Vasathi navya project pdf

32

Transcript of Vasathi navya project pdf

Page 1: Vasathi navya project pdf
Page 2: Vasathi navya project pdf

Highlights

2.5 acres | 190 apartments | 2 BHK

100% Vastu compliant | No common walls | 24/7 security | Power back up

Aesthetically designed landscaped area

Manjeera water supply | Water treatment plant | Lab tested ground water

Page 3: Vasathi navya project pdf

HITEC City 12 km

Kukatpally 4.5 km

Banjara Hills 10 km

Balanagar 4 km

HITEC MMTS Station 5 km

Secunderabad

Railway Station 10 km Airport 40 km

Location

Page 4: Vasathi navya project pdf

Educational Institutions

DAV Public School 5 km

Indu Talent School 1 km

Sri Chaitanya e-Techno School 4 km

Gowtham Model School/Junior College/Degree College 1.5 km

Navya Jyothi High School 2.5 km

Akshara, the Techno School 3 km

New Era High School 3. 5 km

Bhashya Public School 4 km

Bhashyam Brooks 3.5 km

Proximity

Page 5: Vasathi navya project pdf

Proximity

Healthcare Facilities

Ushamullapudi Cardiac Center 8 km

Sandhya Hospitals 1.5 km

Happy Children’s Super Specialty Hospital 2.5 km

Remedy Hospital 5 km

BBR Multi Speciality Hospital 8 km

Ark Hospital 5 km

Page 6: Vasathi navya project pdf

Proximity

Shopping Complexes

More Supermarket 1 km

D Mart 3 km

Value Mart Shopping Mall & Multiplex 3 km

Metro Mall 3.5 km

Brand Factory/NSL Mall 6 km

SHA Theater 3 km

Viswanath/Arjun Theater 5 km

Mallikarjuna Theater 7 km

Page 7: Vasathi navya project pdf

Clean Water at Navya

• Ground water tested and certified as fit for domestic use by Natural Resources Development Cooperative Society .

• Manjeera water supply.

• Water softening plant.

• Rain water harvesting.

• Sewage treatment plant.

Page 8: Vasathi navya project pdf

Elevations

Page 9: Vasathi navya project pdf

Bird View Elevation

Page 10: Vasathi navya project pdf

Grand entry plaza | 5 blocks | 5 floors | Block to block distance 20’ Boulevards |

Master Plan

Page 11: Vasathi navya project pdf

East Facing West Facing

Sizes 981 to 1235 sq ft | Spacious clutter free design | Efficient use of floor space 25% common area | Fully Vastu compliant | 6’x4’ living room window | No shared wall between apartments for enhanced ventilation

Floor Plan – 981 sq ft

Page 12: Vasathi navya project pdf

Floor Plan – 1090 sq ft

East Facing West Facing

Sizes 981 to 1235 sq ft | Spacious clutter free design | Efficient use of floor space 25% common area | Fully Vastu compliant | 6’x4’ living room window | No shared wall between apartments for enhanced ventilation

Page 13: Vasathi navya project pdf

Floor Plan – 1235 sq ft

East Facing West Facing

Sizes 981 to 1235 sq ft | Spacious clutter free design | Efficient use of floor space 25% common area | Fully Vastu compliant | 6’x4’ living room window | No shared wall between apartments for enhanced ventilation

Page 14: Vasathi navya project pdf

Model Apartment

Living Room Master Bedroom

Page 16: Vasathi navya project pdf

Block-D (100% CC Block Work Completed & up to 3rd Floor

Plastering works were Completed) -Status As On

08/10/15

Page 17: Vasathi navya project pdf

Block - D

Handover Schedule

Construction Activity Start Finish

Brickwork 16-May-15 14-Aug-15

Plastering 1-Jun-15 29-Sep-15

Flooring 1-Aug-15 30-Oct-15

finishes/paintings 1-Sep-15 30-Dec-15

External Works 11-Oct-15 18-Feb-16

Handing Over 8-Apr-16

Page 18: Vasathi navya project pdf

Block-C

(5th Floor Block Work , 1st and 3rd Floor

Plastering works are in Progress - Status As

On 08/10/15

Page 19: Vasathi navya project pdf

Block - C

Handover Schedule

Construction Activity Start Finish

4th Floor slab 1-May-15 31-May-15

5th Floor slab 1-Jun-15 1-Jul-15

Brickwork 16-May-15 13-Sep-15

Plastering 1-Jun-15 29-Sep-15

Flooring 1-Aug-15 30-Oct-15

finishes/paintings 1-Sep-15 30-Dec-15

External Works 11-Oct-15 18-Feb-16

Handing Over 8-Apr-16

Page 20: Vasathi navya project pdf

Block - B

(2nd Floor Slab Completed & 1st Floor Block

Work In Progress) -Status As On 08/10/15

Page 21: Vasathi navya project pdf

Block - B

Handover Schedule

Construction Activity Start Finish

2nd Floor slab 6-Jul-15 5-Aug-15

3rd Floor slab 6-Aug-15 5-Sep-15

4th Floor slab 6-Sep-15 6-Oct-15

5th Floor slab 7-Oct-15 16-Nov-15

Brickwork 6-Jul-15 13-Dec-15

Plastering 20-Aug-15 17-Jan-16

Flooring 29-Oct-15 26-Feb-16

finishes/paintings 29-Nov-15 27-Apr-16

External Works 8-Jan-16 6-Jun-16

Handing Over 4-Sep-16

Page 22: Vasathi navya project pdf

Block – A

(1st Floor Slab Completed )Status As On

08/10/2015

Page 23: Vasathi navya project pdf

Block - A

Handover Schedule Construction Activity Start Finish

2nd Floor slab 7-Jul-15 6-Aug-15

3rd Floor slab 7-Aug-15 6-Sep-15

4th Floor slab 7-Sep-15 7-Oct-15

5th Floor slab 8-Oct-15 17-Nov-15

Brickwork 7-Jul-15 14-Dec-15

Plastering 21-Aug-15 18-Jan-16

Flooring 30-Oct-15 27-Feb-16

finishes/paintings 30-Nov-15 28-Apr-16

External Works 9-Jan-16 7-Jun-16

Handing Over 5-Sep-16

Page 24: Vasathi navya project pdf

Block - E

Handover Schedule Construction Activity Start Finish

Sub Stcture works Including Foundations 1-Jan-16 31-Jan-16

Stilt Slab 2-Feb-16 3-Mar-16

First Slab 4-Mar-16 2-Apr-16

Second Slab 5-Apr-16 5-May-16

Third Slab 6-May-16 5-Jun-16

Fourth Slab 6-Jun-16 6-Jul-16

Fifth floor slab 7-Jul-16 6-Aug-16

Brickwork 2-May-16 30-Aug-16

Plastering 23-May-16 20-Sep-16

Flooring 22-Jul-16 20-Oct-16

finishes/Painting 22-Aug-16 20-Dec-16

External Works 1-Oct-16 8-Feb-17

Handing Over 9-Apr-17

Page 25: Vasathi navya project pdf

Amenities Block

Excavation work in progress Status As On

08/10/15

Page 26: Vasathi navya project pdf

Amenities Block

Handover Schedule

Construction Activity Start Finish

Sub Stcture works Including Foundations 1-Jun-16 1-Jul-16

Basement Slab 2-Jul-16 1-Aug-16

Stilt Slab 2-Aug-16 1-Sep-16

First Slab 2-Sep-16 2-Oct-16

Second Slab 3-Oct-16 2-Nov-16

Brickwork 22-Oct-16 20-Jan-17

Plastering 21-Nov-16 21-Mar-17

Flooring&finishes 31-Dec-16 30-May-17

Handing Over 29-Jun-17

Page 27: Vasathi navya project pdf

Technical Specifications

High Quality Attention To Detail

Page 28: Vasathi navya project pdf

Foundation & Structure Earthquake resistant RCC framed structure in accordance with IS 456:2000, 1893:2002 Super Structure External and internal partition walls with good quality of cement concrete blocks Wall Finishes • External: 2- coats of plastering in cement mortar mix, painted with Asian Exterior

Paint . • Internal: Sponge finished cement mortar plastering with luppum finish and painted

with Asian Emulsion Paint or equivalent brand. Flooring • Living & Dining, Kitchen & Bedrooms: 2´x 2´ vitrified tiles of reputed make • Balconies, Utilities & Common Areas: Ceramic tiles of reputed make • Toilets: Anti-skid ceramic tiles of reputed make

Specifications

Page 29: Vasathi navya project pdf

Doors & Windows

• Main Door: Engineered wood door frame and veneer finish flush shutter with melamine polish fixed with SS hardware.

• Internal Doors: Engineered wood door frame and molded shutter painted with enamel paint of Asian or equivalent & fixed with SS hardware

• Windows: Powder coated aluminium sliding frames fitted with plain glass and mild steel safety grills

Kitchen

• Stainless steel sink with polished granite platform

• Provision for exhaust fan

• Provision for water purification system

Dadoing:

• Kitchen: Glazed ceramic tile dado up to 2´ height above platform

• Utility: Glazed ceramic tile dado up to 3´ height

• Toilets: Glazed ceramic tile dado up to door height

Specifications

Page 30: Vasathi navya project pdf

Toilets

• All sanitary fittings of Hindware/CERA/Parryware or equivalent brand

• All CP fittings & accessories of Hindware /CERA/Parryware or equivalent brand

Electrical

• PVC conduction, point wiring and circuit wiring of Polycab or equivalent.

• Three phase meter distribution box of MCB .

• Modular switches of standard make.

• Provision of power points for refrigerator & grinder in kitchen and washing machine in utility area.

• Provision geyser point in bathrooms.

• Telephone and television points in living room.

• Provision of AC point in master bedroom.

Specifications

Page 31: Vasathi navya project pdf

Specifications

Parking Adequate car parking in the cellar and stilt floors.

Lifts Automatic passenger lifts of standard make.

Generator Backup power for one light and one fans in all apartments; 30% power backup in common areas .

Water Management

• Manjeera water connection

• Water softening plant for ground water treatment to make the water suitable for domestic use

• Waste water treated by STP and reused for gardening & flushing

Page 32: Vasathi navya project pdf

THANK YOU

Contact Aman Haq Phone 9000007825 Email :- [email protected]