Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap...

18
Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np [email protected] Date : January, 2017

Transcript of Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap...

Page 1: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

Sano Milti Khola Hydropower

Project, Fulasi VDC, Ramechhap

(3 MW)

Monthly Progress Report Prepared by : Sano Milti Khola Hydropower

Limited

www.smi.com.np

[email protected] Date : January, 2017

Page 2: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

January, 2017

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap

Executive Summary

The Monthly Progress Report is prepared for providing information about the progress of Sano

Milti Khola Hydropower Project, Ramechhap (3 MW). It will contain the information about

the project activities and achievement of the preceding month along with the work plan for the

particular month. This report will be issued in the first week of every month. Major project

activities will be highlighted.

Page 3: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

January, 2017

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap

1.0 Background

The Sano Milti Khola Small Hydroelectric Project (3 MW) is run-off-river type hydropower

project proposed along the Sano Milti Khola in Ramechhap and Dolkha District of Janakpur

Zone. The project area lies within Fulasi VDC of Ramechhap district and Melung VDC of

Dolkha District. Sano Milti Khola Hydropower Ltd. holds the survey license for this project. The

boundary co-ordinates of the project are 86° 02’ 55” E to 86° 04’ 33” E and 27° 29’ 36” N to 27°

30’ 17” N.

Sano Milti Khola Hydroelectric Project has been promoted by SM Investment Ltd (SMI). SMI is

basically a collective effort of Nepalese in South Korea to invest in Sano Milti Khola Small

Hydroelectric Project.

2.0 Project Development Milestones

S No Date Milestone

1 2066/04/28 BS Survey License Issued in the name of Mr Ram Bdr Tamang

2 2070/03/07 BS DoED extended the Date of Survey License of 3000 kW in the name of

Sano Milti Khola Hydropower Pvt. Ltd upto 2071/02/25 BS

3 2071/01/05 BS Ministry of Energy approved the ToR of Sano Milti Khola Hydropower

Project

4 2071/05/05 BS DoED extended the date of Survey License up to 2072/02/25 BS

5 2072/02/24 BS Ministry of Energy approved the IEE Report and at the same day the

approved IEE Report was submitted in DoED

6 2072/02/24 BS Registered application to obtain Generation License

7 2072/03/10 BS Grid Connection Agreement with NEA

8 2073/01/13 BS Power Purchase Agreement with Power Trade Department/NEA

9 2073/02/09 Agreement with Thodung/Waiba & Lama JV for Civil Construction

Works

10 2073/07/01 Generation License Issued by Department of Electricity Development

Page 4: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

January, 2017

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap

3.0 Project Description

3.1 Location & Access

The project site is about 175 km away from Kathmandu, the capital city of Nepal. Manthali, the

nearest trade center or town is about 22 km away towards south from the project site. Another

nearest town is Charikot which is about 37 km away towards north. The powerhouse site of the

project is 3 km far from the Milti Dobhan accessible by the graveled road Charikot – Kirnetar –

Manthali Road. The proposed intake site is located on Milti Khola at about 6 km upstream from

the confluence of Milti Khola and Tamakoshi River at the boundary of Melun and Phulasi VDC.

The forebay location at Aimantar Village can be reached by constructing about 4.5 km road

section from Milti Dobhan. Similarly, the headworks site can be made accessible by excavating

about 3 km long track along the Milti Khola from the Milti Dobhan.

Page 5: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

January, 2017

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap

3.2 Project Layout Map

Project Layout Plan

Page 6: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

January, 2017

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap

3.3 General Features of the Project

Name of River : Sano Milti Khola

Nearest Town : Manthali

Type of Scheme : Run-of-River

Gross Head : 216m

Net Rated Head : 213.32

Installed Capacity : 3.0 MW

Average Annual Energy after Outage : 15.833 GWh

1. Hydrology

Catchment Area : 55 km2

Mean Annual Discharge : 2.17 m3/s

Design Discharge (at Q40 PoE) : 1.7 m3/s

Riparian Release : 0.09m3/sec

Design Flood Discharge : 277m3/sec (100 yr. flood)

Average Annual Precipitation : 1650mm

2. Diversion Weir

Type of Weir : Concrete Weir

Length of Weir : 26 m

Crest Elevation : El. 1020.0 m

3. Intake Structure

Type : Side intake

Size : (1.50 m x 0.80 m)

Nos : 2 (Two)

4. Gravel Flushing structure

Type : Surface, rectangular type

Length : 11 m

Size (Depth) : 1.3 m to 2.50 m

Width : 1.60 m

Nos : 2 (Two)

5. Desanding Basin

Type : Surface, rectangular type, Concrete

No. of Bays : Double

Length : 29 m

Wide : 3.50 m

Total Depth (Including Hopper) : 2.21 to 3.15

Particle size to be settled : 0.20 mm

:

Page 7: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

January, 2017

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap

6. Headrace Canal

Type : Concrete (Rectangular)

Length : 2191 m

Wide : 1.50 m

Height : 1.0 m

7. Forebay

Surface Area : 153 m2 (Length 17 m x Width 4 m)

Volume : 204.00 m3

Bed Level : 1014.90 m

Gate : Sluice Gate

8. Penstock Pipe

Type : Steel

Total Length : 441.00 m

Diameter : 0.90 m

Material/Thickness : Structural Steel, 10 mm to 18 mm

Bifurcation Length : 9.0 m + 9.0 m

Bifurcation Diameter : 0.70m

9. Powerhouse

Type : Surface

Size (L x W) : 32 m x 14 m

Height : 11.00 m

Turbine Axis Level : 802.00 m

10. Tailrace

Type : RCC Structure (Buried)

Section Type : Rectangular

Total length : 62.00 m

Size : 0.85 m x 2.0 m

Tail Water Level : 799.00 m

11. Turbine

Type : Horizontal Axis Pelton

No of unit : 2 (Two)

Rated Output Capacity Per unit : 1500 kW

Rotational Speed : 750 rpm

Efficiency : 88.15%

12. Governor

Type : Electric-electronic

Adjustment for Speed Drop : Between 0 to 10%

Page 8: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

January, 2017

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap

13. Generator

Type : Synchronous, 3 Phase

No. of Units : 2 (Two)

Rated Output Capacity per Unit : 1700 kVA

Power Factor : 0.85

Voltage : 6600 V

Frequency : 50 Hz.

Efficiency : 95%

14. Transformer

Type : Three Phase, Oil Immersed

Nos of Units : 2 (Two)

Rated Capacity per unit : 1700 kVA

Voltage Ratio : 11/33 kV

Efficiency : 99%

15. Transmission Line

Voltage Level : 33 kV

Length : 5 km

From : Powerhouse

To : NEA Kirnetar Substation

Page 9: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

4.0 Construction Schedule:

Page 10: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

5. Project Progress

5.1 Coordination with Department of Forest and Ministry of Energy

Documents for tree cutting and land leasing have been forwarded to the cabinet which will be

approved and forwarded for final agreement with the Department of Forest.

5.2 Meeting with the Banks

The Due Diligence Audit of the project has been requested by the bank. Thereby we are

collecting proposals from the prequalified consultants for finalization of the DDA.

5.3 Meeting with the Electromechanical Suppliers

The proposals of the suppliers are under evaluation for necessary amendment with close

coordination with our Technical Consultants.

5.4 Joint Survey/Investigation of Headrace Section

Based on the detail joint survey/investigation of the headrace section, analysis and necessary

medication of the detail design are being finalized by our consultants.

5.5 Work Progress at the Site:

1. The maintenance of kulo at chainage 2+900 has been completed but the kulo

maintenance at chainage 2+800 is still remaining. The maintenance of kulo was hand

over to the local people on contract. The contract was made and agreed to complete the

work at 20,000 rupees. Out of 20,000, 15,000 have already been given to the responsible

person named Bikram of bagarbese.

Page 11: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

January, 2017

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap

Figure 1: the gabion at chainage 0+310, and filliing area for grade maintenance

Figure 2: gabion wall for filling, flood protection at chainage 0+750-0+765 (Guhey Khola)

Page 12: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

January, 2017

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap

Figure 3: filling done at guhey khola, causeway construction is going on

Figure 4: soling at chainage 1+200 (Shere Kholsi)

Page 13: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

January, 2017

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap

Figure 5: gabion construction at chainage 1+200 (Shere Kholsi)

Figure 6: gabion construction at chainage 1+980-2+00

Page 14: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

January, 2017

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap

Figure 7: gabion wall construction at chainage 2+125 (Bagar Bese)

Figure 8: gabion wall at chainage 2+125 (Bagar Bese)

Page 15: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

January, 2017

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap

Figure 9: gabion construction at chainage 2+800

Figure 10: clearance of kulo at chainage 2+900

Page 16: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

January, 2017

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap

Figure 11: the gabion construction at chainage 3+375+3+400

2. The construction of gabion is nearly in a stage of completion. The remaining chainage for

gabion construction is at chainage 3+375 – 3+400. At it is also in stage of completion.

Previously we have decided to construct the gabion at chainage 3+500 but we have

postponed the construction of gabion at this chainage for next year(if necessary).

3. The survey of penstock alignment and power house is going to be started from

2073/10/18. And it will be completed approximately after 3-4 days.

Figure 12: powerhouse site survey

Page 17: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

January, 2017

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap

Page 18: Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap ...smi.com.np/wp-content/uploads/2017/02/Monthly-Report-Format_Sano... · Sano Milti Khola Hydropower Project, Fulasi VDC,

Monthly Work Plan – February

S No Description Feb Remarks

Week 1 Week 2 Week 3 Week 4

1 Follow up – Tree Cutting Approval – Cabinet and Ministry

2 Access Road Works (Support Strucutures) Site Visit

3 Document Revision for Loan Processing (Bank)

4

Assessment/Meeting with Electromechanical Suppliers at

Office

5 Headrace Section Final Design (Technical Consultant)

6 Audit Report & AGM Date Finalization