VLBA Operational Status

16
Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array VLBA Operational Status Ongoing and Possible Future Upgrades Walter Brisken NRAO, Socorro

description

VLBA Operational Status. Ongoing and Possible Future Upgrades. Walter Brisken. NRAO, Socorro. Current capabilities of the VLBA. 45 baselines from 10 identical 25m antennas Peak / sustainable record rate is 512 Mbps 64 MHz/polarization with 2-bit samples - PowerPoint PPT Presentation

Transcript of VLBA Operational Status

Page 1: VLBA Operational Status

Atacama Large Millimeter/submillimeter ArrayExpanded Very Large Array

Robert C. Byrd Green Bank TelescopeVery Long Baseline Array

VLBA Operational StatusOngoing and Possible Future Upgrades

Walter BriskenNRAO, Socorro

Page 2: VLBA Operational Status

Current capabilities of the VLBA

• 45 baselines from 10 identical 25m antennas• Peak / sustainable record rate is 512 Mbps

– 64 MHz/polarization with 2-bit samples• Operates at select bands between 330 MHz and 90 GHz

– Dual band 2.2 / 8.4 GHz supported• 1-hour continuum sensitivity at 8.4 GHz = 54 Jy RMS• Angular resolution at 8.4 GHz is 1x2 mas• Absolute astrometry to a precision of 100 as• Relative astrometry to a precision of 10 as• Flexible correlation with DiFX

– Can correlate at ~700 Mbps x 10 antennas for typical projects

– 16 playback Mark5 units available– Transient processor

2

Page 3: VLBA Operational Status

VLBA Sensitivity Upgrade Project(http://www.vlba.nrao.edu/memos/sensi/)

• Goal: increase peak bandwidth to 4 Gbps• Began as a project in 2007• Three major components of the upgrade are:

– New correlator• DiFX software correlator was ultimately chosen

– New data recorder• Mark5C, developed by Haystack/Conduant/NRAO

– New antenna back-end electronics• ROACH FPGA-based Digital Back End (RDBE) in

development• Project funded (including media) to complete 2 Gbps capability

– Funding from NRAO, NSF MRI grant and Conacyt (via UNAM)– Initial availability to astronomers anticipated this summer

3

Page 4: VLBA Operational Status

Mark5C recorder• Evolution of Mark5A/B recorder• Records packets transmitted over standard 10 Gb Ethernet• Single module operation demonstrated at 2 Gbps• Dual module operation at 4 Gbps plausible

– Has strong operational downsides– Software for this mode incomplete; mode not yet

testable– Alternatives for > 2 Gbps are being explored

4

Page 5: VLBA Operational Status

ROACH Digital Back-End (RDBE)• Collaborative project

– Hardware: CASPER, KAT, NRAO– Firmware/software: Haystack, NRAO

• One rack-mount chassis contains:– Analog step attenuator– Frequency synthesizer– Two samplers operating at 1 Gsps– 1 Roach board (Xilinx Virtex SX95 FPGA, PPC, QDR memory, …)

• Will replace existing baseband converters, samplers and formatters

• First firmware version, a polyphase filterbank, is nearing completion– 16x 32 MHz channels with coarse tuning

• The digital down-converter version will be much more flexible– Up to 8 (maybe 16 ultimately) fully configurable channels

• Two RDBEs will be installed at each antenna

5

Page 6: VLBA Operational Status

VLBA Sensitivity Upgrade Status

• First fringes were seen in August 2010– One month after first RDBE fringes achieved by

Haystack• 6 antennas demonstrated at 2 Gbps earlier this month• The stability and feature completeness is improving• 2 Gbps observing capability has been advertised in the Jan

7, 2011 VLBA Call for Proposals • Upgrades to the DiFX cluster are on order to increase

throughput to ~2 Gbps for 10 antennas• Early science to begin late March, 2011• First production science on full array expected at end of

June, 2011

6

Page 7: VLBA Operational Status

Wideband C-band Receiver Project• Goal: upgrade the existing 4.6-5.1 GHz receivers

– Main driver: access to the 6.7 GHz methanol maser line for measuring Galactic structure and kinematics (c.f. Reid & Menten)

• Will make use of EVLA technology to extend range from 4.0 to 7.9 GHz

• Down-converter will allow two separate 512 MHz IF pairs to be attached to this receiver

• Major components of this upgrade include– Retrofitted receiver with new Low Noise Amplifiers– New feed– New down-converter– Upgraded (EVLA-based) monitor and control system

• First prototype to be installed in summer 2011• Project to be completed in summer 2012

7

Page 8: VLBA Operational Status

Wideband C-band Receiver Performance

8

Page 9: VLBA Operational Status

Fiber Links to Pie Town and Mauna Kea

• USNO is funding installation and operation of fiber links to PT and MK to the USNO correlator in Washington

• Purpose is rapid eTransfer (non-real-time) of daily UT1-UTC data– Links will be too slow (1 Gbps shared link) to replace

data recorders• Baseline plan includes one USNO Mark5C unit per station

– Alternatives that will be mutually beneficial are being discussed

• David Boboltz to say more…

9

Page 10: VLBA Operational Status

Other Possible VLBA UpgradesI. New capabilities

• Ka-band receivers (costed at $1.6M)• Installation of additional dichroics for dual-band operation

– K/C– Ka/X

• Develop/install an ultra-wideband receiver• New sub-GHz feeds+receivers

– NRAO & NRL are exploring options for EVLA– Is there VLBI demand for this?

• Pie Town-EVLA link– Enhanced version of previous capability

• Wide-band existing receivers– 22 GHz (K-band) for high-z water maser work

10

Page 11: VLBA Operational Status

Other Possible VLBA UpgradesII. Sensitivity enhancements

• Upgrade the data transmission system beyond 4 Gbps– Astro 2010 white paper set goal of 32 Gbps (4 GHz/pol)

• Implement burst mode• Upgrade the Low Noise Amplifiers of the 43 GHz (Q-band)

receivers• Complete holography to improve the dish surface for 86

GHz (W-band)• Install a 86 GHz receiver on Hancock• Increase number of stations!

11

Page 12: VLBA Operational Status

Other Possible VLBA UpgradesIII. New calibration equipment

• Complete installation of dual-frequency GPS receivers– 5 sites remaining

• Develop & install water vapor radiometers– By default this will await such developments on the

EVLA• Installation of 6 m to 12 m diameter phase reference

antennas at each VLBA site– Increases on-source time– Multiple antennas would provide further capabilities

12

Page 13: VLBA Operational Status

Other Possible VLBA UpgradesIV. Infrastructure improvements

• Widen the analog intermediate frequencies (IFs)– Major overhaul to the LO/IF system– Required to transcend the 8 Gbps limit (4 Gbps limit for

most bands)– Not cheap, but possibly synergistic with SKA development

• Complete the migration to the EVLA monitor and control system

• Upgrade the antenna control unit• Acquire a spare hydrogen maser• Array-wide eVLBI

– Not expected to be affordable for most kinds of work– Needed only for a very limited set of applications

• Further increase media pool

13

Page 14: VLBA Operational Status

Back-up slides to follow…

14

Page 15: VLBA Operational Status

VLBA Observing time• Total Hours Used: 2008 2009 2010

– Hours observed: 3093 3572 4678– Mean data rate: 254 Mbps 282 Mbps 344 Mbps– Hours normalized to 256 Mbps: 3069 3934 6290

• What is the bottleneck? (1 year ~ 8700 hours)– Media and correlator throughput currently limit total throughput– Maintenance and test time have impact on available time– Dynamic scheduling does not lend itself to 100% efficiency

• Many projects demand good weather at many sites• Many projects must be run at a predefined time and/or day• However, scheduled projects produce high quality data

– Scheduling efficiency is improving

15

Page 16: VLBA Operational Status

VLBA Key Science Projects• Projects addressing unusually important questions assigned KSP

status– Improved scheduling priority & data quality scrutiny– KSPs are carefully considered when making policy decisions

• Want to promote and preserve the best science• Some example KSPs (mostly astrometric)

– Galactic maser astrometry to yield structure of the Milky Way• A strong impetus behind the C-band receiver upgrade

– Stellar astrometry in star forming regions in Gould’s belt• Yields multiplicity of systems, distances (hence luminosity),

3-D structure of star forming region– An accurate distance to the Pleiades star cluster

• To resolve important, long standing dispute – Megamaser cosmology project

• Distances to galaxies with Keplarian H2O maser disks

• Determine central black-hole masses

16