Updated Initial Environmental Examination (IEE) · Updated Initial Environmental Examination (IEE)...
Transcript of Updated Initial Environmental Examination (IEE) · Updated Initial Environmental Examination (IEE)...
Updated Initial Environmental Examination (IEE)
of
Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and
Reconstruction Sub-project, Sindhuli
Submitted to
Government of Nepal
National Reconstruction Authority
Singhadurbar, Kathmandu
Submitted through
Government of Nepal
Ministry of Federal Affairs and General Administration
Earthquake Emergency Assistance Project
Central Level Project Implementation Unit, Lalitpur
Submitted by
District Level Project Implementation Unit, Sindhuli
April 2018
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli i
g]kfnL sfo{sf/L ;f/f+z1 (Executive Summary in Nepali)
k[i7e"ld
@)&@ ;fn a}zfv !@ ut] uPsf] ljWj+;sf/L e"sDk / ;f]xL jif{ a}zfv @( ut] uPsf] d'Vo k/fsDksf
sf/0f Ifltu|:t :yfgLo ;+/rgfx?sf] k'g:yf{kgf tyf k'glg{df{0f u/L :yfgLo ;d'bfosf] cfly{s tyf
;fdflhs k'gp{Tyfg ug{ Pl;ofnL ljsf; a}+ssf] C0f ;xof]udf tyf :jL; ljsf; lgof]usf] k|fljlws
;xof]udf k|efljt !@ lhNnfdf e"sDk cfktsfnLg ;xfotf cfof]hgf nfu' ul/Psf] 5 . o; cfof]hgfsf]
dfWodåf/f Pl;ofnL ljsf; a}+sn] dxTjk"0f{ ;8s ;+hfnsf] k'glg{df{0f ug{, xhf/f}+ afnaflnsfnfO{ k'gM
ljBfno k'¥ofpg, k|efljt ;d'bfonfO{ cTofjZos ;sf/L ;]jf pknAw u/fpg g]kfn ;/sf/nfO{ ;xof]u
ug]{5 . o; cfof]hgfn] e"sDk tyf klx/f]åf/f Ifltu|:t sl/a !#% ls=ld= /0fg}lts ;8s tyf $%)
ls=ld= u|fld0f ;8ssf] k'glg{df{0f ug]{5 . o; cfof]hgfsf] sfo{sf/L lgsfo /fli6«o k'glg{df{0f k|flws/0f
/x]sf] 5 / u|fld0f ;8ssf] xsdf o; cfof]hgfsf] sfo{Gjog lgsfosf] ?kdf e"sDk cfktsfnLg ;xfotf
cfof]hgf–lhNnf cfof]hgf sfo{Gjog OsfO{ /x]sf] 5 .
lkkneGHofË—xfo"6f/—g]qsfnL u|fld0f ;8s -#&=@) ls=dL=_ k'g:yf{kgf tyf k'glg{df{0f pkcfof]hgf klg
e"sDk cfktsfnLg ;xfotf cfof]hgf cGtu{ts} Pp6f pk–cfof]hgf xf] . pkcfof]hgf k'g{pTyfgsf qmddf
kg{;Sg] ;sf/fTds tyf gsf/fTds jftfj/0fLo Pj+ ;fdflhs k|efjnfO{ ;Daf]wg ug{sf] nflu lhNnf
cfof]hgf sfo{Gjog OsfO l;Gw'nLn] of] k|f/lDes jftfj/0fLo kl/If0f (IEE) k|ltj]bg tof/ u/]sf] xf] .
k|:tfljt lkkneGHofË—xfo"6f/—g]qsfnL ;8s k'g:yf{kgf tyf k'glg{df{0f pkcfof]hgf sfof{Gjogn] @)&@
;fn a}zfv !@ ut] uPsf] ljWj+;sf/L e"sDk / ;f]xL jif{ a}zfv @( uPsf] d'Vo k/fsDksf sf/0f
Ifltu|:t o; ;8snfO{ k'gM ;+rfngdf NofO{ of] ;8s /x]sf] l;Gw'nL lhNnfsf] sdnfdfO{ gu/kflnsf j8f
gF @ / Wofªn]v ufpFkflnsf j8f gF !, @, # / $ sf] lkkn eGHofË, ef]6]:jf/f, v§f/, lga'jf6f/, /fhfafF;,
xfo'6f/, rGbgk'/, ;f]nfeGHofË, g]qsfnL, cfFk6f/ h:tf d'Vo jl:tx? nufot o;sf klZrd tkm{sf cGo
jl:tx?nfO{ ;d]t lhNnf ;b/d'sfd l;Gw'nL tyf b]zsf cGo If]q;Fu ;8s ;+hfn dfkm{t hf]8\g]5 .
k|:tfjs
e"sDk cfktsfnLg ;xfotf cfof]hgf (EEAP) cGtu{t u|fld0f ;8s lkkneGHofË—xfo"6f/—g]qsfnL
;8s -#&=@) ls=dL=_ k'g:yf{kgf tyf k'glg{df{0f pkcfof]hgfsf] lhNnf :t/Lo sfo{sf/L lgsfo Pj+
k|f/lDes jftfj/0f kl/If0fsf] nflu k|:tfjssf] ?kdf lhNnf cfof]hgf sfo{Gjog OsfO, l;Gw'nL /x]sf] 5 .
k|:tfjssf] k'/f 7]ufgf
e"sDk cfktsfnLg ;xfotf cfof]hgf—lhNnf cfof]hgf sfo{Gjog OsfO, l;Gw'nL
l;Gw'nL dfl8, l;Gw'nL
;Dks{ kmf]g M )$&—%@)!)(
O{d]n M [email protected]
1 This is Executive Summary of the IEE report in Nepali language and an English version is given in page vi.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli ii
k|f/lDes jftfj/0fLo k/LIf0fsf] cf}lrTo tyf p2]Zo
e'sDkaf6 k|efljt ;+/rgfsf] k'glg{df0f{ ;DaGwL] P]g, @)&@, e'sDkaf6 k|efljt ;+/rgfsf] k'glg{df0f
;DaGwL lgodfjnL, @)&@ tyf e"sDk k|efljt ;+/rgfsf] k'glg{df{0fsf] nflu jftfj/0fLo k|efj d'Nof+sg
;DaGwL sfo{ljlw @)&@ -cg';'rL !_ Pj+ Pl;ofnL ljsf; a}+ssf] ;'/If0f gLlt syg -;]kmuf8{ kf]nL;L
:6]6d]G6_ @))( cg';f/ jftfj/0fLo k|efjsf] Jojxf/Ls tyf 7fFp laif]z Go"lgs/0f tyf nfe a[[¢Lsf
pkfox? ;'emfj ug{ k|f/lDes jftfj/0fLo kl/If0f cWoog sfo{ cfjZos b]lvG5 .
k|f/lDes jftfj/0fLo k/LIf0f k|ltj]bg cWoogsf] d'Vo p2]Zo pkcfof]hgf If]qsf] ef}lts, h}ljs,
;fdflhs, cfly{s tyf ;f+:s[lts jftfj/0fdf kg]{ k|efjx? kQf nufpg'sf ;fy} jftfj/0fdf kg]{
gsf/fTds k|efjsf] Go"lgs/0fsf pkfox? / ;sf/fTds k|efj a9fpg] pkfox? af/] ;'emfj lbg' /
jftfj/0fLo Aoa:yfkg of]hgf agfO{ sfof{Gjog u/fpg' /x]sf] 5 .
k|:tfjsf] ljj/0f tyf cWoog ljlw
k|:tfljt pkcfof]hgf l;Gw'nL lhNnfsf sdnfdfO{ gu/kflnsf j8f gF @ sf] lkkn eGHofË -tTsflng
eb«sfnL uf=lj=; #_ af6 k|j]z ub{5 / Wofªn]v ufpFkflnsf j8f gF $ -tTsflng g]qsfnL uf=lj=; %_ sf]
dflem6f/ eGg] 7fpFdf cGTo x'g]5 . of] v08nfO{ e"sDk cfktsfnLg ;xfotf cfof]hgf–lhNnf cfof]hgf
sfo{Gjog OsfOn] k'glgld{0fsf] k|:tfj u/]sf] 5 . o; ;8snfO{ k|yd :t/sf] lhNnf ;8ssf] dfkb08df
u|fe]n ul/g] 5 . #&=@) ls=ld nDafO{ gfnL / ;f]Nh/ ;lxt o;sf] s'n rf}8fO{ ^=@% ld= x'g]5 . o;
pkcfof]hgfsf] s'n nfut g]=?= *)&,%%@,@**=$^ / OlGhlgol/ª nfut g]=?=&&&,!!*,^$^=)^ /x]sf] 5 .
of] k|f/lDes jftfj/0fLo kl/If0f k|ltj]bg g]kfn ;/sf/sf] sfg"gL cfj:ostf k'/f ug{ cfjZos ;Gbe{
;fdfu|Lx?sf] k"j{ cWoog / k'glg{df0f k|lws/0fsf] sfo{sf/L clws[tåf/f @)&$.)#.@% ut] :jLs[t
sfo{;'rLsf] clwgdf /lx tof/ ul/Psf] 5 . @)&$ ;fn >fj0f @& b]vL efb| @ ut] ;Dd ul/Psf] :ynut
e|d0f tyf ;j]{If0fjf6 lnOPsf tYofÍ tyf cGo pknAw tYofÍx?sf] s]nfP/ k|f/lDes jftfj/0fLo k/LIf0f
k|ltj]bg tof/ u/L lgisif{ tyf ;'emfjx? lbOPsf 5g\ .
pkcfof]hgfsf] ljBdfg jftfj/0fLo cj:yf
ef}ule{s b[li6sf]0fn] of] If]qdf d'Vo ?kdf kfO{g] r§fgx?df lg;, l;:6, :of08 :6f]g / sªnf]ld/]6 5g eg]
sn'leon, Pn'leon / /];'l8on ;f]on kfO{G5 . lr;fkfgL vf]nf, wgdfg vf]nf, tf? vf]nf, nflGb vf]nf,
l;Dn] vf]nf, a;]/L vf]nf, lnlk vf]nf, l/g vf]nf, dl/g vf]nf, tfdfhf]/ vf]nf o; k|eflat If]qsf] d'Vo
vf]nfx? x'g.
o; pkcfof]hgf If]q ;d'lGb| ;txaf6 %@& ld= b]lv !,!%$ ld6/sf] prfO{df kb{5 . pkcfof]hgf pi0f /
pkf]i0f xfjfkfgL kfOG5 -8f]a|]d]h !(&^_ . lhNnf kfZj{ lrqdf pNn]v eP cg';f/ o; If]qsf] tfkqmd
udL{df #@=#% l8=;]=;Dd k'Ug] / lxpFbdf &=*) l8=;]= ;Dd emg]{ u/]sf] 5 / oxfF jflif{s ;/b/ @,!!$
ld=ld= jiff{ x'g] u/]sf] 5 .
of] pkcfof]hgf v]taf/L, cfjf; If]q, jg If]qaf6 k|j]z ub{5 h;dWo] r]= )±))) b]lv r]= )±$^) / r]=
)±&() b]lv r]= !±*)) ;Dd sflnsf ;fd'bflos ag, r]= !)±@%) b]lv r]= !!±))) ;Dd emNsg]
;fd'bflos ag, r]= !$±&^) b]lv r]= !&±))) ;Dd/ r]= !*±()) b]lv r]= !(±)$) /fgLaf;
;fd'bflos jg, r]= !(±)$) b]lv r]= !(±$^) ;Dd $ j6f sa'lnolt ag -xl/ofnL, k|ultl;n, nfn'kft],
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli iii
/ nflnu'F/f;_, r]= @!±%*) b]lv r]= @!±($) dfg]eGHofË sa'lnolt ag / r]= @&±!*) b]lv r]=
@(±))) / r]= @(±#)) b]lv r]= #)±^)) ;Dd ;/sf/L ag /x]sf] 5 .
o; ;8sdf ldl>t rf]}8fkft] jg g} al9 dfqfdf kfO{Psf] 5 h;df ;fn tyf lrnfpg] k|hftLsf] afx'Notf
/x]sf] 5 . oxfF ;fn, vf]6] ;Nnf, s6';, lrnfpg], plQ;, s'6ld/f], 6'gL cflb h:tf ?vx? kfOG5g\ eg]
r'qf], ;t'jf, dlh7f] h:tf u}x| sfi7 ag k}bfjf/x? kfOG5. To;}u/L h+unL hgfj/x?df lrt'jf, :ofn,
b'D;L, efn', dn;fk|f] cflb /x]sf 5g\ eg] k+IfLdf sflnh, uf}ynL, n'Or], 9's'/, sf]O{nL / ;/L;[k k|hfltdf
l;l/; ;k{, wfdg, kfgL ;k{ cflb kfO{G5 .
o; ;8s cGtu{t lkkn eGHofË, ef]6]:jf/f, v§f/, lga'jf6f/, /haf;, xfo'6f/, rGbgk'/, ;f]nfeGHofË,
g]qsfnL, cfFk6f/ h:tf d'Vo jl:tx? kb{5g\ . k|efljt If]qdf @,*%( 3/w'/L /x]sf] 5 . o; If]qdf tfdfË
hftLsf dflg;sf] afx'Notf /x]sf] 5 eg] cGo k|d'v hfltdf du/, If]qL, afx'g cflb /x]sf 5g\ . cfof]hgf
If]qsf] ;fIf/tf b/ %(=^)Ü -;fdfGo ;fIf/ ;d]t_ k|ltzt /x]sf] 5 . cfof]hgf If]qsf w]/}h;f] AolQmx?
v]lt nufot s[lif / kz'kfng k]zfdf ;+nUg 5g\ eg] cGo d'Vo k]zfdf ;fgf Aofkf/, Hofnf dhb'/L /
j}b]lzs /f]huf/ dxTjk"0f{ 5g\ . k|eflat If]qdf k|fo h;f] :jf:Yo rf}sLklg /x]sf] kfO{of] . vfg]kfgLsf] nflu
*!=&% k|ltzt 3/w'/Ln] kfOkåf/f ljtl/t kfgLsf] k|of]u ub{5g\ . k|efljt If]qsf ^&=*^Ü 3/w'/Ldf ljB't
;]jf k'u]sf] 5 eg] afls #@=!$Ü n] ;f]nf/ aQLsf] k|of]u u/]sf] kfO{of] .
jftfj/0fLo k|efjx?
;sf/fTds k|efjx?
pkcfof]hgf lgdf{0fsf qmddf tTsfn b]lvPsf ;sf/fTds k|efjx?df o;n] !#$,*&& JoQmLlbg a/fj/sf]
c:yfoL /f]huf/Lsf] cj;/ ;[hgf ug]{ 5 . o;}u/L cfof]hgf ;~rfng kl5 x'g] ;sf/fTds k|efjx?df o;
lhNnfsf] sdnfdfO{ gu/kflnsf j8f gF @ / Wofªn]v ufpFkflnsf j8f gF !, @, # / $ sf] lkkn eGHofË,
ef]6]:jf/f, v§f/, lga'jf6f/, /haf;, xfo'6f/, rGbgk'/, ;f]nfeGHofË, g]qsfnL, cfFk6f/ h:tf d'Vo jl:tx?
nufot o;sf cf;kf;sf hgtfnfO{ aif}e/L oftfoftsf] ;'ljwf tyf kx'Fr, :yfgLo s[lif pkhdf cfwfl/t
s[lif pBf]usf] k|j4{g tyf cfly{s ljsf; /x]sf 5g\ . ;+rfngdf cfPkl5 o; pkcfof]hgfn] k|efljt
If]qsf hgtfx?nfO{ ;fdflhs ;]jf h:t}M :jf:Yo, lzIff, ahf/ tyf cGo ;'lawfdf ;xh / b|"t kxF'r k|bfg
ug{]5 . o;sf ;fy} o; If]qdf b}lgs pkEff]Uo a:t'x?, vfB tyf cGo a:t'x?sf] cfk'lt{ ;xh x'g]5 eg]
o; If]qsf] s[lif pkh cflbn] klg ;xh ahf/ k|fKt ug]{5 h;n] ubf{ hLjg:t/ a[l4 x'g]5 / e"sDk
k|efljt hgtfnfO{ ;fdflhs tyf cfly{s k'g:yf{kgfdf d2t k'Ug]5 .
gsf/fTds k|efjx?
pkcfof]hgf lgdf{0fsf qmddf jftfj/0fsf] ;fdflhs cjojdf b]lvg;Sg] k|d'v gsf/fTds k|efjx?df
pknAw ;]jf ;'ljwfdf bjfj, :yfgLo / cfuGt's sfdbf/x? lar åGb l;h{gf, k]zfut :jf:Yo tyf
;'/Iffdf k|efj, cflb d'Vo ;/f]sf/sf /x]sf 5g . ;8s lj:tf/ ubf{ !=^^% x]= v]lt ug]+ hUuf, !=!@) x]=
a:tL If]q, %=#!@ x]= ;/sf/L, )=!#! x]= afFemf] hUuf, / )=)%) x]= vf]nf / vf]N;L ;8sdf kl/at{g x'g]
ePsf]n] e'kl/jt{gdf c;/ kfg]{ b]lvG5 . of] ;+u} af6f] la:tf/df df * j6f lghL ;+/rgf / ;fd'bflos
wf/fdf ;d]t k|ToIf Iflt k'Ug] b]lvG5 . cGo c;/x?df sfo{ / Hofnf ljt/0fdf n}+lus lje]b, hf]lvdk"0f{
sfo{df gfjfnsfx?sf] k|of]u, c:j:y cfjf;sf sf/0f km}lng] /f]u, zf/Ll/s ;Dks{sf sf/0f ;g]{
of}g /f]u tyf cGo ;?jf /f]ux? x'g ;Sg] b]lvG5g\ . ;fy} cfof]hgf ;+rfng kZrft pknAw ;'ljwfsf
sf/0f ;8s lsgf/df cJojl:yt j;f]jf; a9\g uO{ ;8s If]q cltqmd0f x'g] ;Defjgf klg /xG5 .
;8s lgdf{0f k|s[ofdf k|of]u x'g] pks/0f, ;jf/L;fwg Pj+ /;folgs tTjx?sf] sf/0f Wjlg,
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli iv
xfjf / kfgL k|b'lift x'g ;S5 . kmf]xf]/sf] plrt Joj:yfkg gePdf hn tyf hldgsf] k|b'if0fn] cGo
gsf/fTds k|efj lgDTofpg] ;Defjgf /xG5 . lgdf{0f ;fdfu|Lx?sf] ;d'lrt e08f/0f tyf ;+rfng gubf{
r'xfj6sf sf/0f ;txL tyf e'ldut hn k|b'lift x'g;Sb5 . h}ljs jftfj/0fdf kg]{ k|efjsf] ;Gbe{df
rf]/Llzsf/Lsf sf/0f jGohGt'df kg]{ k|efjnfO{ dxTjk"0f{ dfGg ;lsG5 . lgdf{0fsf nflu ;8ssf] b'j} tkm{
s6fg ubf{ $& j6f ;f=jaf6, & j6f sa'lnolt jgaf6, *#@ j6f /fli6\|o ag / #&# j6f gLlh agaf6
?vx? x6fpg' kg]{ b]lvG5 .
;sf/fTds k|efj a9fpg] pkfo
7]s]bf/ / sfdbf/sf nflu ljleGg jftfj/0fLo tyf hgr]tgf d"ns tflndx? -cfocfh{g, OlGhlgol/u+
;+/rgfsf] lgdf{0f tyf h}ljs k|ljlwsf sfd ;DaGwL_ lbO{g] 5g\ . ;8s lgdf{0fsf s|ddf sDtLdf @) %
dlxnf ;xeflutf u/fpg k|f]T;fxg ul/G5 .
Go"lgs/0fsf pkfox?
cfof]hgfsf] gsf/fTds c;/x? Go"lgs/0f ug{sf nflu ljleGg Jojxfl/s tyf ldtJooL pkfox? ;'emfj
ul/Psf] 5 . cfof]hgfsf k|:tfjsn] cfof]hgf lgdf{0f tyf ;~rfngsf] cjlwdf o:tf pkfox? cjnDag
ug]{ 5g\ . cfof]hgf lgdf{0f cjlwsf] qmddf k|:tfjsn] lgdf{0f Joj;foL dfkm{t Go'gLs/0fsf pkfox? nfu"
ug]{]5 . cjnDag ul/g] s]xL k|d'v pkfox? lgDgfg';f/ 5g\ .
lghL ;+/rgf nufotsf lghL ;DklQsf] clwu|x0f ubf{ Ifltk'lt{ lbOg]5 .
k]zfut :jf:Yo / ;'/Iffsf] ;/f]sf/sf nflu cfjZos tof/L ul/g] 5 . sfdbf/x?nfO{ x]Nd]6, kGhf,
a'6, ;'/IffTds k]6L, r:df, df:s cflb k|bfg ul/g] 5 . lgdf{0f / e08f/0f:yndf cgflws[t k|j]z /
ultljlw /f]Sg vt/fsf ;+s]tx?, 5]saf/ Pj+ kfn]sf] Joj:yf ul/g] 5 .
SofDk tyf lgdf{0f If]qdf c:yfO{ rkL{sf] Joj:yf kfgLsf] ;|f]tsf] Aoa:yf ul/g] 5 .
pTvgg\af6 lg:s]sf] df6f]nfO{ lgwf{l/t :yfgdf 6f] jfn, l/6]lgË jfn, j[Iff/f]k0f / cfjZostf cg';f/
gfnLx? lgdf{0f u/L ;xL tl/sfn] Joj:yfkg ul/g]5 .
ljBdfg / ;Defljt klx/f]nfO{ pko'Qm h}ljs k|ljlwsf] k|of]u u/L lgoGq0f tyf /f]syfd ul/g]5 .
cfof]hgf lgdf{0fsf] qmddf lg:sg] 3/]n' tyf lgdf{0fhGo kmf]xf]/d}nfnfO{ gbLIf]q af6 k/ pko'Qm
:yfgdf / efF8f]df ;+sng ul/g] 5 / ltgsf] k|sf/ cg'?k Joj:yfkg ul/g]5 .
lgdf{0f ultljlwdf k|of]u x'g] t]n tyf cGo /;folgs kbfy{x?nfO{ pko'Qm :yfgdf Wofgk'j{s e08f/0f
tyf pkof]u ul/g] 5 .
jGohGt'sf] rf]/Ll;sf/L lgoGq0f tyf ltgsf] ;+/If0f ;DaGwL ;r]tgf hufpg] ;Gb]z af]s]sf] xf]l8{Ë
af]8{x? /flvg]5 .
?vx?sf] Ifltk"lt{ a[Iff/f]k0fsf] nflu ?= #,#&),&**=#% 5'6\ofO{Psf] 5 .
;fj{hlgs k/fdz{ tyf ;"rgf ;fj{hlgs ug]{
k|f/lDes jftfj/0fLo k/LIf0f ug]{ qmddf k|:tfljt ;8s glhssf j:tLx?df ufpmF:t/Lo k|ltlgwL tyf
cGo :yfgLo AolStx?;Fu k|:tfjLt pkcfof]hgfaf6 kg{ hfg] ;sf/fTds tyf gsf/fTds c;/ jf/]
hfgsf/L u/fpg ;fj{hlgs 5nkmn u/LPsf] lyof] . To;}ul/ d:of}bf k|f/lDes jftfj/0fLo k/LIf0f
k|ltj]bg tof/L u/L ;/f]sf/jfnf lgsfox?sf] /fo ;'´fa ;+sngsf] nfuL & lbg] ;fj{hlgs ;'rgf
@)&$÷)%÷@$ ut]sf] /fhwfgL, g]kfnL /fli6«o b}lgsdf k|sflzt ul/of] .
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli v
o;}sf] cfwf/df g]kfnL sfo{sf/L ;f/f+z, ;sf/fTds k|efj a9fpg] pkfox? tyf gs/fTds k|efj
Go'gLs/0f pkfox? / jftfj/0fLo Aoa:yfkg of]hgf ;dfj]z u/L agfOPsf] d:of}bf k|f/lDes jftfj/0fLo
k/LIf0f k|ltj]bg ;lxt /fo ;'´fjsf] nfuL ;fj{hlgs e]nfsf] cfof]hgf ldlt @)&$÷)%÷@( df ul/of] .
/fli6«o k'glgdf{0f k|flws/0faf6 cfPsf] /fo ;'´fj ;dfj]z u/L k|fl/Des jftfj/0fLo k/LIf0f k|ltj]bg
:jLs[tLsf] nfuL k7fO{Psf] 5 .
u'gf;f] lgbfg ;+oGq
pkcfof]hgfsf] jftfj/0fLo / ;fdflhs sfo{;Dkfbgsf] ;Gbe{df :yfgLo hgtfsf] hgu'gf;f] ;'Gg /
tLgsf] plrt tyf ;dofg's'n ;Daf]wg ug{ o; k|f=j=k= k|ltj]bgdf $ txsf] u'gf;f] lgbfg ;+oGqsf]
af/]df cf}+NofOPsf] 5 .
jftfj/0fLo Aoj:yfkg of]hgf
pkcfof]hgfsf] c;/, l:ylt, ltgsf Go"lgs/0fsf pkfox?, cg'udgsf] tl/sf / ;do tlnsf ;d]6]/
cWofo ( df jftfj/0fLo Joj:yfkg of]hgf tof/ kf/LPsf] 5 . o;sf ;fy} Go"lgs/0fsf pkfo sfof{Gjog
/ cg'udgsf] lhDd]jf/ lgsfosf] klxrfg o; jftfj/0fLo Aoj:yfkg of]hgfdf ul/Psf] 5 . k|:tfljt
cfof]hgfsf ef}lts, h}ljs, ;fdflhs tyf ;f+:s[lts jftfj/0f cGtu{tsf ljleGg cg'udgsf ;"rsx?
klg kQf nufOPsf 5g\ . pkcfof]hgf k'glg{df{0fsf] cg'udg /fli6«o k'glg{df{0f k|flws/0f tyf lhNnfsf
cGo lgsfox?n] ug]{5g\ . jftfj/0fLo cg'udgsf] nflu ? #@%,)))=)) ljlgof]hg ul/Psf] 5 . o;
pkcfof]hgfsf] jftfj/0fLo Joj:yfkgsf] nfuL ? !@,)*!,@!!=^* 5'6ofOPsf] 5, h; dWo ?
&,$*%,$@#=## OlGhlgol/ª nfutdf ;dfj]; ul/Psf] 5 .
lgisif{ tyf ;'emfa
o; :t/sf] pkcfof]hgfsf nflu pkcfof]hgfaf6 x'g] gsf/fTds c;/x? guGo 5g\ . w]/}h;f] c;/x?
:yfgLo :t/d} lgdf{0f r/0fdf dfq l;ldt 5g\ . cfof]hgfaf6 x'g] clwsf+z gsf/fTds c;/x?nfO{ lbOPsf
Go"lgs/0fsf pkfox?af6} sd jf Ifltk"tL{ ug{ ;lsG5 / :yfgLo:t/df / lgdf{0f r/0fd} l;ldt ug{
;lsG5 . To;}n] cfof]hgfsf] k|s[lt, o;sf] cjl:ylt, :yfgLo hg;d'bfox?sf] cfof]of]hgf k|ltsf] ?lr tyf
klxrfg ul/Psf ;Defljt gsf/fTds c;/x?nfO{ dWogh/ ub{} k|f/lDes jftfj/0fLo kl/If0f cWoogn]
lgb]{zg u/] cg'?ksf] Go"lgs/0f tyf clej[l4s/0fsf pkfox? cjnDag u/L pkcfof]hgf ;~rfng ug{
pko'Qm b]lvG5 .
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli vi
Executive Summary
Background
In order to accelerate economic and social recovery of the communities through
rehabilitation and reconstruction of local infrastructures damaged due to devastating
earthquake of 25 April 2015 and the major aftershock of 12 May 2015, Earthquake
Emergency Assistance Project (EEAP) has been implemented under loan assistance of
Asian Development Bank (ADB) and technical support of Swiss Agency for Development
and Cooperation (SDC) in 12 affected district. Through this project, the ADB will support the
Government of Nepal (GoN) in its efforts to put thousands of children back into schools,
return vital government services to desperate communities, and create jobs and income for
families by repairing critical road networks. The project will also repair and improve about
135 km of strategic roads and about 450 km of rural roads damaged by the earthquake and
landslides. The National Reconstruction Authority (NRA) is the executing government
agency. Earthquake Emergency Assistance Project (EEAP)-District Level Project
Implementation Unit (DLPIU) is the implementing agency.
Pipalbhanjyang-Hayutar-Netrakali (37.20 Km) Road Rehabilitation and Reconstruction Sub-
project is one of the projects under EEAP. This IEE report has been prepared by DLPIU,
Sindhuli under EEAP to address the likely environmental and social impact, both beneficial
and adverse, due to the proposed upgrading of the road.
The proposed rehabilitation and reconstruction of Pipalbhanjyang-Hayutar-Netrakali Road
Section will render the existing infrastructure devastated by devastating earthquake of 25
April 2015 and the major aftershock of 12 May 2015 fully operative and reinstate the road
access to Kamalamai Municipality ward 2 and Ghyanglekh Rural Municipality ward 1,2,3 and
4 of Sindhuli district with major settlements along the road alignment such as Pipal
Bhanjyang, Bhoteswara, Khatter, Nibuwatar, Buktikhatar, Rajabas, Haitar, Chandanpur,
Solabhanjyang, Chhaukitar, Aaptar etc. as well as the other rural part of Sindhuli district to
the district headquarter and other parts of the country.
The Proponent
The District Level Project Implementation Unit (DLPIU), Sindhuli is the implementing agency
at the district level under Earthquake Emergency Assistance Project (EEAP) project and the
proponent of the Initial Environmental Examination (IEE) study for the rehabilitation and
reconstruction of Pipalbhanjyang-Hayutar-Netrakali Section (37.20 km) of Sindhuli district.
Address of the Proponent
District Level Project Implementation Unit-Earthquake Emergency Assistance Project
Sindhulimadi, Sindhuli District
Telephone No.: 047-520109
Email: [email protected]
Rationale and Objectives of the IEE study
Preparation of IEE for district road is mandatory according to Act Relating to Reconstruction
of the Earthquake Affected Structures 2015, rule relating to reconstruction of the earthquake
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli vii
affected structures 2016, Working Procedure Relating with Environmental Impact
Assessment for Reconstruction of Earthquake Affected Structures, 2016 (schedule 1) and
second amendment (2017) and ADB safeguard policy statement, 2009 to suggest the
appropriate practical & site specific mitigation and enhancement measures to address the
environmental impact of the proposal.
The main objective of the IEE study is to identify the impacts of physical, biological, socio-
economic and cultural environment of the sub-project area and recommend practical and
site specific environmental mitigation and enhancement measures, prepare and implement
environmental management plan for the sub-project.
Project Description and Study Methodology
The proposed sub-project starts from Pipalbhanjyang of Kamalamai Municipality ward no. 2
(then Bhadrakali VDC-3) and ends at Majhitar of Ghyanglekh Rural Municipality-4 (then
Netrakali VDC-5) of Sindhuli district. DLPIU- Sindhuli has proposed to reconstruct the 37.20
km section of the road under EEAP. It will be rehabilitated and reconstructed into a District
Road Core Network (DRCN) standard road with gravel pavement. The road length is 37.20
km with 6.25 meter formation width including shoulder and drainage. The estimated total
project cost is NRs. 807,552,288.46 and the engineering cost is NRs. 777,118,646.06.
This IEE report has been prepared following necessary desk and field study and defined
procedure and also on the basis of the ToR approved on 2017/07/09 A.D by the National
Reconstruction Authority (NRA) to fulfill the statutory requirement of GoN. The findings and
conclusions of the initial environmental examination report are based on the analysis of the
information collected from the field from 2017/08/11 A.D to 2017/08/18 A.D and secondary
information supplemented by the social and technical teams working on the resettlement
survey and detail survey.
Existing Environmental Condition
The dominant rock types present in the sub-project area include gneiss, schist, sandstone
and conglomerate and the common soil types include colluvial, alluvial and residual soils.
Chisapani Khola, Dhanman Khola, Taru Khola, Landi Khola, Simle Khola, Baseri Khola, Lipi
Khola, Rin Khola, Marin Khola, Tamajor Khola are the major stream of the project area.
The elevation of proposed road varies from 527 m to 1154 m from mean sea level. So, it lies
in upper tropical and sub-tropical climatic zone (Dobremez, 1976) and the temperature is
32.35° C during summer and 7.80° C during winter. The average annual rainfall in the district
is 2114 mm.
The sub-project segment lies among cultivation area, settlement, and forest patches. There
is Kalika Community Forest (CF) in between Ch 0+000 to Ch 0+460 & Ch 0+790 to Ch
1+800, Jhalkane CF at Ch 10+250 to Ch 11+000, Ranibas CF at Ch 14+760 to Ch 17+000
and 18+900 to Ch 19+040, four Leasehold Forest (Hariyali, Pragatisil, Lalupate & Laliguras)
in between the Ch 19+040 to Ch 19+460 and Manebhanjyang Leasehold Forest, between
Ch 21+580 to Ch 21+940 and Government Managed Forest between the Ch 27+180 to Ch
29+000 & Ch 29+300 to Ch 30+600.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli viii
Major forest types found in the project area is dominated by tropical mixed broad-leaf forest
dominated by Shorea and Schima species. Major trees include Shorea robusta (Sal), Pinus
roxburghii (Khote Salla), Katus (Castanopsis indica), Schima wallichii (Chilaune), Alnus
nepalensis (Utis), Litsea polyantha (Kutmiro), Toona ciliata (Tuni) etc. Similarly, Berberis
aristata (Chutro), Paris polyphylla (Satuwa), Rubia majith (Majitho) etc. are NTFP reported in
the forests along road alignment. Major wildlife includes Panthera pardus (Chituwa), Canis
aureus (Syal), Hystrix indica (Dumsi), Ursus sp. (Bhalu), Martes flavigula (Malsalpro). Avian
species include Lophura leucomelanos (Kalij), Gallus gallus (Luiche), Streptopelia sp.
(Dhukur), Psittacula sp. (Suga) etc. The extant reptilian species in this forest include
Lycodon aulicus (Siris Sarpa), Ptyas mucosa (Dhaman), Nerodia sipedon (Pani Sarpa) etc.
The major settlements along the alignment include Pipalbhanjyang, Bhoteswara, Khattar,
Nibuwatar, Rajbas, Hayutar, Chandanpur, Solabhanjyang, Netrakali, and Aaptar. 1,365
persons live in 2,859 households in the Directly Impact Area of the sub-project. The
population of the project area is dominated by Tamang. Other main castes include Magar,
Chhetri, Brahmin etc. Total literacy of the project area is 59.60% (including just literate also).
People of the project area are involved in agriculture as their main occupation. Among the
other main occupations, wage labour, foreign employment, and service are important. Health
care service is being delivered by Health Posts and Medicals. Almost 81.75% of the
households use piped water for drinking. 67.86% of the households in the project area have
been supplied with electricity and 32.14% uses solar for the lighting purpose.
Environmental Impacts
Beneficial Impacts
The immediate beneficial impact from the project during construction phase is generation of
temporary employment opportunity of 134,877 person days. The major beneficial impacts
after operation of project includes year round transportation facility and accessibility to the
Kamalamai Municipality-2 and Ghyanglekh Rural Municipality-1, 2, 3 and 4, Pipalbhanjyang,
Bhoteswara, Khattar, Nibuwatar, Rajbas, Hayutar, Chandanpur, Solabhanjyang, Netrakali,
Aaptar and its surrounding settlements of Sindhuli district and promotes the Market
Development, Increase in land Value, Industrial Development, generating employment,
Increase in crop productivity and Increase in sale of local products. Once in operation the
road will offer easy, comfortable and quick access to people of the area to social service
facilities like health, education, market and other facilities. After rehabilitation and
reconstruction of the road, the supply of daily consumables, food and others will be easy and
provide market to local agricultural products which will improve the living standard of and
help the earthquake affected people in social and economic recovery.
Adverse Impacts
Among the adverse impact on the social domain of the environment, pressure on existing
service facilities, possible conflict and clash between local and outside workers, occupational
health and safety are of chief concern. The land acquired for the implementation of the
project can undergo a long-term permanent change in the land use.Changes of land use due
to the construction of road are mainly conversion of 1.665 ha of cultivated land, 1.120 ha
built-up area, 5.312 ha forest and 0.131 ha of barren land, and 0.050 ha of river/ stream
area. Similarly, there will be some change in land use due to expansion of roadside
settlements. Due to the expansion of the road 8 private structure and one community tap will
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli ix
be directly impact. Other impacts are gender discrimination in task and diseases due to
unhygienic living condition, communicable diseases etc. During operation phase, ribbon
settlement along the project alignment could develop haphazardly and encroachment might
occur along road alignment.
Operation of construction equipment and vehicles and use of chemical substances during
construction activates may produce noise, water and air pollution. Improper management of
waste may cause water and soil pollution leading to other deleterious consequences.
Improper storage and handling of construction materials and equipment’s may cause water
and soil pollution through leakage and seepage. Regarding the impact on biological
environment, impact of hunting and poaching on wild animal is considered important. In total,
47 trees from the community forest, 7 trees from the leasehold forest, 832 trees from the
government managedl forest and 373 trees from the private forest and private land need to
be cut down.
Benefit Augmentation Measures
Life skill training such as income generation activities for affected households, construction
of soft engineering structures and bioengineering works for workers will be conducted.
Awareness rising and environmental awareness trainings will be provided. More emphasis
will be given to women workers as at least 20% workers should be women.
Mitigation Measures
A number of practical and cost effective mitigation measures have been suggested to
prevent, correct and compensate the adverse effects of the project implementation. The
project proponent is bound to implement these measures during the construction and
operation of the project. For construction phase, the proponent will implement the mitigation
measures through contractor. Some of the major measures to be adopted are as follows:
Private properties including private structures and private property will be acquired after
compensation.
To address the issue of occupational health and safety, proper safety arrangements will
be made. Safety equipment such as helmets, boots, gloves, safety belts, safety glasses
and masks will be provided to the workers working in the construction sites. Warning
signs, posts, barriers and guards will be installed to restrict access of unauthorized
persons to storage areas.
Arrangements of temporary latrines will be made for workers in proper site.
Spoil generated from earthwork will be disposed in designated location and managed
properly with toe wall and retaining wall, vegetation cover and necessary drainage
structures.
Existing and possible landslides will be controlled or prevented by appropriate bio-
engineering technique.
All the camp wastes and construction wastes will be placed in the designated waste
collection pits away from the water path.
Oils and other chemicals used in construction activities will be handled carefully and
stored in fallow land away from the river beds by using impervious layers.
Hoarding boards carrying messages to aware people on control of hunting and poaching
of wildlife and their conservation will be placed.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli x
NRS. 3,370,788.35 have been allocated for compensatory plantation.
Public Consultation and Information Disclosure
Public consultation was done with the local people living near the proposed road, members
of local organizations and local leaders during the preparation of draft IEE report in order to
aware them of incoming road rehabilitation and reconstruction sub-project and to identify the
possible beneficial and adverse impacts due to this sub-project. After preparation of the draft
IEE report, 7 days public notice was published in 2073/05/24 B.S (2017/09/09 A.D) on
Rajdhani, a national Nepali daily newspaper seeking written opinions from concerned
stakeholders.
Draft IEE report along with executive summary, identified impacts, recommended benefit
augmentation and mitigation measures and EMP was prepared in for public disclosure for
comments and suggestion on the Date 2017/09/14. Likewise, after the incorporation of
comments from NRA, IEE report has been sent for approval.
Grievance Redress Mechanism (GRM)
The IEE report has suggested four (4) levels of GRMs to receive and facilitate resolution of
affected people’s concerns and grievances regarding project’s environmental and social
performances and impacts in a timely and satisfactory manner.
Environmental Management Plan
Environmental Management Plan (EMP) has been proposed with present report including
issues identified, possible effects and impacts, measures for their mitigation, monitoring
methods and schedule in Chapter 9. In addition, agencies responsible for executing
environmental mitigation measures and monitoring have been identified in the EMP.
Different monitoring indicators on the physical, biological, socio-economic and cultural
environment have also been identified. The NRA with district bodies will monitor during
reconstruction and operation phase. For the environmental monitoring, NR 325,000 has
been allocated. The total cost allocated for environment management of the sub-project is
NRs. 12,081,211.68 of which NRs. 7,485,423.33 is already included in civil work cost.
Conclusion and Recommendation
Most of the identified and perceived impacts of the project are of low significance compared
to the project of this scale. With the set of mitigation measures, most of the adverse impacts
can be minimised and/or compensated and limited to locality and construction period.
Hence, it is suitable to implement the project addressing the impacts through the mitigation
and enhancement measures suggested by this IEE, considering the nature of the project, its
location, and people’s positive perceptions and identified environmental impacts.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli xi
Table of Contents
1. Introduction .................................................................................................................... 1
1.1. Background ................................................................................................................ 1
1.2. Proponent ................................................................................................................... 2
1.3. Consultant .................................................................................................................. 2
1.4. Objectives of ToR ....................................................................................................... 2
1.5. Objectives of IEE Study .............................................................................................. 3
1.6. Rationale for Conducting IEE ..................................................................................... 3
2. Detail on Reconstruction and Rehabilitation Work .......................................................... 4
2.1. Location and Access .................................................................................................. 4
2.2. Salient Feature ........................................................................................................... 7
2.3. Components and Activities of the Sub-project ............................................................ 8
2.3.1 Construction Approach .................................................................................... 8
2.3.2 Construction Materials Required ...................................................................... 9
2.4. Human Resource ..................................................................................................... 10
2.5. Land Requirement .................................................................................................... 10
2.6. Cost .......................................................................................................................... 11
2.7. Implementation Schedule ......................................................................................... 11
3. Methodology ................................................................................................................ 12
3.1. Literature Review ..................................................................................................... 12
3.2. Impact Area Delineation ........................................................................................... 13
3.3. Field Investigation .................................................................................................... 13
3.4. Interaction and Public Consultation .......................................................................... 15
3.5. Database Preparation, Interpretation, Identification, Prediction and Evaluation of
Impact ................................................................................................................................. 16
3.6. Study Team .............................................................................................................. 17
3.7. Information Disclosure .............................................................................................. 17
4. Description of the Existing Environment ....................................................................... 18
4.1. Physical Environment ............................................................................................... 18
4.1.1 Topography and Geomorphology................................................................... 18
4.1.2 Land Use Pattern ........................................................................................... 21
4.1.3 Climate and Hydrology ................................................................................... 22
4.1.4 Landslide and Erosion Prone Area ................................................................. 22
4.1.5 Air, Noise and Water Quality .......................................................................... 23
4.2. Biological Environment ............................................................................................. 23
4.2.1 Vegetation Type ............................................................................................. 23
4.2.2 Wildlife ........................................................................................................... 26
4.2.3 Fish ................................................................................................................ 27
4.2.4 Protected Flora and Fauna in Sub-project area .............................................. 27
4.3. Socio-economic and Cultural Environment ............................................................... 28
4.3.1 District Context .............................................................................................. 28
4.3.2 Indirect Impact Area ....................................................................................... 36
4.3.3 Direct Impact Area ......................................................................................... 39
4.3.4 Project Affected Families ............................................................................... 61
5. Impacts of Reconstruction Plan Implementation on Environment ................................. 63
5.1. Beneficial Impacts .................................................................................................... 63
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli xii
5.1.1 Construction Phase........................................................................................ 63
5.1.2 Operation Phase ............................................................................................ 64
5.2. Adverse Impacts ....................................................................................................... 65
5.2.1 Construction Phase........................................................................................ 65
5.2.2 Operation Phase ............................................................................................ 70
5.3. Climate Change Impacts .......................................................................................... 72
6. Analysis of Alternatives ................................................................................................ 73
6.1. No Action Alternative ................................................................................................ 73
6.2. Project Alternatives .................................................................................................. 73
6.3. Alternative Alignment ................................................................................................ 73
6.4. Alternative Design and Construction Approach ......................................................... 73
6.5. Alternative Schedule and Process ............................................................................ 74
6.6. Alternative Resources .............................................................................................. 74
6.7. No Forest Alternative ................................................................................................ 74
7. Environmental Impact Augmentation, Mitigation and Minimization Measures ............... 75
7.1. Mitigation Measures during Pre-construction Phase ................................................. 75
7.1.1 Detailed Survey and Design ........................................................................... 75
7.2. Beneficial Impacts Augmentation Measures ............................................................. 75
7.2.1 Construction Phase........................................................................................ 75
7.2.2 Operation Phase ............................................................................................ 76
7.3. Adverse Impacts Mitigation Measures ...................................................................... 76
7.3.1 Construction Phase........................................................................................ 76
7.3.2 Operation Phase ............................................................................................ 82
7.4. Climate Change Impacts .......................................................................................... 83
8. Legal Framework and Regulatory Requirements for the Project .................................. 85
9. Environmental Management Plan ................................................................................ 91
9.1. Institutions and Their Roles ...................................................................................... 91
9.2. Implementation of Benefit Augmentation and Mitigation Measures ........................... 93
9.3. Mitigation Cost for Executing the Environmental Management Plan ....................... 105
9.3.1 Environmental Monitoring and Reporting Activities ...................................... 105
9.3.2 Major Costs for Environmental Safeguard Measures ................................... 106
9.4. Matters to be monitored while implementing the Proposal ...................................... 107
9.4.1 Baseline Monitoring ..................................................................................... 107
9.4.2 Compliance Monitoring ................................................................................ 107
9.4.3 Impact Monitoring ........................................................................................ 107
9.5. Monitoring Parameters ........................................................................................... 108
9.5.1 Pre-Construction Phase ............................................................................... 108
9.5.2 Construction Phase...................................................................................... 108
9.5.3 Operation Phase .......................................................................................... 109
9.6. Monitoring Indicators .............................................................................................. 109
9.7. Grievance Redress Mechanism .............................................................................. 116
10. Conclusion and Recommendation ............................................................................. 119
References ....................................................................................................................... 120
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli xiii
List of Tables
Table 1: Salient Feature of the Proposed Road..................................................................... 7
Table 2: Possible Quarry Sites .............................................................................................. 9
Table 3: Sources of Construction Materials ......................................................................... 10
Table 4: Additional Land Required Area for Upgrading Pipalbhanjyang-Hayutar-Netrakali
Road ................................................................................................................................... 11
Table 5: Sub-project Implementation Schedule ................................................................... 11
Table 6: Impact Area Delination of Sub-project ................................................................... 13
Table 7: Lithostratigraphy of the Lesser Himalaya Rock Exposed along the Road .............. 18
Table 8: Geology and Types of Soil along the Road Alignment ........................................... 20
Table 9: Land Use along the Road Alignment ..................................................................... 21
Table 10: Location of Landslides and Bio-Engineering Works ............................................. 22
Table 11: Plant species falling under Right-of-Way and Formation-of-Width of Road .......... 23
Table 12: Forests along Road ............................................................................................. 25
Table 13: Protected Flora and Fauna Recorded in Project Area ......................................... 27
Table 14: Demographic Characteristic of Sindhuli District ................................................... 28
Table 15: Absentee populatio .............................................................................................. 28
Table 16: Religion Followed by People of Sindhuli District .................................................. 29
Table 17: Caste and Ethnicity in the Sindhuli District .......................................................... 29
Table 18: Languages Spoken in Sindhuli District ................................................................ 30
Table 19: Educational Status in Sindhuli District ................................................................. 31
Table 20: Status of Drinking Water in Sindhuli District......................................................... 32
Table 21: Status of Toilet Facilities in Sindhuli District ......................................................... 32
Table 22: Types of Toilets in Sindhuli District ...................................................................... 32
Table 23: Status of Energy Used for Cooking in Sindhuli District ........................................ 33
Table 24: Ownership of House in Sindhuli District ............................................................... 34
Table 25: Type of Foundation of House in Sindhuli District ................................................. 34
Table 26: Type of Outer Wall of House in Sindhuli District .................................................. 34
Table 27: Type of Roof of House in Sindhuli District ........................................................... 35
Table 28: Status of Households regarding Facilities to Accessories in Sindhuli District ....... 35
Table 29: Various Facilities Possessed by Households in Sindhuli District .......................... 35
Table 30: General Population Scenario of the Indirectly Affected Areas .............................. 37
Table 31: Ethnic Composition of the Indirectly Impact Areas ............................................... 38
Table 32: Literacy Status of the Indirectly Affected Areas ................................................... 39
Table 33: General Population Scenario of the Project Affected Area ................................... 40
Table 34: General Population Scenario of the Project Affected Areas (Age Group) ............ 40
Table 35: Major Languages Spoken in the Project Affected Areas ...................................... 41
Table 36: Drinking Water Sources in Project Affected Areas ............................................... 42
Table 37: Fuel Source for Cooking in Project Affected Areas .............................................. 42
Table 38: Energy Source for Lighting in Project Affected Areas .......................................... 43
Table 39: Sanitation Status in Project Affected Areas ......................................................... 43
Table 40: Literacy Status in the Indirectly Affected Areas .................................................... 43
Table 41: Major Settlement Located in the Proposed road alignment .................................. 45
Table 42: Household and Population of PAS(s) .................................................................. 45
Table 43: Caste and Ethnicity in PAS(s).............................................................................. 46
Table 44: Religion Followed in PAS(s) ................................................................................ 47
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli xiv
Table 45: Migration Trend in PAS ....................................................................................... 47
Table 46: Occupation in Project Affected Settlement........................................................... 48
Table 47: Livelihood Status in PAS ..................................................................................... 49
Table 48: Housing Structure Type in PAS ........................................................................... 49
Table 49: Available Health Service in PAS .......................................................................... 50
Table 50: Major Disease found in PAS ................................................................................ 51
Table 51: Solid Waste Management Techniques ................................................................ 51
Table 52: Educational Status in PAS ................................................................................... 52
Table 53: Availability and Access to Educational Institutions in PAS(s) ............................... 53
Table 54: Status of Drinking Water in PAS .......................................................................... 53
Table 55: Status of Energy Used for Cooking in PAS .......................................................... 54
Table 56: Status of Energy Used for Lighting in PAS .......................................................... 54
Table 57: Status of Sanitation Condition in PAS .................................................................. 55
Table 58: Status of Telecommunication Facility in PAS ....................................................... 55
Table 59: Major Market in PAS ........................................................................................... 56
Table 60: Status of Refreshment and Shops Facility in PAS ............................................... 57
Table 61: Status of Financial Institutions in PAS ................................................................. 58
Table 62: Land Ownership in PAS ...................................................................................... 58
Table 63: Irrigation Status in PAS ....................................................................................... 59
Table 64: Major Crops in PAS ............................................................................................. 59
Table 65: Major Livestock in PAS ....................................................................................... 59
Table 66: Potential Economic activities by Road Upgrading in local level............................ 60
Table 67: Historical, Cultural, Archaeological, Religious and Tourism Sites ........................ 60
Table 68: Social Centres ..................................................................................................... 61
Table 69: Summary of Affected Households by the Sub-project .......................................... 61
Table 70: Average Income of APs ....................................................................................... 62
Table 71: Food Sufficiency of AP ........................................................................................ 62
Table 72: Possible Spoil Disposal site ................................................................................. 65
Table 73: Proposed Camp site along the road .................................................................... 67
Table 74: Trees to be Cut in Formation Width ..................................................................... 67
Table 75: Summary of Affected Private Structure in the Formation Width ........................... 69
Table 76: Summary of Affected Community structure in the formation width ....................... 69
Table 77: Compensatory Plantation against Tree Loss ....................................................... 79
Table 78: Review of Relevant Acts, Rules, Regulations and Guidelines ............................. 85
Table 79: Institutions and Their Roles ................................................................................. 91
Table 80: Likely Beneficial Impacts and Enhancement Measures ....................................... 94
Table 81 : Likely Adverse Impacts and Proposed Mitigation Measures ............................... 96
Table 82: Environmental Monitoring Cost .......................................................................... 106
Table 83: Estimate for Environmental Enhancement and Mitigation Measures ................. 106
Table 84: Monitoring Indicators Selected for this IEE ........................................................ 109
Table 85: Compliance Monitoring for Pipalbhanjyang-Hayutar-Netrakali Road Sub-project
......................................................................................................................................... 111
Table 86: Impact/Effect Monitoring of Pipalbhanjyang-Hayutar-Netrakali Road Sub-project
......................................................................................................................................... 114
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli xv
List of Figures
Figure 1: Overall Location in GIS Map .................................................................................. 5
Figure 2: Alignment Map of Sub-project ................................................................................ 6
Figure 3: Population of Sindhuli District by Different Age Group .......................................... 29
Figure 4: Literacy Status of Sindhuli District ........................................................................ 31
Figure 5: Status of Energy Used for Lighting in Sindhuli District .......................................... 33
Figure 6: Ethnic Composition of the Indirectly Affected Areas ............................................. 41
Figure 7: Educational Attainment of People in Project Affected Areas ................................. 44
Figure 8: Environmental Management Organisation Structure ............................................ 93
Figure 9: Flow Diagram for Grievance Redress Mechanism .............................................. 117
Appendixes
Appendix I: Approved ToR for IEE Study .......................................................................... 122
Appendix II: Climate Change Checklist ............................................................................. 137
Appendix III: Rapid Environmental Assessment (REA) Checklist ...................................... 139
Appendix IV: Environmental Checklist ............................................................................... 142
Appendix V: Public Notice ................................................................................................. 147
Appendix VI: Project Cost ................................................................................................. 149
Appendix VII: Meeting Minutes and Public Disclosure ....................................................... 151
Appendix VIII: Deed of Inquiry(Muchulka) ......................................................................... 158
Appendix IX: Recommendation ......................................................................................... 172
Appendix X: Consulted Person ......................................................................................... 177
Appendix XI: Trees to be Cut Down .................................................................................. 178
Appendix XII: Affected Structures...................................................................................... 199
Appendix XIII: Photographs............................................................................................... 204
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli xvi
ABBREVIATIONS
ADB: Asian Development Bank
AP: Affected Person
CBO: Community Based Organization
CDC: Compensation Determination Committee
CF: Community Forest
CFUG: Community Forest Users Group
Ch: Chainage
CISC: Central Implementation Support Consultants
CITES: Convention on International Trade in Endangered Species of Wild Fauna and
Flora
CLPIU Central Level Project Implementation Unit
DFO: District Forest Office/Officer
DIA Direct Impact Area
DISC: District Implementation Support Consultants
DLPIU: District Level Project Implementation Unit
DTMP: District Transport Master Plan
DoLIDAR: Department of Local Infrastructure Development and Agricultural Roads
DRCN: District Road Core Network
DRILP-AF Decentralize Rural Infrastructue Livlihood Project-Additional Financing
EA Executing Agency
EARF Environmental Assessment Review Framework
EEAP Earthquake Emergency Assistance Project
EIA: Environmental Impact Assessment
EMP: Environmental Management Plan
EMS: Environmental Management Section
FGD: Focus Group Discussion
GESI: Gender Equality and Social Inclusion
GoN: Government of Nepal
GRC Grievance Redress Committee
Ha: Hectare
Hh: Household
IIA Indirect Impact Area
IEE: Initial Environmental Examination
IUCN International Union for Conservation of Nature
Km: Kilometer
LAC Local Area Committee
LC Least Concern
LEP: Labour based, environment friendly and participatory
LR/NT Lower Risk/Near Threatened
MoFAGA: Ministry of Federal Affairs & General Administration
NCB National Competitive Bidding
NF: National Forest
NRA National Reconstruction Authority
NGO: Non-Governmental Organization
NRs: Nepali Rupees
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli xvii
NTFPs: Non Timber Forest Products
PAS(s): Project Affected Settlements
PF: Private Forest
RM Rural Municipality
RoW Right of Way
SDC: Swiss Agency for Development and Cooperation
SSO: Social Safeguard Officer
ToR: Terms of Reference
VDC: Village Development Committee
ZoI: Zone of Influence
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 1
1. Introduction
1.1. Background
1. Earthquake Emergency Assistance Project (EEAP) is a project being implemented
with the loan financing of ADB, technical assistance from Swiss Agency for Development
and Cooperation (SDC) and counterpart funding from the Government of Nepal (GoN). It
aimed at accelerating economic and social recovery of the communities through
rehabilitation and reconstruction of local infrastructures damaged due to devastating
earthquake of 25 April 2015 and the major aftershock of 12 May 2015. The project will
support the Government of Nepal (GoN) in its efforts to put thousands of children back into
schools, return vital government services to desperate communities, and create jobs and
income for families by repairing critical road networks. The Project covers 12 affected
districts in eastern, middle and western development region of Nepal namely: Kathmandu,
Bhaktapur, Lalitpur, Kavrepalanchowk, Ramechhap, Okhaldhunga, Sindhuli, Solukhumbu,
Ramechhap, Gorkha, Lamjung and Chitwan. The project will repair, retrofit or rebuild at least
700 schools and 300 district-level government buildings damaged by the earthquake to
disaster-resilient standards. The project will also repair and improve about 135 km of
strategic roads and about 450 km of rural roads damaged by the earthquake and landslides.
The road will be rebuilt with improved road safety features and will be designed to withstand
future disasters and the impact of climate change.
2. Total 37.20 km long Pipalbhnajyang-Hayutar-Netrakali road starts at Pipalbhanjyang
of Kamalamai Municipality-2 (then Bhadrakali VDC-3) and ends at Ghyanglekh Rural
Municipality-4 (then Netrakali VDC-5, Majhitar).Then Disitrict Development Committee
(DDC) had opened the track of initial 14 Km road section, from Pipalbhanjyang to Simle
khattar duting 2060 B.S to 2062 B.S and remaining section was constructed during 2066 B.S
– 2067 B.S. This road was reconstructed later by Rural Rehabilitation and Reconstruction
Secto Development Project (RRRSDP) with an average of around 5m.
3. This road was affected by the mega earthquake 2015 in several places. After
completion of this sub-project, the road will connect settlement like Pipalbhanjyang,
Bhoteswara, Khatter, Nibuwatar, Buktikhatar, Rajabas, Hayutar, Chandanpur,
Solabhanjyang, Chhaukitar, Aaptar of KamalamaiMunicipality and Ghyanglekh Rural
Municipality to the BP Highway and to District headquarter Sindhulimadi. Local people will
directly benefit due to transportation facilities, and their economic income will be increase
due to access of local product in the market. In future, the road from Pipalbhanjyang to
Netrakali will meet nearby Nepalthok in BP highway and could be an alternative route for
Kathmandu to Sindhuli. Also, the proposed rehabilitation and upgrading will facilitate the
easy access to the rural people of south-west part of Sindhuli District. Further, the enhanced
road network will provide access to the rural people of these areas to the basic service
facilities like health, education and daily economic activities hence improving their living
standard. Therefore, it has been proposed for rehabilitation and reconstruction and the road
has attracted DTMP priority No-20DR005.
4. The sub-project affected then Bhadrakali VDC is now restructured as ward no. 2 of
Kamalamai Municipality and sub-project affected then VDCs i.e. Amale, Bastipur, Netrakali
and Tamajor is now restructured as ward no. 1, 2, 3 & 4 of Ghyanglekh Rural Municipality
respectively.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 2
1.2. Proponent
5. The proposed sub-project is for the rehabilitation and reconstruction of the Pipal
bhnajyang-Hayutar-Netrakali Road in Sindhuli district. The District Level Project
Implementation Unit (DLPIU) Sindhuli district, being responsible for the district roads is the
proponent for conducting Initial Environmental Examination (IEE) for proposed road under
ADB/SDC and GON funded Earthquake Emergency Assistance Project (EEAP). The
National Reconstruction Authority (NRA) is the concerned authority for the approval of the
IEE study report.
6. Earthquake Emergency Assistance Project (EEAP) under the Ministry of Federal
Affairs and General Administration (MoFAGA) is the implementing agency for the district
road sub-component. EEAP has established Central Level Project Implementation Unit
(CLPIU), headed by Project director in center and District Level Project Implementation Unit
(DLPIU) headed by project manager at district level. DLPIU is supported by District
Implementation Support Consultant (DISC) at district level, Central Implementation Support
Consultant (CISC) and CLPIU at central level.
Address of the Proponent
Earthquake Emergency Assistant Project, District Level Project Implementation Unit,
Sindhuli District
Sindhulimadi
Telephone No.: 047-520149
Fax No.: 047-520544
Email: [email protected]
1.3. Consultant
7. Af-Iteco Ltd., Switzerland acting as Central Implementation Support Consultant of
EEAP has awarded consultancy services to the Joint Venture of Silt
Consultant/TSE/ECN/EC in association with GeoCom International for the consulting service
to prepare Detailed Project Report (DPR) including Initial Environmental Examination (IEE)
Report of the above mentioned road project on behalf of the proponent adhering with all the
prevalent policies, acts, rules and guidelines.
Address of the Consultant
Central Implementation Support Consultant (CISC)
Earthquake Emergency Assistance Project (EEAP)
Ekantakuna, Lalitpur
P.O. Box 113, Kathmandu
Telephone No: 977-1-5543142/43
Fax No: 977-1-5543144
E-mail: [email protected]
Website: www.drilpnepal.org
1.4. Objectives of ToR
8. The main objective of the TOR was to guide the preparation of the comprehensive
and coherent Initial Environmental Examination (IEE) study report as per clause 2 of
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 3
schedule 1 pertaining to section 3 of Working Procedure Relating with Environmental Impact
Assessment for Reconstruction of Earthquake Affected Structures, (second amendment,
2017). The specific objectives of the study were as listed below.
Identify the data requirement of IEE study and general methods for acquisition of such
information
Identify major impacts that may arise as a result of proposed works on physical,
biological, socio-economic and cultural environment of the project area
Identify relevant legal documents that need to be reviewed during the IEE study
Provide an outline on structure of IEE study report.
1.5. Objectives of IEE Study
9. The main objective of the IEE study is to identify the environmental impact due to
implementation of the sub-project in the area and to suggest a sustainable way out, help
decision makers to balance development and protection of human wellbeing and the
environment. The specific objectives of the study are to:
Provide information on the general environmental setting of the project area as baseline
data
Identify, predict and evaluate the major impacts that may arise as a result of proposed
works on physical, biological, socio-economic and cultural environment of the project
area
Recommend practical and site specific environmental mitigation and enhancement
measures
Prepare and recommend environmental management and monitoring plan for the project
1.6. Rationale for Conducting IEE
10. An IEE of the upgrading road is necessary in order to assess the environmental
consequences of the road reconstruction and rehabilitation activities and suggest
appropriate, practical and site specific mitigation and enhancement measures. This is District
Road Core Network (DRCN)2 according to Nepal Rural Road Standard (2055) 1st Revision,
September 2012 of the Department of Local Infrastructure Development and Agricultural
Roads. Preparation of IEE report for district road is mandatory according to act relating to
reconstruction of the earthquake affected structure 2015, rule relating to reconstruction of
the earthquake affected structure 2016, working procedure related with Environmental
Impact Assessment for rehabilitation of earthquake affected structures, second Amendment
2017 (Schedule 1) and safeguard policy statement,2009 of ADB suggest the appropriate
practical & site specific mitigation and enhancement measures to address the environmental
impact of the proposal.
2 A Road within the district joining a VDC headquarter (HQ or a growth centre to the district HQ directly or via other VDC(s), a
neighboring district HQ or the strategic road network is called “district road core network”. Other roads which are not included in this network are village road.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 4
2. Detail on Reconstruction and Rehabilitation Work
2.1. Location and Access
11. The sub-project is located in Kamalamai Municipality ward no. 2 (then Bhadrakali
VDC-3) and Ghyanglekh Rural Municipality 1, 2, 3 & 4 (then Amale VDC, Bastipur VDC,
Netrakali VDC and Tamajor VDC) of Sindhuli district. The proposed road alignment starts at
Pipalbhanjyang of Kamalamai Municipality-2 (then Bhadrakali VDC-3) and ends at
Ghyanglekh Rural Municipality-4 (then Netrakali VDC-5, Majhitar). The major settlements
along the road alignment are Pipalbhanjyang, Bhoteswara, Khatter, Nibuwatar, Buktikhatar,
Rajabas, Hayutar, Chandanpur, Solabhanjyang, Chhaukitar, Aaptar, etc. The main
caste/ethnic groups settled in the project area are Brahmin, Chhetri, Tamang, Magar, Newar,
Sunwar etc.
12. The land use of the sub-project area is mainly covered by cultivated land, forest,
Bagar and built-up area. The elevation of proposed road varies from 527 m to 1154 m from
mean sea level. The project area is located in upper tropical and sub-tropical climatic zone.
The road does not pass through any protected areas, historically and archaeologically
sensitive areas. This road has been proposed for upgrading as gravel and cobble. The road
passes through forests, cultivated land, barren land and settlement area crossing streams
(Kholo/kholsi) such as: Chisapanu Khola, Dhanman Khola, Taru Khola, Landi Khola, Simle
Khola, Baseri Khola, Lipe Khola, Rin Khola, Marin Khola, Tamajor Khola are the major
streams of the project area.
13. Length of this road is 37.20 km and formation width is 6.25 m. Total sub-project cost
is NRs. 807,552,288.46 and civil work cost is NRs. 777,118,646.06 as shown in Appendix
VI. The location of road is given in Figure 1 and 2.
14. In the initial phase, the first 14 Km road section, from Pipalbhanjyang to Simle khattar
was constructed in 2060 to 2062 and remaining section was constructed in 2066 - 2067.
Initially the road was constructed through financial support from DDC and later by RRRSDP.
The average width of the road was around 5m. Road was affected by the mega earthquake
2015 in several places. After completion of this sub-project the road connects several
settlements of KamalamaiMunicipality and Ghyanglekh Rural Municipality to the BP Highway
and to district headquarter Sindhulimadi. Local people will directly benefit due to
transportation facilities, and their economic income will be increase due to access of local
product in the market. In future, the road from Pipalbhanjyang to Netrakali meets nearby
Nepalthok in BP highway and could be an alternative route for Kathmandu to Sindhuli.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 5
Figure 1: Overall Location in GIS Map
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 6
Figure 2: Alignment Map of Sub-project
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 7
2.2. Salient Feature
15. The salient features of Pipalbhanjyang-Hayutar-Netrakali Road, including the
features described in the preceding sections, are summarized in Table 1.
Table 1: Salient Feature of the Proposed Road
S.N Particular Description
1 Name of the Sub-project Pipalbhanjyang-Hayutar-Netrakali Road rehabilitation and
reconstruction sub-project
2 Geographical Location Sindhuli District
3 Starting Point Pipalbhanjyang of Kamalamai Municipality-2 (then
Bhadrakali VDC-3), Sindhuli District
4 End Point Ghyanglekh Rural Municipality-4 (then Netrakali VDC-5,
Majhitar), Sindhuli District
5 Terrain Siwalik and Hilly
6 Municipality/Rural
Municipality along road
corridor
Kamalamai Municipality (then Bhadrakali VDC) and
Ghyanglekh Rural Municipality (then Amale VDC, Bastipur
VDC, Tamajor VDC and Netrakali VDC) of Sindhuli
district.
7 Household Number (DIA) 2,859
8 Major Settlements Pipalbhanjyang, Bhoteswara, Khattar, Nibuwatar, Rajbas,
Hayutar, Chandanpur, Solabhanjyang, Netrakali, Aaptar
9 Geological Feature Basically characterized by gneiss, schist, sandstone and
conglomerate and the common soil types include
colluvial, alluvial and residual soils
10 Climate Upper tropical and Sub-tropical
11 Alignment Existing
12 Classification of Road District Road Core Network (DTMP code: 20DR005)
13 Road Status Earthen
14 Road Length 37.20 km
15 Road Standard NRRS 2055 (second rev 2071)
16 Proposed Pavement Gravel and cobble
17 Right of Way 10 m either side of center line
18 Roadway Width
(Formation)(m)
6.25 with drain
19 Carriage Way Width (m) 3.75
20 Shoulder Width, either
side (m)
0.75
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 8
S.N Particular Description
21 Maximum Gradient (%) 12
22 Minimum Gradient (%) 0.5
23 Retaining structures 29,545.96 m3
24 Stone Masonry Wall 14,038.76 m3
25 Cutting 1,88,385.21 m3
26 Filling 40,820.17 m3
27 Total civil cost (NRs.) 777,118,646.06
28 Bioengineering Works
(NRs.)
5,827,259.86
29 Mitigation Cost (NRs.) 4,270,788.35
30 Monitoring Cost (NRs.) 325,000.00
31 Total EMP Cost (NRs.) 12,081,211.68 ( of which NRs. 7,485,423.33 is included in
civil work cost)
32 Resettlement Cost (NRs.) 25,637,854.05
33 Gender Equality & Social
Inclusion Cost (NRs.)
200,000.00
34 Total Project Cost (NRs.) 807,552,288.46
Employment Generation (Total Person Days)
35 Skilled 31,134
36 Unskilled 103,743
2.3. Components and Activities of the Sub-project
16. Total length of the road is 37.20 km with 6.25 m formation width. Project components
are: construction of structures like toe wall, retaining wall, breast wall as well as earthwork
like site clearance, gravel and cobble works etc. bioengineering, spoil disposal management,
compensatory plantation are the activities during the construction of this road sub-project.
2.3.1 Construction Approach
17. Implementation of road sub-project works shall be carried out by the contractor,
selected through NCB with following features:
Use of heavy machinery for construction.
Balancing cut and fills and reuse of excavated materials as construction materials, and
thus not generating excess spoils as far as possible.
Use of bio-engineering techniques with integrated use of vegetation, simple civil
engineering structures and proper water management systems for slope protection.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 9
2.3.2 Construction Materials Required
18. Construction material investigation was carried out around vicinity of the project sites
along the road alignment. The investigation focused on locating prospective borrows areas
of non-cohesive materials (colluvial and alluvial deposits). The prospective borrow sites were
identified as sources of coarse aggregates.
19. The construction material survey was carried out for the following purposes:
Identification of location, estimation of quantity of sand, boulder, gravel and other
possible construction material in and around the construction site.
Site identification and determination of relevant materials available along river beds that
can be used as concrete aggregates.
20. Based on the construction material survey, different quarry sites are observed along
the road as well as at river bank, possible quarry sites are shown below in Table 2.
Table 2: Possible Quarry Sites
Material Site Average
Distance
Location (Municiplaity /
RM-Ward)
Sand (i) Baseri khola, lipe khola, rin khola,
tamajor khola outside of road alignment
(ii) Dhanman khola, tar khola, langdi
khola along the road alignment (iii)
Alternative source (marin khola, kamala
mai khola etc.)
10 km Kamalamai Municipality-2
and Ghuanglekh Rural
Municipality-1
Stone (i) Baseri khola, lipe khola, rin khola,
tamajor khola outside of road alignment
(ii)Dhanman khola, tar khola, langdi
khola, Ch. 20+410-20+620 and Ch.
20+800-21+160 along the road
10 km Kamalamai Municipality-2
and Ghuanglekh Rural
Municipality-1,2
Gravel (i) Baseri khola, lipe khola, rin khola,
tamajor khola outside of road alignment
(ii) Dhanman khola, tar khola, langdi
khola along the road alignment (iii)
Alternative source (marin khola, kamala
mai khola etc)
10 km Kamalamai Municipality-2
and Ghuanglekh Rural
Municipality-1
Crushed
Aggregate
(i) Kamalamai khola 10 km up to
Ch 0+000
Kamalamai Municipality-2
Source: Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Project (DPR 2017)
21. The main source of construction materials is the Dhanman Khola, Tar Khola, Landi
Khola, Baseri Khola, Lipe Khola, Rin Khola, and Tamajor Khola. The materials from quarry
side are also possible along the road but the quantities are less. The river bed materials from
the Dhanman Khola, Tar Khola, Landi Khola, Baseri Khola, Lipe Khola, Rin Khola, and
Tamajor Khola can be used. The volume of the construction materials is more than sufficient
in quantity for the road construction. The possible areas are given below in Table 3.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 10
Table 3: Sources of Construction Materials
S.N Source Distance from
Road
Composition
Type of Extraction Current
Land
Use
Borrow
Area
Hydrology
Geological
Instability
1 Dhanman
Khola,
Riverbed B-25%;
C+P 60%; S-15%
Gneiss-70%;
Quartzite and schist-
30%
Barren 200x3x2
m3
Stable
2 Tar
Khola,
Riverbed B-35%;
C+P 50%; S-15%
Gneiss-80%;
Quartzite and schist-
20%
Barren 110x4x2
m3
Stable
3 Landi
Khola,
Riverbed B-45%;
C+P 50%; S-5%
Gneiss-20%;
Quartzite and schist-
70%
Barren 200x2x2
m3
Stable
4 Baseri
Khola,
10 km far from
road alignment
riverbed
Gneiss-20%;
Quartzite and schist-
70%
Barren 200x2x2
m3
Stable
5 Lipe
Khola,
10 km far from
road alignment
riverbed
Gneiss-
20%;Quartzite and
schist- 70%
Barren 200x2x2
m3
Stable
6 Rin
Khola,
10 km far from
road alignment
riverbed
Gneiss-20%;
Quartzite and schist-
70%
Barren 200x2x2
m3
Stable
7 Tamajor
Khola
10 km far from
road alignment
riverbed
Gneiss-20%;
Quartzite and schist-
70%
Barren 200x2x2
m3
Stable
Source: Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Project (DPR 2017)
2.4. Human Resource
22. The project requires both skilled and unskilled human resource. Total 134,877
person days human resource (31,134 person days skill and 103,743 person days unskilled)
will require carrying out civil work activities.
2.5. Land Requirement
23. The land acquired for the implementation of the project can undergo a long-term
permanent change in the land use. The formation width of the road is 6.25 m, but the road
width that has been cleared is, on an average, 5.25 m. An additional 1 m (in average) has to
be cleared in order to achieve the desired width. Changes of land use due to the
construction of road are mainly conversion of additional 1.665 ha of cultivated land, 1.120 ha
built-up area, 0.754 ha forest and 0.131 ha of barren land, and 0.050 ha of river/ stream
area. Detail is given in Table 4 below.The existing road has auquired 3.741 ha of forest land,
and with additional 0.754 ha of additional land; the road sub-project requires total 4.495 ha
of forest land (CF/NF/LHF) upto Ch 29+290. Further 0.812 ha of forest land will be lossed
from Ch 29+290 to Ch 37+200.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 11
Table 4: Additional Land Required Area for Upgrading Pipalbhanjyang-Hayutar-
Netrakali Road
S.N Land Use Area
Ha %
1 Cultivated Land 1.665 44.40
Khet 0.915
Bari 0.750
2 Forest (Government) 0.314 8.37
3 Forest (Community) 0.189 5.04
4 Forest (Leasehold) 0.085 2.27
5 Forest (Private) 0.193 5.23
6 Built-up Area (settlement area) 1.120 29.87
7 Barren Land 0.131 3.49
8 River/Stream 0.050 1.33
Total 3.720 100.00
Source: GIS Map prepared for the road Alignment Field Survey; 2017
2.6. Cost
24. Length of this road is 37.20 km and formation width is 6.25 m. Total sub-project cost
of the road is estimated to be NRs 807,552,288.46 and the total civil work cost is NRs.
777,118,646.06 as shown in Appendix VI.
2.7. Implementation Schedule
25. Following Table 5 shows the proposed implementation schedule for the sub-project.
Table 5: Sub-project Implementation Schedule
S.N Activities 2016 2017 2018
I II III IV I II III IV I II III IV
1 Detailed survey, design and
estimate
2 Preparation of resettlement plan
2.1 Life skill and income generation
training
3 Environmental assessment and
implementation
3.1 ToR preparation and approval from
NRA
3.2 Field study
3.3 Draft IEE preparation and notice
publication
3.3 IEE report finalization and approval
from NRA and ADB
3.4 Implementation of EMP
3.5 Environmental monitoring
4 Work implementation
4.1 Civil construction work by contractor
Note:
I - January, February, March II - April, May, June
III - July, August, September IV- October, November, December
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 12
3. Methodology
26. ToR was approved on 2074/03/25 B.S (09/07/2017 A.D) by the CEO level decision of
National Reconstruction Authority (NRA) which is given in Appendix I as per Act Relating to
Reconstruction of the Earthquake Affected Structures 2015, Rules Relating to
Reconstruction of the Earthquake Affected Structures 2016, Working Procedure Relating
with Environmental Impact Assessment for Reconstruction of Earthquake Affected
Structures, (second amendment, 2017).Total road length in ToR was 37.20 km and IEE
report has been prepared accordingly. Climate change checklist as given in Appendix II and
Rapid Environmental Assessment (REA) Checklist as given in Appendix III and
environmental checklist of affected settlement area (Appendix IV) were also considered
during IEE report preparation. Necessary information was collected through literature review
and field study to accommodate all issues as included in the approved ToR to analyze
environmental impacts on physical, biological, socio-economic and cultural issues.
27. The IEE approach, methodology and procedure were followed according to the
provisions of the Act Relating to Reconstruction of the Earthquake Affected Structures 2015,
Rules Relating to Reconstruction of the Earthquake Affected Structures 2016, Working
Procedure Relating with Environmental Impact Assessment for Reconstruction of
Earthquake Affected Structures, (second amendment, 2017). It followed methodology
suggested in the approved ToR for IEE Study (review of literature, sample
survey/inspections/observations making simple measurements, discussion with communities
and other stakeholders, and IEE team judgment).
28. Based on the analysis of information the impacts have been identified, mitigation
measures prepared and monitoring plan has been developed.
3.1. Literature Review
29. IEE study team collected and reviewed the available secondary sources related to
physical, biological, socio-economic and cultural environmental resources of the sub-project
area. After the literature review, sub-project specific checklist was prepared.
a. Physical Environment
30. From various available sources of secondary information (e.g. Topographical Map,
Regional Geological Map, DHM, MoPE, and District Transport Management Plan (DTMP) of
Sindhui and information on topography, geology and precipitations, temperatures were
reviewed and collected.
b. Biological Environment
31. The important secondary sources of information were reviewed from relevant
literatures including other projects IEE/EIA reports, then VDC Profiles, and websites of
MoPE, DoF, then MoFSC, and DNPWC.
c. Socio-economic and Cultural Environment
32. During desk study necessary secondary data and information were gathered from
related organizations/institutions, like cadastral survey maps, National Population and
Housing Census, CBS 2011 A.D (including VDC/Municipality level).Similarly, resettlement
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 13
plan and GESI report for this road sub-project was also reviewed. These documents were
reviewed and relevant information for the study was assembled.
3.2. Impact Area Delineation
33. The project will have direct impact on Kamalamai Municipality ward no 2 (then
Bhadrakali VDC) and Ghyanglekh Rural Municipality 1, 2, 3 & 4 (then Amale VDC, Bastipur
VDC, Netrakali VDC and Tamajor VDC) of Sindhuli district. Detail on delineation of impact
area is given in Table 6.
Table 6: Impact Area Delination of Sub-project
Category Description
Direct Impact Area (Ward
level)
Construction areas which include road alignment & right of
way along with project facilities such as construction camp,
quarry site, spoil disposal sites, material storage, etc.
Considering administrative boundary: Kamalamai Municipality-2 (then
Bhadrakali VDC) and Ghyanglekh Rural Municipality 1, 2, 3 & 4 (then
Amale VDC, Bastipur VDC, Netrakali VDC and Tamajor VDC ) of
Sindhuli district
Indirect Impact Area
(Municipality/Rural
Municipality level)
Immediate areas of construction with moderate and low
impacts. Such area covers area beyond the DIA and within
100 meters each side from the centerline of road including a
buffer area of about 100 meters from the ancillary structure
sites.
(Considering administrative boundary: Kamalamai Municipality and
Ghyanglekh Rural Municipality of Sindhuli district)
3.3. Field Investigation
34. Afte the collection and review of literature, preparation of checklist, IEE study team
was mobilized to field. Data collection was done from 11/08/2017 to 18/08/2017 A.D
(2074/4/27 B.S to 2074/5/2 B.S) with the help of the staff of DISC (Sub-Engineer, Assistant
Sub-Engineer) and DLPIU (Engineer). Field survey comprised of walk through survey,
consultation with community, site inspection and observation. IEE study team also collected
muchulka, recommendation letters after the publication of notice. The following tools were
used for the collection of primary data.
Consultation meeting and focus group discussion (FGD) - To conduct consultation with
the local communities at different settlements, 2 consultation meeting and one FGD was
organized with Leasehold forest group to collect the opinion and suggestion and feed
back towards project.
Key informants survey: It was conducted with knowledgeable persons at different
settlement. It was done to collect biological, socio-economic and cultural environment
related information using a checklist
Walk through survey: Total enumeration was done for the listing of agricultural land,
forest land, affected trees, houses and other infrastructure affected properties within the
formation width of the road alignment.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 14
Stripe map - It was used during walkthrough survey to document environmental features
according to the chainage.
Topographical map - It was used to show environmental features on the map during
walkthrough survey.
a. Physical Environment
35. Physical environment survey was carried out by delineating the impact area, which
might be affected by the proposal activities during construction and operation of the road
main components and support facilities. Field survey was carried out for the land use,
topography, geomorphology, geology, soil, land stability, drainage characteristics, rainfall,
meteorological conditions, noise level, water quality, air quality etc. Site specific information
on the above sectors was collected by direct observations and consultations with the local
communities for the identification of physically critical areas particularly flood prone areas/
landslide/erosion prone areas etc.
b. Biological Environment
36. Total enumeration was done for tree loss assessment within the formation width and
Right of way in the road alignment. The detail vegetation survey was carried out by
walkthrough survey throughout the road alignment. Type of vegetation and forest type (NF,
CF, LHF and PF), floristic composition (Direct Impact Area & Indirect Impact Area), Ethno-
botany (NTFP/MAP) was identified based on the species composition.
37. The protected vegetation (rare, endangered, indigenous etc.) of the influence area as
per IUCN Red Book, CITES Appendices, and GoN list species was enumerated based on
consultation with the local people in the indirect impact areas of the project. The trees to be
felled down from forest for the proposed road was recorded and documented.
38. Wildlife (mammals, birds, reptiles) bio-diversity in the indirect impact areas was
studied through consultation with the local communities, FUGs in the field (Community and
Leasehold Forest Groups). The indicator wildlife and threatened or endangered species (as
per IUCN Red Book, CITES Appendices, and GoN list) in the area was identified through
consultation with different secondary sources.
c. Socio-economic and Cultural Environment
39. Information on general socio-economic conditions of the people of the project
affected wards of Municipality/ Rural Municipality was collected through Key Informant
Interview (Appendix X) or Focused Group discussions, Appendix VII. The information was
collected through pre-designed checklists, which include key socio-economic characteristics
of the people of all class, caste and economic categories. The information include
demographic features of the settlement, migration pattern, employment, landholding size,
agricultural production, food sufficiency, other productive resources, livestock raising,access
to different social infrastructures such as drinking water, education, health-posts, general
health, hygiene and sanitation condition, etc.
40. Inventory of loss was done by keeping record of affected land, structure through
direct observation within COI. A census of socio-economic and loss assessment survey of
sub-project affected household was carried out to document complete socio-economic and
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 15
loss assessment. Socio-economic and loss assessment survey was carried for 133; out of
242 HHs (others were absentee households).
41. Information on social infrastructures such as schools, health posts, drinking water
etc. was collected from the Ward offices of municipality, consultation with village elites and
through focus group discussions at Ward levels to assess the current situation of these
facilities and the general sanitation status of the project area community. Information was
also collected on the conditions of these facilities, their adequacy and beneficiary population.
42. All sites of religious, cultural and historical importance on the direct project affected
area was visited and observed in the area. The social, cultural and religious values and
significance of these sites was noted through consultation with the communities. Possibilities
of protecting, conserving or relocating such sites were also examined thoroughly in
consultation with local people, priests and village elite.
43. The socio-economic, cultural and religious information was cross checked and
analyzed using Microsoft Excel 2010.
3.4. Interaction and Public Consultation
44. During the IEE report preparation, district project team met, discussed and interacted
with concerned staff of the Government of Nepal, municipality, RM in the district head
quarter and teachers, community based organization member and knowledgeable key
persons of surrounding areas within the direct impact area (please refer Appendix VII).In
order to ensure public involvement, the following procedures were followed during IEE report
preparation.
Publication of Notice and Draft IEE Disclosure
45. According to working procedure relating with environmental impact assessment for
reconstruction of the earthquake affected structures 2016, 7 days public notice was
published in 2074/05/24 B.S (09/09/2017 A.D), Rajdhani, a national level daily newspaper
(Appendix\ V) seeking written opinion from concerned RM, DFO, municipality, schools,
health posts and related local organizations; immediately after approval of ToR as per Act
Relating to Reconstruction of the Earthquake Affected Structures 2015, Rules Relating to
Reconstruction of the Earthquake Affected Structures 2016, Working Procedure Relating
with Environmental Impact Assessment for Reconstruction of Earthquake Affected
Structures, (second amendment, 2017).A copy of the public notice was also affixed in the
above mentioned organizations and a deed of enquiry (muchulka) was collected (see
Appendix VIII for deed of inquiry).
46. The IEE team carried out interactions with local communities and related
stakeholders during the field survey to collect public concerns and suggestions. Moreover,
focus group discussions were conducted to collect and solicit information regarding the
biological, physical, socio-economic and cultural aspects of Pipalbhanjyang- Hayutar-
Netrakali road sub-project. The meeting minutes with local are in Appendix VIIa. Also, draft
IEE was disclosed to local people and concerned stakeholder on 2074/05/29 (2017/09/14) at
Rajabas, Sindhuli. The issues, queries, concerns raised during the Public meeting are in
Appendix VIIb. The findings of public consultation are summarized in Appendix VIIc.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 16
3.5. Database Preparation, Interpretation, Identification, Prediction
and Evaluation of Impact
Data Analysis and Interpretation
47. The required data for the study was collected through primary and secondary source
as mentioned above and database was prepared. The collected data was analyzed
qualitatively and quantitatively to establish existing baseline information on physical,
biological, socio-economic and cultural environment. Data and information from the
questionnaires/checklists were entered on processing data entry layout. Data analysis and
interpretation of physical, biological and socio-economic and cultural environments were
carried out by the respective domain specialists. Then interpretation was made based on the
results obtained. In brief these are presented here under.
a. Physical Environment
48. The collected existing baseline condition information and data on such as topography
(i.e. elevation, aspect, and slope), geology and soil type were analyzed. Similarly, qualitative
data on air, water and noise pollution status were analyzed. For instances, measure
discontinuities data were used for slope stability assessment. Likewise, slope stability in
rocks was analyzed with the help of dip version 5.1. The output of analyzed information and
data were interpreted in logical, sequential and consistent order.
b. Biological Environment
49. The biological environmental information (e.g. tree and wildlife species, and bird
species) collected from primary and secondary sources were tabulated. The biological
information were primarily collected with the use of specified checklist during the formal and
informal meetings with the local people. In addition biological experts identified the different
species of wildlife and plants with their expert judgement, identification keys and with the
help of local people. The local name, photographs and information from the expert
judgement thus collected were analysed during report preparation. Forest type with
management ownership was mentioned. Then the recorded species were compared and
verified to the list prepared by IUCN Red Data Book, CITES and List of Endangered, Rare
and Threatened Plant and Wildlife Species published by GoN.
c. Socio-economic and Cultural Environment
50. The collected socio-economic data were entered in MS Excel 2010 and processed as
required. Similarly, qualitative data related to socio-economic and cultural environment was
analyzed to create the existing baseline. Suggestions made by the local people and
stakeholders' during public consultation were also considered for benefit augmentation
measures and mitigation measures for adverse impacts are proposed.
Impact Identification, Prediction and Evaluation Method
a. Impact Identification
51. Based on field visit observation and consultation meeting with local, issues that may
trigger due to project intervention were identified and prioritized. From the exercise both
types of beneficial and adverse impacts were identified for IEE study. The impacts were
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 17
categorized as per environmental domain (i.e. physical, biological, and socio-economic and
cultural environments). Likewise; an impact that may trigger under different phases of project
implementation (i.e. construction and operation) was also taken into account for the
assessment.
b. Impact Prediction
52. Extrapolative (i.e. predictions on the basis of past and present data, and trend
analysis), and experts` experience and judgment (applying past experience and knowledge
of the experts) methods were applied for impact prediction on the basis of identified impacts.
c. Impact Evaluation
53. The assessment of environmental impacts was derived exclusively from the baseline
environmental conditions of the affected environment with the project activities in relation to
spatial and temporal aspects in terms of magnitude, extent and duration of impacts. The
impacts have been predicted in terms of their magnitude (minor, moderate and high), extent
(site specific, local and regional) and duration (short, medium and long term). Evaluation of
the level of significance of impacts was made based on prevailing legislative setup,
numerical values with scoring (National EIA Guideline, 1993), consultation with stakeholders,
expert’s past experience and other criteria.
3.6. Study Team
54. Field survey comprised of walkthrough survey, consultation with community, site
inspection and observation. Data collection was done from 11/08/2017 to 18/08/2017 A.D
(2074/4/27 B.S to 2074/5/2 B.S). The study team members are listed below:
Team Member
Mr. Abhishek B.C- Team Leader/Environment and Social Expert
Mr. Jivan Koirala- Civil Engineer
Mr. Kumar Prasad Aryal- Environmental Anthropologist /Forester
Mr. Phurba Sherpa- Ecologist
Mr. Shashwat Sharma- Environmental Engineer
Mr. Subash Acharya- Geologist
Mr. Dikra Prasad Bajagai-Environmentalist
3.7. Information Disclosure
55. A draft IEE report along with the executive summary, identified impacts,
recommended mitigation measures and the EMP in Nepali language has been prepared and
distributed to the stakeholders and the concerned RM/Municipality for public disclosure. The
draft IEE report was also be kept in information centre of DLPIU, Sindhuli for public
disclosure. Information was also disseminated through person to person contacts, interviews
and group discussions. The approved IEE report will be accessible to interested parties and
the general public through the information centre of DLPIU, Sindhuli and websites of EEAP-
CLPIU, NRA, CISC and ADB.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 18
4. Description of the Existing Environment
56. The baseline information on the existing physical, biological as well as socio-
economic and cultural environment of the proposed sub-project are described as follows:
4.1. Physical Environment
57. The section describes the physical condition of the area that comes under the ZoI of
the road section along its entire length and surrounding area.
4.1.1 Topography and Geomorphology
Topography
58. Nepal Himalayas is located in the seismic risk zone hence it belongs to seismic
active area and has experienced mega earthquakes that have resulted in major destruction,
loss of life and property. Sindhuli is also one of the earthquake affected district in the 2015
earthquake of the Nepal.
59. The road alignment lies in the Himalaya range. The road alignment starts from
Pipalbhanjyang (1154 m amsl) and ends at Simle khola of Netrakali (527 m amsl). The
elevation of proposed road varies from 527 m to 1154 m from mean sea level. The project
area is located in upper tropical and sub-tropical climatic zone. The proposed project site
falls under sivalik and middle mountain physiographic region of Nepal (Topographic Survey
Branch, Department of Survey, HMG, Nepal, 1983). The dominant rock types present in the
sub-project area include of gneiss, schist, sandstone and conglomerate and the common soil
types include colluvial, alluvial and residual soils.
Geomorphology, Geology and Soil Type
60. Initially, the road alignment follows the fragile geological area of the Siwalik range
and also passes through the rocky terrain of the Lesser Himalaya as well as residual soil and
colluvial deposits. The road alignment passes through wet and dry cultivated land,
grassland, forest.
61. The road alignment follows on the rocks of the Middle and Upper Siwaliks of the
Siwalik Group and Benighat Slate, Kalitar Formation, Chisapani Quartzite and Kulikhani
Formation. This road alignment passes through the regional thrust like Main Boundary
Thrust (MBT) and Mahabharat Thrust (MT). The MBT separates the rocks of the Siwalik
Group in south and Lesser Himalayan rocks in north whereas the MT separates the rocks of
the Nawakot Complex in south and Kathmandu Complex in north. Detail is given in Table 7
below.
Table 7: Lithostratigraphy of the Lesser Himalaya Rock Exposed along the Road
Group Formation Lithology Thickness (m) Age
Siwalik
Upper Conglomertae 1500‖
Neogene Middle Sandstone>>mudstone 3000
Lower Siwalik Mudstone>>sandstone 2000+
Main Boundary Thrust (MBT)
Tistung Granite/ quarzite 1000
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 19
Group Formation Lithology Thickness (m) Age
Kathmandu Markhu Marble/schist 500
Pre-
Cambrian
Kulikhani Quartzite 2000
Chisapani Quartzite Quartzite 400
Kalitar Quartzite/schist 1000
Bhaisedovan Marble 2000
Raduwa Schist 1000
MAHABHARAT THRUST(MT)
Upper
Nawakot
Robang Quartzite/schist 800
Pre-
Cambrian
Malekhu Limestone Quartzite, dolomite 1000
Benighat Slate Slate/limestone 3000
62. Engineering Geological study is done based on distribution of failures, soil and rock
along the alignment. Information covers depth of soil, rock and soil type, geological
structures, weathering grade. The road alignment passes through weathered rock and
alluvial, colluvial, residual soil deposits. Thickness of alluvial, colluvial and residual soil
deposits are excess of 5 m.
Pipalbhanjyang to Hayutar Sector
63. The road is about 22.20 km in length and passes gentle slope area along the river
valley area. The road alignment runs on thick residual soil and alluvial deposits and very few
locations covers the bedrock of conglomerate and sandstone of the Middle and Upper
Siwaliks. Thicknesses of residual soil deposits and colluvial deposits as well as alluvial
deposits are about 5 m. The hydrological condition of the road alignment is dry to wet. The
land use pattern along the road alignment is cultivated land, forest and settlement but most
of the alignment follows the cultivated land. The bedrocks of conglomerate and sandstone of
the Middle and Upper Siwaliks are exposed along the road alignment but very few location
bedrocks are exposed and covered by residual soil. The main cause of covering the residual
soil deposits due to presence of the soft rocks in the valley side. The failures occurred along
the road can be mitigated by, applying bioengineering as well as surface drainage,
management and arrangement of the wall. The slope stability condition is more or less
stable even the alignment runs on the residual soil deposits. Between the chainages road
alignment has the low height cut slope on hill side so stability condition seems to be good
but there is high possibility to occur the bank erosion due to bank undercutting along the
river bank. High possibility to see the differential weathering pattern in the sandstone and
mudstone of the Middle Siwalik as well as loose gravel bed and layers of sands and muds.
Hayutar to Majitar Sector:
64. This complete section of the road is about 15 km and is passing 80% on residual
soil/colluvial deposits and 20% only in the rocks of the Lesser Himalaya (quartzite, gneiss,
slate) of the Kalitar, Kulikhani Formation and loose gravel bed of the Upper Siwalik. The road
crosses MBT several times. The road follows gently topography and climbs down to
Majhitar. Some cut slope failures are found along road alignment in hill side. These failures
are developed due to weathering of rocks as well as presence of loose material deposits,
undercutting slope by road cutting. Thickness of the residual soil deposits along the road is
more than 5 m at places. At some places of the road alignment slate, gneiss and quartzite
are exposed. These rocks are slightly to highly weathered. Two to three sets of the joints are
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 20
well observed in rocks exposed along the road alignment. The stereographic projection of
the discontinuities of the rock mass shows more or less stable condition. The persistency of
the rocks mass is moderate to low. The hydrological condition is wet to dry. The land use
pattern is dry cultivated land and forest and settlement. Detail is given in Table 8 below.
Table 8: Geology and Types of Soil along the Road Alignment
Chainage Geology Types of Soil
0+000 - 0+400 Friable pebbly sandstone
and mudstone
Friable pebbly sandstone and mudstone /
colluvial deposits
0+400 - 0+600 Friable pebbly sandstone
and mudstone
Colluvial deposits / residual soil
0+600 - 1+200 Friable pebbly sandstone
and mudstone
Friable pebbly sandstone and mudstone /
colluvial deposits
1+200 - 1+400 Friable pebbly sandstone
and mudstone
Residual soil and alluvial deposits
1+400 - 3+000 Friable pebbly sandstone
and mudstone
Residual soil and alluvial deposits
3+000 - 3+600 Loose conglomerate Alluvial and residual soil deposits
3+600 - 4+000 Loose conglomerate Loose conglomerate and Residual soil
4+000 - 5+400 Loose conglomerate Alluvial and residual soil deposits
5+400 - 7+400 Loose conglomerate Loose conglomerate / alluvial and residual
soil deposits
7+400 - 8+600 Loose conglomerate Alluvial and residual soil deposits
8+600 - 10+500 Loose conglomerate Loose conglomerate / alluvial and residual
soil deposits
10+500 - 11+200 Loose conglomerate Alluvial and residual soil deposits
11+200 - 11+800 Loose conglomerate Loose conglomerate / alluvial and residual
soil deposits
11+800 - 13+700 Loose sandstone and
mudstone
Alluvial and residual soil deposits
13+700 - 14+400 Loose sandstone and
mudstone
Loose sandstone and pebbly sandstone/
alluvial and residual soil deposits
14+400 - 17+400 Loose sandstone and
mudstone
Alluvial and residual soil deposits
17+400 - 18+400 Loose conglomerate Loose conglomerate / alluvial and residual
soil deposits
18+400 - 19+200 Loose conglomerate Alluvial and residual soil deposits
19+200 - 19+800 Loose conglomerate Loose conglomerate / alluvial and residual
soil deposits
19+800 - 20+600 Loose conglomerate Alluvial and residual soil deposits
20+600 - 20+900 Loose conglomerate Loose conglomerate / alluvial and residual
soil deposits
20+900 - 25+800 Loose conglomerate Alluvial and residual soil deposits
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 21
Chainage Geology Types of Soil
25+800 - 29+200 Loose conglomerate/
slate/ quartzite
Loose conglomerate / alluvial and residual
soil deposits
29+200 - 32+200 Gneiss and schist Gneiss/schist
32+200 - 37+200 Loose conglomerate and
quartzite and marble/
schist
Gneiss/schist
Source: Pipalbhanjyang-Hayutar-Netrakali Road (DPR 2017)
4.1.2 Land Use Pattern
65. The project road traverses from Pipalbhanjyang to Netrakali through the settlement
area, forest, barren land, cultivated land etc. Detail is given in the Table 9 below.
Table 9: Land Use along the Road Alignment
Chainage Land Use Pattern
0+000-0+400 Forest
0+400-0+600 Cultivated land and settlements
0+600-1+200 Cultivated land/Forest
1+200-1+400 Forest/Cultivated land and settlements
1+400-3+000 Forest / cultivated land and settlements
3+000-3+600 Cultivated land and settlements
3+600-8+600 Cultivated land
8+600-11+200 Forest / cultivated land
11+200-11+800 Cultivated land
11+800-13+700 Cultivated land and settlement
13+700-14+400 Cultivated land
14+400-17+400 Forest/Cultivated land and settlement
17+400-18+400 Cultivated land
18+400-19+800 Forest / cultivated land
19+800-20+900 Cultivated land
20+900-29+000 Forest / cultivated land
29+000-29+300 Cultivated land
29+300-30+600 Forest
30+600-37+200 Cultivated land and settlement
Source: Pipalbhanjyang-Hayutar-Netrakali Road (DPR 2017)
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 22
4.1.3 Climate and Hydrology
66. Climate is dominated by topographical variations. The sub-project has upper-tropical
and sub-tropical climatic condition with average maximum temperature of 32.35°C and
average minimum of 7.8°C. Average annual rainfall in the project area has been recorded to
be approximately 2,114 mm in the year 2015 (District Climate and Energy Plan, 2017). This
may not be truly representative of the project area because of the location and elevation
difference.
67. The road alignment gently climbs down from Pipalbhanjyang and passes just below
the ridge area and river valley. The road crosses Chhisapani Khola, Dhanman Khola, Taru
Khola, Landi Khola, Simle Khola, Baseri Khola, Lipe Khola, Marin Khola, Rin Khola, Tamajor
Khola etc. Culvert has been recommended in Simle Khola and Causeways have been
recommended for other these major streams based on the condition of the khola. No
wetlands are found within the vicinity of the road
4.1.4 Landslide and Erosion Prone Area
68. During field visit, few minor slides / erosions were observed. The location requires
special consideration during construction period. Gabion walls and toe walls have been
proposed in the design as noted essential during the site visit. Also, bioengineering works
has been proposed in other locations where landslides have occurred though small in scale.
In many locations, where erosion has been witnessed, gabion breast walls have been
proposed. Detail is given in the Table 10 below.
Table 10: Location of Landslides and Bio-Engineering Works
S. No Chainage Length (m) Slope Height (m) Quantity (m2)
From To
1 3+990 4+300 310.00 15.00 4,650.00
2 6+630 6+790 160.00 12.00 1,920.00
3 6+870 6+900 30.00 10.00 300.00
4 7+040 7+115 75.00 10.00 750.00
5 9+980 10+025 45.00 15.00 675.00
6 10+310 10+320 10.00 15.00 150.00
7 11+940 11+980 40.00 10.00 400.00
8 12+000 12+080 80.00 15.00 1,200.00
9 12+285 12+520 235.00 15.00 3,525.00
10 12+565 12+580 15.00 10.00 150.00
11 19+870 19+890 20.00 10.00 200.00
12 30+750 30+780 30.00 10.00 300.00
13 30+970 31+000 30.00 11.00 330.00
Total 1080.00 158.00 14,550.00
Source: Field Survey, 2017
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 23
4.1.5 Air, Noise and Water Quality
Ambient Air Quality
69. This road alignment passed through less traffic influence area; therefore air quality
observed is normal.
Noise
70. The proposed area does not have any sources of noise nuisance.
Water Quality
71. There is no defecation problem observed near and around the drinking water
sources. However, during the monsoon season the quality of water may be polluted due to
the accumulation of silt.
4.2. Biological Environment
72. The project area does not include any sensitive sites such as national parks, buffer
zones etc. Land use includes arable land, forests, and built-up area. The elevation of the
proposed road ranges from 527 m to 1154 m, which falls under the upper tropical and sub-
tropical climatic zone (Dobremez, 1976).
4.2.1 Vegetation Type
73. The major forest type found in the project area is tropical mixed broad-leaf forest
dominated by Shorea and Schima species. Major trees include Shorea robusta (Sal),
Schima wallichii (Chilaune), Pinus roxburghii (Khote Salla), Alnus nepalensis (Utis), Litsea
polyantha (Kutmiro), Toona ciliata (Tuni) etc. Similarly Berberis aristata (Chutro), Paris
polyphylla (Satuwa), Rubia majith (Majitho) etc. are NTFP reported in the forests along road
alignment.
74. The plant species recorded along the road alignment are listed in Table 11 below.
Table 11: Plant species falling under Right-of-Way and Formation-of-Width of Road
S.N. Local Name Scientific Name
1 Aanp Mangifera indica
2 Amala Emblica officinalis
4 Amba Psidium guava
5 Angeri Lyonia ovalifolia
6 Aru Prunus persica
8 Bakaino Melia azedarach
9 Banjh Quercus lanata
11 Barro Terminalia bellerica
13 Berulo Ficus clavata
14 Bhakkamilo Rhus javanica
15 Bhalayo Semecarpus anacardium
16 Chilaune Schima wallichii
19 Dabdabe Garuga pinnata
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 24
S.N. Local Name Scientific Name
20 Chutro Berberis aristata
21 Katus Castanopsis indica
22 Dudhilo Ficus nemoralis
24 Satuwa Paris polyphylla
27 Harro Terminalia chebula
29 Jhigane Eurya cerasifolia
30 Majhitho Rubia majith
31 Khanayo Ficus semicordata
32 Khasre Quercus semecarpifolia
34 Kimbu Morus alba
35 Koiralo Bauhinia variegate
37 Kutmiro Litsea polyantha
38 Malato Macaranga pustulata
40 Nimaro Ficus roxburghii
41 Okhar Juglans regia
42 Khote Salla Pinus roxburghii
43 Pipal Ficus religiosa
44 Saj Terminalia alata
45 Sal Shorea robusta
46 Sami Ficus benjamina
47 Setikath Myrsine capitellata
48 Sisau Dalbergia sisoo
50 Tuni Toona ciliate
51 Utis Alnus nepalensis
Source: Field Survey; August, 2017
Forest Type
75. The road passes through private forest and national forest (leasehold forest,
government managed forest, and community forest). There are six leasehold forests, three
community forests, namely Kalika Community Forest, Jhalkane Community Forest, and
Ranibas Community Forest and government managed forest. Detail is given in Table 12.
76. Kalika Community Forest: This community forest was handed over to the CFUG in
2047 B.S, and includes 192 households that avail resources from it. The forest user groups
are from wards number 1, 4, 8, and of then Bhadrakali VDC. Among the households in the
CFUG, 50% are Tamang, 25% are Newar, 15% belong to the Dalit community, and the
remaining 10% incorporate Brahmin and Chhetri families. Major tree species include Schima
wallichii (Chilaune), Shorea robusta (Sal), Katus (Castanopsis indica), Toona ciliata (Tuni),
Myrsine semiserrata (Kalikath), Eurya cerasifolia (Jhigane), Bombax ceiba (Simal) etc.
Wildlife in the area incorporates Macaca mulatta (Rato Badar), Hystrix indica (Dumsi),
Martes flavigula (Malsapro) etc. Major avian species include Lophura leucomelanos (Kalij),
Streptopelia sp. (Dhukur) and Terpsiphone paradise (Lampuchhre). Reptilian species found
in the area are species of snakes such as Trimeresurus septentrionalis (Hareu), Ptyas
mucosa (Dhaman), Python molurus (Ajingar) etc.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 25
77. Jhalkane Community Forest: This forest was handed over to the CFUGs in 2053
B.S and it has an area of 425 ha. The CFUG comprise of 160-165 households, with majority
of the ethnic composition being that of the Tamang population. Rest includes Brahmin,
Chhetri, and Dalit families. The user groups are from then VDCs of Amale-2, 3, 4 and
Bhadrakali-5. There are only a few user groups from then VDC of Amale-4. Major tree
species include Schima wallichii (Chilaune), Shorea robusta (Sal), Katus (Castanopsis
indica), Toona ciliata (Tuni), Eurya cerasifolia (Jhigane), Bombax ceiba (Simal) etc. Wildlife
in the area incorporates Macaca mulatta (Rato Badar), Hystrix indica (Dumsi), Martes
flavigula (Malsapro) etc. Major avian species include Lophura leucomelanos (Kalij),
Streptopelia sp. (Dhukur) and Terpsiphone paradise (Lampuchhre). Reptilian species found
in the area are species of snakes, such as Trimeresurus septentrionalis (Hareu), Ptyas
mucosa (Dhaman), Python molurus (Ajingar) etc.
78. Ranibas Community Forest: This community forest was handed over to the CFUG
in 2059 B.S, with all households hailing from Ranibas, Ghyanglekh-2. Major tree species
include Schima wallichii (Chilaune), Shorea robusta (Sal), Eurya cerasifolia (Jhigane) and
Myrsine semiserrata (Kalikath) etc. Wildlife in the area incorporates (Rato Badar), Hystrix
indica (Dumsi), Martes flavigula (Malsapro) etc. Major avian species include Lophura
leucomelanos (Kalij) and Terpsiphone paradise (Lampuchhre). Reptilian species found in the
area are species of snakes such as Trimeresurus septentrionalis (Hareu), Ptyas mucosa
(Dhaman) etc.
79. Leasehold Forest: 6 Leasehold Forest have been found along the road alignment.
Among them 4 leasehold forest (ie. Laliguras, Lalupate, Pragatisil, Hariyali) lies in
Ghyanglekh-1(then Amale-6) and rest 2 [(Manebhanjyang (a) & Manebhanjyang (b)] lies
Ghyanglekh-2 (then Bastipur-8 VDC).
Table 12: Forests along Road
Name of Forest Chainage Length
(m)
Total Area
(ha)
Main Species
From To
Kalika CF 0+000 0+460 1470 0.918 Schima wallichii (Chilaune),
Shorea robusta (Sal), Katus
(Castanopsis indica) 0+790 1+800
Jhalkane CF 10+250 11+000 750 0.468 Schima wallichii (Chilaune),
Shorea robusta (Sal), Katus
(Castanopsis indica)
Ranibas CF 14+760 17+000 2380 1.487 Schima wallichii (Chilaune),
Shorea robusta (Sal), Katus
(Castanopsis indica) 18+900 19+040
Total(a) 4600 2.875
Hariyali LHF 19+040 19+270 230 0.143
Schima wallichii (Chilaune),
Shorea robusta (Sal), Katus
(Castanopsis indica)
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 26
Name of Forest Chainage Length
(m)
Total Area
(ha)
Main Species
From To
Pragatisil LHF 19+270 19+340 70 0.043
Schima wallichii (Chilaune),
Shorea robusta (Sal), Katus
(Castanopsis indica)
Lalupate LHF 19+340 19+400 60 0.037
Schima wallichii (Chilaune),
Shorea robusta (Sal), Katus
(Castanopsis indica)
Laliguras LHF 19+400 19+460 60 0.037
Schima wallichii (Chilaune),
Shorea robusta (Sal), Katus
(Castanopsis indica)
Mane
bhanjyang LHF
21+580 21+940 360 0.225
Schima wallichii (Chilaune),
Shorea robusta (Sal), Katus
(Castanopsis indica)
Total (b) 780 0.487
Government
Managed Forest
27+180 29+000 1820 1.137 Schima wallichii (Chilaune),
Shorea robusta (Sal), Katus
(Castanopsis indica) 29+300 30+600 1300 0.812
Total (c ) 3120 1.950
Grand Total (a+b+c) 8500 5.312
Source: Field survey, 2017
4.2.2 Wildlife
80. The forests located along the road alignment are mostly CF, LHF and NF and area is
a habitat for wildlife (mammals, birds and reptiles). Some wild animals are occasionally
observed nearby the forests traversed by road alignment
Mammal
81. The main wildlife species reported in project area Panthera pardus (Chituwa), Canis
aureus (Syal), Hystrix indica (Dumsi), Ursus sp. (Bhalu), Macaca mulatta (Rato Badar),
Martes flavigula (Malsapro), Herpestes auropunctatus (Nyauri Musa), Ratufa bicolor
(Lokharke), Vulpus Montana (Fyauro) etc.
Avifauna
82. The bird reported as well as recorded in the project area are Lophura leucomelanos
(Kalij), Hirundo daurica (Gauthali), Gallus gallus (Luiche), Chalcophaps indica (Dhukur),
Eudynamys scolopacea (Koili), Columba livia (Parewa) Psittacula sp. (Suga), Centropus
sinensis (Kokale), Terpsiphone paradise (Lampuchhre), Corvus splendens (Kaag), Milvus
migrans (Chil), Passer domesticus (Sparrow) etc.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 27
Reptile
83. The reptiles reported in the project area are Ophiophagus harna (Ghurbe Sarpa),
Lycodon aulicus (Siris Sarpa), Ptyas mucosa (Dhaman), Nerodia sipedon (Pani Sarpa),
Varanus bengalensis (Gohoro), Rana Tigerina (Bhyaggutto) etc.
4.2.3 Fish
84. The fish reported in the streams of the project area are Schizothorax richardsonii
(Asala), Tortor hamilton (Katle), Garra annandalei (Buduna), Psilorhynchus pseudechenis
(Tite) etc.
4.2.4 Protected Flora and Fauna in Sub-project area
85. The protected Flora along the road is Saal (Shorea robusta) and fauna found in the
forest along road corridor area given in Table 13.
Table 13: Protected Flora and Fauna Recorded in Project Area
SN Local Name Scientific Name Remarks
IUCN 2008 CITES Code GoN
1 Monkey Macaca mulatta LC Appendix II3
2 Syal Canis aureus LC Appendix III4
3 Dumsi Hystrix indica LC
4 Kalij Lophura leucomelanos LC
5 Chitwa Panthera pardus NT Appendix I5
6 Bhalu Ursus sp. Appendix I
7 Malsapro Martes Flavigula LC
8 Dhukur Streptopelia sp. LC
10 Kalij Lophura leucomelanos LC
11 Lampuchhre Terpsiphone paradise LC
12 Luiche Gallus gallus LC
13 Parewa Columba livia LC
14 Suga Psittacula sp. LC
15 Chil Milvus migrans Appendix II
16 Sal Shorea robusta Banned for
felling,
transporatation
and export for
commercial
purpose
Note: NT= Near Threatened, LC = Least Concern Source: Field survey, 2017
3Species not yet threatened, but which could become endangered if trade is not controlled
4 Species that are protected by individual countries within their borders, and for which co-operation of other convention signatories is sought. 5 Species threatened with extinction.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 28
4.3. Socio-economic and Cultural Environment
86. The socio-economic level of the proposed project is presented at district level,
Municipality/Rural Municipality level and settlement level of the people living close to the
project premises. The socio-economic information at the three levels is envisaged to give a
fair knowledge of the directly impacted people in relation to the district, Municipality/Rural
Municipality.
4.3.1 District Context
87. The project road is located in Sindhuli district so it is termed as Project Affected
District. It is located in Province no. 3 of Nepal. The socio-economic information of this
district is presented in the following sub-sections.
Household and Population
88. The total population of Sindhuli district is 296,192 with male population (47.98%)
slightly lower than female population (52.02%) at the ratio of 1:1.24. The total household of
the district is 57,544 with average household size 5.14. Detail is given in Table 14 below.
Similarly, 12,355 households were absentee households with 91.60 % of male population
absent amongst, please refer Table 15.
Table 14: Demographic Characteristic of Sindhuli District
S.N Description No. %
1 Total Population 296,192
2 Total Male Population 142,123 47.98
3 Total Female Population 154,069 52.02
4 Male Female Ratio 1:1.24
5 Total Nos. of Household 57,544
6 Average Household Size 5.14
Source: Population and Housing Census, 2011, CBS
Table 15: Absentee populatio
S.N Households/population No. Percent
1 Absentee Households 12,355
2 Absentee Male Population 14,003 91.60
3 Absentee Female Population 1,284 8.40
Source: Population and Housing Census, 2011, CBS
Population by Age Group
89. The age group range between 15-44 years is the dominating number (41.96%)
among the age groups. Younger age group (0-14) year represents 39.18% of the total
population, which shows the distinguished representation of younger age group, indicating
the increasing trend of population. The economic active population i.e. age group (15 to 59)
represents 52.86% of the total population. Detail is given in Figure 3 below.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 29
Source: Population and Housing Census, 2011, CBS
Figure 3: Population of Sindhuli District by Different Age Group
Religion
90. Hindu (64.47%), Buddhism (30.43%) and Prakriti (3.29%) are the major religion
followed by the population of Sindhuli district. Detail is given in Table 16 below.
Table 16: Religion Followed by People of Sindhuli District
S.N. Religion Male Female Total
No. % No. % No. %
1 Hindu 91954 31.05 98,998 33.42 190,952 64.47
2 Buddhism 42893 14.48 47,243 15.95 90,136 30.43
3 Christianity 1358 0.46 1,539 0.52 2,897 0.98
4 Islam 113 0.04 66 0.02 179 0.06
5 Kirat 484 0.16 540 0.18 1,024 0.35
6 Prakriti 4584 1.55 5,152 1.74 9,736 3.29
7 Other 737 0.25 531 0.18 1,268 0.43
Total 142,123 47.98 154,069 52.02 296,192 100.00
Source: Population and Housing Census, 2011, CBS
Caste/Ethnic Composition
91. In Sindhuli district, Tamang (26.87%) is the predominant caste among the population
followed by Magar (14.90%), Chhetri (13.66%), Brahmin-Hill (7.79%), Newar (6.28%),
Danuwar (5.82%), Kami (4.58%), Sarki (3.55%), Majhi (3.47%), Damai/Dholi (3.09%), and
Others (9.99%). Detail is given in Table 17 below.
Table 17: Caste and Ethnicity in the Sindhuli District
S.N. Caste/Ethnic
Group
Male Female Total
No. % No. % No. %
1 Tamang 37936 12.81 41654 14.06 79590 26.87
2 Magar 21327 7.20 22819 7.70 44146 14.90
Up to 4 years 5-14 years 15-44 years 45-59 years60 years and
above
Male 15803 42783 55638 16322 11577
Female 15124 42330 68630 15963 12022
Total 30,927 85,113 124,268 32,285 23,599
0
20000
40000
60000
80000
100000
120000
140000
Male
Female
Total
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 30
S.N. Caste/Ethnic
Group
Male Female Total
No. % No. % No. %
3 Chhetree 19409 6.55 21050 7.11 40459 13.66
4 Brahmin-Hill 11035 3.73 12042 4.07 23077 7.79
5 Newar 8990 3.04 9612 3.25 18602 6.28
6 Danuwar 7951 2.68 9285 3.13 17236 5.82
7 Kami 6504 2.20 7047 2.38 13551 4.58
8 Sarki 5063 1.71 5456 1.84 10519 3.55
9 Majhi 4910 1.66 5369 1.81 10279 3.47
10 Damai/Dholi 4358 1.47 4797 1.62 9155 3.09
11 Other 14640 4.94 14938 5.04 29578 9.99
Total 142123 47.98 154069 52.02 296192 100.00
Source: Population and Housing Census, 2011, CBS
Mother Tongue
92. Majority of the population (48.18%) of Sindhuli district speaks national language
Nepali. Other languages of the district are Tamang (26.02%), Magar (10.84%), Danuwar
(5.72%), Newari (2.35%), etc, refer Table 18.
Table 18: Languages Spoken in Sindhuli District
S.N
.
Mother Tongue Male Female Total
No. % No. % No. %
1 Nepali 68542 23.14 74170 25.04 142712 48.18
2 Tamang 36670 12.38 40393 13.64 77063 26.02
3 Magar 15398 5.20 16702 5.64 32100 10.84
4 Danuwar 7818 2.64 9123 3.08 16941 5.72
5 Newari 3418 1.15 3543 1.20 6961 2.35
6 Maithili 2647 0.89 2240 0.76 4887 1.65
7 Majhi 2351 0.79 2489 0.84 4840 1.63
8 Sunuwar 2248 0.76 2465 0.83 4713 1.59
9 Rai 808 0.27 796 0.27 1604 0.54
12 Other 2223 0.75 2148 0.73 4371 1.48
Total 142123 47.98 154069 52.02 296192 100.00
Source: Population and Housing Census, 2011, CBS
Literacy
93. Majority of the population (60.53%) can read and write which indicate good literacy in
this district. However, the illiterate population (that can’t read and write) is also notable
(36.26%) with female number (23.47%) significantly higher than male number (12.79%).
Detail is given in Figure 4 below.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 31
Source: Population and Housing Census, 2011, CBS
Figure 4: Literacy Status of Sindhuli District
Education Status
94. Among the population attending various level of education, majority (66.45%) have
obtained only basic level of education. The population with secondary education level is
remarkable low with 21.64%. Likewise, the lower number of population (1.47 %) has
obtained education of graduate and post graduate levels. Detail is given in Table 19 below.
Table 19: Educational Status in Sindhuli District
S.N Description Population that have completed the educational
level of
Male Female Total
No % No % No %
1 Beginner 4315 2.61 3755 2.27 8,070 4.88
2 Basic level (Upto 8) 59,384 35.91 50,520 30.55 109,904 66.45
3 Secondary Level (Upto 12) 20,791 12.57 15,007 9.07 35,798 21.64
4 Graduate and above 1810 1.09 627 0.38 2,437 1.47
5 Others 4421 2.67 4,759 2.88 9,180 5.55
Total 90,721 54.85 74,668 45.15 16,5389 100.00
Source: Population and Housing Census, 2011, CBS
Drinking Water
95. Majority of households (58.08%) depend on Tap/Piped water for drinking water
supply, followed by uncovered Well/Kuwa (24.24%), Tubewell/Hand Pump (6.40%) etc.
Detail is given in Table 20 below.
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
160,000
180,000
Can read andwrite
Can read only Can't read andwrite
Literacy notstated
88,173
4148
33,918
81
72,385
4196
62,258
106
160,558
8344
96,176
187
Male
Female
Total
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 32
Table 20: Status of Drinking Water in Sindhuli District
S.N Description No. %
1 Tap/Piped 33,424 58.08
2 Spout water 2144 3.73
3 Uncovered well/Kuwa 13,946 24.24
4 Covered Well/Kuwa 1535 2.67
5 River/Stream 2,418 4.20
6 Tubewell/Hand pump 3,681 6.40
7 Other 396 0.69
Total 57,544 100.00
Source: Population and Housing Census, 2011, CBS
Sanitation
96. A huge portion of Households (66.45%) in Sindhuli district do not have toilet and only
33.15% of the total households have toilet. This clearly shows that open defecation can be
one of the major sanitation issues of the district. Detail is given in Table 21 below.
Table 21: Status of Toilet Facilities in Sindhuli District
S.N Description No. %
1 With-toilet 19,075 33.15
2 Without toilet 38,237 66.45
3 Not stated 232 0.40
Total 57,544 100.00
Source: Population and Housing Census, 2011, CBS
97. Among the households having toilet facility, majority of households (67.21%) have
flush toilet with septic tank and 32.79% of household have ordinary toilets. Detail is given in
Table 22 below.
Table 22: Types of Toilets in Sindhuli District
S.N Description No. %
1 Flush toilet (Septic Tank) 12,820 67.21
2 Ordinary 6,255 32.79
Total 19,075 100.00
Source: Population and Housing Census, 2011, CBS
Energy Used for Lighting
98. Electricity is one of the major sources of energy (37.87%) for lighting purpose in
Sindhuli district. While Solar (26.85%) and Kerosene (22.26%) are also some other major
sources of lighting. Detail is given in Figure 5 below.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 33
Source: Population and Housing Census, 2011, CBS
Figure 5: Status of Energy Used for Lighting in Sindhuli District
Energy Used for Cooking
99. Majority of households (90.96%) use firewood for cooking by collecting them from
community and other forest. 5.00% using LP gas and 2.76% households use bio-gas for
cooking purpose. Detail is given in Table 23 below.
Table 23: Status of Energy Used for Cooking in Sindhuli District
S.N Description No. %
1 Wood/firewood 52,342 90.96
2 LP Gas 2,877 5.00
3 Bio-gas 1,588 2.76
4 Kerosene 275 0.48
5 Electricity 12 0.02
6 Cow dung 156 0.27
7 Other 294 0.51
Total 57,544 100.00
Source: Population and Housing Census, 2011, CBS
House Ownership
100. Majority of households (94.31%) has their own house to live in. Moreover, some
households (4.89%) live in rented house too. Detail is given in Table 24 below.
21,791, 37.87%
12,810, 22.26%
15,449, 26.85%
92, 0.16% 7,402, 12.86%
Electricity
Kerosene
Solar
Bio-gas
Other
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 34
Table 24: Ownership of House in Sindhuli District
S.N Description No. %
1 Owned 54,269 94.31
2 Rented 2,815 4.89
3 Institutional 100 0.17
4 Others 360 0.63
Total 57,544 100.00
Source: Population and Housing Census, 2011, CBS
House Type
a. House with Foundation Type
101. Most of the households comprise foundation of houses constructed with wooden
Pillar (57.89%). While significant numbers of household are constructed with mud bonded
bricks/stone (36.14%). Some households (2.12%) comprises of foundation of houses
constructed using RCC with Pillar. There are 3.13% of households built with cement bonded
bricks/stones. Detail is given in Table 25 below.
Table 25: Type of Foundation of House in Sindhuli District
S.N Description No. %
1 Mud bonded bricks/stone 20,798 36.14
2 RCC with pillar 1,222 2.12
3 Cement bonded bricks/stone 1,804 3.13
4 Wooden pillar 33,310 57.89
5 others 67 0.12
6 Not stated 343 0.60
Total 57,544 100.00
Source: Population and Housing Census, 2011, CBS
b. House with Outer Wall Type
102. In Sindhuli district, significant households (51.21%) have constructed their outer wall
of Mud bonded bricks/stone. Significant households (21.53%) are constructed with bamboo
on their outer wall and 16.81% of the houses with the wood/planks as their outer wall.
Houses built with cement bonded bricks/stone are also significant in number (8.84%). Detail
is given in Table 26 below.
Table 26: Type of Outer Wall of House in Sindhuli District
S.N Description No. %
1 Mud bonded bricks/stone 29,469 51.21
2 Cement bonded bricks/stone 5,087 8.84
3 Wood/Planks 9,671 16.81
4 Bamboo 12,389 21.53
5 Unbaked brick 55 0.10
6 Others 494 0.86
7 Not stated 379 0.66
Total 57,544 100.00
Source: Population and Housing Census, 2011, CBS
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 35
c. House with Roof Type
103. Majority of households (53.38%) has constructed their roof of house with Tile/slate
followed by Thatch/straw (32.94%) and Galvanized iron (9.76%). Few households (2.53%)
have RCC roof. Detail is given in Table 27 below.
Table 27: Type of Roof of House in Sindhuli District
S.N Description No. %
1 Galvanized iron 5,614 9.76
2 Tile/slate 30,719 53.38
3 Thatch/Straw 18,955 32.94
4 RCC 1,455 2.53
5 Wood/Planks 197 0.34
6 Mud 16 0.03
7 Others 150 0.26
8 Not stated 438 0.76
Total 57,544 100.00
Source: Population and Housing Census, 2011, CBS
Facilities to Accessories
104. Majority of households in this district possess at least one facility (72.20%). However
significant population (25.19%) possesses no facilities. Detail is given in Table 28 below.
Table 28: Status of Households regarding Facilities to Accessories in Sindhuli District
S.N Description No. %
1 Without Facility 14,493 25.19
2 At least one facility 41,548 72.20
3 Not stated 1,503 2.61
Total 57,544 100.00
Source: Population and Housing Census, 2011, CBS
105. The common facilities possessed by the households consist of Radio (53.76%),
Mobile phone (45.19%), and Television (18.20%). Detail is given in Table 29 below.
Table 29: Various Facilities Possessed by Households in Sindhuli District
S.N Facilities Type No. of HH % of Total HH
1 Radio 30,933 53.76
2 Telivision 10,472 18.20
3 Cable Telivision 5,163 8.97
4 Computer 9,42 1.64
5 Internet 236 0.41
6 Telephone 2,921 5.08
7 Mobile Phone 26,007 45.19
8 Motor 166 0.29
9 Motorcycle 1,180 2.05
10 Cycle 2,143 3.72
11 Other Vehicle 96 0.17
12 Refrigerator 640 1.11
Source: Population and Housing Census, 2011, CBS
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 36
4.3.2 Indirect Impact Area
General Information of the Indirectly Affected Areas
106. Kamalamai Municipality and Ghyanglekh Rural Municipality fall under the project
affected area, which includes not all, but some then VDCs within it that face direct impact
due to project implementation. The demographic, ethnic, and educational parameters of the
Municipality and RM are discussed below.
Population
107. The respective population of Kamalamai Municipality and Ghyanglekh Rural
Municipality is 64,386 and 13,761. The male to female population ratio in each area is
0.898:1 and 0.888:1 respectively. The average household size in Kamalamai Municipality is
4.50, while Ghyanglekh RM has an average household size of 5.60. Detail is given in Table
30 below.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 37
Table 30: General Population Scenario of the Indirectly Affected Areas
S.
N.
Municipality/ Rural
Municipality
Then Municipality
/ then VDCs
No. of
Household
Average
Household
Size
Population
Male Female Total
No. % No. % No. %
1 Kamalamai
Municipality
Kamalamai 9304 4.24 18788 47.67 20625 52.33 39413 100.00
2 Dadiguranse 973 4.94 2262 47.09 2542 52.91 4804 100.00
3 Bhadrakali 848 5.21 2074 46.98 2341 53.02 4415 100.00
4 Jalkanya 395 4.57 822 45.51 984 54.49 1806 100.00
5 Ranichuri 1685 5.27 4189 47.17 4692 52.83 8881 100.00
6 Ranibas 1110 4.56 2327 45.92 2740 54.08 5067 100.00
Sub Total (A) 14315 4.50 30462 47.31 33924 52.69 64386 100.00
1 Ghyanglekh Rural
Municipality
Amale 415 5.45 1047 2.66 1214 3.08 2261 5.74
2 Bastipur 545 5.56 1366 45.10 1663 54.90 3029 100.00
3 Tamajor 445 5.27 1102 24.96 1244 28.18 2346 53.14
4 Netrakali 606 5.61 1612 47.41 1788 52.59 3400 100.00
5 Shanteshwori 446 6.11 1344 49.32 1381 50.68 2725 100.00
Sub Total (B) 2457 5.60 6471 47.02 7290 52.98 13761 100.00
Grand Total (A+B) 16772 4.66 36933 47.26 41214 52.74 78147 100.00
Source: Population and Housing Census, 2011, CBS & GoN, 2017
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 38
Caste/Ethnicity and Religion
108. In the two projects affected areas, Tamang (31.05%) was the dominant caste group,
followed by Chhetree (16.89%), Magar (10.68%), and Newar (9.51%). Other minor castes
made up 15.91% of the total population of these two areas. Detail is given in Table 31
below. Siilarly, the Hinduism and Budhism are major religion in IIA.
Table 31: Ethnic Composition of the Indirectly Impact Areas
S.N
.
Mu
nic
ipality
/
Ru
ral
Mu
nic
ipality
Th
en
VD
Cs/
Mu
nic
ipality
Households Population with Caste/Ethnic Group
To
tal
Ch
hetr
ee
Bra
hm
in
Kam
i
Mag
ar
New
ar
Sark
i
Tam
an
g
Oth
er
1 Kamalamai
Municipality
Kamalamai 9,320 4,343 1,677 3,712 4,941 1,622 7,598 6,200 39,413
2 Dadiguranse 422 526 343 411 110 120 1,503 1,369 4,804
3 Bhadrakali 371 231 212 843 516 59 1878 305 4,415
4 Jalkanya 303 649 72 70 152 112 0 448 1,806
5 Ranichuri 1,330 158 372 1,923 837 394 2,960 907 8,881
6 Ranibas 1,040 570 359 414 77 112 155 2,340 5,067
Sub Total (A) 12,786 6,477 3,035 7,373 6,633 2,419 14,094 11,569 64,386
% 19.86 10.06 4.71 11.45 10.30 3.76 21.89 17.97 100.00
1 Ghyanglekh
Rural
Municipality
Amale 82 39 122 0 0 0 1,921 97 2,261
2 Bastipur 286 0 77 343 0 0 1,726 597 3,029
3 Tamajor 30 0 114 33 177 0 1,937 55 2,346
4 Netrakali 17 31 0 0 336 20 2,931 65 3,400
5 Shanteshwori 0 0 141 595 280 0 1,659 50 2,725
Sub Total (B) 415 70 454 971 793 20 10,174 864 13,761
% 3.02 0.51 3.30 7.06 5.76 0.15 73.93 6.28 100.00
Grand Total (A+B) 13201 6,547 3,489 8,344 7,426 2,439 24,268 12,433 78,147
% 16.89 8.38 4.46 10.68 9.50 3.12 31.05 15.91 100.00
Source: Population and Housing Census, 2011, CBS & GoN, 2017
Literacy
109. Among the population of the two areas that is over the age of 5, 65.16% have the
ability to read and write. 2.58% of the population can only read, whereas 32.23% are
illiterate. A paltry 0.03% of the entire population did not state their literacy status. Detail is
given in Table 32 below.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 39
Table 32: Literacy Status of the Indirectly Affected Areas
S.
N
Municipality
/ Rural
Municipality
Merging
VDCs
Population Above 5 years Total
Can
read
and
write
Can
read
only
Can't
read and
write
Literacy
not
stated
1 Kamalamai
Municipality
Kamalamai 26,679 672 8,740 7 36098
2 Dadiguranse 2,642 139 1,572 0 4353
3 Bhadrakali 2,651 20 1,377 0 4048
4 Jalkanya 1,114 17 497 2 1630
5 Ranichuri 4,445 189 3,327 6 7967
6 Ranibas 2,642 123 1,797 1 4563
Sub Total (A) 40173 1,160 17,310 16 58659
% 68.49 1.98 29.51 0.03 100.00
1 Ghyanglekh
Rural
Municipality
Amale 1,219 159 626 0 2004
2 Bastipur 1,532 58 1,109 0 2699
3 Tamajor 1,073 157 804 0 2034
4 Netrakali 1,174 148 1,653 1 2976
5 Shanteshwori 955 143 1,315 2 2415
Sub Total (B) 5,953 665 5,507 3 12128
% 49.08 5.48 45.41 0.02 100.00
Grand Total (A+B) 46,126 1,825 22,817 19 70787
% 65.16 2.58 32.23 0.03 100.00
Source: Population and Housing Census, 2011, CBS & GoN, 2017
4.3.3 Direct Impact Area
110. The project road is aligned along ward no. 2 of Kamalamai municipality (then
Bhadrakali VDC) and ward no. 1, 2, 3 & 4 Ghyanglekh Rural Municipality (then Amale,
Bastipur, Tamajor, Netrakali VDCs) which are fall under the direct impact area of the project.
The demographic, ethnic, and educational parameters of these affected wards are discussed
below.
Population
111. The total population of the affected areas is 15,451, with 2,859 households and an
average household size of 5.40. The male to female population ratio is 0.873:1. Detail is
given in Table 33 below.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 40
Table 33: General Population Scenario of the Project Affected Area
S.N Municipality/
RM
Former
VDC
No. of
HH
Average
HH Size
Population
Male Female Total
No. % No. % No. %
1 Kamalamai-2 Bhadrakali 848 5.21 2,074 46.98 2,341 53.02 4,415 100.00
2 Ghyanglekh-1 Amale 415 5.45 1,047 46.31 1,214 53.69 2,261 100.00
3 Ghyanglekh-2 Bastipur 545 5.56 1,366 45.10 1,663 54.90 3,029 100.00
4 Ghyanglekh-3 Tamajor 445 5.27 1,102 46.97 1,244 53.03 2,346 100.00
5 Ghyanglekh-4 Netrakali 606 5.61 1,612 47.41 1,788 52.59 3,400 100.00
Total 2,859 5.40 7,201 46.61 8,250 53.39 15,451 100.00
Source: Population and Housing Census, 2011, CBS & GoN, 2017
Population by Age Group
112. The active working group between 15 and 59 years of age make up 49.90%of the
population in the affected wards. 10.94% and 8.34% of the population is up to 4 years old
and above 60 years old respectively. People between the ages of 5 and 14, which mainly
incorporates school going children, make up 30.83% of the affected population. Detail is
given in Table 34 below.
Table 34: General Population Scenario of the Project Affected Areas (Age Group)
S.N Municipality
/RM
Former
VDC
Age Group Total
Up to 4
years
5-14
years
15-44
years
45-59
years
60 years
and
above
1 Kamalamai-2 Bhadrakali 367 1,301 1,789 530 428 4,415
2 Ghyanglekh-1 Amale 257 712 817 276 199 2,261
3 Ghyanglekh-2 Bastipur 330 938 1,160 372 229 3,029
4 Ghyanglekh-3 Tamajor 312 713 878 247 196 2,346
5 Ghyanglekh-4 Netrakali 424 1,099 1,290 350 237 3,400
Total 1,690 4,763 5,934 1,775 1,289 15,451
% 10.94 30.82 38.41 11.49 8.34 100.00
Source: Population and Housing Census, 2011, CBS & GoN, 2017
Caste/Ethnic Composition
113. In the project affected areas, Tamang (67.26%) was the dominant caste group,
followed by Magar (7.89%), Newar (6.66%), and Chhetree (5.09%). Other minor castes
made up 7.24% of the total population of the affected areas. Detail is given in Figure 6
below.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 41
Source: Population and Housing Census, 2011, CBS & GoN, 2017
Figure 6: Ethnic Composition of the Indirectly Affected Areas
Mother Tongue
114. 66.96% of the total affected population has Tamang as their mother tongue, followed
by Nepali (17.6%), and Magar (6.00%). 9.28% of people speak other minor languages.
Detail is given in Table 35 below.
Table 35: Major Languages Spoken in the Project Affected Areas
S.N Municipality
/RM
Former
VDC
Household with Mother Tongue Total
Nepali Maithili Tamang Magar Other
1 Kamalamai-2 Bhadrakali 1,793 0 1,836 563 223 4,415
2 Ghyanglekh-1 Amale 270 0 1,918 0 73 2,261
3 Ghyanglekh-2 Bastipur 419 0 1,724 331 555 3,029
4 Ghyanglekh-3 Tamajor 161 0 1,937 33 215 2,346
5 Ghyanglekh-4 Netrakali 101 0 2,931 0 368 3,400
Total 2,744 0 10,346 927 1,434 15,451
% 17.76 0.00 66.96 6.00 9.28 100.00
Source: Population and Housing Census, 2011, CBS & GoN, 2017
Drinking Water
115. 85.59% of households rely on tap/pipe water. 12.35% of households avail water from
uncovered wells. The remaining households use covered wells, spouts, rivers, tube-wells
etc. Detail is given in Table 36 below.
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Other
Tamang
Sarki
Newar
Magar
Kami
Brahmin
Chhetree
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 42
Table 36: Drinking Water Sources in Project Affected Areas
S.N Municipality/
RM
Former
VDC
Households Utilizing Drinking Water Sources Total
Tap/
Piped
Spout
Water
Uncovered
well /Kuwa
Covered
well
/Kuwa
River/
Stream
Tube
well
Other
1 Kamalamai-2 Bhadrakali 733 0 100 1 12 2 0 848
2 Ghyanglekh-1 Amale 328 0 65 0 19 0 3 415
3 Ghyanglekh-2 Bastipur 379 0 149 0 13 0 4 545
4 Ghyanglekh-3 Tamajor 427 1 15 1 1 0 0 445
5 Ghyanglekh-4 Netrakali 580 0 24 0 0 0 2 606
Total 2,447 1 353 2 45 2 9 2,859
% 85.59 0.03 12.35 0.08 1.57 0.07 0.31 100
Source: Population and Housing Census, 2011, CBS & GoN, 2017
Fuel Source for Cooking
116. Firewood is the main fuel source (97.97%) for cooking, followed by bio-gas (0.92%),
kerosene (0.45%), and LPG (0.28%). 0.38% of households use other sources for cooking
food. Detail is given in Table 37 below.
Table 37: Fuel Source for Cooking in Project Affected Areas
S.N Municipality
/RM
Former
VDC
Households Utilizing Cooking Fuel Total
Wood/
Firewood
Bio
Gas
LP
Gas
Kerosene Electricity Other
1 Kamalamai-2 Bhadrakali 811 26 8 3 0 0 848
2 Ghyanglekh-1 Amale 411 0 0 0 0 4 415
3 Ghyanglekh-2 Bastipur 539 0 0 1 0 5 545
4 Ghyanglekh-3 Tamajor 444 0 0 1 0 0 445
5 Ghyanglekh-4 Netrakali 596 0 0 8 0 2 606
Total 2801 26 8 13 0 11 2859
% 97.97 0.92 0.28 0.45 0.00 0.38 100.00
Source: Population and Housing Census, 2011, CBS & GoN, 2017
Energy Source for Lighting
117. 35.29% of affected households rely on kerosene to fulfil their lighting needs. 28.40%
of households have access to electricity while 23.22% rely on solar energy to light up their
homes. Detail is given in Table 38 below.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 43
Table 38: Energy Source for Lighting in Project Affected Areas
S.N. Municipality/RM Former VDC Electricity Kerosene Bio gas Solar Other Total
1 Kamalamai-2 Bhadrakali 594 183 3 53 15 848
2 Ghyanglekh-1 Amale 13 126 1 147 128 415
3 Ghyanglekh-2 Bastipur 8 170 1 155 211 545
4 Ghyanglekh-3 Tamajor 66 262 1 110 6 445
5 Ghyanglekh-4 Netrakali 131 268 0 199 8 606
Total 812 1009 6 664 368 2859
% 28.40 35.29 0.22 23.22 12.87 100.00
Source: Population and Housing Census, 2011, CBS & GoN, 2017
Sanitation
118. 86.99% of the affected households do not have access to toilets. Among the
households that do possess latrines, 6.40% have flush toilets, while 6.32% have ordinary
toilets. Detail is given in Table 39 below.
Table 39: Sanitation Status in Project Affected Areas
S.N. Municipality /
RM
Former
VDC
HHs without
Toilet
HHs with Toilet Total
Flush Ordinary Others Total
1 Kamalamai-2 Bhadrakali 599 123 126 0 249 848
2 Ghyanglekh-1 Amale 371 26 15 3 44 415
3 Ghyanglekh-2 Bastipur 511 12 19 3 34 545
4 Ghyanglekh-3 Tamajor 434 6 5 0 11 445
5 Ghyanglekh-4 Netrakali 572 16 16 2 34 606
Total 2,487 183 181 8 372 2,859
% 86.99 6.40 6.32 0.28 13.01 100.00
Source: Population and Housing Census, 2011, CBS & GoN, 2017
Literacy
119. Among the population of the project affected areas that is over the age of 5, 55.58%
have the ability to read and write. 3.94% of the population can only read, whereas 40.47%
are illiterate. A partly 0.01% of the entire population did not state their literacy status. Detail
is given in Table 40 below.
Table 40: Literacy Status in the Indirectly Affected Areas
S.N Municipality
/RM
Former
VDC
Can read
and write
Can read
only
Can't read
and write
Literacy
not stated
Total
1 Kamalamai-2 Bhadrakali 2651 20 1377 0 4048
2 Ghyanglekh-1 Amale 1219 159 626 0 2004
3 Ghyanglekh-2 Bastipur 1532 58 1109 0 2699
4 Ghyanglekh-3 Tamajor 1073 157 804 0 2034
5 Ghyanglekh-4 Netrakali 1174 148 1653 1 2976
Total 7649 542 5569 1 13761
% 55.57 3.94 40.47 0.01 100.00
Source: Population and Housing Census, 2011, CBS & GoN, 2017
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 44
Educational Attainment
120. 48.77% of the affected populations have had primary level education, while 20.63%
have attained lower secondary level education. 8.20% of populations have secondary level
education, 6.32% are SLC graduates, and 2.53% have studied up to intermediate level.
7.26% of people have had some form of non-formal education. Detail is given in Figure 7
below.
Source: Population and Housing Census, 2011, CBS & GoN, 2017
Figure 7: Educational Attainment of People in Project Affected Areas
4.3.3.1 Project Affected Settlements of DIA
121. The major settlements located along the road alignment i.e. project affected
settlements (PAS) are mostly rural, non-uniform and dispersed. Most section of road
completely lack settlements.
122. The major settlements located along the road alignment of PAS(s) in Sindhuli District
are presented in the Table 41 below:
0
500
1000
1500
2000
2500
3000
3500
4000
4500 Beginner
Primary
LowerSecondary
Secondary
SLC & Equiv.
Intermediate &Equivalent
Graduate
PostGraduate
Other
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 45
Table 41: Major Settlement Located in the Proposed road alignment
S.N. Name of Settlement District Name of VDC/Municipality and Ward Number
1 Hayutar Sindhuli Ghyanglekh RM-2
2 Koltar Sindhuli Ghyanglekh RM-3
3 Apdanda Sindhuli Ghyanglekh RM-4
4 Bhotesanghara Sindhuli Kamalamai Municipality-2
5 Khattar Sindhuli Kamalamai Municipality-2
6 Chandanpur Sindhuli Ghyanglekh RM-2
Source: Socioeconomic Field Survey; August, 2017
Household and Population
123. The total households and population of PAS(s) of Sindhuli district is 252 and 1365
respectively. The representations of male and female population are 50.18% male and
49.82% female. The average household size of PAS(s) is 5.42.
Table 42: Household and Population of PAS(s)
S.N Settlement
Name
No. of
HHs
Population Average HH
Size Total Male Female
No. % No. %
1 Hayutar 50 250 150 60.00 100 40.00 5.00
2 Koltar 20 150 70 46.67 80 53.33 7.50
3 Apdanda 12 75 40 53.33 35 46.67 6.25
4 Bhotesanghara 30 130 70 53.85 60 46.15 4.33
5 Khattar 80 400 180 45.00 220 55.00 5.00
6 Chandanpur 60 360 170 47.22 190 52.78 6.00
Total 252 1365 680 49.82 685 50.18 5.42
Source: Socioeconomic Field Survey; August, 2017
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 46
Caste/Ethnicity
124. In PAS(s) of Sindhuli district, the major ethnic/caste groups are Tamang (75.40%), Newar (7.94%) and Brahmin (2.38%).
Please refer Table 43 for detail.
Table 43: Caste and Ethnicity in PAS(s)
S.N Settlement
Name
Major Castes (Household) Total
Ma
ga
r
Bra
hm
in
Ne
wa
r
Tam
an
g
Ch
he
tri
Da
ma
i
Ka
mi
Su
nu
wa
r
Ma
dh
es
i
No. % No. % No. % No. % No. % No. % No. % No. % No. % No. %
1 Hayutar 0 0.00 2 4.00 0 0.00 45 90.00 2 4.00 1 2.00 0 0.00 0 0.00 0 0.00 50 100.00
2 Koltar 0 0.00 0 0.00 4 20.00 13 65.00 0 0.00 0 0.00 0 0.00 3 15.00 0 0.00 20 100.00
3 Apdanda 0 0.00 1 8.33 11 91.67 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 12 100.00
4 Bhotesanghara 0 0.00 3 10.00 5 16.67 16 53.33 3 10.00 0 0.00 2 6.67 0 0.00 1 3.33 30 100.00
5 Khattar 0 0.00 0 0.00 0 0.00 80 100.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 80 100.00
6 Chandanpur 9 15.00 0 0.00 0 0.00 36 60.00 12 20.00 1 1.67 2 3.33 0 0.00 0 0.00 60 100.00
Total 9 3.57 6 2.38 20 7.94 190 75.40 17 6.75 2 0.79 4 1.59 3 1.19 1 0.40 252 100.00
Source: Socioeconomic Field Survey; August, 2017
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 47
Religion
125. In Sindhuli district, majority of households of PAS(s) follow Buddhism (82.14%).
Moreover, the households following Hinduism religion is also significant (14.29%). Few people
(3.57%) follow Christian religion. Detail is given in Table 44 below.
Table 44: Religion Followed in PAS(s)
S.N Settlement
Name
Religion Total
Hindu Buddhist Christian
HH No. % HH No. % HH No. % HH No. %
1 Hayutar 5 10.00 45 90.00 0 0.00 50 100.00
2 Koltar 7 35.00 13 65.00 0 0.00 20 100.00
3 Apdanda 1 8.33 11 91.67 0 0.00 12 100.00
4 Bhotesanghara 11 36.67 16 53.33 3 10.00 30 100.00
5 Khattar 0 0.00 77 96.25 3 3.75 80 100.00
6 Chandanpur 12 20.00 45 75.00 3 5.00 60 100.00
Total 36 14.29 207 82.14 9 3.57 252 100.00
Source: Socioeconomic Field Survey; August, 2017
Migration
126. In Sindhuli district, majority of households (75.79%) of PAS(s) are living since generation
and remaining (16.27%) households are living from last 20-30 years, please refer Table 45.
Table 45: Migration Trend in PAS
S.N Settlement
Name
Living Since Total
Households
A g
en
era
tio
n a
go
20-3
0 y
ea
rs a
go
1-2
0 y
ea
rs a
go
Fam
ilie
s w
ho
hav
e
em
igra
ted
in
th
e
pas
t fe
w y
ea
rs
HH
No.
% HH
No.
% HH
No.
% HH
No.
% HH
No.
%
1 Hayutar 50 100.00 0 0.00 0 0.00 0 0.00 50 100.00
2 Koltar 20 100.00 0 0.00 0 0.00 0 0.00 20 100.00
3 Apdanda 12 100.00 0 0.00 0 0.00 0 0.00 12 100.00
4 Bhotesanghara 0 0.00 30 100.00 0 0.00 0 0.00 30 100.00
5 Khattar 69 86.25 6 7.50 4 5.00 1 1.25 80 100.00
6 Chandanpur 40 66.67 5 8.33 15 25.00 0 0.00 60 100.00
Total 191 75.79 41 16.27 19 7.54 1 0.40 252 100.00
Source: Socioeconomic Field Survey; August, 2017
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 48
Occupation
127. The major occupation of PAS(s) in Sindhuli district is agriculture (38.90%). However, majority of (36.70%) of them are also
student. The other occupations are wage labor (10.04%), foreign employment (7.33%), service (4.25%), and business (2.78%),
please refer Table 46
Table 46: Occupation in Project Affected Settlement
S.N Settlement
Name
Occupation Total
Population Agriculture Business Service Wage Labor Foreign
Employment
Student
No. % No. % No. % No. % No. % No. % No. %
1 Hayutar 80 32.00 10 4.00 10 4.00 25 10.00 25 10.00 100 40.00 250 100.00
2 Koltar 75 50.00 4 2.67 3 2.00 10 6.67 8 5.33 50 33.33 150 100.00
3 Apdanda 53 70.67 0 0.00 0 0.00 0 0.00 2 2.67 20 26.67 75 100.00
4 Bhotesanghara 45 34.62 12 9.23 13 10.00 26 20.00 5 3.85 29 22.31 130 100.00
5 Khattar 140 35.00 5 1.25 15 3.75 40 10.00 50 12.50 150 37.50 400 100.00
6 Chandanpur 138 38.33 7 1.94 17 4.72 36 10.00 10 2.78 152 42.22 360 100.00
Total 531 38.90 38 2.78 58 4.25 137 10.04 100 7.33 501 36.70 1365 100.00
Source: Socioeconomic Field Survey; August, 2017
Note: Infant (Age 0 to 5 years) are not considered for occupation
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 49
Livelihood
128. In Sindhuli district, majority of households (80.95%) in PAS(s) have sufficient earning
without surplus to fulfill their livelihood. While, few households (11.90%) have sufficient earning
with surplus. There are also few households (7.14%) which do not have sufficient earning to
fulfill their livelihood, refer Table 47.
Table 47: Livelihood Status in PAS
S.N. Settlement Name Earnings Total Households
Sufficient
with
surplus
Sufficient
without
surplus
Inadequate
to meet
livelihood
No. % No. % No. % No. %
1 Hayutar 4 8.00 36 72.00 10 20.00 50 100.00
2 Koltar 7 35.00 10 50.00 3 15.00 20 100.00
3 Apdanda 0 0.00 10 83.33 2 16.67 12 100.00
4 Bhotesanghara 0 0.00 30 100.00 0 0.00 30 100.00
5 Khattar 12 15.00 68 85.00 0 0.00 80 100.00
6 Chandanpur 7 11.67 50 83.33 3 5.00 60 100.00
Total 30 11.90 204 80.95 18 7.14 252 100.00
Source: Socioeconomic Field Survey; August, 2017
Housing Structure Types
129. Majority of the affected households (98.02%) have temporary structures while 1.98% of
households have permanent housing structures, refer Table 48.
Table 48: Housing Structure Type in PAS
S.N. Settlement Name Structure Type Total
Permanent Temporary
HH No. % HH No. % HH No. %
1 Hayutar 4 8.00 46 92.00 50 100.00
2 Koltar 0 0.00 20 100.00 20 100.00
3 Apdanda 0 0.00 12 100.00 12 100.00
4 Bhotesanghara 1 3.33 29 96.67 30 100.00
5 Khattar 0 0.00 80 100.00 80 100.00
6 Chandanpur 0 0.00 60 100.00 60 100.00
Total 5 1.98 247 98.02 252 100.00
Source: Socioeconomic Field Survey; August, 2017
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 50
Health
130. In Sindhuli district, people of PAS(s) visit health post located in their then VDC for general health treatment. However, in
major health treatment, they visit the district hospital as well as clinic of Sindhuli district. Majority of them walk for 50-1000 meters to
reach the health institutions, please refer Table 49.
Table 49: Available Health Service in PAS
S.N
.
Se
ttle
me
nt
Na
me
Na
me
of
Ne
are
st
He
alt
h
Insti
tuti
on
Lo
cati
on
Dis
tan
ce
or
Du
rati
on
No
. o
f S
taff
Me
mb
ers
Av
ail
ab
le
Se
rvic
es
Inco
min
g
Pa
tie
nts
per
day
Ma
jor
Dis
ea
se
s/
Illn
es
se
s
1 Hayutar Bastipur Ilaka Health Post Ghyanglekh-2 50 m 5 Primary Level
Treatment
30 Cough, cold, dysentery
2 Koltar - - - - - - Fever, cough, cold,
dysentery, pneumonia
3 Apdanda - - - - - - Fever, diarrhoea,
pneumonia, cough, cold
4 Bhotesanghara Bhotesanghara Health Post Bhotesanghara 500 m 4 Primary Level
Treatment
Fever, diarrhoea,
pneumonia, cough, cold
Bhotesanghara Medical Bhotesanghara 1 km 2 Primary Level
Treatment
Fever, cough, cold,
dysentery, pneumonia
5 Khattar - - - - - - Fever, diarrhoea,
pneumonia, cough, cold
6 Chandanpur - - - - - - Fever, diarrhoea,
pneumonia, cough, cold
Source: Socioeconomic Field Survey; August, 2017
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 51
131. In Sindhuli district, the major diseases reported are fever, common cold, dysentery,
pneumonia, and cough, please refer Table 50.
Table 50: Major Disease found in PAS
S.N. Settlement Name Major Diseases/ Illnesses
1 Hayutar Cough, cold, dysentery
2 Koltar Fever, cough, cold, dysentery, pneumonia
3 Apdanda Fever, diarrhoea, pneumonia, cough, cold
4 Bhotesanghara Fever, diarrhoea, pneumonia, cough, cold
5 Khattar Fever, diarrhoea, pneumonia, cough, cold
6 Chandanpur Fever, cough, cold, dysentery, pneumonia
Source: Socioeconomic Field Survey; August, 2017
Solid Waste Management Techniques
132. All the households in the PAS(s) practice composting to the organic waste generated
from their day to day activities. All of the inorganic wastes are burned or done open
dumping, refer Table 51.
Table 51: Solid Waste Management Techniques
S.N
Sett
lem
en
t N
am
e
Solid Waste Management Techniques
Organic Waste Inorganic Waste
Co
mp
osti
ng
Oth
er
To
tal
Incin
era
tio
n
Op
en
Du
mp
ing
Mu
nic
ipal
Co
llecti
on
To
tal
HH
No.
% HH
No.
% HH
No.
% HH
No.
% HH
No.
% HH
No.
% HH
No.
%
1 Hayutar 46 92.00 4 8.00 50 100 20 40.00 30 60.00 0 0.00 50 100.00
2 Koltar 18 90.00 2 10.00 20 100 19 95.00 1 5.00 0 0.00 20 100.00
3 Apdanda 11 91.67 1 8.33 12 100 11 91.67 1 8.33 0 0.00 12 100.00
4 Bhotesanghara 27 90.00 3 10.00 30 100 27 90.00 3 10.00 0 0.00 30 100.00
5 Khattar 64 80.00 16 20.00 80 100 20 25.00 60 75.00 0 0.00 80 100.00
6 Chandanpur 57 95.00 3 5.00 60 100 16 26.67 44 73.33 0 0.00 60 100.00
Total 223 88.49 29 11.51 252 100 113 44.84 139 55.16 0 0.00 252 100.00
Source: Socioeconomic Field Survey; August, 2017
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 52
Education
133. In Sindhuli district, the educational standing in PAS(s) comprises of illiterate (40.4%),
primary (36.97%), Secondary (19.30%) and graduate and above (3.60%), refer Table 52.
Table 52: Educational Status in PAS
S.N Settlement
Name
No. of Education Level Total
Illite
rate
Pri
mary
Level
Seco
nd
a
ry L
evel
Gra
du
ate
an
d
hig
her
No. % No. % No. % No. % No. % ale and
Female
1 Hayutar Males 20 18.2 50 45.45 35 31.82 5 4.55 110 100 230
Females 20 16.7 60 50.00 40 33.33 0 0.00 120 100
2 Koltar Males 3 5.4 50 89.29 3 5.36 0 0.00 56 100 102
Females 4 8.7 40 86.96 2 4.35 0 0.00 46 100
3 Apdanda Males 4 12.5 18 56.25 10 31.25 0 0.00 32 100 70
Females 3 7.9 16 42.11 15 39.47 4 10.53 38 100
4 Bhotesanghara Males 20 33.3 20 33.33 20 33.33 0 0.00 60 100 122
Females 30 48.4 17 27.42 15 24.19 0 0.00 62 100
5 Khattar Males 100 54.1 50 27.03 20 10.81 15 8.11 185 100 359
Females 100 57.5 40 22.99 21 12.07 13 7.47 174 100
6 Chandanpur
Males 99 55.3 48 26.82 27 15.08 5 2.79 179 100 310
Females 79 60.3 32 24.43 19 14.50 1 0.76 131 100
Total 482 40.4 441 36.97 227 19.03 43 3.60 1193 100 1193
Source: Socioeconomic Field Survey; August, 2017
Note: Infant (Age 0 to 5 years) are not considered for educational status
134. In Sindhuli district, the available educational institutions of PAS(s) are from primary
Level to higher secondary level. Students need to walk from 10 to 30 minutes to reach their
school, please refer Table 53.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 53
Table 53: Availability and Access to Educational Institutions in PAS(s)
S.N Settlement
Name
Name of School Level Type Student
No.
Distance or
Duration to
get to
school
Address
1 Hayutar Shree Secondary
School
Seconda
ry
Governmental 580 10 minutes Ghyanglekh-2
Shree Nawadip
Academy
Primary Private 80 10 minutes Ghyanglekh-2
2 Koltar Koltar Primary
School
Primary Governmental 125 20 minutes Koltar
3 Apdanda - - - - - -
4 Bhotesanghara Nibuatar Higher
Secondary
School
Seconda
ry
Governmental 300 15 minutes Nibuatar-9
5 Khattar Shree
Bambeshwari
Lower Secondary
School
Primary Governmental 150 20 minutes Khattar
6 Chandanpur - - - - - -
Source: Socioeconomic Field Survey; August, 2017
Drinking Water
135. In PAS(s) of Sindhuli district, Pipe water supply (81.75%) is the main source of
drinking water. However, majority of households (17.06%) also rely on river water for the
purpose of drinking water, please refer Table 54.
Table 54: Status of Drinking Water in PAS
S.
N
Settlement
Name
HH Consumption of Water Done Through Total
Communal
Tap
River
Water
Well/
Spring
Pipeline
HH
No.
% HH
No.
% HH
No.
% HH
No.
% HH
No.
%
1 Hayutar 0 0.00 0 0.00 0 0.00 50 100.00 50 100.00
2 Koltar 0 0.00 0 0.00 0 0.00 20 100.00 20 100.00
3 Apdanda 0 0.00 0 0.00 0 0.00 12 100.00 12 100.00
4 Bhotesanghara 0 0.00 28 93.33 0 0.00 2 6.67 30 100.00
5 Khattar 0 0.00 7 8.75 1 1.25 72 90.00 80 100.00
6 Chandanpur 0 0.00 8 13.33 2 3.33 50 83.33 60 100.00
Total 0 0.00 43 17.06 3 1.19 206 81.75 252 100.00
Source: Socioeconomic Field Survey; August, 2017
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 54
Energy Used for Cooking
136. In Sindhuli district, majority of households of PAS(s) use firewood (76.59%) for
cooking purpose. Households using LPG for cooking purpose is also significant (23.41%),
refer Table 55.
Table 55: Status of Energy Used for Cooking in PAS
S.N. Settlement
Name
Fuel for cooking (HH Using) Total
Wood LPG
HH No. % HH No. % HH No. %
1 Hayutar 30 60.00 20 40.00 50 100.00
2 Koltar 18 90.00 2 10.00 20 100.00
3 Apdanda 9 75.00 3 25.00 12 100.00
4 Bhotesanghara 1 3.33 29 96.67 30 100.00
5 Khattar 78 97.50 2 2.50 80 100.00
6 Chandanpur 57 95.00 3 5.00 60 100.00
Total 193 76.59 59 23.41 252 100.00
Source: Socioeconomic Field Survey; August, 2017
Energy Used for Lighting
137. In Sindhuli district, most of the households (67.86%) of PAS(s) use Electricity for the
lighting purpose while 32.14% use solar, refer Table 56.
Table 56: Status of Energy Used for Lighting in PAS
S.N Settlement Name HH Using Total
Kerosene Electricity Solar
HH No. % HH No. % HH No. % HH No. %
1 Hayutar 0 0.00 50 100.00 0 0.00 50 100.00
2 Koltar 0 0.00 19 95.00 1 5.00 20 100.00
3 Apdanda 0 0.00 12 100.00 0 0.00 12 100.00
4 Bhotesanghara 0 0.00 30 100.00 0 0.00 30 100.00
5 Khattar 0 0.00 0 0.00 80 100.00 80 100.00
6 Chandanpur 0 0.00 60 100.00 0 0.00 60 100.00
Total 0 0.00 171 67.86 81 32.14 252 100.00
Source: Socioeconomic Field Survey; August, 2017
Toilets
138. In Sindhuli district, almost all households of PAS(s) possess toilet outside their
houses (99.60%) except one in Bhotesanghar, refer Table 57.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 55
Table 57: Status of Sanitation Condition in PAS
S.
N
Settlement
Name
Toilets Total
No
Toilet
No. of Houses with Toilet
Inside the
house
Outside the
house
Pit Latrine
HH
No.
% HH
No.
% HH
No.
% HH No. %
1 Hayutar 0 0 0.00 50 100.00 0 0.00 50 100.00
2 Koltar 0 0 0.00 20 100.00 0 0.00 20 100.00
3 Apdanda 0 0 0.00 12 100.00 0 0.00 12 100.00
4 Bhotesanghara 0 1 3.33 29 96.67 0 0.00 30 100.00
5 Khattar 0 0 0.00 80 100.00 0 0.00 80 100.00
6 Chandanpur 0 0 0.00 60 100.00 0 0.00 60 100.00
Total 0 1 0.40 251 99.60 0 0.00 252 100.00
Source: Socioeconomic Field Survey; August, 2017
Telecommunication
139. In PAS(s) NTC is the major telecom facility (44.44%) along with Ncell (43.25%), and
smart cell (12.30%), please refer Table 58.
Table 58: Status of Telecommunication Facility in PAS
S.N. Settlement Name Telecommunications
NTC Ncell Smart Cell Total
HH No. % HH No. % HH No. % HH No. %
1 Hayutar 45 90.00 0 0.00 5 10.00 50 100.00
2 Koltar 10 50.00 0 0.00 10 50.00 20 100.00
3 Apdanda 1 8.33 0 0.00 11 91.67 12 100.00
4 Bhotesanghara 0 0.00 29 96.67 1 3.33 30 100.00
5 Khattar 40 50.00 40 50.00 0 0.00 80 100.00
6 Chandanpur 16 26.67 40 66.67 4 6.67 60 100.00
Total 112 44.44 109 43.25 31 12.30 252 100.00
Source: Socioeconomic Field Survey; August, 2017
Economic Activities
Market
140. There are various markets in PAS(s) of Sindhuli district. They are temporary and
permanent in type. Most of the small markets are 5 to 30 kilometers from the settlement
center, please refer Table 59.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 56
Table 59: Major Market in PAS
S.
N
.
Settlement
Name
Number of
Bazaars
Name Type of
Bazaar
Distance or Duration
from Settlement Centre
1 Hayutar 1 Hayutar Permanent
2 Koltar 2 Madi Bazar Permanent 38 km
Koldap Temporary 15 minutes
3 Apdanda 1 Simle Bazar Permanent 5 km
4 Bhotesanghara 2 Madi Bazar Temporary 15 km
Bhotesanghara Temporary 15 minutes
5 Khattar 2 Khattar Temporary 5 minutes
Madi Bazar Permanent 45 km
6 Chandanpur 1 Chandanpur Temporary 10 minutes
Source: Socioeconomic Field Survey; August, 2017
Industry
141. In PAS(s) of Sindhuli district, there are no industries.
Refreshment and shops
142. There are 8 hotel and lodges, 18 teashops and 26 ration stores in PAS(s) of Sindhuli
district. Other shops include 2 stationeries and 1 clothing store, please refer Table 60.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 57
Table 60: Status of Refreshment and Shops Facility in PAS
S.N Settlement Name Amenities
Ho
tels
an
d
Lo
dg
es
Resta
ura
nts
Tea S
ho
ps
Rati
on
Sto
re
Sta
tio
nery
Co
sm
eti
cs
Ph
arm
acy
Clo
thin
g
Sto
re
Hard
ware
Meat
Sh
op
s
Tailo
r
To
tal
No. % No. % No. % No. % No. % No. % No. % No. % No. % No. % No. % No. %
1 Hayutar 1 7.69 0 0.00 4 30.77 7 53.85 1 7.69 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 13 100.00
2 Koltar 0 0.00 0 0.00 2 66.67 1 33.33 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 3 100.00
3 Apdanda 0 0.00 0 0.00 3 100.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 3 100.00
4 Bhotesanghara 2 11.76 0 0.00 3 17.65 10 58.82 1 5.88 0 0.00 0 0.00 1 5.88 0 0.00 0 0.00 0 0.00 17 100.00
5 Khattar 4 30.77 0 0.00 4 30.77 5 38.46 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 13 100.00
6 Chandanpur 1 16.67 0 0.00 2 33.33 3 50.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 6 100.00
Total 8 14.55 0 0.00 18 32.73 26 47.27 2 3.64 0 0.00 0 0.00 1 1.82 0 0.00 0 0.00 0 0.00 55 100.00
Source: Socioeconomic Field Survey; August, 2017
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 58
Financial Institutions
143. There is 1 bank, 5 microfinances and 4 co-operatives in the PAS(s) of Sindhuli
district, please refer Table 61.
Table 61: Status of Financial Institutions in PAS
S.N. Settlement Name Financial Institutions
Banks Micro-finance Co-operative Total
No. % No. % No. % No. %
1 Hayutar 0 0.00 1 100.00 0 0.00 1 100.00
2 Koltar 0 0.00 1 100.00 0 0.00 1 100.00
3 Apdanda 0 0.00 0 0.00 1 100.00 1 100.00
4 Bhotesanghara 1 25.00 1 25.00 2 50.00 4 100.00
5 Khattar 0 0.00 2 66.67 1 33.33 3 100.00
6 Chandanpur 0 0.00 0 0.00 0 0.00 0 0.00
Total 1 10.00 5 50.00 4 40.00 10 100.00
Source: Socioeconomic Field Survey; August, 2017
Land Ownership
144. Majority of the households (88.89%) in PAS(s) owe less than 5 ropanis of land.
9.13% HH have 5-10 ropanis of land, while very few (1.98%) of them are landless, refer
Table 62 for detail.
Table 62: Land Ownership in PAS
S.N Settlement
Name
Land Ownership Total
5-10
Ropanis
Upto 5
Ropanis
No Land
(Sukumbasi)
HH
No.
% HH
No.
% HH
No.
% HH
No.
%
1 Hayutar 1 2.00 49 98.00 0 0.00 50 100.00
2 Koltar 4 20.00 16 80.00 0 0.00 20 100.00
3 Apdanda 5 41.67 7 58.33 0 0.00 12 100.00
4 Bhotesanghara 11 36.67 18 60.00 1 3.33 30 100.00
5 Khattar 0 0.00 77 96.25 3 3.75 80 100.00
6 Chandanpur 2 2.50 57 71.25 1 1.25 60 75.00
Total 23 9.13 224 88.89 5 1.98 252 100.00
Source: Socioeconomic Field Survey; August, 2017
Irrigation
145. Majority of the of the agriculture areas of PAS(s) has been linked to the irrigation
systems. Whole of the irrigation land in Hayutar are linked with the irrigation system while
Bhotesanghara have 95% of the linkage of irrigation system with the agricultural land.90 %
of Chandanpur, 60% of Koltar, 25% of Apdanda, and 60% of Khattar are also linked with the
irrigation system, refer Table 63 for detail.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 59
Table 63: Irrigation Status in PAS
S.
N
Settlement
Name
Irrigation Status
Land with Access to
Irrigation
Land without Access to
Irrigation
% %
1 Hayutar 100 0
2 Koltar 60 40
3 Apdanda 25 75
4 Bhotesanghara 95 5
5 Khattar 60 40
6 Chandanpur 90 10
Source: Socioeconomic Field Survey; August, 2017
Crops
146. Major Crop species in the PAS(s) are paddy, millet and maize. Wheat, Buckwheat
and mustard are also cultivated in Bhotesanghara village, refer Table 64 for detail
Table 64: Major Crops in PAS
S.N. Settlement Name Major Crops
1 Hayutar Paddy, Maize, Mustard, Millet
2 Koltar Paddy, Maize, Millet
3 Apdanda Paddy, Maize, Millet
4 Bhotesanghara Paddy, Maize, Wheat, Mustard, Buckwheat
5 Khattar Paddy, Maize, Millet, Wheat
6 Chandanpur Paddy, Maize, Millet
Source: Socioeconomic Field Survey; August, 2017
Livestock
147. Major livestock in the PAS(s) are cow, goat and buffalo. Chicken and Ox are also
some of the minor livestock of the PAS(s) refer Table 65 for detail
Table 65: Major Livestock in PAS
S.N. Settlement Name Major Livestock
1 Hayutar Cow, Buffalo, Goat
2 Koltar Cow, Ox, Buffalo, Goat, Chicken
3 Apdanda Goat, Buffalo, Ox
4 Bhotesanghara Goat, Buffalo, Cow
5 Khattar Cow, Goat, Buffalo, Chicken
6 Chandanpur Cow, Goat, Buffalo, Chicken
Source: Socioeconomic Field Survey; August, 2017
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 60
Economic Activities
148. Majority of people of PAS(s) of Sindhuli district believe that the proposed road project
will enhance local business, commercial farming and livestock rearing in the district through
the export of local agricultural production and increment of business activities, please refer
Table 66 for detail.
Table 66: Potential Economic activities by Road Upgrading in local level
S.
N
Settlement
Name
Areas of Economic Prosperity
1 Hayutar Industries and mills, businesses.
Large areas of cultivable land; prospect of commercial farming and
livestock rearing.
2 Koltar Commercial farming and animal husbandry.
3 Apdanda Local businesses, livestock rearing.
4 Bhotesanghara Commercial farming, religious sites as potential tourist attractions.
5 Khattar Converting Gumbas into tourist attractions.
6 Chandanpur Local businesses, livestock rearing.
Source: Socioeconomic Field Survey; August, 2017
Sites of Historical, Cultural, Archaeological, Religious and Tourism Importance
149. The various sites of historical, cultural, archaeological, religious and tourism
importance in PAS(s) of Sindhuli district is presented in Table 67.
Table 67: Historical, Cultural, Archaeological, Religious and Tourism Sites
S.N. Settlement Name Temples and Religious Sites
1 Hayutar -
2 Koltar Gumba (Pema Sangling)
3 Apdanda Madisthan, Gupteshwari, Kaling
4 Bhotesanghara Ganeshthan
5 Khattar Riyopotala Gumba, Mane Mandir
6 Chandanpur -
Source: Socioeconomic Field Survey; August, 2017
Social Centers
150. During the road rehabilitation except for the Local School in Sanitar none of the other
social centers were recorded to be affected in the PAS(s), pleaserefer Table 68 for detail
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 61
Table 68: Social Centres
S.
N.
Settlement
Name
No. of
Social
Centers
Name of Social
Centre
Physical
Status
Affected due to Road
Rehabilitation (Y/N)
1 Hayutar 1 Hayutar Ilaka
Health Post
Good N
2 Koltar 0 - - -
3 Apdanda 0 - - -
4 Bhotesanghara 2 Sahakari Building Good N
Vegetables and
Fruits Centre
Good N
5 Khattar 0 - - -
6 Chandanpur 0 - - -
Source: Socioeconomic Field Survey; August, 2017
4.3.4 Project Affected Families
151. This section presents the socio-economic profile of the study area and project
affected households due to the road upgrading works.
Demography
152. A detailed socio-economic survey was conducted to investigate affected households
income, food sufficiency, livelihood options, loss of land, structures, trees and other assets.
Of the total 242 affected households, socio-economic survey was carried for 133 households
consisting of 868 populations. Total 106 Janajati households are affected by sub-project
and, m=among them Tamang are of highest proportion (18.87%). The Table 69 provides
summary of the affected households.
Table 69: Summary of Affected Households by the Sub-project
SN Variable Count
1 Total Affected HHs 242
2 Absentee HHs 109
3 Interviewed HHs 133
4 Interviewed Population 868
4.1 Male 450
4.2 Female 418
4.3 Average HHs Size 6.5
4.4 Dalit HHs 9
4.5 Janjati HHs 106
4.6 Brahmin/Chettri HHs 18
4.7 Women Headed HHs 11
Source: Household Survey, 2016
153. Agriculture is the main occupation of the population residing along the road alignment
but it does not contribute much to their total income and food sufficiency. People in the area
grow mostly paddy, potato, millet, barley, wheat and buckwheat.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 62
154. The average agricultural income of the affected households NRs. 48,433.11 in a year
and that of non – agricultural income is NRs. 234,143.61. Please refer Table 70 for detail.
Table 70: Average Income of APs
Annual
Income
(NRs.)
HHs
(No.)
Average
Annual
Agriculture
Income (NRs.)
HHs
(No.)
Average
Annual Non-
agriculture
Income (NRs.)
HHs
(No.)
Average
Annual
Income
(NRs.)
<=12,000 12 48,433.11 11 234,143.61 1 245,410.56
12,000-
25,000
16 0 1
>25,000 85 123 131
Total 133 133
Source: Household survey, 2016
155. The average food sufficiency month of the APs is 10.18 months per year and the
average land holding of affected households is 0.43 ha, please refer Table 71 for detail.
Table 71: Food Sufficiency of AP
S.N Food Sufficiency Months HHs (No.) Remarks
1 < 3 months 1
2 3-6 months 9
3 6-9 months 21
4 9-12 months 102
5 >12 months 0
Average (months) 10.18
Source: Household survey, 2016
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 63
5. Impacts of Reconstruction Plan Implementation on
Environment
156. The identification and assessment of impacts has been carried out by considering the
proposed proposal activities examined in terms of the construction and operation stage.
Several such impacts have been identified based on site observation, field survey and
information obtained from the stakeholders, with a few being identified on value judgment.
The impact of the activities will be on physical, biological, socio-economic and cultural
resources within the ZoI. Impacts from the proposed road sub project can be both beneficial
as well as adverse. Most of the identified impacts have been quantified as far as possible.
The impacts have been predicted in terms of their magnitude (minor, moderate and high),
extent (site specific, local and regional) and duration (short, medium and long term) and
appropriate benefit enhancement and mitigation measures are given in Chapter 7.
5.1. Beneficial Impacts
5.1.1 Construction Phase
Employment Generation
157. One of the major direct beneficial impacts of the road during the construction stage is
the creation of employment opportunities. The road construction will create of 103,743
unskilled and 31,134 skilled person day’s work. There will be positive impacts in other
economic activities in a chained manner creating other income generating activities. The
impact is direct, high, short-term and local in nature.
Economic Increment of Local People
158. The amount of money that is injected in the rural economy in the form of various
commercial & economic activities will directly enhance the economic increment in the project
area. The local people of the project area will have opportunity to sell their agro products
(such as milk, eggs, meat, vegetables, fruits, etc) on better price to the contractors,
construction workforce as well as the personnel of project office. Besides to meet the daily
demands of the contractors and construction workforce, there are possibilities of opening of
new tea stalls, restaurants, and consumer good shops. The local community can get
maximum benefits of these new commercial and economic activities. This impact is direct,
high, local and short-term in nature
Skill Enhancement
159. The construction of road is likely to enhance their skills in construction, and large
number of people will get practical hands on training. Furthermore, the project will also
organize training on road construction and maintenance that will enhance the technical skills
of local people. The skill and knowledge acquired from the project during construction will
enhance employment opportunities. Such trained manpower can earn livelihoods from
similar project in future. This impact is indirect, low, local and long-term in nature.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 64
5.1.2 Operation Phase
Improved access
160. The construction of Road will offer easy, comfortable and quick access to the people
of the project areas to markets and social services. Travelling time will be reduced and the
cost of transportation will be cheaper than present. This is the direct, high, regional impacts
and will have long-term benefits.
Possible Market Development and Business Promotion
161. New market areas and settlements will develop resulting urbanization and
industrialization of the project area, which will lead to the regional development of the area.
There are increased economic opportunities and significant growth and extension of the
minor local markets along the road. There will be many non-farm employment opportunities
for the growing rural population especially for occupational caste groups due to extension of
market centre and development of small towns. The project will have indirect, long term,
local and high benefits.
Increase in Land Value
162. Upgrading of the road leads to appreciation of land values, particularly near the
market and settlement areas. People from the different village will migrate near the road
because of facilities and commercial purpose which increase the demand of plot land near
the road alignment. Increase in the demand will increase the land value. The impact is
indirect, high, local and long term in nature.
Development of Cottage Industries
163. Majority of the people depend upon agriculture and horticulture. During the time of
the field visit it is observed that there is the practice of cultivating commercial farming like
tomato & cabbage. But because of the lack of the market they have not got sufficient benefit
from their product. After completion of upgrading, their economic standard will also grow due
to increase in the commercial farming of these two products because of enhanced
transportation and market facilities. Similarly, there are also chances to develop forest based
industries such as saw mill industries with facilities of transportation. The project will have
indirect, long term, local and high benefits.
Increase in Crop Productivity
164. Once the road is in operation, people should have cheaper and improved access to
many inputs such as seeds, chemical fertilizer and technology, leading to increased
agricultural production and diversification. The farmers will be more interested to increase
agricultural production due to market accessibility. Similarly, there will be diversification in
occupational pattern of local people, who are till now mainly dependent on subsistence
farming. The transportation cost is expected to come down heavily for many of the inputs
that are used by farmers in farm and other goods. This is the direct, moderate, regional and
will have long term benefits.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 65
Increase in Sale of Local Products
165. The local product like vegetable, fruits, cash crops and livestock products will be
increased in almost all the settlement along the road corridor. Due to market accessibility the
local product also take place in local market in reasonable price which preserve time and
money is the motivational factor to the local people. The increase in the product increases in
the sale. This is the indirect, moderate, local and will have long term benefits.
5.2. Adverse Impacts
5.2.1 Construction Phase
5.2.1.1 Physical Aspects
Change in Land Use
166. The land acquired for the implementation of the project can undergo a long-term
permanent change in the land use. Changes of land use due to the construction of road are
mainly conversion of 1.665 ha of cultivated land & 1.120 ha built-up land, 1.950 ha of
Government Managed Forest area, 2.875 ha of CF, 0.166 ha of private forest area, 0.487 ha
leasehold forest, 0.131 ha of barren land, and 0.050 ha of river/ stream area. Similarly, there
will be some change in land use due to expansion of roadside settlements. The impact from
changes in land use will be high, direct, local and long term in nature.
Hazards due to Spoil Disposal
167. There is the possibility of landslides and erosion from cutting the road during the
upgrading process, particularly during monsoon. The common likely problems from
inappropriate disposal of spoils are: gullying and erosion of spoil tips especially when
combined with unmanaged surface water runoff, damage to farm lands, and destruction of
vegetation, crops and property at downhill. The possible spoil disposal sites have proposed
below (Table 72). The impact from spoil disposal will be direct, moderate, site specific and
long term in nature.
Table 72: Possible Spoil Disposal site
S. No. Chainage Location
1 9+000 Bugdi , Khaltar,Kamalamai-2
2 18+900 Rajbas Hill Side, Ghyanglekh-1
3 29+000 Shola Bhanjyang,Ghyanglekh-3
4 33+400 Near Belbot,Ghyanglekh-4
5 35+950 Aapdanda, Ghyanglekh-4
Slope Instability
168. The construction of road on hill slope and terraces will open the new surface may
create land instability and increase the soil erosion. Similarly, the road cut through the
unstable area may lead to the landslide. The baseline study under this study has identified
the problematic areas from the geological point (Refer Table 10). The stability of slopes
along the road corridor depends upon slope angle, the material constituting the slope, rock
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 66
discontinuities and hydrological conditions. The likely impact of slope instability and soil
erosion is indirect, moderate, site specific and long term in nature.
Disruption of Natural Water Flow due to Drainage and Cross Drainage Works
169. Roads usually generate large volumes of concentrated surface runoff. The
concentrated water from the road outlet causes erosion and landslide eventually affecting
the stability of the road. The impact will be indirect, moderate, site specific and medium term.
Air and Dust Pollution
170. Although the air quality of the project area is not measured, the air does not appear
to be polluted. However, during construction of road, there is a strong possibility of dust
pollution. The dust emission is likely to be intense along the construction site. This may
affect the local people and workers, as well as agricultural crops. Dust may create nuisance
to markets, schools and health posts. Impact on air quality will be direct, low, local and short
term in nature.
Noise Pollution
171. The project area at present does not experience high level of noise. However, use of
bull dozer, excavator and rollers may cause air dust and noise pollution to the workers and
people living in nearby areas. The impact of noise will be direct, low, local and short term in
nature.
Water Pollution
172. The water quality within the project area is not tested. Nevertheless, quality of water
in the water bodies within the project area appears to be fairly good as they are widely used
by households for drinking purpose. The haphazard disposal of various types of waste
generated from construction activities might degrade the water sources. If the proper
sanitary condition is not maintained in the labour camps and work camps, water may be
contaminated resulting in the occurrence of water borne diseases may increase. The impact
will be direct, low, local, short term in nature.
Impact due to Quarrying
173. Construction of the road requires boulders and other types of construction materials.
Potential quarry sites have been identified (refer Table 2 &3). The extraction of materials
from inappropriate places or in excessive amounts can damage the local environment. The
potential adverse impacts of quarrying are accelerated erosion, landslides, disturbance in
natural drainage patterns, water logging and water pollution. Quarry site are proposed at the
chainage 20+410-20+620 and 20+800-21+160. The likely impact from the operation of
quarry sites will be direct, low in magnitude, local nature and short term duration.
Impact due to Camp Sites
174. Domestic wastes (both solid and liquid) will be generated from the construction
camps. The haphazard disposal of such domestic waste in the open land will contaminate
the land, generate foul smell and reduce aesthetic attractiveness of the locality. Moreover,
such haphazard disposal of waste can contaminate water sources. Siting of camp may
cause encroachment of forest, agriculture land, and alteration of drainage and waste water
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 67
problems. Appropriate camp sites have been identified and listed below in Table 73. Impact
will be direct, moderate significance, site specific and for short-term.
Table 73: Proposed Camp site along the road
S. No. Chainage Location
1 3+700 Bhoteswara, Kamalamai -2
2 8+900 Khaltar, Kamalamai -2
3 13+600 Simle Khaltar, Ghyanglekh-1
4 17+200 Rajbas, Ghyanglekh-1
5 22+500 Hayutar, Ghyanglekh-2
6 29+000 Shola Bhanjyang, Ghyanglekh-3
7 31+900 Chaukitar, Ghyanglekh-3
8 34+950 Belbot, Ghyanglekh-4
Source: Field survey, 2017
5.2.1.2 Biological Aspects
Loss or Degradation of Forest and Vegetation
175. 1.950 ha of Government Managed Forest(1.137 upto Solbhanjyang and 0.812
beyound Solbhanjyang) , 0.189 ha community forest, 0.166 ha of private forest area, 0.085
ha leasehold forest will be affected due to this sub-project. 1259 no. of trees from National
forest (47 from community forest, 7 from Leasehold forest & 832 from Government Managed
forest) and 373 no. of trees from private forest and private land will be necessary to be cut
down to clear the formation of the road (Table 74 & Appendix XI). Total forest area loss
from Ch 0+000 to Ch 29+290 is 4.495 ha. Similarly, 0.812 of NF will be lossed from Ch The
impact on vegetation/forest resources have been considered to be direct, High in magnitude,
site specific in extent and short term in duration.
Table 74: Trees to be Cut in Formation Width
S.N. Chainage Type of Land No. of Trees Lost From To
1 0+000
0+790
0+460
1+800
Kalika Community Forest 3
2 10+250 11+000 Jhalkane Community Forest 41
3 14+760
18+900
17+000
19+040
Ranias Community Forest 3
4 21+580 21+940 Manebhanjyang Leasehold Forest 7
5 27+180 29+000 Government Forest (Up to Sola Bhanjyang)
709
29+300 30+600 Government Forest (After Sola Bhanjyang)
123
6 0+190 37+200 Private Forest 107
7 5+060 35+950 Cultivated Land 266
Total 1259
Source: Field survey, 2017
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 68
Pressure in Forest Product
176. Local people and labors might be involved in collecting, using and selling the forest
products particularly the timber and firewood to meet the cooking demand of construction
camp. As the economic activities increases, the number of tea stall, restaurants, and lodges
will also increase to provide the services to the construction workers and project staffs.
These may require additional quantity of fuel wood and timber. Moreover, large and small
sized timber may be needed for establishment of temporary huts such that the construction
workers might utilize the forest nearby the construction site (Kalika CF, Jhalkane CF,
Ranibas CF, Hariyali LHF, Pragatisil LHF, Lalupate LHF, Laliguras LHF, Manebhanjyang
LHF and Government Managed Forest) for such purpose resulting in the loss of natural
forest and vegetation resources. The impact will be indirect, low, local and long term in
nature.
Habitat Fragmentation
177. The forest resources of project area have already been in a degraded state and
disturbed condition due to track way opening, settlement development/expansion and
human intervention. However, the construction of the road may disturb wildlife and bird
species present along the road corridor. The movement of labor, use of construction
equipment, and noise during construction may affect the home range of the fauna. The
impact will be indirect, low, local and long term in nature.
Impacts on Flora and Fauna (as listed in CITES and IUCN Red Data Book and
Protected by GoN)
178. The construction of road may disturb wildlife and bird species present along the road
corridor due to increased noise level. Some protected wild fauna (Table 14) of project are in
IUCN list. Similarly, Sal (Shorea robusta), banned for felling, transportation and export for
commercial purpose, is found in project area. The impact will be indirect, low, local and short
term in nature.
5.2.1.3 Socio-economic Aspects
Loss of Land and Productivity
179. In total 1.665 ha of cultivated land will be affected due to the sub-project. The
average land holding of Aps will decrease from 0.43 ha to 0.41 ha. The food sufficiency of
AP from their own land will decrease from an average 10.18 months to 8.76 months. Total
295 plots of lands will be affected during the road reconstruction and rehabilitation activities.
Moreover, spoil on farm land will also affect the production of agricultural crops. It is clear
that the loss of crops from the land acquired by the project will have adverse impact on the
financial stability of the affected households who are dependent on the agricultural
productivity of their land. The impact is expected to be direct, high in magnitude, local in
extent and of long term in duration.
Impact on Private Properties
180. Eight private residences (4 houses and 4 Goth), belonging to eight households, along
the road corridor will be affected as given in Appendix XII and Table 75 in detail. The
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 69
impact is expected to be direct, high in magnitude, site specific in extent and of long term in
duration.
Table 75: Summary of Affected Private Structure in the Formation Width
Ch
ain
ag
e
Str
uc
ture
Typ
e
Na
me
of
Ow
ner
Lo
cati
on
Sto
rey
Re
ma
rks
(Wa
ll/R
oo
f)
Are
a o
f
Str
uc
ture
( S
q M
)
22+900 House Padam Bahadur Bloar Ghyanglekh -2 2 Mud
Stone/CGI
97.25
23+540 House Krishna Bahadur
Syangtan
Ghyanglekh -2 2 Bamboo/Khar 23.24
24+070 Goth Ek Bahadur Khadka Ghyanglekh -2 1 bamboo/CGI 11
24+830 Goth Jas Karna Magar Ghyanglekh -2 2 bamboo/CGI 30.4
24+870 Goth Bir Bahadur Khadka Ghyanglekh -2 2 Mud
Stone/CGI
20.1
26+440 House Tulku Lama Ghyanglekh -2 2 Stone/Bamboo
/CGI
36.49
31+895 House Bishnu Syangten Ghyanglekh -3 1 Stone/CGI 50.4
31+900 Goth Bishnu Syangten Ghyanglekh -3 2 Bamboo/CGI 19.2
Source: Field survey, 2017
Impact on Community Infrastructure
181. There is only one community tap and around 25 m polythene pipe of water that will
be affected due to this project along the road, refer Table 76. The impact is expected to be
direct, high in magnitude, site specific in extent and of long term in duration.
Table 76: Summary of Affected Community structure in the formation width
Chainage Structure Type Location Dimension
24+080 Tap Ghyanglekh -2 2.1 Sq m
19+200 Water pipe Ghyanglekh -1 25 m.
Source: Field survey, 2017
Impacts on Cultural, Religious and Archeological Sites
182. There is no any Cultural, Religious and Archeological Sites within the formation
width.
Impacts on Occupational Health and Safety
183. During construction phase, the work personnel will be exposed to various health risks
and hazards. The hazards will be notable due to injuries to workers while working in the
Project without adequate safety measures and equipment. Typical health hazards can be
encountered during rock cutting, slope cutting, equipment handling, side casting, slope
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 70
stabilization etc. Other potential impacts to health are respiratory disease and eye disease
due to exposure to dust.
184. Unsafe water sources and unhygienic conditions (lack of latrines and washing
facilities) bear the risk of additional and often endemic diseases, such as dysentery, diarrhea
and cholera. . The impacts are direct, low, short term and local.
Impact on Public Health and Safety
185. For the project construction works, people from various parts of the project affected
municipalities/Rural Municipalities as well as country will temporarily migrate in the project
area. Moreover, other people looking for business opportunity will also migrate in project
area in various settlements of the road. Both work force and migrating people might be
suffering from several communicable diseases such that their disease could be transmitted
to local people arising threat to community health.
186. The sanitation condition of project area is good with entire households of project
affected settlements possess toilets. However, the environmental degradation in and around
the project site can occur due to poor sanitation practice of construction camp. The impacts
are direct, low, short term and local.
5.2.2 Operation Phase
5.2.2.1 Physical Aspects
Road Slope Stability and Management
187. The road follows hilly terrain such that the road construction is executed by making
the cut slopes on hillside. The hill slope along the Road alignment and nearby areas may be
destabilized due to inadequate road cutting, inadequate drainage works, and faulty
construction, re-vegetation of the area and monsoon effect. The destabilization of slope may
also be expedited due to human activities in the road neighborhood such as quarrying
stones or soil and irrigated cultivation. The impact will be direct, moderate, local and long
term in nature.
Impact due to Air, Noise and Water Pollution
188. During operation period, a number of vehicles will carry out along the road and will
produce air pollutants. This will increase the pollution level of ambient air, increase in noise
level due to vehicles and blowing of horns along the road corridor. Washing of vehicles in
natural streams may cause contamination in drinking water sources. The vehicular
movement is not expected to be very high; the overall impact will be direct, low, local and
long term.
5.2.2.2 Biological Aspects
Pressure in Forest Resource
189. Due to easy access, forest areas on the roadside may suffer from human
interference such as trampling; grazing of domestic animals and collection of NTFPs may
hinder natural regeneration and growth of plants. Moreover, there is a possibility of
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 71
smuggling of forest products due to easy access and easy transportation facilities. The
impact will be indirect, moderate, local and long term in nature.
Forest Fire
190. With increase human influence in forest area there is the chances of increase forest
fire intentionally and unknowingly. The impact will be indirect, low, local and long term in
nature.
Disturbance to Wildlife
191. Although the wildlife population is reported low, they may be disturbed due to the
frequent movement of the vehicles. Vehicular flow, horn blowing in the forest area will have
impact on the wildlife and bird species. The impact will be indirect, low, local and long term in
nature.
Illegal Hunting
192. There may occur illegal hunting during operation period by the people from market
areas due to easy accessibility. The impact will be indirect, low, local and long term in
nature.
Impact on Protected Species
193. Some protected fauna and flora are reported (refer section Table 14) in project area.
There will be possibilities of impact on these species due to increase in human influence.
The impact will be indirect, low, local and long term in nature.
5.2.2.3 Socio-economic Aspects
Encroachment of Public Land and Ribbon Settlement Development
194. Ribbon like settlement growth is common along the highway in Nepal. The tendency
of encroaching RoW (right of way) is a common scenario in other roads of Nepal. Such sorts
of tendency cannot be neglected for this road as well. If so, this will not only limit the
possibility for future expansion but also increase possibility encroachment of public land,
forest area and also increase the chances of road accident. In addition, the settlement
growth along the roadside is also likely to increase the volume of household wastes as well
as wastes water on the road. The roadside surface water may turn into wastewater drain.
This may block the drain, which may damage and/or degrade the road condition thereby
demanding high cost for the maintenance and repair. The impact will be direct, moderate,
local and medium term in nature.
Increased Traffic Congestion
195. After the upgrading of road to all weather gravel standard road, there will be increase
in vehicular movements. The local community will lose their working concentration and can
get disturbed by the high vehicular transportation and traffic jam. Moreover, the community
will get disturbed by the air pollution through vehicular emission as well as by noise pollution
due to vehicular movement and blowing of pressure horns. The impact will be direct,
moderate, local and long term in nature.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 72
Road Safety
196. Inadequate provisions of road safety measures like road signals, lack of
enforcement of traffic rules, houses built adjoining road within the RoW etc. may invite road
accident, particularly involving children. The impact will be direct, moderate, local and long
term in nature.
5.3. Climate Change Impacts
197. Climate change is an inevitable fact which needs to be considered for future
planning, construction and maintenance of roads located in hilly and mountainous areas.
The need to limit deterioration effects from adverse weather conditions (e.g. prolonged
precipitation, heat stress, freeze-thaw cycle) and damages consequences in case of extreme
events (e.g. embankment failure) is a key factor influencing construction designs Weather
contribution to the ordinary wear & tear of infrastructure and weather disaster risks are
indeed intrinsic parameters for transport system design. Transport conditions are also highly
affected by extreme weather events such as winter storms, ice, and heavy rainfalls.
198. In general, transport can be vulnerable to many different types of weather conditions,
of which, some of them could be exacerbated with climate change. Many of them relate to
extreme weather conditions (e.g. storms, extreme precipitations, and extreme temperatures)
which on their turn may result in severe consequences for the physical environment (e.g.
Floods, landslides, soil erosion) and represent risks for transport infrastructures and
operations.
199. Based on field survey, the study started with an exhaustive list of potential future
impacts for transport (infrastructures/activities), linked to key weather stressors. All modes
and components of the transport system (infrastructures, transport fleet, transportation
operation and transport users) will, to a certain degree, be affected by extreme weather
events. Some of such extreme weather conditions could be exacerbated under future
climate change, thus increasing risks for transport and negatively affecting transport
performance (safety, reliability, cost efficiency). Only few of the potential consequences
could reveal positive (e.g. higher winter temperatures).Please refer Appendix II for detail.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 73
6. Analysis of Alternatives
200. Alternative analysis has been considered as an integral part of IEE study, which
involves an examination of alternative ways of achieving objectives of the proposed sub-
project. The aim of alternative analysis is to reach at a development option, which maximizes
the benefits while minimizing the adverse impacts. The various alternatives to achieve the
sub-project objectives with minimum environmental degradation are discussed in following
sub-sections:
6.1. No Action Alternative
201. This alternative does not allow for the implementation of the proposal. This
alternative has both beneficial and adverse impacts on the environment. If the proposal is
not implemented, the transportation time and cost for the local people to the district
headquarter and markets and vice versa will continue to remain at present rate and hardship
of people will continue. The no action option will conserve some of the environmental
adverse impacts at the cost of poverty and in accessibility of the people.
6.2. Project Alternatives
202. DLPIU has selected Pipalbhanjyang-Hayutar-Netrakali road sub-project as it provides
access to South-West part of district. It will be upgrade road constructed by EEAP and
through this road it will connect south-west part of Sindhuli to district headquarter and BP
Koirala national highway. Other means of transport like constructing a rope way is not
feasible in the project area and there is no airport in this district.
6.3. Alternative Alignment
203. The existing road alignment was finalized and road was opened from a long time with
vehicular operation. Various factors related to geology, hydrology, topography and other
socioeconomic conditions were considered while selecting the existing route in the past.
Thus, considering environmental impact, survey, design and construction cost, serviceability,
etc, the analysis of alternative route only for upgrading purposes is not relevant at the
current context.
6.4. Alternative Design and Construction Approach
204. There are two types of road design approach-conventional and green road approach.
In conventional method, heavy machineries and equipment, explosives, heavy concrete
structures with the application of bituminous surfacing, side drains, bridges and culverts etc.
are extensively involved. On the other hand, labour based, environment friendly and
participatory (LEP) approach or the green road approach focuses to conserve the delicate
mountain ecology through the protection of vegetation cover as means of soil conservation.
205. The road sub-project is proposed for construction through NCB approach by using
local labour as far as possible and spoil disposal is balanced with cutting and filling as far as
possible. There will be minimum use of excavator, rock breaker, compacter, roller and truck
for road construction. Simple dry stone walls, gabion walls and stone causeways are used to
the maximum extent possible.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 74
6.5. Alternative Schedule and Process
206. The schedule for construction works will be arranged such that the rainy season as
well as agricultural seasons will be avoided. Working during the agricultural off-season would
be most appropriate, as the local people be involved as construction workers. The
construction schedule could also be sensitive to the period of utilization of natural drainages
and waterways during irrigation period.
6.6. Alternative Resources
207. The construction materials to be used for the project are boulder for gabion & dry
walls, coarse aggregates of different sizes and fine aggregates for sub-base, base course
and concreting. These materials will be sourced from nearby streams and local hill slopes. In
addition, the reinforcement bars and cement will be used. There are no cost effective
alternatives for the above materials in road construction work. The pavement construction is
intended to be carried out by conventional method, whereas earthwork, construction of
simple structure such as drains, gabion walls etc will be carried out manually. Alternatives of
the selected material will not be carried out manually.
6.7. No Forest Alternative
208. This is an existing road and proposed for rehabilitation and reconstruction passing
through 3 Community Forest, five Leasehold forest and patches of National forest also. The
6.25 m Formation width of the road is needed, only some land is necessary for upgrading
and vegetation to be clear. The additional forest area to be affected by project is only 0.754
ha. The alignment of road to avoid forest area is expected to affect larger parcel of private
land that increase compensation and resettlement cost. Therefore, no forest alternative has
been considered for this road sub-project and compensatory plantation will be done against
tree loss.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 75
7. Environmental Impact Augmentation, Mitigation and
Minimization Measures
209. Mitigation refers to the measures that are designed to cope with adverse
consequences and to enhance the positive impacts on the environment as a result of the
sub-project implementation. An effective implementation of benefit maximization measures
and adverse impacts mitigation measures would optimize the benefits expected from the
sub-project and avoid/minimize the adverse impact. The impacts that have been identified,
predicted and evaluated in Chapter 5 have following benefit enhancement and mitigation
measures.
7.1. Mitigation Measures during Pre-construction Phase
210. The mitigation measures adopted during design or pre-construction phases are
preventive in nature and have two basic objectives.
a. Avoiding costly mitigation measures, and
b. Increasing awareness amongst the stakeholders for environmental management of road
construction and operation.
7.1.1 Detailed Survey and Design
211. The road design has followed the rural road standards developed by DoLIDAR. The
works will be executed through National Competitive Bidding (NCB) package by the
contractors. Bio-engineering techniques will be applied for stabilization of slopes, which is
sustainable, environmental friendly and can be done by using local resources and
manpower. To improve the transport services for the people living along the road and link
local areas with the main market, acquisition of land would be required.
212. Relevant issues raised during public consultation have been addressed under
respective mitigation measures. Therefore, no separate mitigation measures are warranted
for the concerns raised by the local people.
7.2. Beneficial Impacts Augmentation Measures
7.2.1 Construction Phase
Employment Generation
213. Following benefit augmentation measures will be implemented.
Uplifting the socio-economic condition of the affected people through the life skill training
Economic Increment of local people
214. Following benefit augmentation measures will be implemented.
Awareness raising**6 to local entrepreneurs for promoting linkage with cooperatives and
other financial institutions.
Awareness raising** refers one or two awareness program with budget of 350,000.oo in total and will cover all the topic proposed of awareness as mentioned in mitigation or augmentation activities.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 76
Increase in market demand and opportunity.
Skill Enhancement
215. Following benefit augmentation measures will be implemented:
Providing skill training in construction techniques, small engineering structures (masonry
wall construction, netting wires and construction of gabion wall, slope cutting etc.) and
bio-engineering works.
7.2.2 Operation Phase
Improve Access
216. No benefit augmentation measures are planned for this.
Possible Market Development and Business Promotion
217. No benefit augmentation measures are planned for this.
Increase in Land Value
218. No benefit augmentation measures are planned for this.
Development of Cottage Industries
219. No benefit augmentation measures are planned for this.
Increase in Crop Productivity
220. No benefit augmentation measures are planned for this.
Increase in Sale of Local Products
221. No benefit augmentation measures are planned for this.
7.3. Adverse Impacts Mitigation Measures
7.3.1 Construction Phase
7.3.1.1 Physical Aspects
Change in Land Use
222. There will be no mitigation measures for the permanent loss of agricultural, forest
land. However, following mitigation measures will be adopted to compensate the loss of land
into built up area.
Applying additional protective measures (like bio-engineering, toe-wall) that the
remaining land will not be lost due to erosion.
NRs. 450,000.00 has been allocated for roadside plantation along the COI and to reduce
encroachment
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 77
Hazards due to Spoil Disposal
223. The following mitigation measures will be adopted.
Adopting cut and fill balance.
Wherever possible, surplus spoil will be used to fill eroded gullies, quarries and
depressed areas etc.
Top soil will be stored and utilized in farm land
Remaining excess spoils will be disposed in specified tipping sites in a controlled manner
and the tipping sites will be covered by vegetation through bio-engineering techniques
after surplus material is tipped.
Spoils will not be disposed on fragile slopes, farm land, marshy land, natural drainage
path, canals and other infrastructures.
After the disposal, the site will be provided with proper drainage, vegetation and
adequate protection against erosion.
Necessary toe walls and retaining walls will be provided to protect the disposal of soil.
Preparation spoils disposal management plan and its implementation.
Seeking written permission from concerned CFUG/LHFUG before spoil disposal at forest
area
224. Retaining walls are designed to restrain soil to unnatural slopes. They are used to
bound soils between two different elevations often in areas of terrain possessing undesirable
slopes or in areas where the landscape needs to be shaped severely and engineered for
more specific purposes like hillside farming or roadway overpasses. Adopted guidelines for
retaining structures are as per DOR. In this project, the types of retaining structures are
Gabion retaining wall, stone masonry retaining wall, Stone masonry Breast Wall and Stone
Masonry Revetment Wall.
225. Spoil disposal at the chainage 9+000, 18+900, 21+400, 29+000, 33+400 and 35+950
are proposed for proper disposal of spoils. Suitable materials obtained from excavation will
be used for embankment filling, and backfilling of structures. Despite this, the surplus
excavated materials obtained will be disposed at construction site as required. Wherever
possible, the surplus spoil will be used to fill eroded gullies, quarries and depressed areas.
Slope Instability
226. Retaining wall will be built to protect slopes from landslide and bioengineering will be
adopted for stabilizing them. Following mitigation measures will be adopted during the
construction of the proposed road and the cost has been included in the sub-project cost.
Ensuring minimum cut slope
Selecting cut and fill slope at the correct angle, depending upon the soil type
Re-vegetation of cut and fill slope or exposed areas as soon as possible, by using native
plant species
Adoption of bio-engineering techniques
Ensuring minimum damage of vegetation during construction
No construction work during rainy season
Mass balancing in cut and fill volume
Use of check dams and toe walls before disposing spoils on hill slopes
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 78
Disruption of Natural Water Flow due to Drainage and Cross Drainage Work
227. In order to address this, following mitigation measures will be under taken.
Provide adequate and appropriate numbers of drainage structures in order to have
minimum interference with and impact on natural drainage pattern of the area,
Avoid surface water discharge into farmland or risky locations,
Avoid blockage or diversion of natural channels due to construction of road and disposal
of spoils.
Adopt outward road slope as per green road standard to minimize water accumulation.
Air and Dust Pollution
230. The following mitigation measures will be adopted.
Use of face masks by workers to minimize impact from dust generation, covering of dust
source.
Plantation of tree along the roadside to act as dust barrier
Noise Pollution
231. The following mitigation measures will be adopted.
Use of ear muffles to lessen noise pollution during rock breaking
Restrict horn near school, hospital and settlement
Water Pollution
232. The following mitigation measures will be adopted.
Avoiding the disposal of excavated materials in or near water bodies
Construction of toilets in camp sites.
Impact due to Quarrying
233. The following mitigation measures will be adopted.
Quarry operation plan will be prepared.
Quarry sites should be legally recognized by the government.
After the extraction is completed, the quarry site will be rehabilitated to suit the local
landscape, plantation will be done and drainage will be provided.
Impact due to Camp Sites
234. The mitigation measures will be use of local labors; rent local house instead of camp
to keep labors; sitting camp away from productive lands and forest areas (Table 73); pay
compensation for using private farm or lands for storage or camp. Toilet, water and other
basic facilities will be provided to workers. Waste water and solid waste will be properly
managed. Construction material will be properly stored.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 79
7.3.1.2 Biological Aspects
Loss or Degradation of Forest and Vegetation
235. The following mitigation is proposed to cut the trees from the Kalika CF, Jhalkane
CF, Ranibas CF, Hariyali LHF, Pragatisil LHF, Lalupate LHF, Laliguras LHF,
Manebhanjyang LHF and Government Managed Forest area during the road construction.
Forest clearance approval will be obtained from the DFO and MoFE.
Government procedures such as counting the number of trees to be felled, marking and
measuring wood quantity etc. will be followed.
After approval of tree cutting plan, trees will be felled by LHFUG, CFUG or DFO (for NF)
Forest site clearance for construction will be limited to minimum width of road.
236. According to the working procedure to use national forest area for national
priority projects, 2074 B.S (2017 A.D), the sub-project has to carry out plantation (with
protection for five years) or pay for the plantation and protection cost to the District Forest
Office, refer Table 77 for detail. Total 47 trees need to be cut down from community forest.
So, in total 1,175 seedlings have to be planted for compensatory plantation with estimated
cost of NRs. 177,566.00 as given in Appendix XIa. Total 7 trees need to be cut down from
Leasehold forest. So, in total 175 seedlings have to be planted for compensatory plantation
with estimated cost of NRs. 26,446.00 as given in Appendix XIb. 832 trees need to be cut
down from governemnt manage forest as given in Appendix XIc So, in total 20,800
seedlings have to be planted for compensatory plantation with estimated cost of NRs.
3,143,296.00 and 439 trees need to be cut down from the private forest and private land .
So, plantation of 373 seedlings with compensation of NRs. 11,897.55 will be given. Detail is
given in Appendix XId.
Table 77: Compensatory Plantation against Tree Loss
Name of the Forest No. of Trees Compensatory
Plantation (1:25)
Total Cost
(NRs)
Kalika CF 3 75 11,334.00
Jhalkane CF 41 1,025 154,898.00
Ranibas CF 3 75 11,334.00
Mane Bhanjang LHF 7 175 26,446.00
Government Managed Forest 832 20,800 3,143,296.00
Sub-total (National Forest) 886 22,150 3,347,308.00
Private Forest 107 107 6,735.65
Private Land 266 266 5,161.90
Sub-total (Private), 373 373 11,897.55
Total 1,259 22,523 3,359,205.55
237. This cost will be provided to DFO. In case of CFUGs and Leasehold forest user
groups cost will be provided through DFO. Location and type of species for the plantation will
be selected by the UGs/DFO. However, emphasis will be given to local, multiple use, rare,
endangered and protected species. The forests products from the forest will be used by UGs
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 80
and in case of community forest and leasehold forest. Calculation of per plant plantation cost
in community forest, leasehold forest and government managed forest is goven in Appendix
XIe. For the compensatory plantation in forest, compensatory plantation cost, sample
agreement between DFO/concerned UGs/DLPIU has been attached in Appendix XIf and
plantation plan in Appendix XIg.
Pressure in Forest Product
238. The following mitigation measures will be adopted to reduce the pressure in Kalika
CF, Jhalkane CF, Ranibas CF, Hariyali LHF, Pragatisil LHF, Lalupate LHF, Laliguras LHF,
Manebhanjyang LHF and Government Managed Forest
Use of kerosene instead of firewood for cooking
Restriction in collection of forest product.
Awareness raising** programme (NRs. 350,000.00) for the construction workers before
the implementation of sub-project.
Habitat Fragmentation
239. The following mitigation measures will be adopted.
Construction activities near the Kalika CF, Jhalkane CF, Ranibas CF, Hariyali LHF,
Pragatisil LHF, Lalupate LHF, Laliguras LHF, Manebhanjyang LHF and Government
Managed Forest areas will be done only in day time.
Prohibit to wildlife harassment and poaching by the workers.
Coordination with DFO to control activities like poaching of wild lives by enforcing acts
and regulations strictly.
Awareness raising** programme (NRS 350,000.00) for the construction workers before
the implementation of sub-project.
Impacts on Flora and Fauna (as listed in CITES and IUCN Red Data Book and
Protected by GoN)
240. Following mitigation measures will be adopted.
Workers will be actively prohibited from hunting of birds or animals.
Coordination with DFO to control the activities like illegal hunting and poaching by
enforcing acts and regulations strictly.
Emphasis will be given to plant protected species during compensatory plantation.
7.3.1.3 Socio-economic Aspects
Loss of Land and Productivity
241. Mitigation measures will be as follows.
Minimize productive land acquisition through selection, compensation to affected people
as per the resettlement plan.
Compensation for loss of land equivalent to NRs. 11,552,405.89 will be provided to AP.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 81
Impact on Private Properties
242. The following mitigation measures will be adopted.
Compensation will be provided as per the resettlement plan and IEE report to the
affected person for the displacement of houses.
Compensation equivalent to NRs. 6,061,520.24 will be provided to AP.
Impact on Community Infrastructure
243. Compensation will be provided as per the resettlement plan and IEE report to the
affected community.
Compensation equivalent to NRs. 60,000.00 will be paid.
Impact on Cultural, Religious and Archeological Sites
244. There is no impact on cultural, religious and archeological sites and therefore no
mitigation measures are required.
Occupational Health and Safety
245. The following mitigation measures will be adopted.
The workers will be provided with helmets, masks, muffles and boots depending on the
nature of the construction work.
Drinking water facility and temporary pit latrine will be established to control open
defecation and pollution of water bodies by the workers
First aid box will be kept at work sites.
Group accidental insurance will be done for the workers.
First aid training will be provided to field staff.
Labor camp will have room with proper ventilation and natural light, safe drinkable water,
mosquito net, sanitary facility, and solid waste management.
Kerosene or gas stoves will be supplied to labor camps and use of firewood will be
strictly prohibited.
Impact on Public Healthy safety
246. The following mitigation measures will be adopted.
First aid facility will be provided.
NRs. 350,000.00 is allocted for awareness raising** training on public health and safety.
Provision of information of signboards, cautionary ribbons and barricades.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 82
7.3.2 Operation Phase
7.3.2.1 Physical Aspects
Road Slope Stability and Management
247. The following mitigation measures will be adopted.
Rill and gully formations will be regularly monitored and immediately fixed at critical
areas.
Repair and maintenance of the slope protection measures and drainage works.
Minor landslide and mass wasting will be immediately cleared and slope restored with
appropriate technology (bioengineering).
Impact due to Air, Noise and Water Pollution
248. Following mitigation measures will be adopted.
Community and road user awareness raising** programmes (NRS 350,000.00) will be
organized
Signboards restricting the use of horns will be erected near health posts, schools and
settlements.
Plantation will be done near the settlement around school and health post to act as dust
and noise barrier.
Vehicle washing in natural streams will be discouraged.
7.3.2.2 Biological Aspects
Pressure in Forest Resource
249. The mitigation measures recommended are awareness raising** programmes (NRS
350,000.00) to educate local people and providing support to locals for the conservation of
forests.
Forest Fire
NRs. 350,000.00 allocated for promotion of awareness raising** programmes.
Disturbance to Wildlife
250. Following mitigation measures will be adopted to minimize the above-mentioned
impacts.
Appropriate sign boards will be erected informing drivers
Prohibition of blowing horns in the dense forest areas
Potential areas for wildlife crossing
Maintenance workers will be briefed regularly about the importance of rules and
regulation of DFO in order to make them comply with.
Awareness raising** programmes (NRS 350,000.00) about importance of biodiversity to
the local people, students, and vehicle operators will be conducted to limit the speed and
horn.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 83
Illegal Hunting
251. Following mitigation measures will be adopted to minimize the above-mentioned
impacts.
Strictly implemented rules and regulation to control Illegal Hunting.
Awareness raising** programmes (NRS 350,000.00) about importance of biodiversity to
the local people, student, and Forest user groups.
Impact on Protected Species
252. Following mitigation measures will be adopted to minimize the above-mentioned
impacts.
Awareness raising** programmes (NRS 350,000.00) about importance of biodiversity
and protected species to the local people, students and vehicle operators will be
conducted.
7.3.2.3 Socio-economic Aspects
Encroachment of Public Land and Ribbon Settlement Development
253. The mitigation measures to be adopted include.
Awareness raising** programs (NRS 350,000.00) to regulate settlements
Signboards will be erected notifying about legal prosecution for encroachment within
RoW.
NRs. 450,000.00 is allocated for plantations of trees will be done in the RoW so that it is
not encroached.
Increased Traffic Congestion
254. The mitigation measures adopted will be
Required traffic signs will be used along the road.
Applying appropriate traffic rules.
Road Safety Measures
255. The mitigation measures adopted will be
Applying appropriate road safety measures with the help of 3-Es i.e. Engineering,
Enforcement and Education.
Required safety signs will be used along the road such as schools, wildlife crossing area.
Awareness raising** on road safety will be organized for school student
7.4. Climate Change Impacts
256. Following climate change adaptation measures will be considered during the
construction and operation of the road.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 84
Likely local effects of climate change will be assessed through observation and
regular monitoring of drainage system, erosion etc.
Adequate and timely maintenance and early warning system will be done.
Awareness raising** activities will be conducted about climate change issues and
adaptation and mitigation measures.
Compensatory plantation will be done to reduce the loss of vegetation Necessary to
reduce deforestation and compensatory plantation will be done to cut carbon per capita
emissions
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 85
8. Legal Framework and Regulatory Requirements for the
Project
257. GoN has adopted various policies, acts, rules, regulations and guidelines to ensure
the integration of the development and conservation of environment. The policies and
legislative provisions of Nepal that have a direct relevance to proposed project are given in
Table 78. These laws and policies provisions have been duly followed in the IEE process
and proposed mitigation measures.
Table 78: Review of Relevant Acts, Rules, Regulations and Guidelines
A Constitution
The Constitution of Nepal: It has guaranteed every person the right to live in a clean
environment as a fundamental right. As per the constitution, it is also a matter of State
policy to adopt appropriate measures to abolish or mitigate existing or possible
adverse environmental impacts on the nature, environment or biological diversity.
B Plans and Policies
National Reconstruction and Rehabilitation Policy, 2072 B.S (2016 A.D): It has
identified restoration and improvement of access to service and improve
environmental resilience as one of its strategic recovery objectives.
Forest Policy, 2071 B.S (2015 A.D): Plantation is mandatory for environmental
friendly physical infrastructure development along settlement area, road and irrigation
canal.
Land Acquisition, Resettlement and Rehabilitation Policy, 2071 B.S (2014 A.D):
This policy has been formulated to strengthen socio-economic condition of project
affected families with the provision of necessary land acquisition, justifiable
compensation, appropriate resettlement and rehabilitation for the public welfare and
implementation of infrastructure development projects.
Fourteenth Plan, 2073/74-2075/76 B.S: Aimed for economic growth through infrastructure development, commercialization of agriculture and social development. Regarding the road transportation, it has aimed to rehabilitate and reconstruct the road damaged by earthquake. The concept of greenery on either side of road has been introduced and environmental consideration during construction and maintenance of road is pointed.
ADB Safeguard Policy Statement, 2009 A.D: ADB’s Safeguard Policy Framework
consists of three operational policies on the Environment, Indigenous people and
Involuntary resettlement. It requires that (i) impacts are identified and assessed early
in the project cycle, (ii) plans to avoid, minimize, mitigate or compensate for the
potential adverse impacts are developed and implemented and (iii) affected people
are informed and consulted during project preparation and implementation.
20 Year Road Plan, 2059 –2079 B.S (2002-2022 A.D): With main objectives of
development of Strategic Road Networks (SRN), the implementation strategies
include all weather road connection to the District Headquarters (DHQ) and provision
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 86
of road linkages from the DHQ to the adjacent road network of the neighboring
districts and countries
Policy Document, Environmental Assessment in the Road Sector of Nepal, 2056
B.S (2000 A.D): It proposes to adopt measures to improve the way of life of the
affected people and safeguard natural surroundings. In case damage is inevitable
environmental assessment should find ways of reducing or compensating for such
damage. It suggested five types of environmental assessment activities like
Screening, IEE, EIA and Monitoring.
National Biodiversity Strategy and Action Plan, 2014-2020 FY: It is prepared to
provide guiding framework for the management of Nepal’s biodiversity. It has focused
on national needs of biodiversity management and conservation, fulfillment of the
international obligations, sustainable use of its components and equitable sharing of
benefits accrued from conservation and utilization of genetic resources. It has a long
term (i.e. 35 years) vision, and includes specific short term (up to 2020) strategies and
priorities for action.
C Acts
Act Relating to Reconstruction of the Earthquake Affected Structures 2072 B.S
(2015 A.D): This act provides for the creation of the NRA for a period of five years
(which may be extended) and defines its functions, duties and powers. It has
mandated NRA for leading and managing the earthquake recovery and reconstruction
in Nepal. It has delegated the NRA the authority to frame rules (Section 30), may
make and enforce necessary guidelines or procedures in order to conduct its
business (Section 31).
Solid Waste Management Act, 2068 B.S (2011 A.D): It outlines the duties of local
government to take action to control haphazard waste generation, disposal or
collection and has provisions for various punitive measures against those engaged in
activities detrimental to the intentions of the Act.
Child Labour (Prohibition and Regulation) Act, 2057 B.S (2000 A.D): Engaging
children including those who has not attained the age of 14 in risky activities against
his/her will by any means is prohibited. In case any enterprise has to engage a child in
works, an approval has to be obtained from concerned body.
Local Self Governance Act 2055 B.S (1999 A.D): Empowers the local bodies for the
conservation of soil, forest and other natural resources and implements environmental
conservation activities
Forest Act, 2049 B.S (1993 A.D): Requires decision makers to take account of all
forest values, including environmental services and biodiversity, not just the
production of timber and other commodities.
Water Resources Act, 2049 B.S (1992 A.D): It has legal arrangements for
determining beneficial uses of water resources, preventing environment and other
hazardous effects thereof and also keeping water resources free from pollution. It has
clearly mentioned that no one shall pollute water resource by way of using or putting
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 87
any litter, industrial wastes, poison, chemical or toxicant to the effect that the pollution
tolerance limit of the water resource as prescribed.
The Labor Act, 2048 B.S (1992 A.D): Regulates the working environment, deals with
occupational health and safety.
Soil and Watershed Conservation Act (SWCA), 2039 B.S (1982 A.D); It empowers
GoN to declare any area of Nepal as a conserved watershed area, specifying the
borders thereof. The Watershed Conservation Officer (WCO) has the authority to
implement protective infrastructure, vegetation program and regulate agricultural
practices pertinent to soil and watershed conservation. It empowers WCO to prohibit
the commission of any acts that may cause soil-erosion or soil cutting in a land where
any of the acts has been done
Public Roads Act, 2031 B.S (1974 A.D): Act mandates requirement of permission
from the DoR to carry out activities within the limits of the road boundaries and also
provision of notifying the DoR by local governmental offices prior to the start of
activities in the limits of the public roads.
National Park and Wildlife Conservation Act, 2029 B.S (1972 A.D): This act
provides protection to 27 species of mammals, 9 species of birds and three species of
reptiles.
Road Board Act, 2058 B.S: It is expedient to make necessary provisions on having
the roads repaired and maintained, making cost effective the expenditures to be
incurred in repairing and maintaining the roads and making transparent and effective
the repairing and maintenance works of the roads.
D Rules and Regulations
Rule Relating to Reconstruction of the Earthquake Affected Structures 2072 B.S
(2016 A.D): It provides the basis for prioritization of reconstruction. More importantly,
it defines functions, duties and rights of the Chief Executive Officer and Secretary of
NRA and District Coordination Committee.
Local Self Governance Rules 2056 B.S (2000 A.D): It provides procedural
guidelines for implementation of the Local Self Governance Act.
Forest Rules, 2051 B.S (1995 A.D): It elaborates legal measures for the
conservation of forests and wildlife and provides procedural guidelines for
implementation of the Forest Act. It stipulates that in case the execution of any project
having national priority in any forest area causes any loss or harm to any local
individual or community, the proponent of the project itself shall bear the amount of
compensation to be paid.
Road Board Rule, 2060 B.S: Maintenance of road from routine to emergency, DCC
is responsible for district road. DCC will prepare annual road maintenance plan and
forward it to road board through DoLIDAR and board will prepare annual plan.
Solid Waste Management Act, 2070 B.S: It outlines that every waste generator shall
segregate waste and store separately and hand over to Municipal workers or
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 88
authorized waste pickers.
E Work Procedures, Guidelines, Standards and others
Local Body Restructuring Notice, MoFALD, GON, 2017 A.D: Declaration of the
name, number, boundary, ward’s boundary of 744 Rural Municipality and Municipality
with 481 rural municipalities, 246 municipalities, 13 sub-metropolitan cities, 4
metropolitan cities and dissolve of VDC/DDC.
Working Procedure Related with Environmental Impact Assessment for
Rehabilitation of Earthquake Affected Structures 2072 B.S (2016 A.D) and
Second Amendment, 2074 B.S (2017 A.D): These provide procedural guidelines for
undertaking reconstruction and rehabilitation projects. These include a
comprehensive suite of procedures for different activities like environmental impact
assessment, land acquisition, and public procurement for reconstruction projects
(2072 B.S) and grievance management (2073 B.S). It determines the format of IEE
and EIA.
The first amendment has revised the threshold for projects to undergo IEE or EIA. It prescribes (under Clause 2 of Schedule 1) that upgrading, rehabilitation and reconstruction and new construction of district, urban and rural road should follow IEE study and approval.
The second amendment has also revised the threshold for projects to undergo IEE or EIA. It prescribes (under Clause 1 of Schedule 1) 7.5 ha as threshold for screening the project. Project requiring vegetation clearance for more than 7.5 ha will need to carry EIA and equal to or less than 7.5 ha need IEE study.
Working Procedure to Use National Forest area for National Priority Projects,
2074 B.S (2017 A.D): Following are the main features:
• EMP/IEE/EIA study is mandatory for obtaining forestry clearance.
• Alternative analysis has to be done during feasibility study for avoiding forest area or
if not having minimal loss of vegetation.
• Concerned Ministry has to obtain concurrence from Ministry of Forest and Soil
Conservation before approving IEE/EIA
• Provision of compensatory plantation (with protection for five years) at the ratio of
1:25 plants by the project or provide plantation and protection cost to concerned DFO.
Community forest development program guideline (third revision 2071 B.S):
Sustainable and scientific management of forest by the local users including
environment services and facilities for the mitigation of natural calamities, wildlife's
and forest fire
ADB Environmental Assessment and Review Framework (EARF), 2015 A.D for
EEAP: It elaborates environmental legal requirements and procedures according to
the Government of Nepal and Safeguard Policy Statement, 2009 of ADB and guides
the preparation of environmental assessments and environmental management plans.
ADB Resettlement Framework (RF), 2015 A.D for EEAP: It guides the preparation
of resettlement plans by elaborating legal and procedural guidelines according to GoN
and ADP SPS.
Batabaran Parichhyan - Resource Booklet - 2070 B.S (2013): It provides guidance
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 89
for local body to prepare environmental assessment reports of different projects;
construction materials extraction and local roads, on their own.
Environment Friendly Local Governance Framework (EFLG) 2070 B.S (2013
A.D): This framework is prepared to promote environmental conservation through
local institutions to materialize environment friendly local development concept. There
are different level of environment friendly indicators like basic, advanced and special
indicators at household, tole/settlement, ward, VDC, Municipality and District level.
Main objectives of this framework are as follows:
Mainstreaming the environment, climate change, disaster management issues in
local development planning process.
Making environment friendly local governance mechanism.
Strengthening basic level to make environment friendly sustainable development.
Promoting coordination and cooperation within environment and development.
Strengthening local organization to enhance local ownership for the sustainable
development of environment.
Nepal Rural Road Standard, 2012 A.D: Sets the classification and geometric design
standards for the Local Road Network to be followed by all those involved in the
development of the network, including Users, User Committees, VDCs, DDCs, DTOs,
DoLIDAR and its development partners.
National Adaptation Program of Action, 2068 B.S (2010 A.D): The NAPA has been
instrumental in mainstreaming climate change in development planning. The NAPA
has developed a framework for adaptation programme, and has identified key
adaptation needs, existing adaptation practices and options for developed projects
including infrastructure.
Reference Manual for Environmental and Social Aspects of Integrated Road
Development, 2060 B.S (2003 A.D): Suggests stepwise process of addressing
environmental and social issues alongside the technical, financial and other issues.
Batabaraniya Nirdesika (Nepali), 2057 B.S (2000 A.D): Focuses in the practical
implementation of small rural infrastructures through the minimization of
environmental impacts and outlines simple methods of environmental management in
the different phases of the project cycle. More emphasis is given to prevention rather
than cure.
APPROACH for the Development of Agricultural and Rural Roads, 2055 B.S
(1999 A.D): Emphasizes labor based technology and environmental friendly, local
resource oriented construction methods to be incorporated actively in rural
infrastructure process.
Green Roads in Nepal, Best Practices Report – An Innovative Approach for
Rural Infrastructure Development in the Himalayas and Other Mountainous
Regions. GIZ, 1999 A.D: It focuses on participatory, labor based and environment
friendly technology with proper alignment selection, mass balancing, proper water
management, bioengineering and phased construction.
Environmental Management Guidelines, Geo Environmental and Social Unit,
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 90
DoR, 2054 B.S (1997 A.D): It consists of environmental mitigation measures to be
incorporated into DoR projects, procedures for public participation, and socio-
economic consideration. The Environmental Mitigation Measures are broken down
into 12 categories or activities and a method for implementation is given for each
mitigation measures including implementation strategies. These environmental
mitigation measures should be used in conjunction with good engineering design,
construction and operation practices. It also suggests considering the various socio-
economic issues like land acquisition and compensation, economic impacts and
cultural heritage.
Community forest development program guideline (third revision 2071 B.S):
Sustainable and scientific management of forest by the local users including
environment services and facilities for the mitigation of natural calamities, wildlifes and
forest fire
National Environmental Impact Assessment Guidelines, 2050 B.S (1993 A.D):
Provides guidance to project proponent on integrating environmental mitigation
measures, particularly on the management of quarries, borrow pits and stockpiling of
materials, operation of the work camps, earthworks and slope stabilization, location of
stone crushing plants etc.
F International Conventions
Convention on International Trade in Endangered Species of Wild Fauna and
Flora (CITES), 2053 B.S, amended, 2059 B.S (1973 A.D, amended 1979 A.D): It
regulates international trade in endangered wild flora and fauna with the aim of
reducing or eliminating trade in species whose numbers or conditions suggest that
further removal from their natural habitat would lead to their extinction. It urges parties
not to allow trade in specimen of species included in the CITES Appendices I, II and
III with some exception. As the area holds some CITES listed species, this convention
is attracted in case of their trade.
Convention on Biological Diversity, 2049 B.S (1992): It focuses on the
conservation of biological diversity, the sustainable use of its components and the fair
and equitable sharing of the benefits. It urges parties to introduce appropriate
procedures requiring EIA of the proposed projects that are likely to have significant
adverse effects on biological diversity.
Convention (No. 169) Concerning Indigenous and Tribal People in Independent
Countries, 2046 B.S (1989A.D): The convention provides right to the indigenous and
tribal people to decide their own priorities for the process of development. It mandates
participation in formulations of the plan and programs, decision making regarding
national development. It safeguards rights of the indigenous people in territories
traditionally occupied by them.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 91
9. Environmental Management Plan
258. The environmental management plan (EMP) is prepared to guide the implementation
of mitigation measures and monitoring requirements. It includes institutions and their roles,
environmental management activities, environmental management organizational structure
and budget for mitigation measures.
9.1. Institutions and Their Roles
259. Different institutions involved in the IEEs and EMP implementation and roles of these
institutions are given in Table 79. The environmental management organizational structure
is given in Figure 8.
Table 79: Institutions and Their Roles
Institution Role Responsibility in the Project
National
Reconstruction
Authority
Executive agency and
concerned IEE approval
authority as per act relating to
reconstruction of the earthquake
affected structure 2015, rule
relating to reconstruction of the
earthquake affected structure
2016 and Working Procedure
Relating with Environmental
Impact Assessment for
Reconstruction of Earthquake
Affected Structures, second
amendment 2017.
To review and approve IEE Report
Conduct environmental monitoring
from central level.
MoFAGA Co-ordination of project
activities with EEAP
Representation in IEE review team
constituted by NRA
Conduct environmental monitoring
from district level.
CLPIU - EEAP Co-ordinationof project activities
from center
Technical Unit to support and
coordinate all activities for
implementation of EEAP.
Review, comment and forward
ToR for IEE and IEE report to ADB
for concurrence and to NRA for
approval.
CISC Support consultant at Central
Level.
Technical and management
support to CLPIU-EEAP
Supervises and monitors project
consultants and contractors.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 92
Institution Role Responsibility in the Project
Implements and monitor
resettlement plans and
IEEs for the relevant sub-project s
and prepares consolidated reports
on these.
Ensures timely and effective
implementation of the
activities set out in the Gender
Equality and Social Inclusion
(GESI) Action Plan.
Prepares progress reports, as
outlined in PAM
DLPIU DLPIU is project implementing
agency in district
Prepare ToR for IEE and submit
for approval to NRA through
CLPIU
Conduct IEE study, public
consultation and prepare draft IEE
and public disclosure and then
submit for concurrence from ADB
and approval from NRA through
CLPIU
Implement IEE and EMP of sub-
projects and conduct
environmental monitoring and
reporting.
DISC Supporting consultants at
district level
Technical and management
support to DLPIU for the
implementation of project activities
in the districts. Responsible for
supervision and monitoring at field
level.
Grievance
Redress
Committee
Support in addressing
grievances caused due to road
construction related to
environment.
Responsible for addressing
grievances due to road
construction which affects their
livelihood.
260. To support for smooth implementation of the project, there are various district level
committees and groups including DLPIU, DISC to support the project.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 93
Figure 8: Environmental Management Organisation Structure
9.2. Implementation of Benefit Augmentation and Mitigation
Measures
261. The DLPIU will be responsible for the implementation of benefit augmentation and
mitigation measures proposed in Chapter 7. Various agencies including DISC, local bodies
and concerned governmental line agencies will support DLPIU for the implementation of
mitigation measures. The detail action plan for activities to be carried out to augment
beneficial impacts and reduce/mitigate adverse impact produced from the implementation of
the proposal, and the responsible implementing and supporting agencies are provided in
environmental management plan is presented in Table 80 and 81.
DFO, Forest
-UGs
CLPIU-EEAP
Environment safeguard focal
person+ (GRM II level)
CISC
Environment Safeguard Unit
DLPIU-EEAP
Environment safeguard focal
person+ (GRM I level)
DISC Environment safeguard
focal person
Contractor + (GRM I level)
Government of Nepal National Reconstruction Authority (NRA) + (GRM III
level)
MoFAGA/ PCC
ADB, SDC
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 94
Table 80: Likely Beneficial Impacts and Enhancement Measures
Activity Effect Related Beneficial
Impacts
Type of Impact Sig Benefit Augmentation Measures Responsible Agencies
Nat Mag Ext Dur Executing
Agency
Supporting
Agency
Construction Phase
Construction
of road
(Earth
excavation,
spoil
disposal, site
clearance)
Employment
Generation
(31,134 skilled
and 103,743
unskilled person
days)
Increase in income
level
D H
(60)
LC
(20)
ST
(5)
VS
(85)
Life skill training for income
generation activities to improve
their livelihood of the affected
peoples.
DLPIU CLPIU/
DISC/ CISC
Construction
work
Economic
Increment
Increase in income
level
D H
(60)
LC
(20)
ST
(5)
VS
(85)
Awareness raising**
programmes (NRS 350,000.00) to
local entrepreneurs for promoting
linkage with cooperatives and
other financial institutions.
Increase in market demand
and opportunity.
DLPIU CLPIU/
DISC/ CISC
Construction
of road
Skill
Enhancement
Increase in income
generating
activities,
employment
opportunities
IN L
(10)
LC
(20)
LT
(20)
S
(50)
Providing skill training in
construction techniques, small
engineering structures (masonry
wall construction, netting wires
and construction of gabion wall,
slope cutting etc.) and bio-
engineering works.
DLPIU DISC
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 95
Activity Effect Related Beneficial
Impacts
Type of Impact Sig Benefit Augmentation Measures Responsible Agencies
Nat Mag Ext Dur Executing
Agency
Supporting
Agency
Operation Phase
Operation of
Road
Improve Access Saving in travel
time and travel cost
D H
(60)
R
(60)
LT
(20)
VS
(140)
No benefit augmentation
measures are planned
Municipality/RM Municipality/
RM
Operation of
Road
Possible Market
Development
and Business
Promotion
Extension of local
market, non-
agricultural
employment
opportunity.
IN H
(60)
LC
(20)
LT
(20)
VS
(100)
No benefit augmentation
measures are planned
Municipality/RM Municipality/
RM
Operation of
Road
Increase in Land
Value
Improvement in
local economic
condition
IN H
(60)
LC
(20)
LT
(20)
VS
(100)
No benefit augmentation
measures are planned
Municipality/RM Municipality/
RM
Operation of
Road
Cottage
Industries
Development
Employment
opportunities and
self-employee
IN H
(60)
LC
(20)
LT
(20)
VS
(100)
No benefit augmentation
measures are planned
Municipality/RM Municipality/
RM
Operation of
Road
Increase in Crop
Productivity
Enhancement in
local economy
D M
(20)
LC
(20)
LT
(20)
S
(60)
No benefit augmentation
measures are planned
Municipality/RM DADO
Operation of
Road
Increase in Sale
of Local
Products
Shifts towards
improved
agriculture farming
and local goods
production
IN M
(20)
LC
(20)
LT
(20)
S
(60)
No benefit augmentation
measures are planned
Municipality/RM DADO
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 96
Table 81 : Likely Adverse Impacts and Proposed Mitigation Measures
Activity Potential Negative
Effects
Related Adverse
Impacts
Type of Impact Sig Mitigation Measures Responsibility for
Mitigation Measure
Nat Mag Ext Dur Executing
Agency
Supporting
Agency
Construction Stage
Physical Environment
Earth
Excavation
Change in land use
1.665 ha cultivated
land
Loss of agricultural
land, production, loss
of property
D H
(60)
LC
(20)
LT
(20)
VS
(100
)
Applying additional
protective measures (bio-
engineering and toe-wall)
that the remaining land will
not be lost due to erosion.
Contractor/
DLPIU/
DISC/CISC/
CLPIU
Hazard due to
Spoil Disposal
Spoil disposal and
imposed weight of
spoil on fragile
slopes
Gully erosion,
landslide, disruption
of road, damage to
farmland, water
pollution etc.
D M
(20)
SS
(10)
LT
(20)
a) S
(50)
Separation and
utilization of top soil and
proper management of
spoils and waste, provision
of proper drainages, toe
walls.
The spoil will be
disposed in proper location
at the chainage 9+000,
18+900, 21+500, 29+000,
33+400 and 35+950.
Contractor/
DLPIU
DISC/CISC/
CLPIU
Site
clearance,
earth
excavation
Slope Instability at
different chainages
(Ch 3+990-4+300,
6+630-6+790,
Erosion, landslide,
loss of property
IN M
(20)
SS
(10)
LT
(20)
b) S
c) (50)
Bio-engineering
application will be used to
stabilize the slopes.
Necessary slope
Contractor/
DLPIU
DISC/CISC/
CLPIU
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 97
Activity Potential Negative
Effects
Related Adverse
Impacts
Type of Impact Sig Mitigation Measures Responsibility for
Mitigation Measure
Nat Mag Ext Dur Executing
Agency
Supporting
Agency
6+870-6+900,
7+040-7+115,
9+980-10+025,
10+310-10+320,
11+940-11+980,
12+000-12+080,
12+285-12+520,
12+565-12+580,
19+870-19+890,
30+750-30+780 and
30+970-31+000)
stabilization structures will
be constructed
NRs. 5,827,259.86 has
been allocated
Construction
of Road
Disruption of natural
water flow due to
drainage and cross
drainage works
Erosion, landslide,
due to increase in
surface runoff
IN M
(20)
SS
(10)
MT
(10)
d) S
(50)
Proper drainage
structures (cause ways,
drain) will be constructed.
No blockage or
diversion of natural
channels due to
construction of road and
spoil disposal.
Contractor/
DLPIU
DISC/CISC/
CLPIU
Construction
works, spoil
and waste
disposal
Air pollution due to
dust from exposed
surface, from
construction
equipment
Effect on local people
and workers health
D L
(10)
LC
(20)
ST
(5)
INS
(35)
Use of face mask
while working on dust
prone areas, covering of
dust sources.
Contractor/
DLPIU
DISC/CISC/
CLPIU
Noise pollution Disturbance and
annoyance around
D L
(10)
LC
(20)
ST
(5)
INS
(35)
Restrict horn near
school, health posts and
Contractor/
DLPIU
DISC/CISC/
CLPIU
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 98
Activity Potential Negative
Effects
Related Adverse
Impacts
Type of Impact Sig Mitigation Measures Responsibility for
Mitigation Measure
Nat Mag Ext Dur Executing
Agency
Supporting
Agency
school, health posts
and people living in
nearby areas.
settlement area etc.
Water pollution due
to sediment level
Risk of water borne
diseases
D L
(10)
LC
(20)
ST
(5)
INS
(35)
Proper spoil
management and
restriction in urination and
defecation in open areas
and water bodies.
Contractor/
DLPIU
DISC/CISC/
CLPIU
Quarrying Quarry operation
and its potential
effect on instability,
landslide, potential
quarry site are at Ch
20+410-20+620,
20+800-21+160
Water pollution,
damage to farmland,
disturbance in natural
drainage
D L
(10)
LC
(20)
ST
(5)
INS
(35)
Quarry operation
plan will be prepared.
Rehabilitation of
quarry sites after
completion of work.
Contractor/
DLPIU
DISC/CISC/
CLPIU
Establish
labor camp
and storage
deposit
Pollution and impact
due to location of
camp sites
(chainage 3+700,
8+900, 17+400,
22+500, 29+000,
31+900 and
34+950.)
Encroachment of
forest, agriculture
land, solid waste, and
waste water may
cause pollution
D M
(20)
SS
(10)
ST
(5)
INS
(35)
Local houses will be
used as labour camp rent
Compensation will
be paid to land owner of
camping area.
DLPIU/
Contractor
DISC/CLPI
U/CISC
Biological Environment
Clearance of Impact on forest Loss of D H SS ST VS Use kerosene for Contractor/ DFO/CISC/
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 99
Activity Potential Negative
Effects
Related Adverse
Impacts
Type of Impact Sig Mitigation Measures Responsibility for
Mitigation Measure
Nat Mag Ext Dur Executing
Agency
Supporting
Agency
vegetation
necessary for
road formation
land, 1.950 ha of
Government
Managed Forest
area, 2.875 ha of
CF, 0.166 ha of
private forest area,
0.487 ha leasehold
forest, and 0.166 ha
private forest, 886
tree loss from forest
area and 373 from
private forest and
private land
environmental
benefits from
vegetation,
disturbance in
ecological function
(60) (10) (5) (75) heating fuel wood is
prohibited.
NRs. 3,370,788.35
has been allocated for
compensatory plantation.
DLPIU/DIS
C
CFUG/
LHFUG
Construction Pressure in forest
product
Use of firewood for
cooking
IN L
(10)
LC
(20)
LT
(20)
INS
(50)
Use of kerosene in
cooking
Awareness raising**
training (NRS 350,000.000)
has been planned
Contractor/
DLPIU/
DISC
DFO/CISC/
CFUG
/LHFUG
Construction
activity
Habitat
Fragmentation
Disturbance to wildlife
including birds
IN L
(10)
LC
(20)
LT
(20)
INS
(50)
Work only in day
time
No disturbance to
wildlife
NRs 350,000.00 for
awareness raising**
programmes to the
workers.
Contractor/
DLPIU/
DISC
DFO/CISC/
CFUG
/LHFUG
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 100
Activity Potential Negative
Effects
Related Adverse
Impacts
Type of Impact Sig Mitigation Measures Responsibility for
Mitigation Measure
Nat Mag Ext Dur Executing
Agency
Supporting
Agency
Construction
activity
Impact on Flora and
Fauna as listed in
CITES, IUCN and
GoN.
Loss of biodiversity IN L
(10)
LC
(20)
ST
(5)
INS
(35)
Prohibiting workers
for hunting/harassing
wildlife
Contractor/
DLPIU/
DISC
DFO/CISC/
CFUG
/LHFUG
Socioeconomic Environment
Acquisition of
land for
maintaining
road width
Loss or Degradation
of 1.665 ha Farm
Land and
Productivity
Reduced production,
loss of income
D H
(60)
LC
(20)
LT
(20)
VS
(100
)
compensation of
NRs 11,552,405.89 will be
provided to affected people
DLPIU/
DISC
CISC /
CLPIU/
Municipality
/RM
Demolition of
structures
along road
Eight Private
structures along the
road corridor will be
affected.
Loss of services
provided by these
structures
D H
(60)
SS
(10)
LT
(20)
VS
(90)
Compensation of
NRs. 6,061,520.24 will be
allocated for affected
private structures
DLPIU/
DISC
CISC /
CLPIU/
Municipality
/ RM
Demolition of
structures
along road
Impact on one
community tap and
water pipe
Loss of Services D H
(60)
SS
(10)
LT
(20)
VS
(90)
Compensation of
NRs. 60,000.00 has been
allocated.
DLPIU/
DISC
CISC /
CLPIU/ /RM
Municipality
Construction
activity
Impact on
occupational health
and safety
Injury, fatal accidents,
outbreak of
epidemics and
diseases, decline in
capacity to work
D L
(10)
LC
(20)
ST
(5)
INS
(35)
First aid facility at
sites with health treatment
arrangements
Proper drinking
water and toilet facility for
construction workers
Safety gears
(helmet, face masks,
DLPIU/Cont
ractor
CISC/
CLPIU
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 101
Activity Potential Negative
Effects
Related Adverse
Impacts
Type of Impact Sig Mitigation Measures Responsibility for
Mitigation Measure
Nat Mag Ext Dur Executing
Agency
Supporting
Agency
goggles, gloves, boots) and
accidental insurance of
workers.
Construction
activity
Impact on Public
health and safety
Work force and
migrating people
might be suffering
from several
communicable
diseases such that
their disease could be
transmitted to local
people arising threat
to community health
D L
(10)
LC
(20)
ST
(5)
INS
(35)
First aid facility at
sites with health treatment
arrangements
NRs 350,000.00 is
allocated for awareness
raising** training on public
health and safety
DLPIU/Cont
ractor /DISC
CISC/CLPI
U
Operation Stage
Physical Environment
Operation of
road
Road Slope Stability
and Management
Slides and slope
failure, Disturbance to
traffic flow, pollution
of water bodies,
impacts on
agriculture land, loss
of vegetation.
D M
(20)
LC
(20)
LT
(20)
S
(60)
Regular
maintenance of slope
protection structures and
bioengineering techniques
on slopes.
RM
/Municipality
RM
/Municipalit
y
Operation of
vehicles
Air, Noise and Water
Pollution
Disturbance to
students, patients,
local people effect to
D L
(10)
LC
(20)
LT
(20)
S
(50)
Community
awareness raising**
programme (NRs.
RM/
Municipality
RM/
Municipality
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 102
Activity Potential Negative
Effects
Related Adverse
Impacts
Type of Impact Sig Mitigation Measures Responsibility for
Mitigation Measure
Nat Mag Ext Dur Executing
Agency
Supporting
Agency
nearby agriculture
land and crops
350,000.00) conduction
No horn signs near
schools, health posts.
Restriction on
washing of vehicles in local
streams.
Biological Environment
Road
operation
Pressure in Forest
Resources
Loss of timber, forest
resources and
benefits
IN M
(20)
LC
(20)
LT
(20)
S
(60)
Awareness raising**
programmes (NRs.
350,000.00) for
conservation of forest
resources
enforcement of law
along with community
participation
RM/
Municipality
DFO/
CFUGs/LH
FUG
Road
operation
Forest Fire Loss of forest IN L
(10)
LC
(20)
LT
(20)
S
(50)
NRs 350,000.00 is
allocated for awareness
raising** programmes.
RM/
Municipality/
local people
DFO/CFUG
/LHFUG
Road
operation
Disturbance to the
Wildlife
Collision of wildlife
with vehicles,
disturbance in their
normal activities
IN L
(10)
LC
(20)
LT
(20)
S
(50)
Warning traffic signal
Awareness raising**
training (NRs. 350,000.00)
to drivers to limit speed and
horn use
RM/
Municipality
/local NGOs
DFO/
CFUGs/
LHFUG
Road
operation
Illegal Hunting Depletion of faunal
diversity
IN L
(10)
LC
(20)
LT
(20)
S
(50)
Strictly implemented
rules and regulation to
RM/
Municipality
DFO/
CFUGs/
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 103
Activity Potential Negative
Effects
Related Adverse
Impacts
Type of Impact Sig Mitigation Measures Responsibility for
Mitigation Measure
Nat Mag Ext Dur Executing
Agency
Supporting
Agency
control Illegal Hunting
Awareness raising**
programmes (NRS
350,000.00) about
importance of biodiversity
to the local people, student
and forest user groups.
/local NGOs LHFUG
Road
operation
Impact on protected
species
Possibilities to impact
in protected fauna
due to increase in
human influence
IN L
(10)
LC
(20)
LT
(20)
S
(50)
Conduct awareness
raising** programmes
(NRs. 350,000.00)
Strictly prohibited to
enter the forest area
Enforcement of law
RM/
Municipality
DFO/CFUG
s/LHFUG
Socioeconomic Environment
Road
operation
Encroachment of
Public Land and
Ribbon Settlement
Development
Encroachment of
RoW, increased
accidents, depletion
of local resources,
water pollution
D M
(20)
LC
(20)
MT
(10)
S
(50)
Awareness raising**
programmes (NRs.
350,000.00) conduction
and enforcement of law
Roadside plantation
of trees in COI (NRs.
450,000.00)
RM/
Municipality
RM/
Municipality
Operation of
Road
Increase Traffic
Congestion
delay in traffic
movement, noise
pollution
D M
(20)
LC
(20)
LT
(20)
S
(60)
Manage traffic
congestion by applying
appropriate traffic rule and
RM/
Municipality
RM/
Municipality
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 104
Activity Potential Negative
Effects
Related Adverse
Impacts
Type of Impact Sig Mitigation Measures Responsibility for
Mitigation Measure
Nat Mag Ext Dur Executing
Agency
Supporting
Agency
traffic signals
Operation of
Road
Road Safety Increase in accidents D M
(20)
LC
(20)
LT
(20)
S
(60)
Appropriate road
safety measures, safety
sign boards along the road,
NRs 350,000.00 is
allocated for awareness
raising** program.
RM/
Municipality
RM/
Municipality
Note:
Magnitude H= High M= Moderate L= Low (depending on the scale or severity of change.)
Extent R= Regional LC= Local SS= Site specific
Duration LT= Long term (more than 20 years) MT= Medium term (3-20 years) ST= Short term (less than 3 years)
Nature D= Direct; IN= Indirect
Impact upto 44; insignificance (INS) 45-74; significance(S) 75 or greater; very significance (VS)
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 105
9.3. Mitigation Cost for Executing the Environmental Management
Plan
262. The estimated cost for beneficial augmentation measures like awareness raising
program, skill training, promotion of small scale industries, and income generation activities
will be covered by the improved community development and rural livelihood restoration
component of the Project. The design and cost estimate for most of the suggested mitigation
measures such as slope stabilization, spoil disposal, landslide construction will be
incorporated in the design and cost estimates. However clear BoQ will be prepared for
supply of face masks, helmets, muffles, accidental insurance, bioengineering measures,
plantation and environmental protection awareness trainings. Therefore, most of the
mitigation measures suggested would be a part of road design and construction without
additional cost. All proposed mitigation measures will be integrated in the sub-project design
so that these measures may automatically form part of the construction and operational
phases of the Sub-project.
9.3.1 Environmental Monitoring and Reporting Activities
263. The CLPIU, with the DLPIU will monitor and measure the progress of EMP
implementation. The monitoring activities will be corresponding with the project’s risks and
impacts and will be identified in the IEE. In addition to recording information of the work,
deviation of work components from original scope, the CLPIU with the DLPIU will undertake
site inspections and document review to verify compliance with the EMP and progress
toward the final outcome.
264. DSC will submit monthly monitoring and implementation reports to the CLPIU, who
will take follow-up actions, if necessary. CLPIU will submit the quarterly monitoring and semi-
annual monitoring reports to ADB. Project budgets will reflect the costs of monitoring and
reporting requirements. Monitoring reports will be posted in a location accessible to the
public.
265. The CLPIU will document monitoring results, identify the necessary corrective
actions, and reflect them in a corrective action plan. Compliance with loan covenants will be
screened by the executing agency.
266. ADB will review project performance against the executing agency’s commitments as
agreed in the legal documents. The extent of ADB's monitoring and supervision activities will
be commensurate with the Project’s risks and impacts. Monitoring and supervising of
environmental safeguards will be integrated into the project performance management
system. ADB will monitor projects on an ongoing basis until a project completion report is
issued. ADB will carry out the following monitoring actions to supervise project
implementation:
267. Conduct periodic site visits for projects with adverse environmental impacts;
Review the periodic monitoring reports submitted by the executing agency to
ensure that adverse impacts and risks are mitigated as planned and as agreed
with ADB;
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 106
268. Work with executing agency to rectify to the extent possible any failures to comply
with their safeguard commitments, as covenanted in the legal agreements, and
exercise remedies to re-establish compliance as appropriate; and
269. Prepare a project completion report that assesses whether the objective and
desired outcomes of the safeguard plans have been achieved, taking into
account the baseline conditions and the results of monitoring.
270. Total cost of environmental monitoring (field visits, observation, review of reports and
report preparation) is estimated NRs. 325,000 as given in Table 82.
Table 82: Environmental Monitoring Cost
Manpower requirement Duration
(days)
Rate (NRs) Amount (NRs)
Team Leader/Environmental Specialist 8 7,000 56,000
Engineer 6 5,000 30,000
Forestry expert 6 5,000 30,000
Socio-economist 6 5,000 30,000
Support staff 6 1500 9,000
Transportation cost LS 40,000
Report preparation LS 30,000
Central level monitoring LS 100,000
Total 325,000
9.3.2 Major Costs for Environmental Safeguard Measures
271. The environmental management cost of this project is NRs. 4,595,788.35 and is
summarized in Table 83. In addition to this cost, different environmental mitigation and
management activities like bio-engineering, insurance of workers etc. are covered by civil
work cost.
Table 83: Estimate for Environmental Enhancement and Mitigation Measures
1.1 Environmental Management Cost Cost (NRs.)
1.1.1 Environmental Awareness raising** training 350,000.00
1.1.2 Compensatory plantation & protection cost for trees on CF
and private land
3,370,788.35
1.1.3 Road side plantation 450,000.00
1.1.4 Road safety and informative signboard 100,000.00
1.1.5 Environmental monitoring cost 325,000.00
Sub-total (i) 4,595,788.35
1.2 Other environmental cost( included in civil works cost also)
1.2.1 Occupational health and safety (GPA insurance) 1,658,163.47
1.2.2 Bioengineering works 5,827,259.86
Sub-total (ii) 7,485,423.33
Total (i+ii) 12,081,211.68
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 107
9.4. Matters to be monitored while Implementing the Proposal
272. Monitoring of the implementation of environmental protection measures provides a
basis for logical comparison for the predicted and actual impacts of a proposal.
Environmental monitoring will involve the systematic collection of data to determine the
actual environmental impacts of the sub-project, compliance of the sub-project with
regulatory standards, and the degree of implementation and effectiveness of the
environmental protection. Monitoring will be an integral part of the implementation of the
mitigation measures during project construction, and will generate important information. It
will improve the quality of sub-project implementation.
273. The Working Procedure Relating with Environmental Impact Assessment for
Reconstruction of Earthquake Affected Structures, second ammendment, 2074 B.S) requires
a monitoring plan and indicators, schedules and responsibility to be identified in the IEE
report. The National EIA Guidelines, 1993 has suggested three stages of the monitoring i.e.
baseline monitoring, compliance monitoring and impact monitoring.
9.4.1 Baseline Monitoring
274. Baseline monitoring helps to update the baseline information collected during
IEE/EIA study when there is a significant time gap between IEE/EIA approval and proposal
implementation. In general, it is carried out if there is a significant time lapse between the
preparation of the IEE report and the construction stage or a change in environmental quality
is noticeable. This sub-project will proceed for construction immediately after the approval of
this IEE report and hence, baseline monitoring is not required for this sub-project.
9.4.2 Compliance Monitoring
275. Compliance monitoring is essential in order to ensure that environmental protection
measures recommended by this study and other requirements set forth during the approval
of the sub-project are complied with. This monitoring is not concerned with determining the
actual effect of the sub-project activities on the environment.
276. The proponent will ensure compliance of activities such as; inclusion of mitigation
measures in the design and tender documents, budget allocation for mitigation measures
and monitoring, compensation arrangements and other compliances spoil disposal, storage
sites, arrangement of construction activities etc.
9.4.3 Impact Monitoring
277. Impact monitoring is generally carried out to assess the effectiveness of the
environmental mitigation measures and provides actual levels of impacts in the field. Hence
an impact monitoring evaluation study is proposed by the end of the sub-project construction
phase or within two years of sub-project implementation. Impact monitoring will focus on
each predicted impact and effectiveness of environmental protection measures. This will
also focus on the stability of slopes; spoil disposal sites, work camps and labour camps,
wastes on the local environment. The utilization of cash compensation to the extent possible,
condition of the forest in the vicinity of the sub-project area, water management, damage to
human facilities, incremental change in production of high value commodities, increase in
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 108
other sources of income, employment generation, road side plantation, social status,
impediment to wildlife movement, etc.
9.5. Monitoring Parameters
278. These would be based on the level of site-specific information or existing data series
and impacts prediction. Efforts will be made to make the indicators measurable and
diagnostic with low natural variability and broad applicability. In this context, the following
physical, biological and social indicators will be monitored during the construction and
operational stages of the sub-project.
9.5.1 Pre-Construction Phase
279. During this phase the Consultant (DISC) bear the main responsibility in ensuring that
the environmental and social safeguard considerations are adequately incorporated in the
Project design and that the respective clauses to address the identified impacts are
sufficiently included in the specifications and work contracts.
9.5.2 Construction Phase
280. In this phase the monitoring focuses on impacts on the environmental and social
setting caused by the ongoing sub-project. This monitoring checks compliance with the
practices, norms, standards and technical solutions prescribed in the design and in the EMP.
The specific monitoring tasks will include
Verify and quantify the ongoing slope protection measures, and propose rectifying
measures as needed;
Verify and quantify the ongoing activities in propose rectifying measures as needed;
Verify and quantify the ongoing/completed tree felling actions;
Verify and quantify the course of any environmental degradation caused, their likely
consequences, and propose corrective measures, including the identification of
responsibilities and costs;
Verify and quantify the effects of disposal of spoil and construction wastes and their
consequences;
Verify and quantify the effects of disruption of natural water courses, drainage work, and
their consequences;
Monitor by utilizing structured checklists and questionnaires, the contractor’s full
compliance with the occupational health and safety regulations for the work staff;
Verify and quantify the effects of losses in wildlife, degradation of forests, illegal
extraction of forest products, hunting, wildlife trade and disturbance to wildlife;
Identify and assess the environmental implications on the people’s status of knowledge
and awareness in relation to ongoing education campaigns;
Verify and quantify losses/damage to private property and community facilities;
Verify and quantify losses/damage to cultural properties;
Explore mechanisms to stipulate strict application of the EMP and identify consequences
to be borne by the contractors/BGs in case of non-compliance.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 109
9.5.3 Operation Phase
281. The specific monitoring tasks in this phase will include:
Assess changes in land-use patterns, development of cottage industries, services and
demographic composition that may be caused by the road development;
Verify and quantify the occurrence of ribbon development, resulting in encroachment and
hindrance of traffic on the road;
Verify all activities for decommissioning work sites and construction to their former
functional stage, as applicable. This refers also propose rectifying measures as needed.
Verify and quantify the adequacy of the executed bio-engineering works for slope
protection and erosion control;
Verify and quantify the adequacy of the drainage structures, functionality of these
structures, shortcomings in maintenance, and possible effects on private and communal
lands, as well as on aquatic resources;
Verify and quantify the course of any environmental degradation caused by Project
activities, their likely consequences, and propose corrective measures, including the
identification of responsibilities and costs;
Verify and quantify the effects of disruption of natural water courses, drainage work, and
their consequences;
Verify the success/failure of skill development and job opportunities’ training carried out ;
Verify and quantify the effects of losses in wildlife, degradation of forests, illegal
extraction of forest products, hunting, wildlife trade and disturbance to wildlife.
9.6. Monitoring Indicators
282. The monitoring will include specific cause-effect analyses for the impacts observed.
Following Table 84 specifies the set of verifiable indicators that will be used for monitoring.
Table 84: Monitoring Indicators Selected for this IEE
Monitored Sector Parameters Selected for Monitoring
Soils, Landslides, Erosion, Waste
management Sites
Number, location and extent of slope failures
Cause analysis for slope failure natural/man-made
Area (ha.) of land, forest and properties affected
Number and extent of gully erosions and
pavement failures
Suitability of corrective/bio-engineering measures
Sites and suitability for safe disposal of wastes and
garbage
Bio-engineering Number and plant species selected for bio-
engineering, disaggregated by protective function
Water Pollution, Water
Resources and their uses
Blockage of waterways - extent and secondary
impacts
Water pollution incidents due to unsafe disposal of
waste and spoil
Damage to farm lands
Air and Noise Level in relation to Assessment of noise level in site by direct
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 110
Monitored Sector Parameters Selected for Monitoring
traffic volume observation and interview with stakeholders
Visual assessment of dust development at
selected sites/sensitive spots and interview with
local stakeholders
Traffic volume measurements
Road Safety Number and type of road accidents recorded in the
Traffic Police and in local health service centers
Suitability of local road signs
Wildlife/ Habitat Disturbance
Impacts on Forest Resources
Nos and extent of road accidents inflicting wildlife
DFO records of illegal timber extraction and wildlife
trade
Observations and handling of invasive species.
Socio-economic Development
near Road
Number and extent of new settlements / types and
ethnic groups
Number and extent of new businesses
Number and extent of new services and utilities
Resettled Households and
livelihood restoration
Number of HHs resettled
Income situation and opportunities for the
resettlers
Verification of compensation and assistance to
resettlers
Community awareness
programmes relating to
environment protection and
avoidance of social conflicts
Number /schedule of campaigns and number of
beneficiaries
Revision of training agenda & information material
Number of beneficiaries having received
awareness training
283. The following Table 85 identifies the specific compliance monitoring activities.
Phase-wise/chronological details are provided for the methods, schedules, responsible
implementing agency and the responsible monitoring agency. The compliance monitoring
refers primarily to the pre-construction and construction stage of the project. Table 86 details
the impact and effect monitoring activities envisaged for this sub-project.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 111
Table 85: Compliance Monitoring for Pipalbhanjyang-Hayutar-Netrakali Road Sub-project
Parameters/Indicato
r
Responsible
Implementing
Agency
Verifiable
Indicators
Verification
Methods
Schedule Responsible
Monitoring Agency
Final alignment
selection
DLPIU Incorporation of walkover
recommendations into
alignment selection
process and design
document
Walkthrough along
final road
alignment, verifying
sensitive areas
Initial stage of
preconstruction
phase
RM/Mnicipality
Land and property
acquisition and
compensation
CDC with
assistance of
DLPIU
Cadastral records, land
and properties
acquisition procedures;
verification report
Public consultation,
photos; geo-
referencing
Initial stage pre-
construction phase
RM/Municipality
Site selection and
preparation of
construction logistics
DLPIU/Contractor Project’s arrangement for
materials storage, and
construction activities
Site observation,
geo-referencing
and photographic
documentation
Beginning of
construction period
RM/Municiplaity
/DLPIU
Awareness and
orientation training on
road construction to
technicians, and
locally employed
laborers
DISC Training programmes for
skill development,
occupational safety and
environmental protection
associated with road
construction works
Specifications;
training records,
check training
programme
reports, assess
feedback from
participants
Beginning of
construction and
during construction
RM/Municiplaity
/DLPIU
Compliance to DISC/Contractor/ Health and safety Spot checks at Throughout RM/Municiplaity/
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 112
Parameters/Indicato
r
Responsible
Implementing
Agency
Verifiable
Indicators
Verification
Methods
Schedule Responsible
Monitoring Agency
occupational health
and safety matters
DLPIU regulations, first aid and
medical arrangements,
number and type of
safety equipments such
as mask, helmet, glove,
safety belt, accidental
insurance
work sites, photos,
accident records,
interviews
construction
activities
DLPIU
Grievance Redress
Mechanism
Contractor/DISC/D
LPIU/CLPIU/CISC
Project arrangements for
the affected people's
concerns and grievances
about the project's
environmental and social
performance
No of complaints
and grievances
record
During construction RM/Municiplaity/
DLPIU
Measures to avoid
pressure on forest
and wildlife
DLPIU/DISC Use of firewood or fossil
fuel by construction
crew, events of hunting
and poaching of wildlife
Inspection,
interview with local
people
Once a month
during construction
DFO/CFUGs/LHFUG
Measures to protect
environment from air
& noise pollution
Contractor/ DLPIU Dust level and noise
level at work sites, major
settlements and
sensitive spots like
health centers and
schools
Visual observation
and discussion with
residents and
workers
Once in a month
during construction
RM/Municiplaity/
DLPIU
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 113
Parameters/Indicato
r
Responsible
Implementing
Agency
Verifiable
Indicators
Verification
Methods
Schedule Responsible
Monitoring Agency
Measures to protect
water bodies from
pollution
Contractor/DLPIU/
DISC
Visual observation,
observation of open
defecation and waste
disposal around water
sources near
construction sites
Site inspection,
interview with local
people
Once in a month
during construction;
upon demand for
testing with field kit
RM/Municiplaity
Adequate technical
and environmental
supervision
CISC/DISC/DLPIU Adequate number of
technicians regularly at
site with ability to
implement labour based
road construction
concept
Check number and
type of technicians
available at site,
skill of work carried
out, discussion
Twice a month
during construction
CLPIU/CISC
Clean up and
reinstatement of the
construction sites
(camps, quarries)
Contractor/DISC/
DLPIU
Decommissioned sites
indicate no
adverse/residual
environmental impacts,
and are rehabilitated to
the satisfaction of the
supervisor and land
owners
Site observation;
comparing photos;
consultation with
land owners and
community based
organizations
At the end of
construction period
RM/Municiplaity
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 114
Table 86: Impact/Effect Monitoring of Pipalbhanjyang-Hayutar-Netrakali Road Sub-project
Parameters
/Indicator
Verifiable Indicators Verification
Methods
Location Schedule Responsible
Implementation and
Monitoring Agency
Slope stability
and
erosion
Inclination, slope failures, causes;
drainage facilities such as catch
drain, side drains and functionality
of cross drainage structures; fresh
gullies and erosion; success/failure
of bio-engineering solutions
Site observation, photos
discussion with people
and technicians
Near steep slopes and
at landslide areas and
sites
Continuously
during
construction and
operation
DLPIU during
construction; District
Soil Conservation
Office during operation
Bio-engineering
of disturbed
slopes
Re-vegetation through bio-
engineering application on disturbed
slope; establishment of nursery
Site observation;
inspection of nursery
and its production rate,
photos, measurements
Cut slope area, where
vegetation is cleared;
nursery sites
During and at the
end of Sub-
project
construction
DLPIU
Disposal of spoils
and construction
wastes
Affected aesthetic value, affected
forest and agriculture land, initiated
land erosion by local blocked
drainage, hazard to downhill slope
residents and agricultural lands
Site observation and
interviews, photos, geo-
referencing sites
At specific locations
where such sites
occur
During
construction
DLPIU
Loss or
degradation of
farmland, houses
and properties
Status of road side land;
production/yield;
status of road side houses; status of
standing crop along alignment
Observation, data
collection and analysis
and interview with
stakeholders
Road side land and
houses
During
construction
DLPIU
Water quality Observation of open defecation and
waste disposal around water
sources near construction sites
Visual observation Local streams During
construction;
upon demand for
testing with field
kit
DLPIU
Air quality Dust level in ambient air Visual inspection At construction sites
and at sensitive spots
During
construction
DLPIU
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 115
Parameters
/Indicator
Verifiable Indicators Verification
Methods
Location Schedule Responsible
Implementation and
Monitoring Agency
Forest and
vegetation
Numbers of trees, presence of
ground vegetation, signs of illicit
logging and extraction of NTFPs
Observations, DFO
/CFUGs/LHFUG
records, photos
In and around the
construction sites,
markets
During
construction and
Operation
DLPIU/DFO during
construction;
DFO during operation
Wildlife Wildlife hunting and poaching by
work force, trade of wildlife, road
accidents inflicting wildlife
Interview with local
people/CFUGs/LHFUG
DFO and observations
Forest areas at
roadside
Twice a year
during
construction and
routine during
operation
DLPIU/DFO/CFUGs
during construction;
DFO/CFUGs/LHFUG
during operation
Change in
economy
Numbers of people employed by the
project during construction,
numbers of women in work forces
Records kept by the
project management,
discussion with
stakeholders
Sub-project area Trimester during
construction
phase
DLPIU
Trade and
commerce
Numbers of shops increased or
decreased, rental of houses and
land spaces
Records, interviews,
observations, photos
Throughout sub-
project area
Once in a year DLPIU/Municipality/RM
Occupational
safety and hazard
Type and number of accident
occurred during construction;
adequacy of occupational safety
measured provided; compensation
provided in case of fatal accidents
Observations, photos,
spot checks,
contractors and health
centre records interview
with workers
Throughout sub-
project area
During
construction
DLPIU
Change in socio-
economic
structure
Number and extent of new
settlements/types and ethnic
groups; nos. and extent of new
businesses; nos and extent of new
services and utilities, social conflicts
Observations, interview
with local people, then
local bodies record
Throughout sub
project area
During operation DLPIU/Municipality/RM
Ribbon
settlement
Congestions to road users and nos.
of accidents, RoW encroachment
Records, observations Throughout sub
project area
During operation DLPIU/Municipality/RM
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 116
9.7. Grievance Redress Mechanism
284. The objective the grievance redress mechanism (GRM) is to resolve complaints as
quickly as possible and at the local level through a process of conciliation; and, if that is not
possible, to provide clear and transparent procedures for appeal. A well-defined grievance
redress and resolution mechanism will be established to resolve grievances and complaints
in a timely and satisfactory manner. All affected persons will be made fully aware of their
rights, and the detailed grievance redress procedures will be publicized through an effective
public information campaign. The grievance redress process includes four levels:
285. First level of GRM: The first level and most accessible and immediate contact for
the fastest resolve of grievances are the contractors, and design and supervision consultants
on site. Prior to construction of any works, the CLPIU and DLPIU will ensure local
community meetings are held to notify local residents and businesses of any temporary
disturbances, and to inform them of the Project. If a local area committee (LAC) exists in the
area, they should also be informed. If any complaints arise, the contractors, consultants, and
DLPIU can immediately resolve the complaint on site. The CLPIU can also be involved in
grievance redress at this stage. The CLPIU and DLPIU office phone number will be posted
in public areas within the sub-project areas and construction sites. Any person with a
grievance related to the project works can contact the project to file a complaint. The DLPIU
offices will have a safeguards focal person to field and resolve complaints. The safeguards
(environment and resettlement) focal person will document the complaint, and immediately
address and resolve the issue with the contractor within 1-2 days, if the complaint remains
unresolved at the field level. The DLPIU may seek the assistance of the consultant
safeguards specialists (the environmental specialist or social safeguards specialist) to
resolve the issue. The DLPIU safeguards focal person will notify the CLPIU safeguards focal
person that a complaint was received, and whether it was resolved. The DLPIU safeguards
focal person will fully document the following information: (i) name of the person; (ii) date
complaint was received; (iii) nature of complaint; (iv) location, and (v) how the complaint was
resolved.
286. Second level of GRM: if the grievances remain unresolved; the DLPIU will forward
the complaint to the CLPIU safeguards focal person. The person filing the grievance will be
notified by DLPIU safeguards focal person that the grievance was forwarded to the CLPIU
safeguards focal person. The CLPIU will address the grievance. Grievances will be resolved
through continuous interactions with affected persons, and the CLPIU will answer queries
and resolve grievances regarding various issues including environmental or social impacts.
Corrective measures will be under taken at the field level by the CLPIU safeguards focal
person within 7 days. He/she will fully document the following information: (i) name of the
person; (ii) date complaint was received; (iii) nature of complaint; (iv) location and (v) how
the complaint was resolved.
287. Third level of GRM: if the grievance remain unresolved, the PIU’s project director
will activate the third level of the GRM by referring the issue (with written documentation) to
a Grievance Redress Committee (GRC) constituted by the EA, which will, based on review
of the grievances, address them in consultation with CLPIU, DLPIU, and affected persons.
The GRC will consist of EA leadership, affected persons, and local area committee, among
others—determined to provide impartial, balanced views on any issues. The GRC should
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 117
consist of at least five persons. A hearing will be called with the GRC, if necessary, where
the affected person can present his/her concern and issues. The process will promote
conflict resolution through mediation. The GRC will meet as necessary when there are
grievances to be addressed. The GRC will suggest corrective measures at the field level and
assign clear responsibilities for implementing its decision within 15 days. The functions of the
GRC are as follows: (i) to provide support to affected persons on problems arising from
environmental or social disruption, asset acquisition (where required), and eligibility for
entitlements compensation, and assistance; (ii) to record grievances of affected persons,
categorize and prioritize them, and provide solutions within 15 days; and (iii) to report to the
aggrieved parties developments regarding their grievances and decisions of the GRC.
288. Fourth level of GRM: In the event that a grievance is not addressed by the
contractor, DISC, CLPIU, DLPIU or GRC, the affected person can seek legal redress of the
grievance in the appropriate courts, the fourth level of the GRM, which is the formal legal
court system. The GRM however does not prevent affected persons from seeking legal
redress at any time. The grievance redress mechanism and procedure is depicted in Figure
9 below.
Note: CLPIU- Central Level Project Implementation unit, DLPIU- District Level Implementation Unit, DSC- Design
and Supervision Consultant, CISC- Central Implementation Support Consultant, DISC- District Implementation
Support Consultant
Figure 9: Flow Diagram for Grievance Redress Mechanism
289. Safeguard monitoring reports will include the following aspects pertaining to progress
on grievances: (i) number of cases registered with the GRC, level of jurisdiction (first,
second, and third levels), number of hearings held, decisions made, and the status of
Grievance
2nd Level Grievance
3rd Level Grievance
1st Level Grievance
First Level:
Contractor,
DISC, DLPIU
CLPIU, CISC
4th Level Grievance
Grievance
Redressed
Committee
Grievance
Redressed
Grievance
Redressed
Grievance
Redressed
Higher
Authority/Court
of Law
Not redressed
Not redressed
Not redressed
1-2 days
7 days
15 days
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 118
pending cases; and (ii) lists of cases in process and already decided upon may be prepared
with details such as affected person, date of notice, date of application, date of hearing,
decisions, remarks, actions taken to resolve issues, and status of grievance (i.e. open,
closed, pending).
290. All costs involved in resolving the complaints (meetings, consultations,
communication and reporting / information dissemination) will be borne by the project
291. ADB’s accountability mechanism will also be explained to affected households.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 119
10. Conclusion and Recommendation
292. The IEE study of the proposed Pipalbhanjyang-Hayutar-Natrakali road sub-project
does not pass through any environmentally sensitive areas and has minimal adverse
impacts. Most of the adverse impacts predicted are of low significance and short term, as
well as of reversible nature. The beneficial impacts that come with the facility of access to
market centers and the location of social services will enhance the productivity of the area
and improve the quality of life of the people. In addition, local people will get direct
employment as workers, which will contribute significantly to improving their livelihood.
These benefits from the implementation of the proposed road sub-project are more
significant and long term in nature compared to the adverse impacts, most of which can be
mitigated or avoided. Relevant issues raised during public consultation have also been
addressed in the mitigation measures.
293. The project attracts clause 1 and 2 of schedule 1 pertaining to section 3 of working
procedure relating environmental impact assessment for reconstruction of the earthquake
affected structure, 2016. And the IEE has shown that none of the anticipated environmental
impacts of rehabilitating the road are significant enough to need a detailed follow-up EIA
294. The proposed road sub-project is recommended for implementation with
incorporation of mitigation measures and the environmental management plan.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 120
References
Asian Development Bank. (2009). Safeguard Policy Statement. Manila: ADB. Department of Road. (2007). Environmental and Social Management Framework, a
guideline to the environmental and social issues associated with new road construction and upgrading. Kathmandu: Ministry of the Physical Planning and Works.
Asian Development Bank. (2015). Earthquake Emergency Assistance Project: Resettlement Framework:. Manila: ADB.
Asian Development Bank. (2015). Environmental Assessment and Review Framework: Earthquake Emergency Assistant Project. Manila: ADB.
Central Bureau of Statistics. (2011). National Population and housing census. Kathmandu: CBS.
Department of Road. (2003). Reference manual for the Environmental and Social aspects of the Integrated Road Development. Kathmandu: Ministry of Physical Planning and Works.
Dhital, MR. (2015). Geology of Nepal Himalaya, Regional Geology Reviews. Switzerland: Springer International Publishing.
Dobremez, J. (1976). Nepal Ecologie et Biogeography. Paris, France: Editions du Centre national de la Recherche Scientifique.
Ministry of Law, Justice and Parliamentary Affairs. (1992). Water Resources Act. Kathmandu: Law Books Management Board.
Ministry of Law, Justice and Parliamentary Affairs. (1993). Water Resources Regulation. Kathmandu: Law Books Management Board.
Ministry of Law, Justice and Parliamentary Affairs. (1999). Local Self Governance Act. Kathmandu: Law Books Management Board.
Ministry of Law, Justice and Parliamentary Affairs. (2000). Local Self-Governance Regulations. Kathmandu: Law Books Management Board.
Ministry of Law, Justice and Parliamentary Affairs. (2011). Solid Waste Management and Resource Mobilization Act. Kathmandu: Law Books Management Board.
Ministry of Law, Justice and Parliamentary Affairs. (2012). Solid Waste Management and Resource Mobilization Regulation. Kathmandu: Law Books Management Board.
Ministry of Law, Justice and Parliamentary Affairs. (2015). Constitution of Nepal 2072. Kathmandu: Law Books Management Board.
NRA. (2016). Grievance Management Procedure for Reconstruction of Earthquake Affected Structures. Kathmandu: National Reconstruction Authority.
Upreti, B. K. (2003). Safeguarding the resources Environmental Impact Assessment process and Practice. Kathmandu.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 121
APPENDICES
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 122
Appendix I: Approved ToR for IEE Study
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 123
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 124
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 125
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 126
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 127
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 128
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 129
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 130
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 131
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 132
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 133
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 134
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 135
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 136
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 137
Appendix II: Climate Change Checklist
Checklist for Preliminary Climate Risk Screening
Screening Questions Score Remarks
Location
and Design
of Project
Is siting and/or routing of the
project (or its components) likely
to be affected by climate
conditions including extreme
weather-related events such as
floods, droughts, storms,
landslides?
1
There are landslide-prone
areas at very specific places
along the entire length of the
road. These slopes may be
risky during months of
incessant rainfall.
Would the project design (e.g.
the clearance for bridges) need
to consider any hydro-
meteorological parameters (e.g.
sea-level, peak river flow,
reliable water level, peak wind
speed etc.)?
1
During months of heavy
downpour, the rivers along
the road section have a high
probability of being
inundated, which might pose
serious problems.
Materials
and
Maintenance
Would weather, current and
likely future climate conditions
(e.g. prevailing humidity level,
temperature contrast between
hot summer days and cold
winter days, exposure to wind
and humidity, hydro-
meteorological parameters)
likely affect the selection of
project inputs over the life of
project outputs (e.g.
construction materials)?
0
Steel and RCC structures
will seldom be used during
construction. Therefore, the
contraction and expansion
of such materials can be
discounted. Even during
extreme conditions such as
heavy rainfall, construction
materials are not under any
major threat of
disintegration.
Would weather, current and
likely future climate conditions
and related extreme events
likely affect the maintenance
(scheduling and cost) of project
output(s)?
0
Maintenance, being a
manual job, will be difficult
during weather extremes
such as soaring mid-
summer temperatures and
sub-zero winter
temperatures.
Performance
of Project
Would weather/climate
conditions and related extreme 1
Even if high quality control is
achieved, the performance
Project Title: Earthquake Emergency Response Program (EEAP) Sub-Project Sector: Sub-Sector: Division/Department:
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 138
Output(s) weather events likely affect the
performance (e.g. annual power
production) of project output(s)
(e.g. hydropower generation
facilities) throughout their design
lifetime?
of the road will likely be
affected due to fluctuating
weather phenomena.
Options for answers and corresponding score are provided below:
Response Score
Likely Not 0
Likely 1
Very Likely 2
Responses when added that provide a score of 0 will be considered low risk project. If
adding all responses will result to a score of 1-4 and that no score of 2 was given to any
single response, the project will be assigned a medium risk category. A total score of 5 or
more (which include providing a score of 1 in all responses) or a 2 in any single response will
be categorized as high risk project.
Result of Initial Screening (Low, Medium, High): Medium
Other comments:
Prepared by: ______________________________________________
1
If possible, provide details on the sensitivity of project components to climate conditions, such as how
climate parameters are considered indesign standards for infrastructure components, how changes in
key climate parameters and sea level might affect the siting/routing of project, the selection of
construction material and/or scheduling, performances and/or the maintenance cost/scheduling of
project outputs.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 139
Appendix III: Rapid Environmental Assessment (REA) Checklist
Rapid Environmental Assessment (REA) Checklist: (Transport Infrastructure)
Instructions:
(i) The IA completes this checklist to support the environmental classification of a project.
It is to be attached to the environmental categorization form and submitted to ADB.
(ii) This checklist focuses on environmental issues and concerns. To ensure that social
dimensions are adequately considered, refer also to ADB's (a) checklists on involuntary
resettlement and Indigenous Peoples; (b) poverty reduction handbook; (c) staff guide to
consultation and participation; and (d) gender checklists.
(iii) Answer the questions assuming the ―without mitigation‖ case. The purpose is to
identify potential impacts. Use the ―remarks‖ section to discuss any anticipated mitigation
measures.
Project Title:
Sub-project:
IA:
SCREENING QUESTIONS Yes No REMARKS
A. Project sitting
Is the project area adjacent to or within any
of the following environmentally sensitive
areas?
Cultural heritage site No cultural heritage sites.
Protected area No protected areas.
Wetland No wetlands.
Mangrove No mangroves.
Estuarine No estuaries.
Buffer zone of protected area Project site does not fall in any
buffer zone.
Special area for protecting biodiversity No special area for biodiversity
protection.
B. Potential environmental impacts
Will the project cause…
Encroachment on historical/cultural
areas; disfiguration of landscape by road
embankments, cuts, fills, and quarries?
No historical/cultural area
Earthquake Emergency Assistance Project (EEAP)
Pipal Bhanjyang-Haitar-Netrakali Road Rehabilitation and Reconstruction
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 140
SCREENING QUESTIONS Yes No REMARKS
Encroachmenton precious ecology (e.g.
sensitive or protected areas)?
No encroachment.
Alteration of surface water hydrology of
waterways crossed by roads, resulting in
increased sediment in streams affected
by increased soil erosion at construction
site?
The existing road is muddy
throughout, which poses
problems as heavy rain
causes erosion along the hill
slopes, which consequently
increases sediment deposit
in the existing water sources.
Deterioration of surface water quality due
to silt runoff and sanitary wastes from
worker-based camps and chemicals used
in construction?
No haphazard waste dumping
from camping sites.
Increased local air pollution due to rock
crushing, cutting and filling works, and
chemicals from asphalt processing?
Very insignificant level of air
pollution.
Risks and vulnerabilities related to
occupational health and safety due to
physical, chemical, biological, and
radiological hazards during project
construction and operation during project
construction and operation?
No such hazards are present.
Noise and vibration due to blasting and
other civil works?
Minor vibrations only on the
road during excavator usage;
insignificant effect on
surrounding households.
Dislocation or involuntary resettlement of
people?
No involuntary resettlement of
people
Dislocation and compulsory resettlement
of people living in right-of-way?
7 structuresin total that are
affected directly.
Disproportionate impacts on the poor,
women and children, Indigenous Peoples
or other vulnerable groups?
No such discrimination.
Other social concerns relating to
inconveniences in living conditions in the
project areas that may trigger cases of
upper respiratory problems and stress?
Absence of such conditions.
Hazardous driving conditions where
construction interferes with pre-existing
roads?
Road clearing has created a
very muddy landscape along
certain sections of the road,
especially during monsoon.
Also, there are landslide prone
areas in certain parts long the
road that might prove
hazardous for commuters.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 141
SCREENING QUESTIONS Yes No REMARKS
Poorsanitation and solid waste disposal
in construction camps and work sites,
and possible transmission of
communicable diseases (such as STI's
and HIV/AIDS) from workers to local
populations?
No such conditions are
present.
Creationof temporary breeding habitats
for diseases such as those transmitted by
mosquitoes and rodents?
No immediate problems but if
population influx increases
alongside the rehabilitation,
then the resulting density and
pollution might entail breeding
sites for mosquitoes and
rodents.
Accident risks associated with increased
vehicular traffic, leading to accidental
spills of toxic materials?
No vehicle numbers and there
is no such problem.
Increased noise and air pollution resulting
from traffic volume?
No such conditions.
Increased risk of water pollution from oil,
grease and fuel spills, and other materials
from vehicles using the road?
No such problems.
Social conflicts if workers from other
regions or countries are hired?
Unlikely, as all workers are
hired locally.
Large population influx during project
construction and operation that causes
increased burden on social infrastructure
and services (such as water supply and
sanitation systems)?
Very unlikely for the creation
of such circumstances.
Risks to community health and safety due
to the transport, storage, and use and/or
disposal of materials such as explosives,
fuel and other chemicals during
construction and operation?
No risks to community health
as no harmful and/or
hazardous chemicals will be
used.
Community safety risks due to both
accidental and natural causes, especially
where the structural elements or
components of the project are accessible
to members of the affected community or
where their failure could result in injury to
the community throughout project
construction, operation and
decommissioning.
No such safety risks as all
existing structures are well
designed and there are
engineering measures in
place (gabion wall, breast
wall) in case of natural
calamities such as
landslides.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 142
Appendix IV: Environmental Checklist
a:tL :tl/o ;'rgf ;+sng
;f]n'v'Da' lhNnfsf] ufdf{—g]n]—af]un ;8ssf]]] k|f/lDes jftfj/0fLo kl/If0f
!= a:tLsf] hfgsf/L
s= a:tLsf] gfdM v= xfnsf] uf=kf=÷g=kf M
u= xfnsf] jf8{ g+= M 3= ;flas ufla;÷ g=kf, jf8{ g+=
ª = 3/w'/L ;+VofM r = hDdf hg;+Vof
5= dlxnf ÷k'?if hg;+VofM
@= ;fdflhs tYofÍ
s|=; laa/0f 3/w'/L ;+Vof wd{
s= d'Vo hfthftL
!=!
!=@
!=#
!=$
!=%
!=^
!=&
!=*
v= a;fO;/fO{ 3/w'/L ;+Vof s}lkmot
@=! Ps k':tf cuf8L b]lv
@=@ @) – #) jif{ cufl8 b]lv
@=# xfn} - ! b]lv @) jif{ cufl8 _
@=$ s]lx aif{ clu o; 7fFp 5f]8]sf kl/jf/
u= k]zf 3/w'/L ;+Vof s}lkmot
#=! s[lif
#=@ Aofkf/
#=# gf]s/L
#=$ Hofnf dhb'/L
#=% a}b]lzs /f]huf/
#=^ laBfyL{
#=& cGo
3 lhlasf]kfh{g 3/w'/L ;+Vof s}lkmot
$=! cfDbfgLn] vfg k'uL art ;d]t x'g]
$@ h;f]t;f] vfg k'Ug]
$=# Vffg gk'Ug]
ª 3/sf] ;+/rgf 3/w'/L ;+Vof s}lkmot
%=! kSsL
%@ sRrL
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 143
#= :jf:Yo ;]jf
s|=; :jf:Yo
;:yfsf] gfd
:yfg b'/L sd{rf/L
;+Vof
pknAw
;]jfx?
cfuGt's la/fdL
;+Vof
b]lvg] d''Vo /f]ux?
!=
@=
#=
$=
$ lzIff ;]jf
$=! z}lIfs ca:yf
hg;+Vof -g+= jf Ü_ lg/If/ k|fyflds tx dfWoflds tx :gfts jf ToFxf eGbf dfly
k'?if
dlxnf
$=@ z}lIfs ;+:yfx?
s|= ;= :s'nsf] gfd k|sf/ -
;/sf/L÷gLlh_ tx
laBfyL{
;+Vof
b'/L jf k'Ug
nfUg] ;do 7]ufgf
!=
@=
#=
%= vfg]kfgL tyf ;/;kmfO{
s= Vffg]kfgLsf] cfk'lt{
nfeflGjt 3/w'/L -Ü_
;fd'bflos wf/f Vff]nfsf] kfgL d'n÷Ogf/÷s'jf kfO{k cGo
v= rkL{
nfeflGjt 3/w'/L -Ü_
rkL{ gx'g] rkL{ x'g]
:yfO{ c:yfO{
3/ leq 3/ aflx/ vfN8] rkL{ cGo
u= kmf]xf]/ d}nfsf] Aoa:yfkg
nfeflGjt 3/w'/L -Ü_
uNg] kmf]xf]/ guNg] kmf]xf]/
sDkf]l:6Ë cGo hnfpg] ;fa{hlgs
:yfgdf km\ofSg]
gu/kflnsfnfO{
k7fpg]
cGo
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 144
^= cGo ;]jfx?
;]jfx?
s=vfgf ksfpg] OGwg
nfeflGjt 3/w'/L -Ü_
bfp/f u'O7f Affof] Uof; Pn=lk=lh cGo
v= phf{÷ aQL
nfeflGjt 3/w'/L -Ü_
dl§t]n lah'nL aQL ;f]nf/ cGo cGo
u= ;+rf/ ;]jf
n]g nfOg g]kfn 6]lnsd Pg ;]n x'nfs ;]jf cGo
3= ahf/
!= :yfO{ ahf/ If]q
;+Vof gfd k|sf/ b'/L
@= c:yfO{ ahf/ If]q
;+Vof gfd k|sf/ b'/L
ª= sn sf/vfgf
7'nf] dWood ;fgf] cGo cGo
r= xf]6n, nh÷k;n÷cGo -;+Vofdf_
xf]6n tyf
nh
/]i6'/]G6 lrof k;n ls/fgf k;n cGo -:6];g/L, s:d]l6s,
cf}iflw, km]G;L, xf8{jo/, :kf]6{
df;' k;n, cflb_
5=lalQo ;+:yfx? -;+Vof_
a}s nB'laQ ;xsf/L cGo
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 145
&= hUuf hdLgsf] ca:yf
hUuf
hdLg
@) /f]kgL
eGbf dfly
!) b]lv @)
/f]kgL ;Dd
% b]lv !)
/f]kgL ;Dd
% /f]kgL ;Dd hUuf hdLg gePsf]
-;'s'Daf;L_
3/w'/L
;+Vof
l;+rfO{sf] ca:yf
l;+rfO{sf] ;'lawf ePsf] hdLg -Ü_ l;+rfO{sf] ;'lawf gePsf] hdLg -Ü_
*= ;fd'bflos k|of]hgsf eagx?÷:yfgx?
;fd'bflos eag÷:yfgx?sf]
gfd
ca:yf Aff6f] la:tf/n] c;/ kfg]{÷gkfg]{
(= o; If]qdf nufOg]] k|d'v afnLx?
!)= o; If]qdf u/Lg] k|d'v kz'kfngx?
!!= o; If]qdf kfOg] k|d'v af]6 la?jfx?
!@= o; If]qdf kfOg] k|d'v h+unL hgfj/x?
!#= o; If]qdf kfOg] k|d'v r/fr'?ËLx?
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 146
!$= o; If]qdf kfOg] k|d'v df5fsf k|hfltx?
!%=o; If]qdf kfOg] ;/L;[a k|hfltx?
!^= k|d'v d7dlGb/ tyf ;f:s[lts w/f]x/x? / To;sf] P]ltxfl;s dxTj
!&= o; If]qdf /x]sf] jf ;DefAo cfly{s pGgtLsf If]qx?
!*= cfof]hgfn] kfg]{ ;sf/fTds k|efj jf kmfObfx?
!(= cfof]hgfn] kfg]{ gsf/fTds k|efj jf c;/x?
@)= cfof]hgf k|lt hg;d'bfosf] wf/0ff
@!= cfof]hgf k|lt tkfO{sf] ;Nnfxf ;'emax?
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 147
Appendix V: Public Notice
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 148
English Translation Of Public Notice
Government of Nepal
Ministry of Federal Affairs and Local Development
Earthquake Emergency Assistance Project (EEAP)
District Level Project Implementation Unit
Sindhuli
Public Notice for Comments and Suggestion on the Initial Environmental Examination
(IEE)
(Date of First Publication: 2017/09/09)
The Earthquake Emergency Assistance Project (EEAP) is a project being implemented by loan assistance
from Asian Development Bank (ADB) and technical assistance from Swiss Agency for Development and
Cooperation (SDC), counterpart funding from Government of Nepal (GoN) for reconstruction and
rehabilitation of local roads. District Level Project Implementation Unit, Sindhuli, being the proponent of
Pipalbhanjyang-Hayutar-Netrakali Road, has prepared Draft Initial Environmental Examination (IEE)
report and this notice has been published for the implementation of report as per the provision of the
Section 12 (2) of the Working Procedure relating to Earthquake Affected Structure 2016 (Second
Amendment 2017).
Proponent: District Level Project Implementation Unit, Sindhuli.
Affected Rural Municipality and Municipality: Kamalamai Municipality and Ghyanglekh Rural
Municipality
Proposal Description: The proposed road sub-project starts from Pipalbhanjyang of Kamalamai
Municipality-2 (then Bhadrakali VDC-3) and ends at Majhitar of Ghyanglekh Rural Municipality-3 (then
Netrakali VDC-3). The total length of road is 37.20 km and width is 6.25 m with drainage.
Venue for Meeting: Ghyanglekh Rural Municipalaity-1, Rajbas.
Date: 14 September, 2017
As per Section 12 (3) of the working procedure, concerned rural municipality, municipality, school, health
post, forest user group, concerned stakeholders, organization and local people are requested to present at
Ghyanglekh Rural Municipalaity-1, Rajbas on 14 September, 2017 for discussion environment impacts,
information on reconstruction, resettlement and relocation through the implementation of sub-project. The
concerned people or organization can obtain the draft IEE report from District Coordination Committee,
Sindhuli; District technical Office, Sindhuli; District Level Project Implementation Unit, Sindhuli and
Earthquake Emergency Assistance Project (EEAP)- Central Level Project Implementation Unit, Lalitpur as
per section 12 (5) of the working procedure
It is requested to send the comments and suggestions within 7 days of notice publication at national daily
newspaper. Accordingly, the comments and suggestions can also be sent to National Reconstruction
Authority, Ministry of Federal Affairs & Local Development, Singhadurbar, Kathmandu
Address to send comments and suggestions:
Central project Implementation Unit, Earthquake
Emergency Assistance Project (EEAP), Lalitpur
Telephone no: 01-5260565
Email: [email protected]
District Level project Implementation Unit
Earthquake Emergency Assistance Project
, Sindhuli
Telephone no: 047-520109
Email:[email protected]
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 149
Appendix VI: Project Cost
a. Total Civil Cost
Cost Estimate of Contract Package 01 NRS
Base Cost 193,924,050.58
VAT (13%) 25,210,126.58
Total Cost including Base Cost and VAT 219,134,177.16
Cost per KM as per Base Cost and VAT 15,217,651.19
Work Charge Staff and Small Miscellaneous Expenses (3%) 5,817,721.52
Provision of Physical Contingency (10%) 19,392,405.06
Total Cost including Base Cost, VAT, Work Charge Staff and
Physical Contingency
244,344,303.73
Cost Estimate of Contract Package 02
Base Cost 219,583,979.43
VAT (13%) 28,545,917.33
Total Cost including Base Cost and VAT 248,129,896.76
Cost per KM as per Base Cost and VAT 16,664,197.23
Work Charge Staff and Small Miscellaneous Expenses (3%) 6,587,519.38
Provision of Physical Contingency (10%) 21,958,397.94
Total Cost including Base Cost, VAT, Work Charge Staff and
Physical Contingency
276,675,814.08
Cost Estimate of Contract Package 03
Base Cost 203,252,800.20
VAT (13%) 26,422,864.03
Total Cost including Base Cost and VAT 229,675,664.23
Cost per KM as per Base Cost and VAT 28,713,047.16
Work Charge Staff and Small Miscellaneous Expenses (3%) 6,097,584.01
Provision of Physical Contingency (10%) 20,325,280.02
Total Cost including Base Cost, VAT, Work Charge Staff and
Physical Contingency
256,098,528.25
Grand Total 777,118,646.06
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 150
b. Total Sub-project oCst
SN Particulars Amount (NRs.)
1.1 Environmental Management Cost
1.1.1 Environmental Awareness raising** training 350,000.00
1.1.2 Compensatory plantation & protection cost for trees on CF and private land 3,370,788.35
1.1.3 Road side plantation 450,000.00
1.1.4 Road safety and informative signboard 100,000.00
1.1.5 Environmental monitoring cost 325,000.00
Sub-total (i) 4,595,788.35
1.2 Other environmental cost( included in civil works cost also)
1.2.1 Occupational health and safety (GPA insurance) 1,658,163.47
1.2.2 Bioengineering works 5,827,259.86
Sub-total (ii) 7,485,423.33
Total (i+ii) 12,081,211.68
2 Civil Work Cost
2.1 Total civil work cost 777,118,646.06
2.2 Other environmental cost included in civil work cost (as given in item 1.2
above) for occupational health & safety, bioengineering works, toe wall for
spoil management
7,485,423.33
2.3 Civil work cost excluding occupational health & safety and bioengineering for
management (B)
769,633,222.74
3 Resettlement Cost
3.1 DIRECT COST
3.1.1 Compensation for Private Land 11,552,405.89
3.1.2 Total structures 61,21,520.24
3.1. 3 Allowances 150,000
3.1.4 Compensation for private Trees 43,726.41
3.1.5 Private Fruits 405,500.00
3.1.6 Broom Grass 2,000.00
3.1.7 Bamboo 124,575.00
3.1.8 Compensation for Agriculture Crops 300,817.50
Sub Total (A) 18700545.04
3.2 INDIRECT COST
3.2.1 Deed Transfer Fees 155,200.00
3.2.2 Deed Transfer Assistance 242,000.00
3.2.3 Income Generation and Livelihood Improvement Program 2,800,000.00
Sub Total (B) 3,197,200.00
3.3 Contingency (20%) for indirect costs only (C) 3,740,109.01
GRAND TOTAL (A+B+C) 25,637,854.05
Sub-total (C) 25,637,854.05
4 Gender Equality & Social Inclusion Cost
4.1 Disaster preparedness works session visual/ documentary show on D & RM 100,000.00
4.2 Campaign program (Awareness program on CLS IT) 100,000.00
Sub-total (D) 200,000.00
Grand Total Sunb-project Cost (A+B+C+D) 807,552,288.46
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 151
Appendix VII: Meeting Minutes and Public Disclosure
a. Public consultation
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 152
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 153
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 154
b. IEE Disclosure
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 155
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 156
c. Findings of Public Consultation and IEE Disclosure
Summaries of Public Consultation
Date Place for
Public
Meeting
Participants Issues/ Queries/ Concerns/ Demands
2074/04/28
B.S
(12/08/2017
A.D)
Bhoteswahara,
Kamalamai
Municipality-2
(Former:
Bhadrakali
VDC-9)
13 There are many rivers around the
settlement such as Chisapani Khola,
Dhanamana Khola, Taru Khola, Langdi Khola,
and Simle Khola. These rivers become
swollen during periods of heavy downpour.
Therefore, construction of an RCC bridge is
essential.
The private lands that fall within the
formation width must be compensated for
fairly.
Irrigation canals will also likely be
damaged during road reconstruction phase.
Therefore, the construction of those canals is
of high priority.
The Dhanamana Khola borders the
south bank of this settlement. During heavy
rainfall, the river swells up and causes
significant damage to the road as well as the
settlement. Therefore, construction of a dam
at this location is necessary.
2074/04/30
B.S
(14/08/2017
A.D)
Chandanpur/B
astipur,
Ghyanglekh
Rural
Municipality-2
(Former:
Bastipur-6)
7 Talks of road rehabilitation and
reconstruction have been going on for a while
now, but there has not been any progress
towards achieving this goal. So, the project
should go forward without further delay.
Locals involved in commercial farming
have been dejected at the delay in
reconstruction. The farmers would be elated if
the project picked up pace as soon as
possible.
During the course of reconstruction,
technical examinations must be done at major
rivers such as Thade Khola, Marin Khola etc.
as a bridge is absolutely essential over these
rivers.
The budget allocated for the project,
along with all relevant expenses, must be
public record.
Compensation for all affected land
holders and home owners must be
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 157
Date Place for
Public
Meeting
Participants Issues/ Queries/ Concerns/ Demands
guaranteed.
2074/04/30
B.S
(14/08/2017
A.D)
Ghyanglekh
Rural
Municipality-2
(Former:
Bastipur-8,9)
10 (Mane
Bhanjyang
Leasehold
Forest (A, B)
Group)
The trees that are cleared during road
reconstruction must be accounted for and
afforestation must be done accordingly.
The land that is cleared from either
side of the road can pose a serious landslide
threat. Therefore, proper engineering
measures must be adopted in order to avoid
any possible calamities.
The funeral site for all the residents in
this settlement lies within the leasehold forest.
Therefore, the locals have requested the help
of concerned authorities in building a Gumba
so that the funeral processions are not
hindered.
Source: Field survey, 2017
Summaries of Issues Raised during IEE Disclosure
Blacktop is better than gravel for upgrading of road.
Due to construction of road the water pipe at Ch. 19+200 was affected so, proper
management should be done.
Compensation should be provided for the trees to be cut down.
Possibility of affecting Tunibhanjyang school Ghyanglekh - 1 and alternative Rajbas
school. So, protective measures should be used during construction.
Preservation of Sahid smriti park
Compensation for physical infrastructures should be given.
Proper management of irrigation.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 158
Appendix VIII: Deed of Inquiry(Muchulka)
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 159
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 160
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 161
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 162
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 163
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 164
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 165
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 166
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 167
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 168
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 169
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 170
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 171
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 172
Appendix IX: Recommendation
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 173
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 174
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 175
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 176
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 177
Appendix X: Consulted Person
SN Name Designation Address
1. Shyam sundar Mishra Acting Project Manager DTO, Sindhuli
2. Man bahadur Magar District Team Leader DISC
3. Dilli Sher Rai Sub-Engineer DISC
4. Rajan Adhikari Social Safeguard Officer DISC
5. Durga devi Sunuwar Vice – president Ghyanglekh RM
6. Sambhu bahadur yonjan Ghyanglekh RM Ward no 2
7. Ratna Bahadur Vice – Secretait Jhalkane CFUG
8. Gada bahadhur khetang Principal Shree Netrakali School
9. Bigyannath Sharma Principal Ma. Bhi. Pipalbhanjyang
10. Nar bahadur Bal Office helper Ghyanglekh RM ward no. 4
11. Dhan bahadur Bal Sub – Engineer Ghyanglekh RM ward no. 3
12 Surya ram Moktan Ranibas CFUG
13. Sanak bahadur waiba President Manebhanjyang Leasehold
Forest
14 Sunita Kumari Singha ANM Netrakali Health post
15 Sumsher bahadur
Sunuwar
Principal Shree Netrakali S.S,
Aapdanda
16 Sanjeev kumar Mukhiya HA Tamajor health post
17 Sunita Shrestha ANM Shree Bastipur Health post
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 178
Appendix XI: Trees to be Cut Down
a. Trees from Community Forest
Name of the Forest Chainage Species Scientific Name No. of
Trees
Compensatory
Plantation (1:25)
Rate/plant
(NRs)
Total Cost
(NRs) From To
Kalika Community
Forest, Kamalamai
Municipality
0+000
0+790
0+460
1+800
Chilaune Schima wallichii 1 25 151.12 3,778.00
Katus Castanopsis indica 2 50 7,556.00
Sub – Total 3 75 11,334.00
Jhalkane Community
Forest, Amale
10+250 11+000 Sal shorea robusta 29 725 109,562.00
Other 1 25 3,778.00
Chilaune Schima wallichii 2 50 7,556.00
Jhigane Eurya cerasifolia 4 100 15,112.00
Sajh Terminalia alata 3 75 11,334.00
Bhalayo Semecarpus
anacardium
1 25 3,778.00
Katus Castanopsis indica 1 25 3,778.00
Sub – Total 41 1025 154,898.00
Ranibas Community
Forest, Amale
14+760
18+900
17+000
19+040
Chilaune Schima wallichii 3 75 11,334.00
Sub – Total 3 75 11,334.00
Total 47 1175 177,566.00
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 179
b. Trees from Leasehold Forest
Name of the
Forest
Chainage
Species Scientific Name No. of
Trees
Compensatory
Plantation (1:25)
Rate/plant
(NRs)
Total
Cost
(NRs) From To
Mane
Bhanjang LF,
Bastipur
21+580 21+940 Sal shorea robusta 6 150 151.12 22668
Chilaune Schima wallichii 1 25 3778
Total 7 175 26446
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 180
c. Trees from Government Managed Forest
Name of the
Forest
Chainage Species Scientific Name No. of
Trees
Compensatory
Plantation
(1:25)
Rate/plant
(NRs)
Total Cost
(NRs) From To
Government
Forest,
Tamajor
27+180 29+000 Banjh Quercus lanata 12 300 151.12 45,336
Bot dhayaro Lagerstroemia parviflora 1 25 3,778
Chilaune Schima wallichii 136 3,400 513,808
Other 2 50 7,556
Jhigane Eurya cerasifolia 6 150 22,668
Katus Castanopsis indica 40 1,000 151,120
Mauwa Madhuca longifolia 1 25 3,778
Sal Shorea robusta 511 12,775 1,930,558
Sub – Total 709 17,725 2,678,602
Government
Forest,
Tamajor
29+300 30+600 Sal Shorea robusta 5 125 18,890
Katus Castanopsis indica 15 375 56,670
Chilaune Schima wallichii 75 1,875 283,350
Kalikath Myrsine semiserrata 1 25 3,778
Other 1 25 3,778
Bajh Quercus lanata 16 400 60,448
Amala Emblica officinalis 2 50 7,556
Jhigane Eurya cerasifolia 5 125 18,890
Mauwa Madhuca longifolia 3 75 11,334
Sub – Total 123 3075 464,694
Total 832 20,800 3,143,296
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 181
d. Trees from Private Land
Land
Type
Chainage Species Scientific Name No. of
Trees
Compensatory
Plantation (1:1)
Rate/plant
(NRs)
Total Cost
(NRs) From To
Private
Forest
0+000 29+200 Aanp Magnifera indica 3 3 62.95 188.85
Baans Bambusoideae 6 6 377.7
Chilaune Schima Wallichii 23 23 1447.85
Kalikath Myrsine semiserrata 3 3 188.85
Katus Castanopsis indica 3 3 188.85
Sal Shorea robusta 21 21 1321.95
Sisau Dalbergia sisoo 2 2 125.9
Berulo Ficus clavata 4 4 251.8
Ginari Pieris formosa 7 7 440.65
Khanayo Ficus semicordata 6 6 377.7
Koiralo Bauhinia variegata 8 8 503.6
Kutmiro Litsea polyantha 8 8 503.6
Pipal Ficus religiosa 1 1 62.95
Others 7 7 440.65
Utis Alnus nepalensis 5 5 314.75
Sub-Total 107 107 6735.65
Cultivated
Land
0+000 29+200 Aanp Magnifera indica 4 4 251.8
Amaro Spondias pinnata 2 2 125.9
Amba Psidium guava 1 1 62.95
Baans Bambusoideae 13 13 440.65
Bakaino Melia azedarach 8 8 377.7
Chilaune Schima Wallichii 91 91 503.6
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 182
Land
Type
Chainage Species Scientific Name No. of
Trees
Compensatory
Plantation (1:1)
Rate/plant
(NRs)
Total Cost
(NRs) From To
Dabdabe Garuga pinnata 3 3 62.95
Ginari Pieris formosa 2 2 62.95
Katahar Artocarpus integra 1 1 62.95
Katus Castanopsis indica 30 30 188.85
Khanayo Ficus semicordata 6 6 125.9
Khirro Sapium insigne 6 6 125.9
Kutmiro Litsea polyantha 6 6 188.85
Others 2 2 125.9
Sal Shorea robusta 58 58 188.85
Simal Bombax ceiba 3 3 62.95
Sisau Dalbergia sisoo 5 5 314.75
Angeri Lyonia ovalifolia 5 5 314.75
Utis Alnus nepalensis 4 4 314.75
Kutmiro Litsea polyantha 3 3 314.75
Lakuri Fraxinus floribunda 1 1 314.75
Mauwa Madhuca longifolia 8 8 314.75
Jhigane Eurya cerasifolia 4 4 314.75
Sub-Total 266 266 5161.9
Total 373 373 11897.55
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 183
e. Calculation of Plantation Cost in NF/CF/LF
Item No. Description Unit Total
quantity
Rate
(NRs.)
Amount
(NRs.)
Remarks
Seedling cost No 1760 20 35,200.00
20 Plantation per ha
20(1) Site selection and survey Persondays 3 500 1,500.00
20.2(b) Site clearance Persondays 10 500 5,000.00 25% shrubs and grasses
20.3 Fixing of pit distance (1600 pits) Persondays 3 500 1,500.00
20.5(a)i Pitting of 45X30X30 cm pit Persondays 32 500 16,000.00 50% slope
20.6(a)iii Seedling transportation Persondays 6 500 3,000.00 1 km distance
20.6(b)iii Seedling transportation (within) Persondays 3 500 1,500.00
20.7(a) Plantation Persondays 20 500 10,000.00 Up to 50% slope
32.1(b) Weeding Persondays 18 500 9,000.00
32.3 Replacement plantation (10%) Persondays 9 500 4,500.00
33.1(b) Prunning Persondays 25 500 12,500.00 Up to 50% slope
Sub-total 99,700.00
35 Fencing per 200 running meter
35.2(a)ii Preparation of 100 poles of 30-40cm girth and 1.8m height Persondays 8 500 4,000.00
35.4 Five line barbed wire fencing (100 running meter)
35.4(a) Barbed wire (14 gauge) Kg 143 125 71,500.00
Wooden pole (10cmx10cmx1.8m) No 88 No cost
Unail Kg 4.2 125 2,100.00
35.3(b) Pitting for poles Persondays 14 500 28,000.00
35.4(c) Stretching and tightening of barbed wire Persondays 24 500 48,000.00
Sub-total 153,600.00
Total 253,300.00
Contingency (5%) 12,665.00
Grand Total 265,965.00
Per plant cost 151.12 1600+10% plants with 2.5m x
2.5m spacing
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 184
f. Compensatory Plantation Agreement
Ifltk"lt{ a[Iff/f]k0f (Compensatory Plantation)
k[i7e"dL
e"sDk cfktsfnLg ;xfotf cfof]hgf (EEAP) PlzofnL ljsf; a}+ssf] ;x'lnotk"0f{ C0f ;xof]u,
:jL; ljsf; ;xof]u lgof]usf] k|fljlws ;xof]u tyf g]kfn ;/sf/ ;d]tsf] nufgLdf z'? ePsf] xf]
o; cfof]hgfsf] p2]Zo @)&@ a}zfv !@ ut]sf] e"sDk kl5 e"sDk If]qdf k"g;+/rgf / k"glg{df0f
sfo{df ;xof]u ug{' xf] . o; cfof]hgfn] ljBfno, ;8s, ;/sf/L ejg k"glg{df0f ul/ ;Defljt
k|sf]kaf6 ;dfg's"ng ug{' /x]sf] 5 . of] sfo{s|d k"g;+/rgf / k"glg{df{0f sfo{k2tLdf cfwfl/t /xg]
5 . o;n] ;8s If]qsf e"sDk k|efljt hgtfnfO{ ;xhtf k|bfg ug]{5 . l;Gw'nL lhNnfdf cjl:yt
k|:tfljt ;8s pk–cfof]hgf e"sDk cfktsfnLg ;xfotf cfof]hgf (EEAP) cGtu{t ;+rfng ug{
nfuLPsf] Ps pkcfof]hgf xf] .
lkkne~Hofª – xfo'6f/ – g]qsfnL ;8s pk–cfof]hgf l;Gw'nL lhNnfsf] sdnfdfO{ gu/kflnsfsf]
lkkne~Hofªaf6 z'? eO{ Wofªn]v ufFpkflnsfsf] dfemL6f/df df 6+'luG5 . of] ;8ssf] rf}8fO{ ^=@%
dL= / hDdf nDafO{ #&=@) ls=dL= kb{5 .
;fGb{lestf
/fli6«o k|fyldstf k|fKt of]hgfsf] nflu /fli6«o jg If]q k|of]u ug]{ ;DaGwL sfo{ljlw, @)&$ cg';f/
lkkne~Hofª – xfo'6f/ – g]qsfnL ;8s pk–cfof]hgfsf] lgdf{0f s|ddf sfl6g] ?vx?sf] Ifltk"lt{
;DaGwdf hlt ?v sfl6G5g To;sf] !M@% cg'kftdf Ifltk"lt{ a[Iff/f]k0f / % aif{ ;Dd ;+/If0f ug'{
kg]{ x'G5 .
jgdf sfl6g] ?vx?sf] ;+Vof / Ifltk"lt{ jfkt a[Iff/f]k0f ug'{ kg]{ ?v ;+Vof / cg'dflgt nfut
pk/f]Qm cg';f/ lkkne~Hofª – xfo'6f/ – g]qsfnL ;8s pk–cfof]hgf ;fd'bflos, sa'lnolt tyf
/fli6«o jg eP/ hfg] / sfl6g] ?vx?sf] ;+Vof, Ifltk"lt{ jfkt a[Iff/f]k0f ug'{ kg]{ ?v ;+Vof /
cg'dflgt nfut ;d]t 6]a'n ! df lbO{Psf] 5 .
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 185
6]a'n ! /fli6«o, sa'lnolt tyf ;fd'bflos jgdf sfl6g] ?vx?sf] ;+Vof, Ifltk"lt{ jfkt a[Iff/f]k0f
ug'{ kg]{ ?v ;+Vof / cg'dflgt nfut
l;g+ jgsf] gfd sfl6g]
?v
;+Vof
Ifltk"lt{
a[Iff/f]k0f
?v ;+Vof
-!M@%_
la?jf, a[Iff/f]k0f
/ 3]/jf/ nfut
klxnf] ls:tf
-g]=?=_
uf]8d]n, k'g/f]k0f
nfut
bf]>f] ls:tf
-g]=?=_
hDdf nfut
-g]=?=_
! sflnsf ;f= j= # &% !),!&)=&% !,!^#=@% !!,##$=))
@ emNsfg] ;f= j= $! !)@% !#(,)))=@% !%,*(&=&% !%$,*(*=))
# /gLaf; ;f= j= # &% !),!&)=&% !,!^#=@% !!,##$=))
$ dfg] e~Hofª
sa'lnolt jg
& !&% @#,&#!=&% @,&!$=@% @^,$$^=*)
% /fli6«o jg &)( !&,&@% @,$)#,^*&=@% @&$,(!$=&% @,^&*,^)@=))
!@# #,)&% $!&,)))=&% $&,^(#=@% $^$,^($=))
hDdf **^ @@,!%) #,))#,&^!=%) #$#,%$^=%) #,#$&,#)*=))
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 186
lhNnf cfof]hgf sfo{Gjog OsfO{ , lhNnf jg sfof{no / ;fd'bflos jg pkef]Qmf ;d"xsf]
aLrdf
Ifltk"lt{ a[Iff/f]k0f -Compensatory Plantation_sfof{Gjog ug{ ePsf] ;+Demf}tf
-Agreement_kq
s_ sfof{Gjog ug]{ ;+:yfsf] lhDd]jf/L tyf bfloTj
lhNnf cfof]hgf sfof{Gjog OsfO{ , l;Gw'nL
!= Ifltk"lt{ a[Iff/f]k0f sfo{ ug{sf] nfuL Joj:yfkg ug]{ h:t}, lj?jf pTkfbg÷9'jfgL ug]{,
a[Iff/f]k0f ug]{ sfo{ cflb . a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf]
/sd -klxnf] ls:tf_ ;DalGwt ;fd'bflos jg pkef]Qmf ;d"x -;f=j=p=;=_ nfO{ lhNnf jg
sfof{no dfkm{t pknAw u/fpg] .
@= a[Iff/f]k0f ul/Psf] If]qsf] ;'kl/j]If0f tyf cg'udgdf ;j} ;/f]sf/jfnfnfO{ ;xefuL u/fpg]
.
#= a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL /
k'gM/f]k0f ug{_ afFsL /sd -bf]>f] ls:tf_ ;DalGwt ;fd'bflos jg pkef]Qmf ;d"xn] kfpg] u/L
lhNnf jg sfof{nosf] k|fljlwssf] l;kmfl/;sf] ;fy} /f]xj/df pknAw u/fpg Joj:yf
ldnfpg] .
lhNnf jg sfof{no, l;Gw'nL
!= lj?jf vl/b, ;Íngsf] ;fy} a[Iff/f]k0f ug{ k|ljlws ;xof]u pknAw u/fpg] .
@= ;f=j=p=;=n] u/]sf] sfdsf] cg'udg u/L lhNnf cfof]hgf sfof{Gjog OsfOdf k|utL
k|ltj]bg k]z ug]{ .
#= a[Iff/f]k0fsf] ;'kl/j]If0f tyf cg'udgdf lhNnf cfof]hgf sfof{Gjog OsfO nfO{ ;xof]u
k'¥ofpg]sf] ;fy} ;+o'Qm cg'udgdf ;xefuL x'g] .
sflnsf ;fd'bflos jg pkef]Qmf ;d"x
!= a[Iff/f]k0f ug{ rflxg] la?jfsf] dfu ;+sng ug]{ .
@= lj?jf pTkfbg vl/b tyf pknAw u/fpgsf] ;fy} :yfgLo ?kdf 9'jfgL ug{ ;xof]u
k'¥ofpg] .
#= a[Iff/f]k0f If]qdf 5]sjf/ ug]{, Kjfsn vGg] / la?jf /f]Kg] sfddf clgjfo{ ;xefuL x'g] .
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 187
$= a[Iff/f]k0f If]qsf] Joj:yfkg k|ljlws ;xof]udf cfkm} ug'{kg]{ .
%= lhNnf cfof]hgf sfof{Gjog OsfO ÷ lhNnf jg sfof{non] ug]{ cg'udg sfo{df ;xof]u
k'¥ofpgsf] ;fy} ;d'xn] :jMcg'udg u/L k|ltj]bg lbg'kg]{ .
v_ ;xof]uL ;+:yfsf] lhDd]jf/L tyf bfloTj
lhNnf sfof{Gjog ;xof]u k/fdz{bftf, l;Gw'nL
!= a[Iff/f]k0f sfo{sf] nflu ;fd'bflos jg pkef]Qmf ;d"x, lhNnf cfof]hgf sfof{Gjog OsfO{,
lhNnf jg sfof{no;+u ;dGjo ug]{ .
@= la?jf pTkfbg÷9'jfgL tyf a[Iff/f]k0f sfo{df ;xof]u k'¥ofpg] .
#= a[Iff/f]k0f If]qsf] ;'kl/j]If0f tyf cg'udgdf k|fljlws tyf ;+:yfut ;xof]u k'¥ofpg] .
$= jg tyf e"–;+/If0f dGqfno Pjd\ ;+3Lo dfldnf tyf :yfgLo ljsf; dGqfno /
cGt/utsf lgsfo tyf /fli6«o k'glg{df{0f k|flws/0faf6 a[Iff/f]k0f cg'udg ug{ cfPsf]
6f]nLnfO{ ;xof]u k'¥ofpg] .
u_ e'QmfgL ug]{ sfo{ ljlwM
;8s lgdf{0f s|ddf sfl6g] # ?vx?sf] nflu !M@% cg'kftdf ul/g] Ifltk"lt{ a[Iff/f]k0f -&%
lj?jfx?_ jfkt hDdf g] ?= !!,##$=)) lgDgfg';f/ pknAw u/fO{g] 5 .
!—klxnf] ls:tfM
a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf] /sd g] ? !),!&)=&%
;DalGwt ;fd'bflos jg pkef]Qmf ;d"x -;f=j=p=;=_ nfO{ lhNnf jg sfof{no dfkm{t
pknAw u/fpg] .
@—bf]>f] ls:tfM
a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL /
k'gM/f]k0f ug{_ afFsL /sd g] ?= !,!^#=@% ;DalGwt ;fd'bflos jg pkef]Qmf ;d"xn] kfpg]
u/L lhNnf jg sfof{nosf] /f]xj/df pknAw u/fpg]] .
lhNnf cfof]hgf sfof{Gjog
OsfO sfof{nosf] tkm{ af6
lhNnf jg sfof{nosf] tkm{
af6
;fd'bflos jg pkef]Qmf ;d"xsf]
tkm{ af6
x:tfIf/M
gfdM
kbM
ldltM
5fkM
x:tfIf/M
gfdM
kbM
ldltM
5fkM
x:tfIf/M
gfdM
kbM
ldltM
5fkM
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 188
lhNnf cfof]hgf sfo{Gjog OsfO{ , lhNnf jg sfof{no / ;fd'bflos jg pkef]Qmf ;d"xsf]
aLrdf
Ifltk"lt{ a[Iff/f]k0f -Compensatory Plantation_sfof{Gjog ug{ ePsf] ;+Demf}tf
-Agreement_kq
s_ sfof{Gjog ug]{ ;+:yfsf] lhDd]jf/L tyf bfloTj
lhNnf cfof]hgf sfof{Gjog OsfO{ , l;Gw'nL
!= Ifltk"lt{ a[Iff/f]k0f sfo{ ug{sf] nfuL Joj:yfkg ug]{ h:t}, lj?jf pTkfbg÷9'jfgL ug]{,
a[Iff/f]k0f ug]{ sfo{ cflb . a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf]
/sd -klxnf] ls:tf_ ;DalGwt ;fd'bflos jg pkef]Qmf ;d"x -;f=j=p=;=_ nfO{ lhNnf jg
sfof{no dfkm{t pknAw u/fpg] .
@= a[Iff/f]k0f ul/Psf] If]qsf] ;'kl/j]If0f tyf cg'udgdf ;j} ;/f]sf/jfnfnfO{ ;xefuL u/fpg]
.
#= a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL /
k'gM/f]k0f ug{_ afFsL /sd -bf]>f] ls:tf_ ;DalGwt ;fd'bflos jg pkef]Qmf ;d"xn] kfpg]
u/L lhNnf jg sfof{nosf] k|fljlwssf] l;kmfl/;sf] ;fy} /f]xj/df pknAw u/fpg Joj:yf
ldnfpg] .
lhNnf jg sfof{no, l;Gw'nL
!= lj?jf vl/b, ;Íngsf] ;fy} a[Iff/f]k0f ug{ k|ljlws ;xof]u pknAw u/fpg] .
@= ;f=j=p=;=n] u/]sf] sfdsf] cg'udg u/L lhNnf cfof]hgf sfof{Gjog OsfOdf k|utL
k|ltj]bg k]z ug]{ .
#= a[Iff/f]k0fsf] ;'kl/j]If0f tyf cg'udgdf lhNnf cfof]hgf sfof{GjognfO{ ;xof]u
k'¥ofpg]sf] ;fy} ;+o'Qm cg'udgdf ;xefuL x'g] .
emNsfg] ;fd'bflos jg pkef]Qmf ;d"x,
!= a[Iff/f]k0f ug{ rflxg] la?jfsf] dfu ;+sng ug]{ .
@= lj?jf pTkfbg vl/b tyf pknAw u/fpgsf] ;fy} :yfgLo ?kdf 9'jfgL ug{ ;xof]u
k'¥ofpg] .
#= a[Iff/f]k0f If]qdf 5]sjf/ ug]{, Kjfsn vGg] / la?jf /f]Kg] sfddf clgjfo{ ;xefuL x'g] .
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 189
$= a[Iff/f]k0f If]qsf] Joj:yfkg k|ljlws ;xof]udf cfkm} ug'{kg]{ .
%= lhNnf cfof]hgf sfof{Gjog OsfO ÷ lhNnf jg sfof{non] ug]{ cg'udg sfo{df ;xof]u
k'¥ofpgsf] ;fy} ;d'xn] :jMcg'udg u/L k|ltj]bg lbg'kg]{ .
v_ ;xof]uL ;+:yfsf] lhDd]jf/L tyf bfloTj
lhNnf sfof{Gjog ;xof]u k/fdz{bftf , l;Gw'nL
!= a[Iff/f]k0f sfo{sf] nflu ;fd'bflos jg pkef]Qmf ;d"x, lhNnf jg sfof{no÷ lhNnf
cfof]hgf sfof{Gjog OsfO{;+u ;dGjo ug]{ .
@= la?jf pTkfbg÷9'jfgL tyf a[Iff/f]k0f sfo{df ;xof]u k'¥ofpg] .
#= a[Iff/f]k0f If]qsf] ;'kl/j]If0f tyf cg'udgdf k|fljlws tyf ;+:yfut ;xof]u k'¥ofpg] .
$= jg tyf e"–;+/If0f dGqfno Pjd\ ;+3Lo dfldnf tyf :yfgLo ljsf; dGqfno /
cGt/utsf lgsfo tyf /fli6«o k'glg{df{0f k|flws/0faf6 a[Iff/f]k0f cg'udg ug{ cfPsf]
6f]nLnfO{ ;xof]u k'¥ofpg] .
u_ e'QmfgL ug]{ sfo{ ljlwM
;8s lgdf{0f s|ddf sfl6g] $! ?vx?sf] nflu !M@% cg'kftdf ul/g] Ifltk"lt{ a[Iff/f]k0f -
!,)@% lj?jfx?_ jfkt hDdf g] ?= !%$,*(*=)) lgDgfg';f/ pknAw u/fO{g] 5 .
!—klxnf] ls:tfM
a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf] /sd g] ? !#(,)))=@%
;DalGwt ;fd'bflos jg pkef]Qmf ;d"x -;f=j=p=;=_ nfO{ lhNnf jg sfof{no dfkm{t
pknAw u/fpg] .
@—bf]>f] ls:tfM
a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL /
k'gM/f]k0f ug{_ afFsL /sd g] ?= !%,*(&=&% ;DalGwt ;fd'bflos jg pkef]Qmf ;d"xn] kfpg]
u/L lhNnf jg sfof{nosf] /f]xj/df pknAw u/fpg]] .
lhNnf cfof]hgf sfof{Gjog OsfO
sfof{nosf] tkm{ af6
lhNnf jg sfof{nosf]
tkm{ af6
;fd'bflos jg pkef]Qmf
;d"xsf] tkm{ af6
x:tfIf/M
gfdM
kbM
ldltM
5fkM
x:tfIf/M
gfdM
kbM
ldltM
5fkM
x:tfIf/M
gfdM
kbM
ldltM
5fkM
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 190
lhNnf cfof]hgf sfo{Gjog OsfO{ , lhNnf jg sfof{no / ;fd'bflos jg pkef]Qmf ;d"xsf]
aLrdf
Ifltk"lt{ a[Iff/f]k0f -Compensatory Plantation_sfof{Gjog ug{ ePsf] ;+Demf}tf
-Agreement_kq
s_ sfof{Gjog ug]{ ;+:yfsf] lhDd]jf/L tyf bfloTj
lhNnf cfof]hgf sfof{Gjog OsfO{ , l;Gw'nL
!= Ifltk"lt{ a[Iff/f]k0f sfo{ ug{sf] nfuL Joj:yfkg ug]{ h:t}, lj?jf pTkfbg÷9'jfgL ug]{,
a[Iff/f]k0f ug]{ sfo{ cflb . a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf]
/sd -klxnf] ls:tf_ ;DalGwt ;fd'bflos jg pkef]Qmf ;d"x -;f=j=p=;=_ nfO{ lhNnf jg
sfof{no dfkm{t pknAw u/fpg] .
@= a[Iff/f]k0f ul/Psf] If]qsf] ;'kl/j]If0f tyf cg'udgdf ;j} ;/f]sf/jfnfnfO{ ;xefuL u/fpg]
.
#= a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL /
k'gM/f]k0f ug{_ afFsL /sd -bf]>f] ls:tf_ ;DalGwt ;fd'bflos jg pkef]Qmf ;d"xn] kfpg] u/L
lhNnf jg sfof{nosf] k|fljlwssf] l;kmfl/;sf] ;fy} /f]xj/df pknAw u/fpg Joj:yf
ldnfpg] .
lhNnf jg sfof{no, l;Gw'nL
!= lj?jf vl/b, ;Íngsf] ;fy} a[Iff/f]k0f ug{ k|ljlws ;xof]u pknAw u/fpg] .
@= ;f=j=p=;=n] u/]sf] sfdsf] cg'udg u/L lhNnf cfof]hgf sfof{Gjog OsfOdf k|utL
k|ltj]bg k]z ug]{ .
#= a[Iff/f]k0fsf] ;'kl/j]If0f tyf cg'udgdf lhNnf cfof]hgf sfof{Gjog OsfOnfO{ ;xof]u
k'¥ofpg]sf] ;fy} ;+o'Qm cg'udgdf ;xefuL x'g] .
/gLaf; ;fd'bflos jg pkef]Qmf ;d"x,
!= a[Iff/f]k0f ug{ rflxg] la?jfsf] dfu ;+sng ug]{ .
@= lj?jf pTkfbg vl/b tyf pknAw u/fpgsf] ;fy} :yfgLo ?kdf 9'jfgL ug{ ;xof]u
k'¥ofpg] .
#= a[Iff/f]k0f If]qdf 5]sjf/ ug]{, Kjfsn vGg] / la?jf /f]Kg] sfddf clgjfo{ ;xefuL x 'g] . $= a[Iff/f]k0f If]qsf] Joj:yfkg k|ljlws ;xof]udf cfkm} ug'{kg]{ .
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 191
%= lhNnf cfof]hgf sfof{Gjog OsfO ÷ lhNnf jg sfof{non] ug]{ cg'udg sfo{df ;xof]u
k'¥ofpgsf] ;fy} ;d'xn] :jMcg'udg u/L k|ltj]bg lbg'kg]{ .
v_ ;xof]uL ;+:yfsf] lhDd]jf/L tyf bfloTj
lhNnf sfof{Gjog ;xof]u k/fdz{bftf, l;Gw'nL
!= a[Iff/f]k0f sfo{sf] nflu ;fd'bflos jg pkef]Qmf ;d"x, lhNnf jg sfof{no÷ lhNnf
cfof]hgf sfof{Gjog OsfO{;+u ;dGjo ug]{ .
@= la?jf pTkfbg÷9'jfgL tyf a[Iff/f]k0f sfo{df ;xof]u k'¥ofpg] .
#= a[Iff/f]k0f If]qsf] ;'kl/j]If0f tyf cg'udgdf k|fljlws tyf ;+:yfut ;xof]u k'¥ofpg] .
$= jg tyf e"–;+/If0f dGqfno Pjd\ ;+3Lo dfldnf tyf :yfgLo ljsf; dGqfno /
cGt/utsf lgsfo tyf /fli6«o k'glg{df{0f k|flws/0faf6 a[Iff/f]k0f cg'udg ug{ cfPsf]
6f]nLnfO{ ;xof]u k'¥ofpg] .
u_ e'QmfgL ug]{ sfo{ ljlwM
;8s lgdf{0f s|ddf sfl6g] # ?vx?sf] nflu !M@% cg'kftdf ul/g] Ifltk"lt{ a[Iff/f]k0f -&%
lj?jfx?_ jfkt hDdf g] ?= !!,##$=)) lgDgfg';f/ pknAw u/fO{g] 5 .
!—klxnf] ls:tfM
a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf] /sd g] ? !),!&)=&%
;DalGwt ;fd'bflos jg pkef]Qmf ;d"x -;f=j=p=;=_ nfO{ lhNnf jg sfof{no dfkm{t
pknAw u/fpg] .
@—bf]>f] ls:tfM
a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL /
k'gM/f]k0f ug{_ afFsL /sd g] ?= !,!^#=@% ;DalGwt ;fd'bflos jg pkef]Qmf ;d"xn] kfpg]
u/L lhNnf jg sfof{nosf] /f]xj/df pknAw u/fpg]] .
lhNnf cfof]hgf sfof{Gjog
OsfO sfof{nosf] tkm{ af6
lhNnf jg sfof{nosf]
tkm{ af6
;fd'bflos jg pkef]Qmf ;d"xsf]
tkm{ af6
x:tfIf/M
gfdM
kbM
ldltM
5fkM
x:tfIf/M
gfdM
kbM
ldltM
5fkM
x:tfIf/M
gfdM
kbM
ldltM
5fkM
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 192
lhNnf cfof]hgf sfo{Gjog OsfO{ , lhNnf jg sfof{no / dfg] e~Hofª sa'lnolt jg
pkef]Qmf ;d"xsf] aLrdf
Ifltk"lt{ a[Iff/f]k0f -Compensatory Plantation_sfof{Gjog ug{ ePsf] ;+Demf}tf
-Agreement_kq
s_ sfof{Gjog ug]{ ;+:yfsf] lhDd]jf/L tyf bfloTj
lhNnf cfof]hgf sfof{Gjog OsfO{ , l;Gw'nL
!= Ifltk"lt{ a[Iff/f]k0f sfo{ ug{sf] nfuL Joj:yfkg ug]{ h:t}, lj?jf pTkfbg÷9'jfgL ug]{,
a[Iff/f]k0f ug]{ sfo{ cflb . a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf]
/sd -klxnf] ls:tf_ ;DalGwt sa'lnolt jg pkef]Qmf ;d"x -s=j=p=;=_ nfO{ lhNnf jg
sfof{no dfkm{t pknAw u/fpg] .
@= a[Iff/f]k0f ul/Psf] If]qsf] ;'kl/j]If0f tyf cg'udgdf ;j} ;/f]sf/jfnfnfO{ ;xefuL u/fpg]
.
#= a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL /
k'gM/f]k0f ug{_ afFsL /sd -bf]>f] ls:tf_ ;DalGwt sa'lnolt jg pkef]Qmf ;d"xn] kfpg] u/L
lhNnf jg sfof{nosf] k|fljlwssf] l;kmfl/;sf] ;fy} /f]xj/df pknAw u/fpg Joj:yf
ldnfpg] .
lhNnf jg sfof{no, l;Gw'nL
!= lj?jf vl/b, ;Íngsf] ;fy} a[Iff/f]k0f ug{ k|ljlws ;xof]u pknAw u/fpg] .
@= s=j=p=;=n] u/]sf] sfdsf] cg'udg u/L lhNnf cfof]hgf sfof{Gjog OsfOdf k|utL
k|ltj]bg k]z ug]{ .
#= a[Iff/f]k0fsf] ;'kl/j]If0f tyf cg'udgdf lhNnf cfof]hgf sfof{Gjog OsfOnfO{ ;xof]u
k'¥ofpg]sf] ;fy} ;+o'Qm cg'udgdf ;xefuL x'g] .
dfg] e~Hofª sa'lnolt jg pkef]Qmf ;d"x
!= a[Iff/f]k0f ug{ rflxg] la?jfsf] dfu ;+sng ug]{ .
@= lj?jf pTkfbg vl/b tyf pknAw u/fpgsf] ;fy} :yfgLo ?kdf 9'jfgL ug{ ;xof]u
k'¥ofpg] .
#= a[Iff/f]k0f If]qdf 5]sjf/ ug]{, Kjfsn vGg] / la?jf /f]Kg] sfddf clgjfo{ ;xefuL x 'g] . $= a[Iff/f]k0f If]qsf] Joj:yfkg k|ljlws ;xof]udf cfkm} ug'{kg]{ .
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 193
%= lhNnf cfof]hgf sfof{Gjog OsfO ÷lhNnf jg sfof{non] ug]{ cg'udg sfo{df ;xof]u
k'¥ofpgsf] ;fy} ;d'xn] :jMcg'udg u/L k|ltj]bg lbg'kg]{ .
v_ ;xof]uL ;+:yfsf] lhDd]jf/L tyf bfloTj
lhNnf sfof{Gjog ;xof]u k/fdz{bftf, l;Gw'nL
!= a[Iff/f]k0f sfo{sf] nflu sa'lnolt jg pkef]Qmf ;d"x, lhNnf jg sfof{no÷ lhNnf
cfof]hgf sfof{Gjog OsfO{;++u ;dGjo ug]{ .
@= la?jf pTkfbg÷9'jfgL tyf a[Iff/f]k0f sfo{df ;xof]u k'¥ofpg] .
#= a[Iff/f]k0f If]qsf] ;'kl/j]If0f tyf cg'udgdf k|fljlws tyf ;+:yfut ;xof]u k'¥ofpg] .
jg tyf e"–;+/If0f dGqfno Pjd\ ;+3Lo dfldnf tyf :yfgLo ljsf; dGqfno / cGt/utsf
lgsfo tyf /fli6«o k'glg{df{0f k|flws/0faf6 a[Iff/f]k0f cg'udg ug{ cfPsf] 6f]nLnfO{
;xof]u k'¥ofpg] .
u_ e'QmfgL ug]{ sfo{ ljlwM
;8s lgdf{0f s|ddf sfl6g] & ?vx?sf] nflu !M@% cg'kftdf ul/g] Ifltk"lt{ a[Iff/f]k0f -!&%
lj?jf_ jfkt hDdf g] ?= @^,$$^=*) lgDgfg';f/ pknAw u/fO{g] 5 .
!—klxnf] ls:tfM
a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf] /sd g] ? @#,&#!=&% lhNnf
jg sfof{nonfO{ pknAw u/fpg] .
@—bf]>f] ls:tfM
a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL /
k'gM/f]k0f ug{_ afFsL /sd g] ?= @,&!$=@% lhNnf jg sfof{no nfO{ pknAw u/fpg]] .
lhNnf cfof]hgf sfof{Gjog
OsfO sfof{nosf] tkm{ af6
lhNnf jg sfof{nosf]
tkm{ af6
sa'lnolt jg pkef]Qmf ;d"xsf]
tkm{ af6
x:tfIf/M
gfdM
kbM
ldltM
5fkM
x:tfIf/M
gfdM
kbM
ldltM
5fkM
x:tfIf/M
gfdM
kbM
ldltM
5fkM
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 194
lhNnf cfof]hgf sfof{Gjog OsfO
/
lhNnf jg sfof{noxsf] aLrdf
Ifltk"lt{ a[Iff/f]k0f -Compensatory Plantation_ sfof{Gjog ug { ePsf] ;+Demf}tf
-Agreement_ kq
s_ sfof{Gjog ug]{ ;+:yfsf] lhDd]jf/L tyf bfloTj
lhNnf cfof]hgf sfof{Gjog OsfO , l;Gw'nL
!= Ifltk"lt{ a[Iff/f]k0fsfo{ ug{sf] nfuL Joj:yfkg ug]{ h:t}, lj?jf pTkfbg÷9'jfgL, a[Iff/f]k0f
ug]{ sfo{ cflb . a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf] /sd -klxnf]
ls:tf_ ;DalGwt lhNnf jg sfof{nonfO{ pknAw u/fpg] .
@= a[Iff/f]k0f ul/Psf] If]qsf] ;'kl/j]If0f tyf cg'udg ug]{ .
#= a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL /
k'gM/f]k0f ug{_ afFsL /sd -bf]>f] ls:tf_ ;DalGwt lhNnf jg sfof{nonfO{ pknAw u/fpg
Joj:yf ldnfpg] .
lhNnf jg sfof{no, l;Gw'nL
!= a[Iff/f]k0f ug{ rflxg] la?jfsf] dfu ;+sng ug]{ .
@= lj?jf pTkfbg÷9'jfgL ug{{ ;xof]u k'¥ofpg] .
#= a[Iff/f]k0f If]qdf 5]sjf/ ug]{ Kjfsn vGg] / la?jf /f]Kg] sfddf ;xof]u ug]{ .
$= a[Iff/f]k0f If]qsf] Joj:yfkg ug]{ .
%= lhNnf cfof]hgf sfof{Gjog OsfO ÷ jg tyf e"–;+/If0f dGqfno÷;+3Lo dfldnf tyf
:yfgLo ljsf; dGqfnon] ug]{ cg'udg sfo{df ;xof]u k'¥ofpg] .
v_ ;xof]uL ;+:yfsf] lhDd]jf/L tyf bfloTj
lhNnf sfof{Gjog ;xof]u k/fdz{bftf, l;Gw'nL
!= a[Iff/f]k0f sfo{sf] nflu lhNnf jg sfof{no tyf lhNnf cfof]hgf sfof{Gjog OsfO;+u
;dGjo ug]{ .
@= la?jf pTkfbg÷9'jfgL tyf a[Iff/f]k0f sfo{df ;xof]u k'¥ofpg] .
#= a[Iff/f]k0f If]qsf] ;'kl/j]If0f tyf cg'udgdf k|fljlws tyf ;+:yfut ;xof]u k'¥ofpg] .
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 195
$= jg tyf e"–;+/If0f dGqfno Pjd\ ;+3Lo dfldnf tyf :yfgLo ljsf; dGqfno /
cGt/utsf lgsfo tyf /fli6«o k'glg{df{0f k|flws/0faf6 a[Iff/f]k0f cg'udg ug{ cfPsf]
6f]nLnfO{ ;xof]u k'¥ofpg] .
u_ e'QmfgL ug]{ sfo{ ljlwM
;8s lgdf{0f s|ddf sfl6g] *#@ ?vx?sf] nflu !M@% cg'kftdf ul/g] Ifltk"lt{ a[Iff/f]k0f -
@),*)) lj?jf_ jfkt hDdf g] ?= #,!$#,@(^=)) lgDgfg';f/ pknAw u/fO{g] 5 .
!—klxnf] ls:tfM
a[Iff/f]k0f tyf 3]/jf/ -fencing_ ug{ nfut cg'dfg cg';f/sf] /sd g] ? @,*@),^**=))
lhNnf jg sfof{nonfO{ pknAw u/fpg] .
@—bf]>f] ls:tfM
a[Iff/f]k0f ul/;s] kl5 lj?jf afFr]sf] cfwf/df jg Joj:yfkg -uf]8d]n, xfFuf s6gL /
k'gM/f]k0f ug{_ afFsL /sd g] ?= #@@,^)*=)) lhNnf jg sfof{no nfO{ pknAw u/fpg]] .
lhNnf cfof]hgf sfof{Gjog OsfO
sfof{nosf] tkm{ af6
lhNnf jg sfof{nosf] tkm{ af6
x:tfIf/M
gfdM
kbM
ldltM
5fkM
x:tfIf/M
gfdM
kbM
ldltM
5fkM
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 196
g. Plantation Plan in District
Compensatory plantation: CF/NF/LHF
Requirements for plantation activities
1) Coordination with DFO - Meeting will be held with DFO and CFUG/LHFUGss to discuss
about the plantation management
2) Agreement with DFO/LHFUG/CFUGs/DLPIU - Agreement will be done with DFO and
DLPIU for the compensatory plantation
3) Managing planting stock - Nursery establishment and operation
From DFO/CFUG nursery
From private nursery owner from districts
Fruit trees in private land - Horticulture farms in districts.
4) Identification and survey of plantation area - Plantation area will be identified by DFO
and survey will be done.
5) Fencing - Fencing will be done by concerned DFO/CFUG/LHFUG.
6) Pitting - Pits of 45cmx30cm x 30cm size will be dug.
7) Transportation of seedlings - From nursery to the planting sites
8) Planting - It will be done by the DFO/CFUGs/LHFUG in the starting of monsoon
9) Weeding - After the monsoon season, weeding is done to reduce the competition by
weeds.
10) Survival count - Before winter starts, survival of the plantation will be done for casualty
replacement before next monsoon.
Plan of Action for Plantation in CF/NF/LHF
Activities May
18
June
18
July
18
Aug
18
Sep
18
Oct
18
Nov
18
Dec
18
Jan 19
Agreement with
DFO/CFUG/LHF
UG/DLPIU
Managing
planting stock
Survey of
plantation area
Fencing
Pitting
Transportation of
seedlings
Planting
Weeding
Survival count
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 197
Plantation in Private Land
Coordination with affected landowner - Meeting will be held with concerned affected
landowner to discuss about the plantation trees in their land.
1) Managing planting stock
From DFO/CFUG nursery
From private nursery owner from districts
Fruit trees in private land - Horticulture farms in districts.
2) Identification and survey of plantation area - Plantation area will be identified in
coordination with affected landowner.
3) Protection- Protection of planted trees will be done by the landowner.
4) Pitting - Pits of appropriate size will be dug depending on the species.
5) Transportation of seedlings - From nursery to the planting sites
6) Planting - It will be done by the affected landowner and cost will be provided in the
starting of monsoon
7) Weeding - After the monsoon season, weeding is done to reduce weed competition.
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 198
Roadside plantation
1) Coordination with local communities, Municipality, RM and DFO - Meeting will be held
with concerned local communities, Municipality, RM and DFO to discuss about the
plantation management
2) Agreement with concerned stakeholders - Agreement will be done with concerned local
communities, Municipality, RM and DFO for the road side plantation
3) Managing planting stock - Nursery establishment and operation
From DFO nursery
From private nursery owner from districts
Fruit trees in private land - Horticulture farms in districts.
4) Identification and survey of plantation area - Plantation area will be identified by
concerned local communities, Municipality, RM, and DFO and survey will be done.
5) Fencing - Fencing will be done by concerned local communities, Municipality, RM and
DFO.
6) Pitting - Pits of appropriate size will be dug depending on species
7) Transportation of seedlings - From nursery to the planting sites
8) Planting - It will be done in the starting of monsoon
9) Weeding - After the monsoon season, weeding is done to reduce the competition by
weeds.
10) Survival count - before winter starts, survival of the plantation will be done for casualty
replacement before next monsoon.
Plan of Action for Roadside Plantation
Activities May 18 June 18 July 18 Aug 18 Sep 18
Agreement with local
communities, Municipality,
RM and DFO
Managing planting stock
Survey of plantation area
Fencing
Pitting
Transportation of seedlings
Planting
Weeding
Survival count
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 199
Appendix XII: Affected Structures
a. Private Structure
Details of Structures
Total Area
( Sqm)
Affected
Area
(Sqm)
storey Rate /Sqm Estimated
Cost
Total
Amount
House 97.25 2 8304 1615128 1630128.00
Other Str.
Total 1615128.00
Allowance 15000
Other Informations
Structure
Type
Roof
Type
Wall Type Current Use Affected Earthquake
Affected
Year of
Constructio
n
Load
Bearing
C.G.I stone/Wood Good Yes No 2048
Str.No. Land owner Name: Chainage/S.N. Plot No. Distance Form No. Address Village/Settlemen
ts
1 Padam Bahadur Bloar 22+900 Ghyanglek-2 (Haytar)
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 200
Details of Structures
Total Area
( Sqm)
Affected Area
(Sqm)
storey Rate /Sqm Estimated
Cost
Total
Amount
House 23.24 2 6200 288176 303176.00
Other Str.
Allowance 15000
Other Informations
Structure
Type
Roof Type Wall Type Current Use Affected Earthquake
Affected
Year of
Construction
Load
Bearing
Khar Bamboo Normal Yes No 2066
Str.No. Land owner Name: Chainage/S.N. Plot No. Distance Form No. Address Village/Settlements
2 Krishna Bahadur Syangten 23+540 Ghyanglek-2 Chalise Bagar
Details of Structures
Total Area (
Sqm)
Affected Area
(Sqm)
storey Rate /Sqm Estimated
Cost
Total
Amount
Goth 11 1 (L.S) 50000 65000.00
50000.00
Allowance 15000
Other Informations
Structure
Type
Roof
Type
Wall Type Current Use Affected Earthquake
Affected
Year of
Construction
Load Bearing C.G.I Bamboo Not Good Yes No 2069
Str.No. Land owner Name: Chainage/S.N. Plot No. Distance Form No. Address Village/Settlemen
ts
3 Ek Bahadur Khadka 24+070 Ghyanglek-2 Khattarmathi
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 201
Details of Structures
Total Area (
Sqm)
Affected Area
(Sqm)
storey Rate /Sqm Estimated
Cost
Total
Amount
Goth 30.4 2 (L.S) 100000 115000.00
Other Str.
Allowance 15000
Other Informations
Structure
Type
Roof
Type
Wall Type Current Use Affected Earthquake
Affected
Year of
Construction
load Bearing C.G.I Bamboo Good Yes Yes 2062
Str.No. Land owner Name: Chainage Plot No. Distance Form No. Address Village/Settlements
4 Jaskarna Magar 24+830 Ghyanglek-2 SimlePhant
Total Area (
Sqm)
Affected Area
(Sqm)
storey Rate /Sqm Estimated Cost Total
Amount
Goth 20.1 2 (L.S) 100000 115000.00
Allowance 15000
Other Informations
Structure
Type
Roof
Type
Wall Type Current Use Affected Earthquake
Affected
Year of
Construction
Load Bearing C.G.I Stone/Bamboo Normal Yes No 2060
Str.No. Land owner Name: Chainage Plot No. Distance Form No. Address Village/Settlemen
ts
5 Bir Bahadur Khadka 24+870 Ghyanglek-2 SimlePhant
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 202
Details of Structures
Total Area
( Sqm)
Affected Area
(Sqm)
storey Rate /Sqm Estimated
Cost
Total
Amount
House 36.49 2 8304 606025 621025.00
Other Str.
Allowance 15000
Other Informations
Structure
Type
Roof
Type
Wall Type Current
Use
Affected Earthquake
Affected
Year of
Construction
Load
Bearing
C.G.I Stone/Wood/Bamboo Good Yes No 2064
Str.No. Land owner Name: Chainage/S.N. Plot No. Distance Form No. Address Village/Settlements
6 Tulpu Lama 26+440 Ghyanglek-2 DumriGoth
Details of Structures
Total Area (
Sqm)
Affected
Area (Sqm)
storey Rate /Sqm Estimated
Cost
Total
Amount
House 50.4 1 8304 418521.6 433521.60
Other Str.
Allowance 15000
Other Informations
Structure
Type
Roof
Type
Wall Type Curre
nt Use
Affected Earthquake
Affected
Year of
Construction
Load Bearing C.G.I Stone+Cement Mortar Good NO 2070
Str.No. Land owner Name: Chainage/S.N. Plot No. Distance Form No. Address Village/Settlemen
ts
7 Bishnu Syangten 31+895 Ghyanglek-3 Chaukitar
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 203
Details of Structures
Total Area (
Sqm)
Affected Area
(Sqm)
storey Rate /Sqm Estimated
Cost
Total
Amount
Goth 19.2 1 (L.S) 50000 65000.00
Other Str.
Allowance 15000
Other Informations
Structure
Type
Roof
Type
Wall Type Current Use Affected Earthquake
Affected
Year of
Construction
Load Bearing C.G.I Bamboo Good Yes No 2065
8 Bishnu Syangten 31+895 Ghyanglek-3
b. Public Structure
Picture Detail
1
Chainage 24+080
Structure Type Tap
Address Ghanglek Rural Municipality-2
Built Year 2070
Present Status On use (Good)
Total cost (NRs.) 35000
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 204
Appendix XIII: Photographs
a. Road Alignment at Various Points
Photograph 1: Road alignment at Pipalbhangyang
(0+000)
Photograph 2: Road alignment at Potential
Landslide area
Photograph 3: Road alignment passing edge of
the Dhanamana Khola
Photograph 4: Vehicle movement along the Road
alignment
Photograph 5: Road alignment at Hayutar bazar Photograph 6: Existing road conditions
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 205
b. Consultation Meetings
Photograph 1: Consultation meeting at Bhoteswora
Photograph 2: Consultation with community
forest users
Photograph 3: Consultation meeting at Chandanpur
Photograph 4: Interaction with affected family
Photograph 5: consultation with Leasehold forest
users
Photograph 6: Interaction with local teacher
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 206
c. Vegetation and Physical Survey
Photograph 1:Measuring DBH Photograph 2: Vegetation survey in GMF
Photograph 3: Road alignment at Jhalkane CF Photograph 4: Road alignment
at Government Forest
Photograph 5: Measuring the width of the road
(at 0+000)
Photograph 6: Leasehold forest along the road
alignment
IEE of Pipalbhanjyang-Hayutar-Netrakali Road Rehabilitation and Reconstruction Sub-project, Sindhuli 207
d. Different Species Captured during Field Visit
Photograph 1:Domestic dove at Khattar
Photograph 2: Fish species found in Simle khola
Photograph 3: Domestic cat at Amale
Photograph 4: Maina found at Hayutar