UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011
description
Transcript of UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011
![Page 1: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/1.jpg)
UNDIP TEAMSEMARANG Meeting, 9 – 13 July 2011
TWG IV:RE Project Development
Development of BIOGAS at Seruni Village, Musuk Sub District, Boyolali Regency
![Page 2: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/2.jpg)
Activities during March – July 2011 and Next Actvities
After installed demo unit, now 2 digester was constructed and 7 household already fill the HIVOS administration form and was given to LPTP.
PUSDILAT KEBT took the film at KUD Mojosongo and Sruni Villages for the television program “ development Biogas program for MEMR“
Training Biogas – Cooperate with HIVOS, pusdiklat KEBT (ETCEREE) and UNDIP on April at Boyolali ( 3 days ). The participants from the cow farms, local government and koperasi(KUD)
on 18 June 2001, Met with KUD Musuk ( almost 50 % cow farms are member of Koperasi Unit Desa Musuk ) as a MFI , to speed up the program installation biogas digester and to discuss about the possibility Koperasi Susu Musuk can do install biogas digester (CPO)
Arrange the meeting with HIVOS, KUD Musuk, KUD Mojosongo (MFI) , LPTP (CPO), Regional office , and UNDIP to implement the Project of the Biogas at Sruni ( Schedule 26 July 2011).
Prepare Draft Complete report on end of July and Final report on end of August 2011
![Page 3: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/3.jpg)
Outline Presentation
Background of the Selection Location
1. Executive Summary2. Market analysis3. Product description4. Regulatory setting5. Project management6. Technical feasibility7. Financial analysis8. Risk analysis and contingency
planning
![Page 4: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/4.jpg)
Background of the Selection Location
SITE SURVEY
After resulting potential locations, in May 2010 a site survey was conducted together with Dinas.
First location visited is Musuk Subdistrict, Boyolali District
The subdistrict was selected from potential locations because:a. Boyolali is a district which produces a great amount of
milk from dairy cows (greatest amount in Central Java);b. Musuk subdistrict does not receive any funds from Hivos
project, as well as from other institutions, while other
subdistricts receive.
![Page 5: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/5.jpg)
MAP of BOYOLALI district
![Page 6: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/6.jpg)
Subdistrict Musuk and Sruni Village Offices
![Page 7: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/7.jpg)
BIOGAS POTENTIAL IN BOYOLALI
Number of cows (source: Dinas ESDM)
The number of cow at Sruni is 1248, so this equal to 5 % from the total of Musuk distric
![Page 8: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/8.jpg)
1. Executive Summary
What are you planning to implement?The proposed renewable energy project to be developed under the Casindo TWG IV in Central Java is household biogas.
Where are you planning to implement?Seruni Vilage is the name of the target location chosen for the implementation of the renewable energy project in the program Casindo.
![Page 9: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/9.jpg)
Executive Summary (cont)
How will the project be implemented? With what funds or what funds does it need?Project of biogas technology will build in a self funding from people of meet criteria established by the BIRU program. Then the number of households that are eligible to be selected as the target of the program were 80 families; instead with 194 cow farmerNowday, BIRU Central Java and UNDIP and LPTP will cooperate with MFI (KUD Musuk and Bank BRI) getting financial institution to provide the credit in biogas digester construction, so that funds originated from vilagers and subsidy from Hivos.
![Page 10: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/10.jpg)
Executive Summary (cont)
Why is it desirable for the project to be implemented? What benefits will it bring?If the project to be implemented, very desirable many benefits for poor people in location target and its project suistain for the long time;BIRU program will have broad effects of health conditions and job creation as well as the local economy.
![Page 11: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/11.jpg)
2. Market analysis1. Geographic description of selected location:1. Geographic description of selected location:
- Geographic description of selected location:
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Map of Boyolali Regency and Musuk Distric (20 vilages)
![Page 12: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/12.jpg)
Market analysis (cont)1. Geographic description of selected location:1. Geographic description of selected location:
- Geographic description of selected location:
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Map of Sruni Village
![Page 13: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/13.jpg)
Market analysis (cont)1. Geographic description of selected location:1. Geographic description of selected location:
- Demographic profile of selected location
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Population of Sruni Village
Village/Sub VillagePopulation
HouseholdMale Female Total
RW I 239 245 484 131RW II 301 302 603 174RW III 388 377 765 229RW IV 205 213 418 114RW V 306 337 643 183TOTAL 1439 1474 2913 831
Household Sruni Village
Size of household Percent (%)
1. – 3 person 484 – 6 person 51
> 7 person 1
Source from : Seruni Village office
Source from : Seruni Village office
![Page 14: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/14.jpg)
Market analysis (cont)1. Geographic description of selected location:1. Geographic description of selected location:
- Demographic profile of selected location
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Age Structure of Sruni Village
Education Background of Household Sruni Village
Age structure (year) Percent (%)
Children & adolescents : < 17 tahun 35
Adult : 18 s/d 50 tahun 55
Elderly : > 50 tahun 10
Education Level Total of Household
SD ( Basic Scholl) 355SMP (Yunior Scholl) 225SMA ( High Scholl) 218< D3 (Academic)
33S1 ( University)S2 ( Master )
Source from : Seruni Village office
Source from : Seruni Village office
![Page 15: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/15.jpg)
Market analysis (cont)1. Geographic description of selected location:1. Geographic description of selected location:
- Demographic profile of selected location
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Education Facilities and number of student Sruni Village
NoEducation Level Total Education
Facilities
Number of student
1 Kindgarden 1 40
2 SD ( Basic School) 2 220
3 SMP ( Yunior School) 1 400
4 SMA (high School) - -
Source from : Seruni Village office
![Page 16: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/16.jpg)
Market analysis (cont)1. Geographic description of selected location:1. Geographic description of selected location:
- Economic profile
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
type of work Sruni Village
No Type of Work Percentage (%)
1 Un irrigated Farmland worker 30 %
2 Government / Teacher 4 %
3 Cow Breeder 48 %
4 Entreprenuer 2 %
5 Industrial Labor 6 %
6 Buliding worker 5 %
7 Merchant 5 %
Source from : Seruni Village office
![Page 17: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/17.jpg)
Market analysis (cont)1. Geographic description of selected location:1. Geographic description of selected location:
- Economic profile
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Chart of The Percentage of Income Clas Sruni Village
From survey need assesment
![Page 18: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/18.jpg)
Market analysis (cont)1. Geographic description of selected location:1. Geographic description of selected location:
- Economic profile
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Average Expenses of sruni Village
No Type of Expenses Total Amount ( IDR)/month
1 Food Rp. 600.000,-
2 Energy for cooking Rp. 66.000,-
3 Energy for Electricity & Gasoline Rp. 100.000,-
4 School Rp. 100.000,-
5 Health Rp. 50.000,-
TOTAL Expenses/Month Rp. 916.000,-
From survey need assesment
![Page 19: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/19.jpg)
Market analysis (cont)1. Geographic description of selected location:1. Geographic description of selected location:
- Energy profile (current household energy situation):
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
From the energy need survey, the following energy use patern emerged : 1.The type of energy uses for cooking are wirewood and LPG 2. Energy for ligting is electricity3. Energy for vechicle is gasoline
Energy expenditure per fuel type at Sruni Village
Energy service Fuel type Average monthly consumption
Average cost(in IDR, at the time of
writing)Total monthly cost
Cooking LPG 3 – 4 botle 3 kg Rp. 15.000/botle Rp. 45.000 -60.000
Cooking Wood + LPG 1 botle 3 kG + 30 bundle Fire Wood
Rp.15.000/bottle + Rp 1000/bundle
Rp. 45.000
Cooking Wood 60 bundle Rp 1000 Rp.60.000,-
Lighting kerosene lamp - - -
Lighting Electricity 100 kwh Rp 600 /kwh Rp. 75.000,-Transportation Gasoline 5 liter Rp 5.000 Rp. 25.000,-From survey need assesment
![Page 20: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/20.jpg)
Market analysis (cont)1. Geographic description of selected location:1. Geographic description of selected location:
- Current energy provision
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Size of Energy suppy
Type of energy Energy Supply (Bundle/Litre/Watt) Remark
Wood CookingKerosene - Cooking &Lighting
Electricity /PLN - LightingGasoline Transportation
![Page 21: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/21.jpg)
Market analysis (cont)1. Geographic description of selected location:1. Geographic description of selected location:
- Estimate of total demand for the proposed technology
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Detail of dairy cow farm at Sruni Village
NO Description Quantity of Dairy cow farmer TOTAL QTY OF
COW
1 Dairy cow farmer with 1 cow 108 108
2 Dairy cow farmer with 2 cow 112 224
3 Dairy cow farmer with 3 cow 75 225
4 Dairy cow farmer with 4 cow 49 196
5 Dairy cow farmer with 5 cow 20 100
6 Dairy cow farmer with 6cow 17 102
7 Dairy cow farmer with 7cow 12 84
8 Dairy cow farmer with 8cow 6 48
9 Dairy cow farmer with 9cow 5 45
10 Dairy cow farmer with 10cow 3 30
11 Dairy cow farmer with 11cow 3 33
12 Dairy cow farmer with 12cow 2 24
13 Dairy cow farmer with 13cow 0 0
14 Dairy cow farmer with 14cow 1 14
15 Dairy cow farmer with 15cow 1 15
TOTAL 414 1248
![Page 22: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/22.jpg)
Market analysis (cont)1. Geographic description of selected location:1. Geographic description of selected location:
- Estimate of total demand for the proposed technology
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
detail of goat farm at Sruni Village
NO Description Quantity of Dairy Goat
farmer TOTAL QTY OF GOAT
1 Dairy cow farmer with 1 goat 14 14
2Dairy cow farmer with 2 goat
19 38
3Dairy cow farmer with 3 goats
16 48
4Dairy cow farmer with 4 goats
7 28
5Dairy cow farmer with 5goats
8 40
6Dairy cow farmer with 6 goats
7 42
7Dairy cow farmer with 7 goat
3 21
8Dairy cow farmer with 8 goat
0 0
9Dairy cow farmer with 9 goat
1 9
10Dairy cow farmer with 10 goat
1 10
TOTAL 76 250
![Page 23: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/23.jpg)
Market analysis (cont)1. Geographic description of selected location:1. Geographic description of selected location:
- Estimate of total demand for the proposed technology
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Chart of the total amount of breeder at Sruni Village
From survey need assesment
![Page 24: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/24.jpg)
Market analysis (cont)1. Geographic description of selected location:1. Geographic description of selected location:
- Estimate of total demand for the proposed technology
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Chart of the total corespondent of each background
From survey need assesment
In the need assessment, we conducted survey with the total respondets are 40 people with the background of each respondent as followings
![Page 25: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/25.jpg)
Market analysis (cont)1. Geographic description of selected location:1. Geographic description of selected location:
- Estimate of total demand for the proposed technology
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Chart of the total Biogas Energy Demander
From survey need assesment
Based on the survey, most of the people want to build the biogas digester. From the 40 respondents, 23 people or 58 % have a high demand to build the digester and 11 people or 28 % want to build the digester. Only 6 people or 15 % not decide yet to build the digester
![Page 26: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/26.jpg)
Market analysis (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricCaiptal cost for construction/pre contrsuction Caiptal cost for construction/pre contrsuction
Dairy Cow Breeder414 household
Total Cow 1248
Potency Total Dairy Cow Breeder
have more 3 cows is 194 Cow Breeder So the potency of biogas at Sruni 194 digester
Can be builded
Biogas Potency at Seruni…
![Page 27: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/27.jpg)
Market analysis (cont)1. Geographic description of selected location:1. Geographic description of selected location:
- Estimate of total demand for the proposed technology
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Target digester will be builded
No Description Qty Target digester will be builded 2011 2012 2013 2014
1 Dairy cow farmer with 3 cows 75 8 8 8 8
2 Dairy cow farmer with 4 cows 49 5 5 5 5
3 Dairy cow farmer with 5 cows 20 2 2 2 2
4 Dairy cow farmer with more than 5 cows
50 5 5 5 5
Total of dairy cow farmer 194 20 20 20 20
![Page 28: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/28.jpg)
The Indonesian Domestic Biogas Programme (IDBP) is in Indonesia Better known as the BIRU Programme. Biru means “ Blue” and BIRU Program (Domestic Biogas) are managed and implemented by Hivos (Humanitarian Institute for Development Cooperation) and SNV-both are from the Dutch development agency, and funded by the Embassy of the Kingdom of the Netherlands and supported by the Directorate General of Electricity and Energy Utilization of Ministry of Energy and Mineral Resources .
3. Product descriptionBIRU (BIOGAS RUMAH ) PROGRAMME
1. Geographic description of selected location:1. Geographic description of selected location:
- Introduction of the BIRU PRIGRAMME
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
![Page 29: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/29.jpg)
BIRU (BIOGAS RUMAH ) PROGRAMME
1. Geographic description of selected location:1. Geographic description of selected location:
- Introduction of the BIRU PRIGRAMME
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
![Page 30: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/30.jpg)
BIRU (BIOGAS RUMAH ) PROGRAMME
1. Geographic description of selected location:1. Geographic description of selected location:
Technology description
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
The reactor used by BIRU has six components, namely: • 1) inlet that serves as a mixing room for the entry of animal manure, • 2) reactor that serves as the anaerobic decomposition chamber; • 3) gas container, storage space, • 4) outlet which serves as a space divider, • 5) the gas transporter room, and • 6) hole deposition as a place to rest processed biogas reactor.
![Page 31: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/31.jpg)
BIRU (BIOGAS RUMAH ) PROGRAMME
1. Geographic description of selected location:1. Geographic description of selected location:
Technology description
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
the figure of reactor components
![Page 32: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/32.jpg)
BIRU (BIOGAS RUMAH ) PROGRAMME
1. Geographic description of selected location:1. Geographic description of selected location:
Technology description
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Diagram of installation of biogas reactors
![Page 33: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/33.jpg)
BIRU (BIOGAS RUMAH ) PROGRAMME
1. Geographic description of selected location:1. Geographic description of selected location:
Technology description
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
The technical design of a typical biogas reactor of the BIRU program
![Page 34: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/34.jpg)
BIRU (BIOGAS RUMAH ) PROGRAMME
1. Geographic description of selected location:1. Geographic description of selected location:
The cost of a biogas installation and financing options
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
The detail estimated cost of the biogas reactor according to the size of the volume for area Boyolali regency
Sizes (m3) 4 6 8 10 12
Cows (ekor) 3 4-5 6 7-8 9
Total kg of manure per day
30 45 60 75 90
Gas produced (m3) 1 1,5 2 2,5 3
Duration of use to stove (hour)
4 6 8 10 12
Construction cost (IDR million)
5,7 6,3 7 8 8,8
Subsidies from Hivos(IDR million)
2 2 2 2 2
The cost to be paid (IDR million)
3,7 4,3 5 6 6,8
![Page 35: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/35.jpg)
• BIRU biogas reactor has a standard in the construction i.e standard materials, standard work processes, standards builders and supervisors, the standard way of working, and management standards. So when the construction of biogas reactors is in accordance with these standards, special mantainance is not required , the most important thing is to continuously incorporate manure in accordance with the provisions of the biogas reactor operation.
• Usually maintenance is maintenance performed on the leakage of the reactor that is guaranteed for 3 years, maintenance of the supporting component (stove, pipe, main valve, hose, etc.) that are guaranteed for one year.
BIRU (BIOGAS RUMAH ) PROGRAMME
1. Geographic description of selected location:1. Geographic description of selected location:
Mantainance requirements
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
![Page 36: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/36.jpg)
BIRU (BIOGAS RUMAH ) PROGRAMME
1. Geographic description of selected location:1. Geographic description of selected location:
Construction process
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
![Page 37: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/37.jpg)
BIRU program will have broad effects of health conditions and job creation as well as the local economy, including:
• Strengthen the integration of agriculture and cattle breeding for the improvement of agricultural resources
• Creating jobs in the biogas construction sector • Strengthen food security by improving agricultural output through the use of biogas slurry• Empowering women by providing opportunities in the national domestic biogas program as
an operator of biogas engines, lights, and refrigerator. In Indonesia, women also can take the role as campaigners for biogas, biogas users coaches, and entrepreneurs of small and medium-scale slurry
• Reducing deforestation• Controlling greenhouse gas emissions from livestock and organic waste disposal• Recycling of nutrients and restore soil fertility• Promoting environmental awareness and link it to economic advantage
BIRU (BIOGAS RUMAH ) PROGRAMME
1. Geographic description of selected location:1. Geographic description of selected location:
Social and economic impact description
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Economic benefits
![Page 38: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/38.jpg)
• Social benefits to adopting the proposed technology are:– Reducing the burden of women to collect firewood and facilitates alternative
additional activities to fill the time available, especially for female family members
– Improving access to sanitation and to reduce diseases associated with poor sanitation
– Reducing air pollution from smoke, which is closely related to respiratory diseases, eye infections, and accidental fires accidents due to the use of fire in open space
– Improving sanitation and hygiene education
BIRU (BIOGAS RUMAH ) PROGRAMME
1. Geographic description of selected location:1. Geographic description of selected location:
Social and economic impact description
Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Social benefits
![Page 39: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/39.jpg)
Currently energy issues in Indonesia is extremely complex, so it will need the policy that support the achievement of self sufficient energy. In the energy policy can be grouped into energy policy in national level, provincial level and district level.Generally policy is a policy that can be applied national level, while the provincial and district levels is emphasized policy accordance with the conditions of each region
4. Regulatory setting1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
![Page 40: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/40.jpg)
Regulatory setting1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
example of good policy in the national level, regional and district level
![Page 41: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/41.jpg)
Regulatory setting1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
![Page 42: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/42.jpg)
• To developing biogas-based muli- sector involves various parties such as service providers and local construction workers are supported by institutional training providers. The increasing interest of the community against the biogas must be balanced with the kompetetif price and satisfactory after sales services. BIOGAS Program must be done collaborations with some parties such as private parties, government and civil society to ensure the establishment of domestic biogas industry infrastructure. Credit lending institutions such as banks and cooperatives, educational institutions such as universities, such as milk processing industry, household appliances manufacturers of biogas and organic farmers' associations are some examples of institutions that participate in the program BIOGAS.
5. Project management1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Description of the project champion
![Page 43: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/43.jpg)
In the program activities in the village Biogasisasi Sruni we call Sruni BIOGAS DEVELOPMENT TASK FORCE (SBDTF), several parties who were directly involved in this activity include:
• Embassy of Netherlands Kingdom • Energy Research Centre of Netherlands • HIVOS Indonesia and HIVOS Solo• Ministry of MEMR • Engineering Faculty Diponegoro University/ Casindo Jateng • LPTK Solo as CPO• KUD Musuk as Multi Finance Institution • Representative of cow farmer
Project management1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Organization of the project
![Page 44: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/44.jpg)
Project management1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
BIRU Organization Structure
CPO
• Mencari pasar•Melakukan pekerjaan
konstruksi & Memberikan garansi
•Mendapatkan pelatihan tukang
MFI•Memberikan akses kredit pada konsumen yang tidak dapat membayar tunai
SLURRYextension
•Memberikan informasi mengenai pengolahan slurry
•Menampung slurry untuk diolah menjadi pupuk
•Mendistribusikan dan menjual pupuk
CPO : Construction Partner MFI : Multi Finance Institution
![Page 45: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/45.jpg)
Project management1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Organization of the project Development of BIOGAS at Seruni Village
CASINDO
JATENG
HIVOS
JATENG
TASK FORCE
SERUNI BIOGAS
DEVELOPMENT
Embassy of Netherlands Kingdom , ECN, HIVOS, Ministry of MEMR
CPO
(LPTK)
MFI
KUD Musuk
Reprsentative of cow farmer
Team Sozialitaion
and Slurry Extion
![Page 46: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/46.jpg)
The name of the project management for the Biogas Project at the Sruni Village as the following :
• The Head of HIVOS Office Solo as a Head of Task Force Sruni BIOGAS Development Project ( Mr William HIVOS SOLO Office )
• The Coordinator of Casindo Project Central Java as a vice of Task Force Seruni Biogas Development Project ( Joko Windarto - Enginneering Faculty of Diponegoro University – Semarang – Jl Prof Sudarto – Kampsu Undip Tembalang Semarang, Telp 024-7460057 )
• LPTP Solo as a CPO Task Force Biogas Development Project at Sruni Village ( Mr. lilik – LPTP Office Jl. Raya Palur km 5, Tegal Asri RT 04/VI, Kelurahan Ngringgo, Jaten, Karanganyar 27772, Jateng Telp : 0271 826620)
• KUD Musu k as a MFI Task Force Biogas Development Project at Sruni Village ( Mr Tirtihardi, Desa Musuk, Kec. Musuk Boyolali..Jateng )
• Mrs Bernard from HIVOS Office Solo and Mr Zulian from Undip as a technical team
Project management1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
The Name and Address of Project Management
![Page 47: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/47.jpg)
• The authorities are monitoring the biogas reactor construction after construction completed is CPO / LPO and audit quality from Hivos. CPO / LPO regularly monitoring the biogas reactor is built. Each reactor biogas given the responsibility of a supervisor certified (ID card) in charge of some people is also a certified builders (ID card).
• Audit quality monitoring on a regular basis every 6 months until the guarantee is completed (3 years). Monitoring conducted to see if the biogas reactor to function properly, resulting in gas with 80 cm of water pressure, no leakage of the reactor, no hose and faucet leaks, the stove burning with blue flame, forming slurry, and so forth
Project management1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Monitoring after construction
![Page 48: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/48.jpg)
6. Technical feasibility1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Technical requirements of the technology (for each of the different installation options)
Size of land requirement for the each digester size
Sizes (M3) 4 6 8 10 12
Space requirement (M x M) (3 x 6) (3,5 x 7) 4 x 8 4,5 x 9 5 x 10
![Page 49: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/49.jpg)
• Biogas reactor to produce gas that has a gas pressure of 80 cm of water. min 55 cm water pressure, 2 days after full charging has begun to burn, and cook with blue flame and faster than kerosene stove.
• Consumers needs fuel that: 1) cheap, and easy to cook on, 2) saves time (no need to search for firewood, not lining up to buy kerosene), 3) safe when used against explosion, 4) clean and healthy, and 5) increase family welfare. Biogas meets all these needs.
Technical feasibility (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Output
![Page 50: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/50.jpg)
Technical feasibility (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Availability of input requirements in the selected location • Based on the survey conducted in the villagem the number of households that
have 3 or more cows is 149 households. At the Sruni village, the Water avalibility in the selected location is not very sufficient. All household gets the water from the water rain, Every wet season , They keep the water from the rain in the tank. They people also uses the water for cooking, bathing, and wasing from the rain water.
• Based on the needs assessment questionnaire the households in the selected location (villages) have extensive land. At the Sruni village , almost the the households have sufficient space to install the digesters.
• According the situation at the Sruni village, the cow farmer is dairy milk. It mean they will have the cow in the every time and we belive the hosehold always have a cow. When the household have 3 or more cows, the supply of feedstock for the digester will be constant. So the produce of the biogas from the biodigester will not reduce and the household can uses the gas for cooking every day 65 is only from the 100 surveyed households; but you do not know, if there are more households with 3 or more cows in Jeruk Manis.
![Page 51: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/51.jpg)
7. Financial analyses1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Cost of the Project Biogas at Sruni Village
Capital cost for planning
Planning Costs Year 0
P1 Obtaining all permits - 0
P2 Technical analysis - 0
Subtotal 0
TOTAL all years - 0
![Page 52: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/52.jpg)
vFinancial analyses (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Cost of the Project Biogas at Sruni VillageCaiptal cost for construction/pre contrsuction
Caiptal cost for construction/pre contrsuction Caiptal cost for construction/pre contrsuction
Construction / Pre-operations Costs Year 0 Year 1 Year 2
C1 Land Acquisition - - 0 0
C2Final engineering
and design - - 0 0C3 Workers training - - 0 0C4 Machinery - - 0 0C5 Machinery - - 0 0C6 Machinery - 0 0C7 Testing - 0 0C8 Testing - 0 0C9 Testing - 0 0
Subtotal - -0 -0TOTAL all years - 0 0
![Page 53: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/53.jpg)
Financial analyses (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Cost of the Project Biogas at Sruni VillageTotal Cost of digester with size 4 , 6, 8, 10 m3 per each unit
Caiptal cost for construction/pre contrsuction Caiptal cost for construction/pre contrsuction
No Description Unit price/unit qty Total Price qty Total Price qty Total Price qty Total PriceA MATERIAL1 brick pcs 400,00Rp 1400 560.000Rp 1600 640.000Rp 1900 760.000Rp 2100 840.000Rp 2 coarse agrreagte m3 140.000,00Rp 0,8 112.000Rp 1 140.000Rp 1,3 182.000Rp 1,5 210.000Rp 3 fine agreegate m3 140.000,00Rp 1,1 154.000Rp 1,2 168.000Rp 1,3 182.000Rp 1,4 196.000Rp 4 spilt m3 140.000,00Rp 1,3 182.000Rp 1,5 210.000Rp 1,7 238.000Rp 1,9 266.000Rp 5 cement 40 kg sak 41.000,00Rp 20 820.000Rp 25 1.025.000Rp 30 1.230.000Rp 35 1.435.000Rp 6 steel bar pcs 33.000,00Rp 3 99.000Rp 3 99.000Rp 4 132.000Rp 5 165.000Rp 7 steel wire kg 14.000,00Rp 1 14.000Rp 1 14.000Rp 1 14.000Rp 1 14.000Rp 8 Nail and Clamp pcs 1.000,00Rp 30 30.000Rp 30 30.000Rp 30 30.000Rp 30 30.000Rp 9 1 Main Pipe Gas (1,5")pcs 105.000,00Rp 1 105.000Rp 1 105.000Rp 1 105.000Rp 1 105.000Rp
Capacity : 4m3 Capacity : 6m3 Capasity 8m3 Capasity 10m3
![Page 54: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/54.jpg)
Financial analyses (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Cost of the Project Biogas at Sruni VillageTotal Cost of digester with size 4 , 6, 8, 10 m3 per each unit
Caiptal cost for construction/pre contrsuction Caiptal cost for construction/pre contrsuction
No Description Unit price/unit qty Total Price qty Total Price qty Total Price qty Total Price10 Fitting PVC 0,5"pcs 20.000,00Rp 10 200.000Rp 10 200.000Rp 10 200.000Rp 10 200.000Rp 11 PVC Pipe Gas (0,5")pcs 15.000,00Rp 12 180.000Rp 12 180.000Rp 12 180.000Rp 12 180.000Rp 12 Main Valve pcs 45.000,00Rp 1 45.000Rp 1 45.000Rp 1 45.000Rp 1 45.000Rp 13 Sieve Coarse (1/4")m2 15.000,00Rp 1 15.000Rp 1 15.000Rp 1 15.000Rp 1 15.000Rp 14 Water Drain pcs 45.000,00Rp 1 45.000Rp 1 45.000Rp 1 45.000Rp 1 45.000Rp 15 Gas Valve pcs 120.000,00Rp 2 240.000Rp 2 240.000Rp 2 240.000Rp 3 360.000Rp 16 Stove pcs 100.000,00Rp 1 100.000Rp 1 100.000Rp 1 100.000Rp 2 200.000Rp 17 1 set Manometerpcs 125.000,00Rp 1 125.000Rp 1 125.000Rp 1 125.000Rp 1 125.000Rp 18 Mixer pcs 125.000,00Rp 1 125.000Rp 1 125.000Rp 1 125.000Rp 1 125.000Rp 19 Hose Gas 3/8" meter 14.000,00Rp 1 14.000Rp 1 14.000Rp 1 14.000Rp 2 28.000Rp 20 Seal tape pcs 10.000,00Rp 2 20.000Rp 2 20.000Rp 2 20.000Rp 2 20.000Rp 21 PVC inlet D 4" pcs 140.000,00Rp 2 280.000Rp 2 280.000Rp 2 280.000Rp 2 280.000Rp 22 PVC pipe glue pcs 10.000,00Rp 2 20.000Rp 2 20.000Rp 2 20.000Rp 2 20.000Rp 23 Emulsion paint liter 65.000,00Rp 2 130.000Rp 2 130.000Rp 2 130.000Rp 2 130.000Rp
Capacity : 4m3 Capacity : 6m3 Capasity 8m3 Capasity 10m3
TOTAL COST FOR MATERIAL (A) Rp 3.615.000 Rp 3.970.000 Rp 4.412.000 Rp 5.034.000
![Page 55: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/55.jpg)
Financial analyses (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Cost of the Project Biogas at Sruni VillageTotal Cost of digester with size 4 , 6, 8, 10 m3 per each unit
Caiptal cost for construction/pre contrsuction Caiptal cost for construction/pre contrsuction
No Description Unit price/unit qty Total Price qty Total Price qty Total Price qty Total Price
BLABOR COST
24 Tukang (Skill Labor )Person 60.000,00Rp 9 540.000Rp 10 600.000Rp 11 660.000Rp 12 720.000Rp 25 Buruh (unskill Labor)Person 40.000,00Rp 19 760.000Rp 22 880.000Rp 24 960.000Rp 28 1.120.000Rp
Capacity : 4m3 Capacity : 6m3 Capasity 8m3 Capasity 10m3
SUBSIDY FROM HIVOS 2.000.000Rp 2.000.000Rp 2.000.000Rp 2.000.000Rp HOUSEHOLD SOULD BE PAID 3.615.000Rp 4.200.000Rp 4.832.000Rp 5.724.000Rp
SERVICE FEE + maintenance 700.000Rp 750.000Rp 800.000Rp 850.000Rp TOTAL COST OF BIODIGESTER 5.615.000Rp 6.200.000Rp 6.832.000Rp 7.724.000Rp
TOTAL LABOR COST (B) Rp 1.300.000 Rp 1.480.000 Rp 1.620.000 Rp 1.840.000
TOTAL COST FOR MATERAL AND LABOR COST (A+B) 4.915.000Rp 5.450.000Rp 6.032.000Rp 6.874.000Rp
![Page 56: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/56.jpg)
Financial analyses (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricCaiptal cost for construction/pre contrsuction Caiptal cost for construction/pre contrsuction
Dairy Cow Breeder414 household
Total Cow 1248
Potency Total Dairy Cow Breeder
have more 3 cows is 194 Cow Breeder So the potency of biogas at Sruni 194 digester
Can be builded
Biogas Potency at Seruni…
![Page 57: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/57.jpg)
Financial analyses (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Cost of the Project Biogas at Sruni VillageTotal target the digester will be builded to Sruni till 2014
Caiptal cost for construction/pre contrsuction Caiptal cost for construction/pre contrsuction
No Description Qty Target digester will be builded
2011 2012 2013 2014
1 Dairy cow farmer with 3 cows 75 8 8 8 8
2 Dairy cow farmer with 4 cows 49 5 5 5 5
3 Dairy cow farmer with 5 cows 20 2 2 2 2
4 Dairy cow farmer with more than 5 cows
50 5 5 5 5
Total of dairy cow farmer 194 20 20 20 20
![Page 58: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/58.jpg)
Financial analyses (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Cost of the Project Biogas at Sruni Village
Total cost to develop biogas at Sruni Village till year 2014
Caiptal cost for construction/pre contrsuction Caiptal cost for construction/pre contrsuction
OPERATING COSTSYear 2011
(Rp)Year 2012
(Rp) Year 2013 (Rp) Year 20144 (Rp)
O1General and Administrative Costs 14,000,000
14,000,000
14,000,000
14,000,000
O2 Labor costs 26,000,000 26,000,000
26,000,000
26,000,000
O3 Material costs 72,300,000 72,300,000
72,300,000
72,300,000
TOTAL 112,300,000 112,300,000
112,300,000
112,300,000
![Page 59: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/59.jpg)
Chapter 7 : Financial analyses1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
Cost of the Project Biogas at Sruni VillageTotal cost to develop biogas at Sruni Village till year 2014
Caiptal cost for construction/pre contrsuction Caiptal cost for construction/pre contrsuction
OPERATING COSTSYear 2011
(Rp)Year 2012
(Rp) Year 2013 (Rp) Year 20144 (Rp)
O1General and Administrative Costs 14,000,000
14,000,000
14,000,000
14,000,000
O2 Labor costs 26,000,000 26,000,000
26,000,000
26,000,000
O3 Material costs 72,300,000 72,300,000
72,300,000
72,300,000
TOTAL 112,300,000 112,300,000
112,300,000
112,300,000
Grants and Subsidies Rp Year 0Year 2011
(Rp)Year 2012
(RP)Year 2013
(Rp) Year 2014
(Rp)
1 Pre-operation support (Casindo)
2 For Operation ( Hivos) 40,000,000
40,000,000
40,000,000
40,000,000
Subtotal - 40,000,000
40,000,000
40,000,000
40,000,000
TOTAL all years
160,000,000
The total cost for subsidy biogas at Sruni Village till 2014
![Page 60: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/60.jpg)
Financial analyses (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
RevenuesThe total revenue till year 2014 for biogas program at Sruni
Caiptal cost for construction/pre contrsuction Caiptal cost for construction/pre contrsuction
Revenues Year 1 Year 2 Year 3 Year 4
R1 Revenue from 1 Rp. 72,300,000 Rp. 72,300,000 Rp. 72,300,000 Rp. 72,300,000
Units 20 20 20 20
Revenue per Unit Rp. 3,615,000 Rp. 3,615,000 Rp 3,615,000 Rp. 3,615,000
R2 Revenue from 2 -
Units
Revenue per Unit
REVENUES Rp. 72,300,000 Rp. 72,300,000 Rp. 72,300,000 Rp. 72,300,000
![Page 61: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/61.jpg)
The cash flow projection is also the bases to calculate the following financial indicators, which funders use to decide whether to fund a project or not:
• the Net Present Value of Net Income (NPV NI), which is the difference between the discounted costs and revenues and shows what is the future income stream that the project would generate worth today.
• the Benefit cost ratio (B/C ratio), which shows whether and by how much the project revenues exceed the project costs and by this whether it is profitable or not. If the B/C ratio is less than one, then the project is not profitable (which does not mean it is not worth implementing, but then its social and environmental benefits must be made very clear).
• the Internal rate of return (IRR), which is the discount rate at which the NPV of the investment project is zero (this is very relevant for projects that need external financing; if the bank loan interest rate is higher than the project IRR, then such a project likely will not get funded).
Financial analyses (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
The cash flow
Caiptal cost for construction/pre contrsuction Caiptal cost for construction/pre contrsuction
![Page 62: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/62.jpg)
In the Project Biogas at Sruni village, the IRR for commercial bank is 12 % so we use this amount to calculate the cash flow and the detail calculation of cash flow can be looked at table
Financial analyses (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
The cash flow
Caiptal cost for construction/pre contrsuction Caiptal cost for construction/pre contrsuction
![Page 63: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/63.jpg)
Financial analyses (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
The cash flow ( option I)
Caiptal cost for construction/pre contrsuction Caiptal cost for construction/pre contrsuction
Detail of Cash flow for Bioags Project at Seruni Village ( subsidy Hivos till 2014)
TOTALS Year 0 Year 1 Year 2 Year 3 Year 4
COSTS (& GRANTS/SUBSIDIES) 2010 2011 2012 2013 2014
Capital Cost 0.0 0.0 0.0 0.0 0.0
Capital / pre-operation grants 0.0 0.0 0.0 0.0 0.0
Operating costs 0.0 112,300,000.0 112,300,000.0 112,300,000.0 112,300,000.0
Operating grants 0.0 40,000,000.0 40,000,000.0 40,000,000.0 40,000,000.0
TOTAL COSTS 0.0 72,300,000.0 72,300,000.0 72,300,000.0 72,300,000.0
NPV TOTAL COSTS (discount rate = 12%) 219,600,357.8 0.0 64,553,571.4 57,637,117.3 51,461,711.9 45,947,957.1
BENEFITS
Revenues 0.0 72,300,000.0 72,300,000.0 72,300,000.0 72,300,000.0
NPV revenues 219,600,357.8 0.0 64,553,571.4 57,637,117.3 51,461,711.9 45,947,957.1
Interest
Taxes
Depreciation
NET INCOME 0.0 0.0 0.0 0.0 0.0
Accumulated Income* 0.0 0.0 0.0 0.0 0.0
NPV NET INCOME 0.0 0.0 0.0 0.0 0.0 0.0
Benefit / Cost Ratio 1,00
![Page 64: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/64.jpg)
Financial analyses (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
The cash flow (option II )
Caiptal cost for construction/pre contrsuction Caiptal cost for construction/pre contrsuction
Detail of Cash flow for Bioags Project at Seruni Village ( subsidy till 2012)
TOTALS Year 0 Year 1 Year 2 Year 3 Year 4COSTS (& GRANTS/SUBSIDIES) 2010 2011 2012 2013 2014
Capital Cost Cc 0.0 0.0 0.0 0.0 0.0
Capital / pre-operation grants Gc 0.0 0.0 0.0 0.0 0.0
Operating costs Co 0.0112,300,000.0 112,300,000.0 112,300,000.0 112,300,000.0
Operating grants Go 0.0 40,000,000.0 40,000,000.0 0.0 0.0
TOTAL COSTS TC = (Cc-Gc)+(Co-Go) 0.0 72,300,000.0 72,300,000.0 112,300,000.0 112,300,000.0NPV TOTAL COSTS (discount rate = 10%)
NPV TC = TC / (1+disc rate)t; t = year of operation 12% 273,492,290.8 0.0 64,553,571.4 57,637,117.3 79,932,921.8 71,368,680.2
BENEFITS Revenues R 0.0 72,300,000.0 72,300,000.0 72,300,000.0 72,300,000.0
NPV revenuesNPV R = R / (1+disc rate)t; t = year of operation 12% 219,600,357.8 0.0 64,553,571.4 57,637,117.3 51,461,711.9 45,947,957.1
Interest
Taxes
Depreciation
NET INCOME NIt = Rt -TCt 0.0 0.0 0.0 -40,000,000.0 -40,000,000.0
Accumulated Income* AIt = AIt-1 + NIt 0.0 0.0 0.0 -40,000,000.0 -80,000,000.0
NPV NET INCOMENPV NI = NI / (1+disc rate)t; t = year of operation 12% -53,891,933.0 0.0 0.0 0.0 -28,471,209.9 -25,420,723.1
Benefit/cost Ratio B/C ratio = NPV R / NPV TC 0.803
![Page 65: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/65.jpg)
Financial analyses (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
The cash flow ( option III)
Caiptal cost for construction/pre contrsuction Caiptal cost for construction/pre contrsuction
detail of the cash flow for the option 2 with the interest rate 6 % from the bank and given to the customers ( cow farmer ) 12 % ( Subsidy till 2014)
TOTALS Year 0 Year 1 Year 2 Year 3 Year 4COSTS (& GRANTS/SUBSIDIES) 2010 2011 2012 2013 2014Capital Cost 0.0 0.0 0.0 0.0 0.0
Capital / pre-operation grants 0.0 0.0 0.0 0.0 0.0
Operating costs 0.0 112,300,000.0 112,300,000.0 112,300,000.0 112,300,000.0
Operating grants 0.0 40,000,000.0 40,000,000.0 40,000,000.0 40,000,000.0
TOTAL COSTS 0.0 72,300,000.0 72,300,000.0 72,300,000.0 72,300,000.0NPV TOTAL COSTS (discount rate = 10%) 12% 219,600,357.8 0.0 64,553,571.4 57,637,117.3 51,461,711.9 45,947,957.1 BENEFITS
Revenues 0.0 72,300,000.0 72,300,000.0 72,300,000.0 72,300,000.0
NPV revenues 6% 250,527,135.8 0.0 68,207,547.2 64,346,742.6 60,704,474.2 57,268,371.9
Interest
Taxes
Depreciation
NET INCOME 0.0 0.0 0.0 0.0 0.0
Accumulated Income* 0.0 0.0 0.0 0.0 0.0
NPV NET INCOME 12% 0.0 0.0 0.0 0.0 0.0 0.0
Benefit/cost Ratio 1.141
![Page 66: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/66.jpg)
Financial analyses (cont)1. Geographic description of selected location:1. Geographic description of selected location:Map of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk DistricMap of Boyolali Regency and Musuk Distric
The cash flow ( option IV)
Caiptal cost for construction/pre contrsuction Caiptal cost for construction/pre contrsuction
detail of the cash flow for the option 2 with the interest rate 6 % from the bank and given to the customers ( cow farmer ) 12 % ( note : the subsidy HIVOS till 2012)
TOTALS Year 0 Year 1 Year 2 Year 3 Year 4COSTS (& GRANTS/SUBSIDIES) 2010 2011 2012 2013 2014
Capital Cost 0.0 0.0 0.0 0.0 0.0
Capital / pre-operation grants 0.0 0.0 0.0 0.0 0.0
Operating costs 0.0 112,300,000.0 112,300,000.0 112,300,000.0 112,300,000.0
Operating grants 0.0 40,000,000.0 40,000,000.0 40,000,000.0 40,000,000.0
TOTAL COSTS 0.0 72,300,000.0 72,300,000.0 72,300,000.0 72,300,000.0
NPV TOTAL COSTS (discount rate = 10%) 12% 219,600,357.8 0.0 64,553,571.4 57,637,117.3 51,461,711.9 45,947,957.1
BENEFITS
Revenues 0.0 72,300,000.0 72,300,000.0 72,300,000.0 72,300,000.0
NPV revenues 6% 250,527,135.8 0.0 68,207,547.2 64,346,742.6 60,704,474.2 57,268,371.9
Interest
Taxes
Depreciation
NET INCOME 0.0 0.0 0.0 0.0 0.0
Accumulated Income* 0.0 0.0 0.0 0.0 0.0
NPV NET INCOME 12% 0.0 0.0 0.0 0.0 0.0 0.0
Benefit/cost Ratio 1.141
![Page 67: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/67.jpg)
8. Risk analysis and contingency planning
![Page 68: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/68.jpg)
Completion riskThere are several things that can cause delays in the construction of the biogas digesters although funds were available, including:
The cost of cement: cement is a very significant material in the construction of a biogas digester, and if cement prices increase by the run cause delayed biogas digester construction. Some of the professional mason (trained for this job) might go after another job that is more promising (where cost of labour is higher) compared with standard from HIVOS.CPO or Hivos could be late in responding to users who are interested to build a biogas digester.
![Page 69: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/69.jpg)
Technology riskThe biogas digester technology used in the BIRU program gets a warranty for 3 years. The BIRU program is almost 100% successful in building biogas digesters which are operating properly on the Central Java Province. Thus the risk of the technology not performing well is negligible. So far, the BIRU program in Central Java Province No have problems in the seruni vilage ( 3 digesters was Built). But biru have one problem with 1 user at Mojosongo District (37 digesters was built), where the inserted cow manure did not produce gas for 7 days. That means that the only plausible technology risk is possible wrong mixing of manure or have leakage at the Dome digesters. This risk can be eliminated with a proper socialization process and a user manual, also should be monitoring and supervise by the CPO .
![Page 70: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/70.jpg)
Supply riskThe materials needed to build a biogas digester are available in adequate quantity around the location, so there is no risk of supply shortage of construction material.There is no possible risk of the delivery the components for biogas stoves.
![Page 71: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/71.jpg)
Economic riskThere is a real risk that people in the village can not the pay for the biogas digester, because the price to build a biogas digester is 3 million IDR and more (after the subsidy). Average income per month of the villagers is medium income. But, the Hivos subsidy is not sufficient to build a biogas digester because almost all the farmers if they have the cash money, they just thinking .Economic risk would be smaller if there are support from the government, cooperatives, banks, other financial institutions to build a biogas digester through soft loans or credit.
![Page 72: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/72.jpg)
Financial riskChanges in interest rates would cause financial risk to occur. Historical growth shows that interest rates in Indonesia are relatively stable (constant) so that the financial risk is very small.
![Page 73: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/73.jpg)
Political risk
The political framework at the national, regional level in Central Java Province and also the local government are supporting the implementation of the biogas digester program, because the government's main priority now is to increase the of renewable energy target on 2025 is 17 %.In addition, national level and regional leves have the program DESA MANDIRI ENERGY ( Self Sufficient Energy ) Program which aims to achieve the target in year 2014 are 20 villages DME in Central Java province which fits well with the BIRU program.
![Page 74: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/74.jpg)
Environmental riskBiogas digesters have no negative environmental impact on the community or a user, but several positive impacts, including:
dirty cages and cows that used to disturb the environment, are now clean, tidy and do not represent a health hazard.The smoke from wood stoves and fuel oil which can harm the health, is now replaced by a clean and safe cooking fuel.Less pressure on forests around the village which are harvested by residents looking for firewood.
![Page 75: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/75.jpg)
Social risk
Implementation of biogas can be burdened by possible social risks for some people, namely:
Residents who have not obtained the education and socialization of the benefits of biogas still think of it as a taboo / unclean use of cow dung. So that important to carry out more socialization.The implementation schedule can create jealousy with those that cannot afford a digester, or towards those that get it first to etc.
![Page 76: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/76.jpg)
Force majeure riskForce majeure risk that may occur is the occurrence of earthquakes, volcanic eruption, or landslide. Generally, often occurrence of earthquakes in Lombok island, but the scale under 5.0 SR and the occurrence of volcanic eruption or landslide not occur in last 10 year.
![Page 77: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/77.jpg)
Documentation and discussion
![Page 78: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/78.jpg)
Energy used for cookingAlthough electricity has reached entire of the village and most households have gas stove for cooking, there are still many households use firewood for cooking because of expensive price of LPG gas.
![Page 79: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/79.jpg)
Install one digester at seruni vllage for demo unit (capacity 8 m2 )
Start Construction 24 Sept 2010 Finish on 5 Oct 2010 Start using for Cooking on 14 Oct 2010 for 3 house hold ( capacity 8m2, with 10 cows )
![Page 80: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/80.jpg)
Site Visit to Koperasi Susu Mojosongo, Boyolali Regency
Koperasi Susu Mojosongo as MFI and CPO Koperasi Susu Mojosongo installed 35 Biogas Digester Household as a member Koperasi Susu Mojosongo very easy to get a credit for installation biogas digester System payment, deduct of production milk from the own of cow breeder . Per day deduct 2,3 liter milk / day
![Page 81: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/81.jpg)
Site Visit to Koperasi Susu Mojosongo, Boyolali Regency
![Page 82: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/82.jpg)
Site Visit to Koperasi Susu Mojosongo, Boyolali Regency
Slurry, can be used for fertilizer (liquid )
![Page 83: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/83.jpg)
Closing…
Any comments?
Thank you…Thank You
![Page 84: UNDIP TEAM SEMARANG Meeting, 9 – 13 July 2011](https://reader035.fdocuments.us/reader035/viewer/2022081511/568165f8550346895dd9227b/html5/thumbnails/84.jpg)
PER BULAN Slurry Rp. 162.000 ???PER BULAN LPG Rp. 30.000Kebersihan Rp. 8.000KEUNTUNGAN PER BULAN = Rp
200.000KEUNTUNGAN PER TAHUN = Rp.
1.400.000KEUNTUNGAN 3 TAHUN = Rp.
4.200.000Peternak akan untung setelah 3
tahun