UAT PLAN – Overview
WHAT WHEN
Solution Set 1 Apps 10/10/13 to 11/7/13
Legacy Data Migration Public Works Environmental
10/28/13 to 10/31/13(4-days only!)
Solution Set 2 Apps 11/21/13 to 12/12/13
10/10/2013 2
UAT PLAN – Solution Set 1 Apps
WHAT to test WHO will test
County Owned Property Robin Giove, Rick Cody (test access)
Fire Hydrant Maintenance Rick Cody, Robin Giove (test access)
Future Land Use Viewer Alan Shellhorn, Michael Schoderbock
GIS Intranet Page Mike Roiland, Corey Atha
Public Notifications Charlie Dye, Kristin Preston
10/10/2013 3
Core Team members listed are main point of contact for all testers in department
UAT PLAN – Legacy Data Migration
WHAT to test WHO will test
Data Migration: Environmental Management Datasets
Rob Burnes, Steve Harper
Data Migration: Public Works Penny Simone
10/10/2013 4
Core Team members listed are main point of contact for all testers in department
UAT PLAN – Issue Tracking
SharePoint – one User ID + password for all testers User ID: [email protected] Password: GIS4test
Each Issue is an entry in the table GISi may access the Issues list SharePoint “Views” created
UAT Coordinator: Christy Kretschmann
10/10/2013 5
UAT PLAN – Issues ListFirst, log in:
User ID: [email protected] Password: GIS4test
Links:• To ADD an issue:
– http://pinellas.collaborationhost.net/eGIS/workinggroup/_layouts/listform.aspx?PageType=8&ListId={556D7F8B-BFA9-433F-8A3E-871D2FB4F064}&RootFolder=
– Or, go to any List View, then click on “Add new item” (at the bottom of the list).• To see ALL issues:
– http://pinellas.collaborationhost.net/eGIS/workinggroup/Lists/UATGISiEngagement2013/AllItems.aspx
• To see only ACTIVE issues:– http://pinellas.collaborationhost.net/eGIS/workinggroup/Lists/UATGISiEngagement201
3/active.aspx
• To see only NON-ACTIVE issues:– http://pinellas.collaborationhost.net/eGIS/workinggroup/Lists/UATGISiEngagement201
3/NonActive.aspx• To EDIT an existing issue, simply click on the issue, and make any changes or add any
additional remarks
10/10/2013 11
GIS Inc. Project Elements• Solution Set 1 (internal apps & legacy data migration)
a) County Owned Propertyb) Fire Hydrant Maintenancec) eGIS Viewer MOVED TO SS-2d) Future Land Use Viewer e) Geo-processing Tool TAKEN OUT OF SCOPEf) GIS Intranet Pageg) Public Notificationsh) Data Migration: Environmental Management Datasets (all)i) Data Migration: Public Works (subset)
• Solution Set 2 (external apps)a) eGIS Data Downloadsb) Future Land Usec) GIS Internet Web Paged) MPO Road Projectse) My Neighborhood
10/10/2013 12
Workshops to Conclude Crosswalks (DROP DEAD DATE) GISi pushing datasets to temp file
geoDB, daily & Bureau accelerated data validation (not UAT)
GISi pushing datasets to temp file geoDB, daily & Bureau accelerated data validation (not UAT)
GISi pushing datasets to temp file geoDB, daily & Bureau accelerated data validation (not UAT)
GISi pushing datasets to temp file geoDB, daily & Bureau accelerated data validation (not UAT)
Load to Temp SDE (Read
Only)
UAT of LDM by Data Stewards + Data Certification w/BureauLegacy Edit Cut-Off Date
SS1 Apps Ready for UAT (except eGIS
Viewer)
JOINT
GISi BTS
BUREAU