UNIVERSITY OF WATERLOO MATH AND COMPUTER BUILDING MAIN COMPUTER ROOM UPS REPLACEMENT MAIN COMPUTER...

47
UNIVERSITY OF WATERLOO MATH AND COMPUTER BUILDING MAIN COMPUTER ROOM UPS REPLACEMENT MAIN COMPUTER ROOM AIR CONDITIONER GENERATOR

Transcript of UNIVERSITY OF WATERLOO MATH AND COMPUTER BUILDING MAIN COMPUTER ROOM UPS REPLACEMENT MAIN COMPUTER...

UNIVERSITY OF WATERLOOMATH AND COMPUTER BUILDING

MAIN COMPUTER ROOM UPS REPLACEMENTMAIN COMPUTER ROOM AIR CONDITIONER

GENERATOR

MAIN COMPUTER ROOM UPS REPLACEMENT PROJECT:

REPLACE MULTIPLE UPS SYSTEMS THROUGHOUT COMPUTER ROOM WITH LARGE THREE PHASE UPS THAT PROVIDES:

30 MINUTES OF BATTERY BACK FOR ENTIRE ROOM

INSTALLED WHILE EXISTING SYSTEM RUNS

HAS REDUNDANT FAILSAFE FEATURES

CAN EASILY BE MONITORED (Batteries)

CAN GROW TO FOUR (4) TIMES THE CURRENT CAPACITY OF THE

EXISTING EQUIPMENT WITH IN THE COMPUTER ROOM

COMPUTER ROOM DRAW:Based Upon Measurements Provided by University of Waterloo PersonnelStatement by University Personnel that at any given time 10% of the computer room is down for

upgrades and repairs.

CURRENT MEASUREMENTS

LARGEST DRAW PER PHASE AMPS

PHASE A: 190

PHASE B: 224

PHASE C: 144

TOTAL: 558

SUBTOTAL WATTS 66960

10% UNITS SWITCHED OFF 6696

TOTAL WATTS 73656

FOUR (4) TIMES GROWTH WATTS: 294624

SOME POINTS:

Why Watts?I. There is a difference in watt (kW) actual power and VA (kVA) apparent power ratings in UPSII.Watts is the lower rating in UPS Systems. But the important one.III.University of Waterloo could not tell us if the meter measured watts, va or both.IV.Assume worst case scenario.

How did you get the totals?

I. 208/120 volt 3 Phase.II.Any individual phase to ground or neutral 120 VACIII.Add all three phases current draw together multiply by 120IV.Add 10% for equipment turned off (University of Waterloo)

UPS SYSTEM RECOMMENDATION:

Eaton Powerware 9390 160 KVA / 144 KW

Parallel Redundant System Upgradeable to 480 KVA / 432 KW System with

one (1) 160 KVA / 144 KW N+1 Redundancy

EATON POWERWARE 9390 UPS System

Powerware 9390 UPS SystemSetting the New Standard for Three-Phase Power Protection

Powerware 9390 System Overview● Next-Generation, Three-Phase UPS

System Modern Design Advanced performance

● Transformerless● Active Front-End Converter● Double Conversion

Increased reliability● Advanced Battery Management● Remote Monitoring

Better serviceability● Front access● Warranty/Service coverage

Consistent design for entire system● UPS modules● Battery cabinets● Integrated Distribution Cabinet

Key Features Power PerformanceWarranty and ServiceBattery ManagementScalabilityPower DensityServiceability

Power Performance

Input THD Output PF Efficiency● 9390 <4.5% 0.9 94%

● Galaxy PW <7.5% 0.9 92 - 93%● Comet <10%* 0.8 90 - 95%● Npower <10%* 0.8 92 - 93%● Silcon n/a 1.0 92 - 95%● Toshiba 4100 <3% 0.8 90%● Mitsu 2033 <3-6% p0.8 ???● * With optional filter

Warranty and Service

Powerware 9390 provides the best warranty/service

5x8Limited 7x24

7x247x247x247x24Tech Support

$1,417 per YR

Included no charge ($2,095 5x8, $2,575 7x24)

1-YR parts and labor, 5x8, 4hr

Liebert

$1,650 cust. installed

Web included free for YR1, $2,000/YR after

Modem monitoring free w/contract (+ $500 modem buy)

Web monitoring 2-YR no chrg, $1,500/YR after

Monitoring

$1,490 5x8$1,864 7x24

$1,783 5x8Included no charge ($1,965 7x24)

5x8 included no charge ($500 upgrade to 7x24)

Start-up

2-YR parts and labor, 7x24, 8hr (excludes battery)

2-YR parts, 5x8 Next Day

90 days labor, 1 YR parts (1 YR ProActive 7x24, 8hr)

2-YR parts & labor, 5x8, Next Day

Warranty

MGEComet

APC Symmetra PX

9315-509390

Scalability

Available in 40, 80, 120, and 160 kVA single power module ratingsPowerware Hot SyncTM Paralleling

● Tried-and-true technology● Peer-to-peer paralleling without wires

Parallel for redundancy or capacity● Up to four (4) modules without tie cabinet ● Up to eight (8) modules maximum● Total capacity of 1280 kVA

Easy to parallel units● X-slot parallel card● Firmware setting changes

Powerware 9390 provides scalability for future growth

35% smaller than nearest competitor Front access only

Back-to-wall and side-to-wall installation

561

1062864

10941240 1277 1278

13841584

0200400600800

10001200140016001800

Manufacturer

Sq

ua

re in

ch

es

Power DensityOur 160 kVA is smaller than most other

80 kVA UPS's

Powerware 9390 provides the highest power density

Power Density (cont’d) Half the weight of nearest competitor

● Reduced transportation and installation costs● Easy to handle

600950 1166

2115

11651700

2700 2800 3050

0500

100015002000250030003500

Manufacturer

Po

un

ds

Our 160 kVA is lighter than other 80 kVA's

Powerware 9390 Specification Snapshot

Power Ratings kVA 40 80 120 160

kW 36 72 108 144Efficiency 94%Input Power Factor 0.99Input THD <4.5%Voltage 208/208, 400/400, 480/480 (standard)

480/208, 600/600, 600/208 (optional)

Battery OptionsTypes VRLA, AGM, Gel, Wet

Voltage 384 - 480, variable

Charging Method Advanced Battery ManagementTM

Design Characteristics

8 Lines x 40 Characters Back-lit display Multilingual Powerware logo “screensaver”

Design Characteristics

Output Power Connections

Top or bottom cable entry standard

Wireway top to bottom

Battery Cable Connections

Removable Conduit Plate

Your Initial System

2 x 9390 160 KVA/ 144KWTie Cabinet4 x Remote Power Panel (RPP)

Why 160 KVA when the model is available in 100, 120, and 160 KVA and is field Upgradeable?

Answer:Cost vs Price.9390 100 KVA 208/208 List Price $59,100.009390 160 KVA 208/208 List Price $69,000.00Difference: $9,900.00 per system9390 100 KVA Field Upgrade to 160 KVA $18,500.00 per system

How it Works (Simplified)160 KVA/ 144 KW

Parallel Redundant System

UPS Systems Share 73656 Watts. Each UPS carrying

36828 Watts.With Battery

Cabinet recommended62.5 Minutes

Tie Cabinet

UPS UPS

RPP RPP RPP RPP

How it Works (Simplified)160 KVA/ 144 KW

Parallel Redundant System

UPS Systems Share 73656 Watts. One UPS carrying

73656 Watts.With Battery

Cabinet recommended

18 Minutes

Tie Cabinet

UPS UPS

RPP RPP RPP RPP

How it Works (Simplified)320 KVA/ 288 KW

Parallel Redundant System

UPS Systems Share 150000

Watts. Each UPS carrying 50000

Watts.With Battery

Cabinet recommended

30 Minutes

Tie Cabinet

UPS UPS

RPP RPP RPP RPP

UPS

How it Works (Simplified)320 KVA/ 288 KW

Parallel Redundant System

UPS Systems Share 150000

Watts. Each UPS carrying 75000

Watts.With Battery

Cabinet recommended

17 Minutes

Tie Cabinet

UPS UPS

RPP RPP RPP RPP

UPS

Each Powerware 9390 UPS System Comes With:SNMP Web/Hub Adapter

Environmental Monitoring Probe

SNMP WEB / HUB Card Allows:Treat UPS as a node on the Network

Allow Access for E-Notify by Service Organization

Allow Monitoring of UPS Systems from anywhere via your Network or via the Web (access permitted).

Allows for Broadcast Messages over Network

E-mail error messages (with software)

Environmental Monitoring Probe:Works with SNMP Web Card

Monitors Temperature and Humidity

User programmable High and Low Levels

Two (2) extra relay contacts for additional signals.

Recommended Software:POWERVISION FACILITY EDITION

Built In Multiples Server OS Shutdown (unlimited)

Monitor Multiple Networks, Enterprise Wide, 1000 of UPS

Monitor other manufacturers' UPS systems

Monitore Parallel System Shutdowns

Monitor other Equipment (Air Conditioners, Generators, Etc.)

Everything from a central location

Where is it installed:

Main Breakers from Maintenance Room Transformers to be installed in unused Staircase – StackedUPS Systems, Battery Cabinets, Tie Cabinets . Against Computer Room

Back Wall.Distribution Panels: One in Red Room. Three Down the Center Aisle of

Racks. One on each end one in the middle.

Please Note: That once the initial UPS systems are installed. The existing UPS systems along back wall will be removed. Making Room for the Additional UPS and Batteries as required.

Computer Room System Dimensions:

9390 160 KVA UPS System: 35.6” W x 31.5” D x 73.6” HBattery Cabinets: 43” W x 31.5” D x 73.6” HParallel Tie Cabinet: 38"W x 18"D x 92"H

Initial System requires 16.26 Linear feet along back wall.Remaining two Systems require an additional 13.1 Linear Feet Along Back wall.

Your System to Include:

Two (2) 160 KVA / 144 KW 9390 UPS SystemsTwo (2) Battery CabinetsParallel Tie Cabinet with Qty: Four (4) 600 Amps. 3 pole Input Breakers Qty:

Eight (8) 225 Amps. 3 pole Output BreakersFour (4) Remote Power Panels with 2 x 42 Circuit Breaker Panels and 225

Main BreakersThirty (30) 30 amp 208 Circuit Breakers for RPPTwo (2)SNMP Web CardsTwo (2) Environmental Monitoring ProbesPowerVision Facility Edition SoftwareTwo (2) 180 KVA 600VAC/208 VAC Step Down TransformersInside DeliveryElectrical Installation of Equipment on 5 x 8 Standard Day7 x 24 Start Up of UPSLocal Two Year (7 x 24) On site ServiceRemoval of old electrical wiring after installationInfrastructure for a Total of Four160 KVA / 144KW 9390 systems in a Parallel

Redundant configuration N+1Additional Floor Support where required for UPS and Battery System.

Budgetary Price based upon above.

$406,689.00 (Taxes Extra)

What can Change?

Most Economical Solution For example Rough Estimate of a 600/600 System would be $526,844.00. and increase Linear feet for base system to 30.05.Can adjust quantities of Distribution Cabinets (RPP)Can limit growth to three UPS systems which will reduce cost of Tie

Cabinet.

BOTTOM LINE: Things can be changed when you come to a final decision. Cost savings can be found.

MAIN COMPUTER ROOM AIR CONDITIONER PROJECT:

Replace chillers with air conditioning unit. possibly leave chillers in room for emergency back up of air conditioner. Concern is temperature not humidity with new equipment.

CURRENT LOAD: 73656 WATTS

ADD 10% FOR UPS: 7366 WATTS

TOTAL CURRENT LOAD: 81022

CONVERT TO BTU'S : 276,447,064

AIR CONDITIONER TONNE: 21265 (30 TONNE)

FUTURE LOAD: 294,624 WATTS

ADD 10% FOR UPS: 29463 WATTS

TOTAL CURRENT LOAD: 324087 WATTS

CONVERT TO BTU'S : 1,105,784,844

AIR CONDITIONER TONNE: 85061 (90 - 100 TONNE)

Concerns:

Too much growth in future forecastSizing unit for potential future load increases Air Conditioner

dramatically reducing efficiency with current load and increasing operating expenses.

Recommending Solutions from Carrier and Rheem

Economical and Well Built unitsRoof Top and In Room Systems availableIs possible to develop an in room modular system

that will grow with you as required.Regardless of In Room or Roof Top System you

should factor in approximately $3,500 per Tonne.

30 Tonne System: $105,000.00 (Electrical and Mechanical)

100 Tonne System: $350,000.00 (Electrical and Mechanical)

GENERATOR PROJECT:

Required: A 1000KW Natural Gas Generator to be installed in Maintenance room of Math and Computer Building.

Concerns:

Indoor installation will involve a lot of mechanical work Installation costs for this option will be very high compared to an outdoor

alternative. Generator must be taken apart and reassembled to fit into the room.Pricing Shown is for Units Only. Does not include Installation, Permits, any

required engineering.Count on installation costs of 40% minimum for inside installation

Inside Room

40' x 26.6' at widest point

Option # 1: Given for Size Comparison

Baldar 875 KW16.25' L x 8' W$411,765.00 + Install

Option # 1: Given for Size Comparison

Baldar 880 KW16.25' L x 8' W$411,765.00 + Install

This product could also be used for a prime power/load curtailment application if U of W works something out with Waterloo North Hydro.

Option # 2:

SimPower 1000 KW$764,705.00 + Install

Specification under revision

Option # 3:

Generac 1000 KWParallel Redundant36' X 14' Total Space $447,059.00 + Install

p

Advantages to a Parallel System.

System Outdoors with Weather Proof and Sound Proof Enclosures.$588,236.00 plus considerable less installation Expense.

Option # 4:

Generac 1125 KW Parallel RedundantBi-Fuel (Diesel and Natural Gas System). 23.4' X 14' Total Space $411,765.00 + Install

Advantages to a Parallel System.

System Outdoors with Weather Proof and Sound Proof Enclosures.$529412.00 plus considerable less installation Expense.

Brochures on CD ROM

What Are the Next Steps?

Determine what is reasonable for Computer Room. Explore Modular air Conditioning system. More in Depth presentations on individual systems. Check on City Bylaws and codes for Generators. Create a Specification.

We would be happy to arrange more in-depth presentations.Thank You.