Production Schedule

Tuesday 26 th January 2016

Scene: School; all of scene recorded in school

Call Time: All cast to be on scene for 3:15pm

Crew required at Location: Camera Operator, Director, Actors & Costume

Actors Required: Sam, Lucy, Chloe, Danni, Danielle, Zoe and others

Set Up Start Time: 3:10pm

Set Up Finish Time: 3:25pm

W/S of boy walking through corridor: 3:26pm-3:37pm

W/S of students laughing at boy-3:38pm-3:41pm

C/U panning in M/S of boy running down to the toilets: 3:42pm-3:48pm

M/S & W/S of boy placing VO5 on his hair: 3:49pm-3:55pm

C/U panning into M/S of boy leaving toilet: 3:56pm-4:00pm

W/S, M/S & C/U’s of boy walking back to class, being surrounded and taken out by screaming girls: 4:01pm-4:20pm

Set de-rigged between 4:21pm-4:30pm