MANAKAMANA ENGINEERINGHYDROPOWER COMPANY(P) LTD.
GhatteKholaSmallHydropowerProjectDolakha
CONSULTINGSERVICES AND
CONSTRUCTIONSUPERVISION
MONTHLYPROGRESSREPORT
March 2017
Submitted By:
TAC Hydro Engineers Pvt. Ltd.
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report March 2017
TABLE OF CONTENTTABLE OF CONTENT i
LIST OF ANNEXES ii
LIST OF ABBREVIATIONS iii
SALIENT FEATURES OF THE PROJECT iv
PROJECT LOCATION MAP viii
1 GENERAL 1
1.1 Introduction 1
1.2 WorkNature 1
1.3 ReportSetup 2
2 PROJECTMANAGEMENT 2
2.1 OrganizationalSetup 2
2.2 ConstructionManagement 2
2.3 VisittotheWorkSite 3
3 PROJECT ENGINEERING 3
3.1 Major EngineeringActivities 3
3.2 Major Construction Activities 4
3.2.1 Civil Works 4
3.2.2 Hydromechanical Works 5
3.2.3 Electromechanical Works 5
3.2.4 Transmission Line Works 5
4 CLAIMSANDVARIATIONS 5
5 CONCLUSIONANDRECOMMENDATION 5
TAC Hydro Engineers Pvt. Ltd. i
TAC Hydro Engineers Pvt. Ltd.
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report March 2017
LIST OF ANNEXESAnnex–A ListofpersonneloftheEmployer,theConsultantandtheContractor
Annex–B ProgressSheets
Annex–C DeviationsinTimeSchedule
Annex–D MostImportantActivities:DelaysActivities
Annex–E Photographs
TAC Hydro Engineers Pvt. Ltd.
ii
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report March 2017
LIST OF ABBREVIATIONS
BOK
COD
-
‐Bank of Kathmandu Limited
CommercialOperationDate
CMA ‐ ConstructionManagementAdvisor
DoED ‐ DepartmentofElectricityDevelopmentDS ‐ Downstream
EM ‐ Electro‐mechanical
HW ‐ Headwork
HM ‐ Hydro‐mechanical
HR ‐ Headrace
NEA ‐ NepalElectricityAuthority
PC ‐ Penstock
PH ‐ Powerhouse
PPA ‐ PowerPurchaseAgreement
JV ‐ JointVenture
RCOD ‐ RequiredCommercialOperationDate
SHEP ‐ SmallHydroelectricProject
SS ‐ Substation
TACHydro ‐ TACHydroEngineersPvt.Ltd.
TR ‐ Tailrace
TL ‐ TransmissionLine
US ‐ Upstream
VCB ‐ VacuumCircuitBreaker
TAC Hydro Engineers Pvt. Ltd.
iii
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report March 2017
SALIENT FEATURES OF THE PROJECTProject Location : MarbuVDC
ofDolakh
aDistrict,CentralDevelopmentRe
gion, Nepal
Longitude : 27o46′25″Nto27o47′14″N
Latitude : 86o17′00″Nto 86o18′35″N.
Type : RORSmallHydro
Hydrology
Catchment Area (Intake Site) : 30 km 2
(Total) Average Flow : 3.20 m3/s
DesignFlow : 1.78 m3/s (Q40)
1:100yearsflood : 90.70 m3/s
Weir
Type : Concretediversionweir
withcontrolledspillway
CrestElevation : 1906.00 masl
CrestLength : 15.00 m
Maximum Height : 5.00 m (From Foundation)
TAC Hydro Engineers Pvt. Ltd.
iv
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report March 2017
Intake
Type : OrificeIntake
InvertLevel : 1904.5 masl
NormalWaterLevel : 1906.00 masl
WidthxHeight : 3.0 m x0.40 m
Undersluice
InvertLevel : 1901.5 masl
NormalWaterLevel : 1906.00 masl
WidthxHeight : 2.0 m x2.5 m
Desander
Type : Dufour
Length : 38.00 m
Width : 3.00 m
Depth : 4.20 m
Flushing : Simple headcutting (Inthemonsoon)
Water Conveyance System(Headrace Pipe)
Length : 2085 m
Diameter : 1.3 m
Thickness : 6 mm
Surge Tank Dimensions
Height : 17 mTAC Hydro Engineers Pvt. Ltd.
v
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report March 2017
Diameter : 3.5m
NormalWater Level : 1904.44 msl
StaticWater Level : 1906.44
mslMinimumDownsurgelevel : 1894.23
mslMaximum upsurge level : 1912.44
mslInvertLevel ofPenstockIntake: 1892.94 msl
Surface Penstock/ Manifold
PenstockLength : 1015. m
Diameter (Internal) : 0.90
mThickness(Steel) : 6 mm to
15 mmNumber ofAnchorBlocks : 20
ManifoldLength :
8.0
mDiameter (Internal) :
0.64 m
Thickness(Steel) : 15 mm
PowerFacilities
Powerhouse Type : Surface
Dimensions(LxBxH) : 24.00 m x10.00
mx14.00 mGrossHead : 345.20m
NetHead : 338.47m
Installed Capacity(Q40) : 5000
KWAverage Annual EnergyOutput :
29.87GWhEnergyOutput(DrySeason) :
4.4
GWhEnergyOutput(Wet Season) : 25.4
GWh
TAC Hydro Engineers Pvt. Ltd.
vi
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report March 2017
TransmissionLineandSustation
TransmissionLine : 14.0 km (33 kV Single Circuit)
Sub station : Singati
Cost
Total Cost with Financing : Rs. 87.63 Crore
Loan Amount : Rs. 61.00 Crore
Promoter Equity : Rs. 26.63 Crore
Cost per MW : Rs. 17.53 Crore
Revenue per MW : Rs. 2.90 Crore
Financial Indicators
Financial Cost : Rs. 87.63 Crore
IDC : Rs. 6.13 Crore
IRR : 13.84 %
Return on Equity : 18.52 %
NPV : Rs. 24,705 thousand
Benefit Cost Ratio (B/C) : 1.33
Debt Service Capacity Ratio : 1.62
Payback Period - Simple : 6.47 years
Payback Period - Discounted : 10.81 years
Construction Period : 1.5 Years
TAC Hydro Engineers Pvt. Ltd.
vii
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report March 2017
PROJECT LOCATION MAP
TAC Hydro Engineers Pvt. Ltd.
viii
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report March 2017
1 GENERAL
1.1 Introduction
GhatteKholaSmallHydroelectricProjectwithinstalledcapacityof5000kW,beingconstructedbyM
ANAKAMANAENGINEERINGHYDROPOWERCOMPANY(P)LTD.,isin the preliminary
phase of construction.ConstructionsiteofthisprojectisattheGhatteKhola,Marbu‐VDC,Dolakha,whichisatributaryofKhareRiver.Thisisarun‐off‐riverscheme with orifice side
intake. The proposed headworks site is located on the left bank of Ghatte Khola about 100 m
downstream from the confluence of Thado Khola and Ghatte Khola at an elevation of 1906
masl in MarbuVDC-7. Similarly, the powerhouse site has been proposed on the left bank of
Ghatte Khola around 125m upstream of the confluence of Khare Khola and Ghatte Khola in
the same VDC at an elevation of about 1575 masl.
Geographically,theprojectislocatedinbetwee
n86°17′00″Nto86°18′35″NLatitudesand27°46′25″Nto27°47′14″NLongitudes.
Waterwillenterintothesystemthroughorificesideintakeontheleftbankoftheriver.Diversionweiris
ofnon‐regulatedtype,withOrificetypeintake&oneunder‐sluiceontheleftbank.Waterwillbecarriedt
othe32m.longdoublechamberdesandingbasinthrough30mlongpowercanalhaving7m long
spillway.Waterisconveyedthrougha2234mlongsteelheadracepipehaving1300mmdiameterand1
015mlongsteelpenstockpipe.Circular Steel Surge Tank of diameter 5m is used to regulate the
surge.
Therearetwonumbersofpelto
nturbineseachofinstalledcapacity2500kW.A14.5kmlong33kVtransmissionlinewillfeedgener
atedpowerfromthePowerhouse(switchyard)toSingatisubstation.
1.2 WorkNature
Constructionworkcomprisesof construction of access road to Headworks and Powerhouse,
civilworksatheadworks,headrace
alignment,penstockandpowerhousearea,fabricationanderectionofsteelpipeforheadraceandpenst
ockpipe,installationandcommissioningofelectromechanicalequipmentinpowerhouse,switchyar
TAC Hydro Engineers Pvt. Ltd.
1
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report March 2017
dandSingatisubstation,erectionoftransmissionlineandotherrelatedworks.
Sakurapower/Biruwa/DivyajyotiJ.V. has been selected for the construction of all civil works.
Hydromechanical and electromechanical contractor are yet to be selected. Consulting and
construction supervision has been awarded to TAC Hydro Engineers Pvt. Ltd.
17km.ofMotorabletrackgoesfromSingatitoMarbu(Powerhousesite).Singatiisconnecte
dtoCharikot(DistrictHeadquater) by 47km. good gravel road. 450 m access road to
Powerhouse has been constructed to reach the Powerhouse and 500 m to reach Headworks
along Ghatte khola.Theoveralllengthoftrackopening for waterway alignment is around 2234
m.Atpresentfullloadedtruckcanreach to the Surge Tank area and opening of proposed access
road towards Headworks and Powerhouse.
1.3 ReportSetup
TACHydrowas responsible for carrying out the detailed design of the project. In addition, it
has been awarded the consulting services for the engineering supervision of all the
construction works going on at site including managerial activities at Kathmandu office.
ThisisMonthlyProgressReportforthemonthofMarch2017,whichconsistsofanaccountofpre-
construction and
constructionactivitiesofcivilstructures,hydromechanicalcomponents,electromechanicalequipm
ent,transmissionlineandprojectinfrastructurescarriedoutinthepastmonth,majorproblemsarisen,d
eviationsfromtheoriginalworkingscheduleandthecatch‐upplans,photographsofprogressesmadeinthelastmonthsandotherrelevantdetails as per the
activities being carried out.
ThisreportincludesthefollowingAnnexes:
ListofpersonneloftheEmployer,theConsultantandtheContractoraregiveninAnnex–
A.ProgressSheetsaregiveninAnnex–B.DeviationsinTimeScheduleispresentedinAnnex–
C.MostImportantActivities:DelayedActivitiesareshowninAnnex‐DandphotographsarepresentedinAnnex‐E.
2 PROJECTMANAGEMENT
2.1 OrganizationalSetup
TAC Hydro Engineers Pvt. Ltd.
2
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report March 2017
ThisprojectisunderdirectsupervisionofCompany’sDirectors.TACHydroassiststheManage
mentbylookingafterallthetechnicalmattersoftheProject.Allotherissuesaredirectlytakenover
bytheManagement.
2.2 ConstructionManagement
OneofthedirectorsoftheCompanyisplannedtobestationed
atsite,sothatimmediatedecisionscanbemadewheneverneeded.Technicalmattersareallhandledbyt
heengineersdeputedatsitefrom the Consultant, TACHydro. There isoneCivilEngineerand two
CivilSub‐Engineers / surveyorstationedatsite. Considering work progress one more engineer
and two supervisors shall be deputed at site.Otherkindsofengineeringprofessionals wi l l
handlethetechnicalmattersfromKathmandu,andthey willvisitsiteeverynowandthen.During gate
erection and electromechanicalinstallationworks, one Mechanical and
electricalengineeralong with supervisorshallbedeputedatsite.
2.3 VisittotheWorkSite
Projectofficials,Consultantsandbank’srepresentativesfrequentlyvisittheworksitetoapprisethems
elvesoflatestsituation.
3 PROJECT ENGINEERINGAnAgreementwassignedbetweenManakamanaandTACHydroforConstructionSupervisionand
management
ofsiteworksoftheProject.Aspertheprovisionsandscopeofconsultingservices,theConsultantmake
saconstantcontrolandmonitoringofContractor’sworkswithintheframeworkoftheTechnicalSpeci
ficationsandreportstimelytotheProject,withsuggestionsandrecommendationsforfurtheractions.
TheConsultantalsomakesobservationsofoverallprogressatsiteandchecksitagainstthetimeschedu
leoftheProject.TheConsultantalsoindicatesthoseactivitieswhicharelaggingandneedspecialattent
ionandeffortstocompletetheactivitiesinordertocatchuptheschedule.
3.1 MajorEngineeringActivities
Followingarethemajorprojectactivitiesintheperiodofthisreport:
TAC Hydro Engineers Pvt. Ltd.
3
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report March 2017
i. After few days rainfall, unexpected landslide occurred in the power house area.
Immediate site visit was made by Geologist and Senior Hydropower Engineer and
recommended to shift the power house to the best available location (i.e. 75 m
upstream of the landslide area ) considering long term safety of Power House.
ii. Power house design as per Electromical Requirement has been received from the EM
Supplier (Flovel India). After reviewing it by the consultant considering site condition
and structural requirement, Flovelindia has revised the drawings few times. The
supplier has provided the loading diagram and structural design from TAC Hydro is
ongoing.
iii. A team comprising of Mr. K B Uprety (Client, Chairperson) , Mr. BigyanGhimire
(BOK Lumbini), Mr. Prahlad Chaudhary (Consultant, Project Coordinator) and Mr.
UjjwalPrajuli (Consultant, Mechanical Engineer ) had made a visit to pipe
manufacturer, China. Manufacturing of Spirally Welded Pipe is ongoing. Mr.
UjjwalPrajuli has been deputed in the factory to inspect and maintain the quality
control. He will be back once the manufacturing and quality check of SW pipe
completes.
iv. Bids for fabrication of gates and installation of all hydro mechanical componentshas
been received and opened. Bidder have been sort listed and shall be called for
negotiation.
v. Inspection, measurement and quality control of civil construction works (construction
materials, excavation, bar bending schedule, concreting etc.)
vi. Internal Discussionandplanningofconstructionworks.
vii. Discussion and planning of construction works with the contractor for the full
mobilization of human resource.
viii. SuggestionsandrecommendationsforImprovingthespeedofconstructionworks.
ix. Discussion and carrying out all other day to day engineering matters like attending
meetings regarding project with Banks, DOED, NEA as required by Clients.
3.2 Major Construction Activities
3.2.1 Civil Works
TAC Hydro Engineers Pvt. Ltd.
4
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report March 2017
i. About 70% (7150m3) of excavation work at new power house location has been
completedtill the preparation of this report. Out of the excavated material, 79%
material is Boulder mixed soil (BMS) and remaining 21% is rock (Boulder).(1510).
ii. Construction of access road (About 500 m stretch) to headworks area has been
completed.
iii. Site clearance and sorting of boulder for rip rap in weir area.
iv. Foundation preparation for river training works (Gabion wall) at the left bank near
power house area has been completed and about 80 m3 gabion has been constructed.
3.2.2 Hydromechanical Works
3.2.2.1 Procurement and Transportation of Spirally Welded Pipe
SW Pipe is being manufactured in china. Mr. UjjwalParajuli (Mechanical
Engineer),consultant’s representative is at factory for quality control.
3.2.2.2 Fabrication and Installation of Gates and Pipes
Bids for the above-mentioned work has been received and opened. Bidders shall be
called for negotiation soon.
3.2.3 Electromechanical Works
Flovel India is manufacturing Electromechanical equipment’s. Drawings have been
revised few times considering site and structural requirement. Detail design of power
house is ongoing.
3.2.4 Transmission Line Works
Survey work for transmission route from Power House to Bhorle bridge is completed.
Remaining survey work from Bhorle to Singati Sub station is planned to continue
from mid of April.
4 CLAIMSANDVARIATIONSNoissueofclaimsandvariationshasbeenarisensofar.
5 CONCLUSIONANDRECOMMENDATIONThe report is concluded with following recommendations:
i. Crusher plan will start to produce construction material from the mid of April.
TAC Hydro Engineers Pvt. Ltd.
5
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report March 2017
ii. Site has been closed time and again due to disturbance of local people regarding work.
After multiplenegotiation with the local people interested in construction activities,
understanding has been made to provide them work considering their capability and
start work at headworks area and written consent was made for no further disturbance.
iii. It was planned to construct weir before this monsoon. However,due to disturbance
from local people of Headworks, excavation work at headworks has been delayed.As a
result, weir clearance and excavation work shall be carried out before this monsoon
and concreting work shall be done just after the monsoon.
iv. Excavation at power house is going on and shall be completed by the first week of
April if the underground soil condition is as expected.
v. Selection of cement and reinforcement after laboratory testing of their material
properties like compressive strength and tensile stress.
vi. Immediate Opening of LC for construction material purchase (Reinforcement and
Cement)
vii. It is recommended to select HM contractor immediately so that camp and workshop
can me made ready for the fabrication of bend and frames in the first stage.
TAC Hydro Engineers Pvt. Ltd.
6
Consulting Services and Construction Supervision of Ghatte Khola SHP Progress Report March 2017
TAC Hydro Engineers Pvt. Ltd.
7
Consulting Services and Annex A Construction Supervision of Ghatte Khola SHP Progress Report March 2017
LIST OF PERSONNEL
EMPLOYER: Manakamana Engineering Hydropower Pvt. Ltd.Name of Project staff deputed in the ProjectS.N
Name Designation
Staffs deputed at site / Frequent site visit1 Tek Prasad Chaulagain Managing Director2 Tilak Aral PRO / Management Officer3456789
1011121314
Staffs deputed at KTM office12345
TAC Hydro Engineers Pvt. Ltd. i
Consulting Services and Annex A Construction Supervision of Ghatte Khola SHP Progress Report March 2017
CONSULTANT: TAC Hydro Engineers Pvt. Ltd.Name of staffs involved in Ghatte Khola SHP
S.N
Name Designation Remarks
1 Prahlad Chaudhary Technical Coordinator Frequent visit to site2 DipeshThapa Project Manager Frequent visit to site3 Balkrishna Pangeni Resident Engineer Site Stationed4 Nagendra Chaudhary Electrical Engineer Frequent visit to site5 BishnuShiwakoti Geologist Frequent visit to site6 Ghanshyam Rana Sub-Engineer Site Stationed7 Chandra Thapa Sub-Engineer / Surveyor Site Stationed
CONTRACTOR: Sakurapower/Biruwa/DivyajyotiJ.V.Name of staffs involved in Ghatte Khola SHP
S.N
Name
1 DipendraPoudel Site In-charge2 Riken Gautam Civil Engineer3 DevendraPoudel Sub Engineer/ Surveyor4 Gopal Gurung Senior Supervisor5 AnjanAdhikari Supervisor6 Operator/Driver/Helper 6 Nos.789
Equipment’s Mobilized by Contractor at SiteS.N
Name
1 Excavator (PC 225, Doosan) 32 Breaker 23 Dumper (Tipper) 14 Bolero 15
TAC Hydro Engineers Pvt. Ltd.
ii
Consulting Services and Annex A Construction Supervision of Ghatte Khola SHP Progress Report March 2017
6789
TAC Hydro Engineers Pvt. Ltd.
iii
Consulting Services and Annex BConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
PROGRESSSHEET NO.1
CivilConstructionWorks
TAC Hydro Engineers Pvt. Ltd. i
Components Sub-Components ExcavationFoundation Preparation
Bar Bending / Form Work / Concreating
Stone Masonary / Protection work
Filling / Finishing Work
Sub-Components
Progress
Progress Till Last Month
Progress Till This Month
A1. To Headworks 100% 100% 100%A2. To Power House 100% 100% 100%B1. Weir 10% 0% 0% 0% 2.50%B2. Undersluice and Intake 0% 0% 0% 0.00%B4. Approach Canal 0% 0% 0% 0% 0.00%B5. Settling Basin 0% 0% 0% 0.00%B6. Filling Work 0% 0.00%C1. Track and/or Trench 4% 0% 0% 2.22%C2. Anchor Block 0% 0% 0% 0.00%C3. Saddle Support 0% 0% 0% 0% 0.00%C3. Saddle Pad 0% 0% 0% 0.00%
D. Surge Tank D1. Surge Tank 0% 0% 0% 0% 0.00% 0.00% 0.00%E1. Track and/or Trench 0% 0% 0% 0.00%E2. Anchor Block 0% 0% 0% 0.00%E3. Saddle Support 0% 0% 0% 0% 0.00%F1. Power House 70% 0% 0% 7% 0% 18.20%F2. Tailrace 0% 0% 0% 0% 0.00%
6.24%2.32%
Civil Construction Work Progress
Overall Civil Progress
1.00%
0.00%
0.33%
0.00%
2.59%
March, 2017
C. Headrace Alignment
B. Headworks
A. Access Road 2.00%
0.14%
0.33%
F. Power House 3.77%
This Months Progress
E. Penstock Alignment 0.00%
Consulting Services and Annex BConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
PROGRESSSHEET NO.2
HydromechanicalWorks
No construction works yet started
TAC Hydro Engineers Pvt. Ltd.
ii
Consulting Services and Annex BConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
PROGRESSSHEET NO.3
ElectromechanicalWork
No construction works yet started
TAC Hydro Engineers Pvt. Ltd.
iii
Consulting Services and Annex BConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
PROGRESSSHEET NO.4
TransmissionLineWorks
Survey of Transmission line route up to Bhorle.
TAC Hydro Engineers Pvt. Ltd.
iv
Consulting Services and Annex CConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
DEVIATIONSINTIMESCHEDULE
1. Site Mobilization
15 15Falgun chaitra: 73
1 30Chaitra Chaitra: 73
2. Access Road
25 30Falgun Falgun:73
1. Structural Works (Undersluice + Weir + Intake)1 15
Chaitra Chaitra:7315 30
Chaitra Chaitra:732. Structural Works (Desander , Approach Canal & Headpond)
15 20Chaitra Chaitra: 73
1 30Jestha Jestha:74
1Asar
1 15Baishak Jestha:74
1. Excavation Works1 30
Baishak Baishak: 7415 30
chaitra Jestha:741 30
Baishak ashar:7415 30
chaitra chaitra;732. Primary Anchor Block & Saddle supports
15 30baishak ashar:74
1 30jestha ashar:74
3. Protection works & Backfillings works
1. Excavation Works30
Falgun: 731 15
chaitra chaitra:152. Structural Works
15 30chaitra jestha:30
1 30Jestha Bhadra: 74
1 15chaitra baishak:74
1 30baishak baishak:74
2.1 Foundation Excavation 5
D. Power House Areas
1.2 Foundation Excavation
1.1Weir + Undersluice (Surface Excavation) and river diversion 15
1.2Foundation Excavation (clearance of rock and boulder) 15
1.1Headrace (0+450m chainage upto 1+000m chainage) 30
C. Headrace Alignment / Penstock Alignment
1.3Headrace (1+200m chainage upto 1+800m chainage) 90
2.2 Bed concreting (3nos panel) 30
2.3 Construction of baffle wall 60During monsoon
season
2.4 Protection works (nearby big boulder)
Partially mobilized at construction
B. Headworks
2.1 Access from existing road to Power House Completed
2.2Opening of Track upto Headworks from river crossings 5 Completed
S. No.
Description of WorksYear 2073
Start Date Target Date9 10 11 12
Duration RemarksYear 2074
1 2 3
1.3 Establishment of Crusher Plant
4
A : Mobilization
45
Parallel excavation will be done providing
150m to 250m working front for HM
1.2 Headrace (Bell mouth upto 0+450m chainage) 75
30 continued
1.4 Establishment of Labrotary and Stores 30
1.1 Construction of site camps & accessories Completed
1.2 Mobilization of equipments
1.1 Surface Excavation 30
Parallel work will be done providing 150m to
250m work front for HM
2.1Headrace (0+450m chainage upto 1+000m chainage) 75
1.4Penstock Alignment : Site camp to Power house 15
2.2 Headrace (Bell mouth upto 0+450m chainage) 60
2.4 Drainage works 30
2.3 Protection Works 45
Parallel ongoing works3.1
2.2 Superstructural work upto finishing lvl. 60
45
2.1 Substructural works upto plinth Lvl. 75During monsoon
season
TAC Hydro Engineers Pvt. Ltd. i
Consulting Services and Annex DConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
MOSTIMPORTANTACTIVITIES:DELAYS ACTIVITIES1. Excavation at headworks area has been delayed due to obstruction by local people.
The issue has been resolved. Site clearance and sorting of boulder for rip rap is going
on in full swing.
2. Crusher installation has been delayed due delay in sending welding manpower by the
crusher supplier. However, it will be start producing material by the mid of April
2017.
TAC Hydro Engineers Pvt. Ltd. i
Consulting Services and Annex DConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
TAC Hydro Engineers Pvt. Ltd.
ii
Consulting Services and Annex EConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
PHOTOGRAPHS
Figure 1 Breaker busy in breaking boulder as seen from uphill of power house area.
TAC Hydro Engineers Pvt. Ltd. i
Consulting Services and Annex EConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
Figure 2 Two excavators at work as seen from road on the right bank.
TAC Hydro Engineers Pvt. Ltd.
ii
Consulting Services and Annex EConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
Figure 3 Boulder of area about 150 m3 at Power house being broken by breaker.
TAC Hydro Engineers Pvt. Ltd.
iii
Consulting Services and Annex EConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
Figure 4 Dumping of excavated material at downstream of power house near crusher area.
TAC Hydro Engineers Pvt. Ltd.
iv
Consulting Services and Annex EConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
Figure 5 Protection work (Gabion work) at the left bank near power house.
TAC Hydro Engineers Pvt. Ltd.
v
Consulting Services and Annex EConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
Figure 6 Earth resistance measurement at power house area.
TAC Hydro Engineers Pvt. Ltd.
vi
Consulting Services and Annex EConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
Figure 7 Welding of J hook for crusher installation.
TAC Hydro Engineers Pvt. Ltd.
vii
Consulting Services and Annex EConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
Figure 8 Unloading of main crusher block at crusher area.
TAC Hydro Engineers Pvt. Ltd.
viii
Consulting Services and Annex EConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
Figure 9 Construction of store room near crusher area.
TAC Hydro Engineers Pvt. Ltd.
ix
Consulting Services and Annex EConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
Figure 10 Maintenance of road on the way to Headworks from Power House.
TAC Hydro Engineers Pvt. Ltd.
x
Consulting Services and Annex EConstruction Supervision of Ghatte Khola SHP Progress Report March 2017
Figure 11 Site clearance and sorting of boulder for rip rap.
TAC Hydro Engineers Pvt. Ltd.
xi