat on the ground for a fencing minimum 100 mm on the habitat side of the frog fencing.
• The lip of the pressed steel or aluminium must be located on
the habitat side of the frog fencing.
• Frog fencing must be designed and installed without sharp
edges which could cause injury to fauna or humans.
• Galvanised star pickets must be installed at 3.2 m intervals
or at a distance to ensure the top edge of the fence does not
sag.
Location of
fencing and visual
and urban design
• Frog fencing must be provided, as a minimum, where there
is identified habitat and/or breeding ponds for the Green-
thighed frog and in accordance with the Environmental
Scope of Works and Technical Criteria Page 16 Appendix 5 RFT
Pacific Highway upgrade – Warrell Creek to Nambucca Heads Provisions for Fauna
Frog Fencing
Issue
Requirement
issues Documents and Scope of Works and Technical Criteria.
• Frog fences must:
o be installed as close as possible to the road,
taking into account the visual and urban design
principles in Appendix 15 of the Scope of Works
and Technical Criteria;
o be located between the road and associated
drainage (including catch drains, table drains and
the inlet and outlet of transverse and longitudinal
drainage structures);
o avoid rough topography; and
o be provided with maintenance access;
• Rubber sheeting must be black or a similar dark colour to be
less visible and blend into the surrounding environment.
Revegetation in
the vicinity of frog
fencing
• Native shrub seeding and planting stock must not be used
within 1 metre of frog fencing as part of any revegetation.
• Revegetation must be designed to reduce vines and heavy
vegetation / grass growth in and adjacent to frog fences and
suitable measures must be implemented to reduce the
extent of regrowth and maintenance. Details of design and
installation measures to address this issue must be provided
in the Design Documentation.
Maintenance and
inspections of the
frog fencing.
• Inspections and maintenance of the frog fencing must be
addressed in the Flora and Fauna Management Plan.
• Within 3 months prior to opening any section of the Works to
traffic, all frog fences along the section of Works which is to
be opened to traffic must be installed and must be inspected
Scope of Works and Technical Criteria Page 17 Appendix 5 RFT
5.5
Pacific Highway upgrade – Warrell Creek to Nambucca Heads Provisions for Fauna
Frog Fencing
Issue
Requirement
by the Contractor for:
o sagging of the top edge of the fence;
o adequate laying of the rubber sheet;
o gaps between the pressed steel or aluminium
and the rubber sheet; and
o any shrub vegetation located within 1 metre of
the frog fencing which could allow frogs across
the fence.
• A report on the inspection must be provided to RMS
Representative, including resolution of any issues arising
from the inspection.
Waterway and Drainage Structures
Transverse drainage structures must be “fish friendly”, accommodate the needs of
fish and must comply with the requirements detailed in Table 4. Fish friendly
drainage structures must be identified within the Flora and Fauna Management Plan.
The design of fish friendly drainage structures must be undertaken in consultation
with Department of Primary Industries (Fishing and Aquaculture). The design of fish
friendly drainage structures must comply with the Environmental Documents,
Department of Primary Industries (Fishing and Aquaculture) guidelines identified in
Appendix 8 of the Scope of Works and Technical Criteria and address the
requirements in Table 4. The design must match preferred crossing type to
waterway type in accordance with Why do Fish Need to Cross the Road, Fish
Passage Requirements for Waterway Crossings, NSW Fisheries, January 2003.
The Contractor must comply with the requirements identified in Table 4 and address
them in the Design Documentation. The Contractor must prepare and keep records
of all agreements reached with agencies and include these records in the Design
Documentation.
Scope of Works and Technical Criteria Page 18 Appendix 5 RFT
Extract from SWTC Appendix 4 4.15 Ecological Monitoring Program (a) Further to and as a consequence of condition B10. of the Planning and Infrastructure Minister's Approval and commitment F13 of the Statement of Commitments, RMS has commissioned Benchmark Environmental Management to develop an ecological monitoring program, noting that the program is based on and only addresses the impacts associated with the assumptions and inputs, including an assumed concept design, identified in the program and not the Final Design Documentation. The program is titled “Warrell Creek To Urunga Pacific Highway Upgrade Ecological Monitoring Program Stage 2: Nambucca Heads To Warrell Creek” (“Ecological Monitoring Program”)” and is Information Document 250. (b) The Contractor must implement the: (i) requirements of the Ecological Monitoring Program; and (ii) other requirements; (iii) which are detailed in section 14.9 of Appendix 14 of the Scope of Works and Technical Criteria. Extract from SWTC Appendix 14 14.9 Ecological Monitoring Program (a) Further to section 4.15 of Appendix 4 of the Scope of Works and Technical Criteria, the Contractor must implement the mitigation methods and ecological monitoring methods detailed in in the Ecological Monitoring Program in:
(a) section 2,1;
(b) section 2,5;
(c) section 2.6;
(d) section 3.2 except for submission of reports to EPA;
(e) section 3.9; and
(f) Table 4.1 with respect to “Clearing Procedures”. (b) In addition, the Contractor must prepare the clearing report required by section 5 of the Ecological Monitoring Program.
MD.R201.D02.A
NOTE
NOTE
Post
FAUNA EXCLUSION FENCE
3 1
14 Gauge Tek screw( fixed to vertical postto prevent rotation )
Galvanized weather caps on all posts
twisted tightly together
400
mm
Ground Mesh
Fastening Pins
32 NB galvanized steel pipe
Strainer struts at fence angles
Fence line.
PLAN OF FENCE ANGLE
Strainer struts at fence angles
32 NB galvanized steel pipe
Varying L
engths
o
o
ELEVATION
FASTENING PIN DETAIL
GROUND MESH FIXING DETAIL
45
All dimensions are in millimetres unless otherwise shown.
GroundGroundGround6
00
90
0
90
0
25
Max. 4000 @ endsMax. 4000 between uprights
50
0
20
0
Pins @ 1000 c / c
11
67
60
0
10
00
11
67
Mesh to overhang min. 500
ROAD SIDE
100
min.
For loose or sandy soils
350 (min.) galvanised
fastening pins must be used
2 x 3.15 dia. wires
Fir
st I
ssued :
Ju
ly 2009
Galvanized steel
intermediate post 32 NM min.
(XL 350 structural grade pipe)
erected vertically
Cable ties at 350 (max.) intervals
See Sheet 3
For Footing Details
Galvanised steel
corner or strainer
post 50 NB min.
( XL 350 structural
grade pipe) - Erected
vertically
This side of fence to face the side of fauna habitat
20
0
7 Hot Dipped
Galvanized Steel Pin
Connect 2.5 mesh to
3.15 mesh @ 210 centres
and overlap
50 chain-link fencing fabric 2.5 dia. heavily
galvanized wire.( Knuckle / Knuckle mesh )
Min internal angle 135
Fix laps within
100 horizontally
both sides of the
post
50
TY
PIC
AL
3.15 dia. heavily galvanized wire
50 chain-link fencing fabric
( Knuckle / Knuckle mesh )
AMENDMENT DETAILS DATE
SCALE No. OF SHEETS SHEET No.
DRAWING NUMBER
Roads and Traffic Authority, NSW
N.T. S
MD.R201.D02.A
INTERMEDIATE POST AT LOW POINT
GENERAL
FAUNA PROTECTION DRAINAGE DETAILS
20%
FAUNA EXCLUSION FENCE
3 2
All dimensions are in millimetres unless otherwise stated.
11
67
2.5 mesh to be pinned
over concrete drain.
1500
100 min.
NOTE
At drainage lines and gates light corrosion - resistant
metal flap to be installed with less than 50 gap.
Flap to be designed to suit hydraulic flows and drain
shape in stormwater flow paths.
Metal flap to be connected to fence on downstream side of fence.
90
060
0
Ground
Ground
Footing 900 x 200
( Applies where post RLs
vary by more than 800 )
Concrete Drain
FAUNA
HABITAT
SIDE
Metal Flap
60
0
Ground
Ground
Max. 4000 between uprights
Fasting pins @ 300 centres
Pins to be min. 300 x10 dia.
hot dip galvanized.
For vertical curve sags
intermediate post footing
increased to prevent uplift
ELEVATION
Fir
st I
ssued :
Ju
ly 2009
Posts set in 200 dia.
concrete footing
(See sheet 3 for details)
AMENDMENT DETAILS DATE
SCALE No. OF SHEETS SHEET No.
DRAWING NUMBER
Roads and Traffic Authority, NSW
N.T. S
Floppy top mesh
continuous lapped
( not Fixed )
4000 3000
Hinges to be installed on either
side to allow for correct
openingCable ties at 350 (max.) intervals
Galvanized steel
pipe 32 NM min.
(XL 350 structural
grade pipe)
32 NB galvanised
steel pipe strainer
struts at fence angles
Crank to be angled to allow
for opening of gate
(hinge side only)
3.15 dia. heavily galvanized wire
50 chain-link fencing fabric
( Knuckle / Knuckle mesh )
Locking
MD.R201.D02.A
50 NB Galv Post32 NB Galv Post
INTERMEDIATE POSTS FOOTING DETAILS AT LOW POINT
INTERMEDIATE POSTS FOOTING DETAILS
FAUNA EXCLUSION FENCE
3 3
WITH GATE
All dimensions are in millimetres unless otherwise shown.
1167
50 NB pipe
( XL 350
structural grade
pipe)
50 NB pipe
( XL 350
structural grade
pipe)
Ground
20 d
om
ed c
oncre
te
20 d
om
ed c
oncre
te
Posts set in 200 dia.
concrete footing
60
0
Minimum
20 MPa
concrete.
Minimum
20 MPa
concrete.
90
0
90
0
90
09
00
32 NB Galv Post
20 d
om
ed c
oncre
te
Minimum
20 MPa
concrete.
90
0
100
min.
Posts set in 300 dia.
concrete footing
Posts set in 300 dia.
concrete footing
Posts set in 200 dia.
concrete footing
Posts set in 200 dia.
concrete footing
MAINTENANCE GATE DETAILS
Fir
st I
ssued :
Ju
ly 2009
Ground mesh not fixed
at upturn to gate structure
to allow for opening of gate
STRAINER & CORNERPOSTS FOOTING DETAILS
Chain
AMENDMENT DETAILS DATE
SCALE No. OF SHEETS SHEET No.
DRAWING NUMBER
Roads and Traffic Authority, NSW
N.T. S