Update-May2007-e

14
AIRPORT MASTER PLAN UPDATE May 2007

Transcript of Update-May2007-e

Page 1: Update-May2007-e

AIRPORT MASTER PLAN UPDATEMay 2007

Page 2: Update-May2007-e

Purpose of the Project

Strategic Goal

To ensure continued operational and service excellence in the management

of the Ottawa’s international airport within the next five years, ten years and

to 2020-2030.

Contractual Obligation

To fulfill Section 7.01.02 of the Ground Lease that states:

“The Tenant’s Airport Master Plan shall be updated and such update

adopted no earlier that the tenth (10th) anniversary of the Date of

Commencement and no later than the eleventh (11th) anniversary of the

Date of Commencement and every ten (10) years thereafter. “

Page 3: Update-May2007-e

Guiding Principles

The existing Airport Master Plan will be updated in a manner that will:

– ensure that the Airport Authority is in a position to respond to client

needs, industry trends and regulatory requirements in a timely and cost-

effective manner over the timeframe of the plan;

– build upon the Airport Authority’s existing strategic approach to

addressing operational issues, environmental concerns and

development matters to 2030; and

– create a blueprint for pragmatic decision-making and airport

management within the three defined time periods.

Page 4: Update-May2007-e

Project Team

Jacobs Consultancy Canada- Airport and Capital Planning

JL Richards & Associates

- Urban Planning and Engineering

mcfarlaneGreen Architecture + Design

- Architectural Services

Page 5: Update-May2007-e

Project Focus

The Airport Master Plan project will accomplish the

following central priorities: – update aviation forecasts for three planning horizons (5 year, 10

year and 2020-2030);

– quantify airfield and airport terminal ground transportation and

airside business requirements; and

– identify aviation support facility and service requirements to meet

future needs and demands.

Page 6: Update-May2007-e

Objectives

Describe existing physical conditions and operations, outline environmental impacts and identify key issues

Revise aviation forecasts and project physical and operational requirements to 2030

Formulate options to address issues and meet forecasted needs

Develop alternative spatial representations for translation into a land use plan

Assess the environmental impact of proposed future facilities, activities and operations

Page 7: Update-May2007-e

Stakeholders Governments

– Federal– Province of Ontario– Municipal (City of Ottawa, Ville de Gatineau)

Airport Clients– Tenants– Airlines– Aviation Support Services

Community Interests– Politicians– Community Associations and the public-at-large

NavCanada Aviation Organizations Business Groups Tourism Industry

Page 8: Update-May2007-e

Communication and Consultation Strategy General Consultation and Communication Tools

– Introduction letter to a wide variety of general stakeholders such as but not limited to: area politicians, airport tenants, development and business organizations

– Web page for the project containing information regarding the project purpose, background, process, timelines and consultation avenues

– Project specific electronic mailbox

– Public Open House to be held in November

Page 9: Update-May2007-e

Communication and Consultation Strategy

Specific Consultation Tools

– Interviews and meetings with key stakeholders such as the airlines, airport tenants, aviation support service providers, area municipalities, Transport Canada, Department of National Defense, Public Works and Government Services Canada, National Capital Commission

– Presentations to government agencies, technical consultation

– Interim meeting with key stakeholders to review project findings, key directions, a preliminary land use plan and possible recommendations

Page 10: Update-May2007-e

Schedule – Phase 1

1.1 Project Initiation

1.3 Data Collection

1.5 Traffic Forecasts

1.6 Client Review – Phase 1

1.4 Stakeholder Consultations & Interviews

Page 11: Update-May2007-e

Schedule – Phase 2

2.1 Terminal Area Demand/ Capacity

2.2 Terminal Area Requirements

2.3 Airside Demand/Capacity

2.4 Airside Requirements

2.5 General Aviation Demand/Capacity

2.6 General Aviation Requirements

2.7 Airport & Airline Support & Utilities Demand Analysis

2.8. Airport and Airline Support & Utilities Requirements

2.9 Environmental Impacts

2.10 Client Review Phase II

Page 12: Update-May2007-e

Schedule – Phase 3

3.12 Final Master Plan & Overview Document

3.1. Option Development 3.2. Cost Estimates

3.3. Evaluate Options

3.4. Client Review – Options Report

3.6. Update Airport Capital Plan

3.7. Airport Development Plan and Land Use Plan

3.9 Draft Master Plan and Client Review of First Draft MP

3.5. Key Stakeholder Review

3.8 Phasing Plan

3.10 Open House

3.11 Final Client Review

Page 13: Update-May2007-e

Schedule

Page 14: Update-May2007-e

Thank You

Should you have questions please contact either:

– Ann M. Tremblay

Director, Planning, Ottawa International Airport Authority

613-248-2172

[email protected]

– Michael Tubridy

Director, Jacobs Consultancy

613-236-4318

[email protected]